Attachement 1_Section J - 49M ERS West SB SATOC_.xlsx
XLSX spreadsheet 21 KB Posted
- Solicitation number
- W9128F20R0046
About this file
This document contains a price spreadsheet template and description of a federal solicitation. The price spreadsheet template outlines estimated annual costs for a Small Business Set-Aside Indefinite Delivery/Indefinite Quantity Single Task Order Contract for Environmental Remediation Services in support of the U.S. Army Corps of Engineers, Northwestern Division, Omaha District. Key details include a total estimated contract value of $49 million over a 5-year base period and two 1-year option periods, with task orders to be issued on an as-needed basis. Offerors must submit proposals in response to solicitation W9128F20R0046 by November 2, 2020 to be considered for this opportunity.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section J Price Spreadsheet
| Price Information | ||||
| W9128F-20-R-0046 $49M ERS (West) SB SATOC | ||||
| Section J- Attachment Cost Spreadsheet (BLANK) | ||||
| Year 1- (Base Period) | ||||
| A. Home Office Personnel | Fully Burdened Binding Capped Labor Rate (Hourly) | Units | Quantity | Subtotal |
| Program Manager | Hrs. | 60 | $ - 0 | |
| Project Manager | Hrs. | 220 | $ - 0 | |
| Senior Contract Manager | Hrs. | 80 | $ - 0 | |
| Procurement Specialist | Hrs. | 140 | $ - 0 | |
| Safety & Health Manager (SHM) | Hrs. | 100 | $ - 0 | |
| Clerical | Hrs. | 100 | $ - 0 | |
| Total Section A- Home Office Personnel | $ - 0 | |||
| B. Field Office Personnel | Fully Burdened Binding Capped Labor Rate (Hourly) | Units | Quantity | Subtotal |
| Site Superintendent / On-Site Supervisor | Hrs. | 170 | $ - 0 | |
| Environmental Engineer | Hrs. | 170 | $ - 0 | |
| Chemist | Hrs. | 150 | $ - 0 | |
| Site Safety & Health Officer | Hrs. | 170 | $ - 0 | |
| Contractor Quality Control Supervisor | Hrs. | 170 | $ - 0 | |
| Regulatory Specialist | Hrs. | 170 | $ - 0 | |
| Hazardous Waste/Transportation Specialist | Hrs. | 170 | $ - 0 | |
| Process Engineer | Hrs. | 110 | $ - 0 | |
| Total Section B- Field Office Personnel | $ - 0 | |||
| C. Other Direct Costs | Units | Quantity | Subtotal | |
| Materials, supplies, equipment, and other ODCs (plugged number) | Each | 15,000.00 | $ 15,000.00 | |
| Markup Rate (Base Period Year 1) | 0% | |||
| Markup Amount (Base Period Year 1) | $ - 0 | |||
| Subtotal | $ 15,000.00 | |||
| Subcontract effort (plugged number) | Each | 125,000.00 | $ 125,000.00 | |
| Markup Rate (Base Period Year 1) | 0% | |||
| Markup Amount (Base Period Year 1) | $ - 0 | |||
| Subtotal | $ 125,000.00 | |||
| Total Section C | $ 140,000.00 | |||
| Total Estimated Cost (A+B+C) | ||||
| Total Estimated Cost | $ 140,000.00 | |||
| Profit | ||||
| Profit Rate | 0% | |||
| Profit Amout | $ - 0 | |||
| Year 1 Total | $ 140,000.00 |
| Year 2- (Base Period