This abstract of bids summarizes offers received in response to a solicitation for chute repair work along the Missouri River in Missouri and Nebraska. The U.S. Army Corps of Engineers received bids by September 7th for repairing priority structures damaged in 2018 and 2019 flooding at three locations. Work includes placing rock armor at control structures, dikes, banks and islands. Estimated tonnages, unit pricing and totals are provided for base line work and five options. The low bidder offered a total bid of $3,657,478 for all work, while bids ranged from $3,657,478 to $5,338,116. This project has an estimated value between $1-5 million and is restricted to small businesses, with a period of performance of 730 days from notice to proceed.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2. DATE ISSUED 3. DATE OPENED

3-Aug-21 7-Sep-21

I CERTIFY THAT I HAVE OPENED, READ AND

AND RECORDED ON THIS ABSTRACT

ALL OFFERS RECEIVED IN RESPONSE DATE SIGNED

Chute Repair FY21 Missouri River Atchison and Holt County, Missouri Nemaha County, Nebraska

C. REASONABLE CONTRACT

7A 7B 7C D. E. F.

ITEM # DESCRIPTION OF OFFER ITEM EST. QUANTITY UNIT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT

Basic - Deroin Bend RM 521 - 516

0001 Entire work, complete, for Revetment 562.1 as shown on the drawings and in the specifications 11,790 Tons $63.80 $752,202.00 $70.00 $825,300.00 $56.00 $660,240.00 $90.00 $1,061,100.00

0002 Entire work, complete, for Deroin Breach Closure as shown on the drawings and in the specifications 2,500 Tons $63.80 $159,500.00 $85.00 $212,500.00 $69.50 $173,750.00 $71.50 $178,750.00

0003 Entire work, complete, for Deroin Lower Control Structure Revetment as shown on the dra ings and in the specifications 2,500 Tons $63.80 $159,500.00 $85.00 $212,500.00 $75.00 $187,500.00 $74.50 $186,250.00

0004 Entire work, complete, for Deroin Side Channel Grade Control Structures as shown on the drawings and in the specifications 3,600 Tons $63.80 $229,680.00 $85.00 $306,000.00 $68.00 $244,800.00 $69.50 $250,200.00

0005 Entire work, complete, for Dike/L-head 558.6/558.6A as shown on the dra ings and in the specifications 9,000 Tons $63.80 $574,200.00 $70.00 $630,000.00 $56.00 $504,000.00 $90.00 $810,000.00

0006 Entire work, complete, for the mobilization / demobilization of all marine equipment as shown on the drawings & in the specifications 1 Job $55,000.00 $55,000.00 $255,000.00 $255,000.00 $270,000.00 $270,000.00 $316,200.00 $316,200.00

0007 All remaining work Except for Option Items listed below 1 Job $70,000.00 $70,000.00 $42,500.00 $42,500.00 $465,000.00 $465,000.00 $280,000.00 $280,000.00

TOTAL BASIC AMOUNT (CLIN 0001-0007) $2,000,082.00 $2,483,800.00 $2,505,290.00 $3,082,500.00

Option 1 - Langdon Bend RM 530.7

0008 Entire work, complete, for Dike 572.9 as shown on the drawings and in the specifications 1 Job $54,600.00 $54,600.00 $12,500.00 $12,500.00 $20,200.00 $20,200.00 $15,000.00 $15,000.00

0009 Entire work, complete, for Dikes 572.82 & 572.81 as shown on the drawings and in the specifications 2,400 Tons $64.00 $153,600.00 $60.00 $144,000.00 $63.00 $151,200.00 $100.00 $240,000.00

0010 All remaining work in the option area as shown on the drawings and in the specifications 1 Job $14,000.00 $14,000.00 $8,500.00 $8,500.00 $1,500.00 $1,500.00 $25,000.00 $25,000.00

TOTAL AMOUNT - OPTION 1 (CLIN 0008-0010) $222,200.00 $165,000.00 $172,900.00 $280,000.00

Option 2 - Deroin Bend RM 521 - 516

0011 Entire work, complete, for Random fill on Deroin Island Tip as shown on the drawings and in the specifications 5,800 CY $21.22 $123,076.00 $82.00 $475,600.00 $33.50 $194,300.00 $35.62 $206,596.00

0012 Entire work, complete, for Topsoil on Deroin Island Tip as shown on the drawings and in the specifications 1,200 CY $36.85 $44,220.00 $84.00 $100,800.00 $41.00 $49,200.00 $36.00 $43,200.00

0013 All remaining work in the option area as shown on the drawings and in the specifications 1 Job $11,600.00 $11,600.00 $17,500.00 $17,500.00 $1,500.00 $1,500.00 $31,500.00 $31,500.00

TOTAL AMOUNT - OPTION 2 (CLIN 0011-0013) $178,896.00 $593,900.00 $245,000.00 $281,296.00

Option 3 -Rush Bottoms RM 501.1

Bid Security 20% C. AMENDMENTS ACKNOWLEDGED : Yes

NO. 3

C. OFFEROR

Hendrickson Transportation

Bid Security 20%

2762 310th Street Hamburg, IA 51640

C. AMENDMENTS ACKNOWLEDGED : Yes

Bid Security 20% C. AMENDMENTS ACKNOWLEDGED : Yes

(Without Profit)

(Including Profit)

Nebraska City, NE 68410

B. REASONABLE CONTRACT

Western Contracting Corporation

6. NUMBER OF AMENDMENTS ISSUED

A. OFFEROR B. OFFEROR

705 Douglas St, Ste 400 Sioux City, IA 51101-1087

PO Box 610

A. HIRED LABOR

IGE Midwest Construction

NO. 1 NO. 2

9. OFFERS

1. SOLICITATION NUMBER

W9128F21B0018

4. ISSUING OFFICE

8. GOVERNMENT ESTIMATE

(Check A, B or C AND COMPLETE D, E AND F)

5. PROJECT TITLE

TO THIS SOLICITATION

l PAGES

SIGNATURE

NAME AND TITLE OF CERTIFYING OFFICIAL (Type)

OMAHA, NE 68102-1618

1616 CAPITOL AVENUE

CONTRACTING DIVISION (CENWO-CT)

US ARMY CORPS OF ENGINEERS

ABSTRACT OF OFFERS - CONSTRUCTION

9/7/21

Lee M McCormick

0014 Entire work, complete, for Rush Grade Control Repair as shown on the dra ings and in the specifications 1,440 Tons $70.00 $100,800.00 $77.00 $110,880.00 $83.00 $119,520.00 $115.00 $165,600.00

0015 All remaining work in the option area as shown on the drawings and in the specifications 1 Job $12,300.00 $12,300.00 $8,500.00 $8,500.00 $1,500.00 $1,500.00 $40,000.00 $40,000.00

TOTAL AMOUNT - OPTION 3 (CLIN 0014-0015) $113,100.00 $119,380.00 $121,020.00 $205,600.00

Option 4 -Deroin Bend RM 521 - 516

0016 Entire work, complete, for Dike/L-head 558.7/558.7A as shown on the drawings and in the specifications 9,000 Tons $64.00 $576,000.00 $60.00 $540,000.00 $52.00 $468,000.00 $90.00 $810,000.00

0017 All remaining work in the option area as shown on the drawings and in the specifications 1 Job $11,600.00 $11,600.00 $8,500.00 $8,500.00 $1,500.00 $1,500.00 $25,000.00 $25,000.00

TOTAL AMOUNT - OPTION 4 (CLIN 0016-0017) $587,600.00 $548,500.00 $469,500.00 $835,000.00

Option 5 -Deroin Bend RM 521 - 516

0018 Entire work, complete, for Deroin Dike Field Revetment as shown on the drawings and in the specifications 8,500 Tons $64.00 $544,000.00 $77.00 $654,500.00 $68.00 $578,000.00 $70.32 $597,720.00

0019 All remaining work in the option area as shown on the drawings and in the specifications 1 Job $11,600.00 $11,600.00 $8,500.00 $8,500.00 $1,500.00 $1,500.00 $56,000.00 $56,000.00

TOTAL AMOUNT - OPTION 5 (CLIN 0018-0019) $555,600.00 $663,000.00 $579,500.00 $653,720.00

TOTAL AMOUNT BASIC PLUS OPTIONS (ITEMS 0001 - 0019) $3,657,478.00 $4,573,580.00 $4,093,210.00 $5,338,116.00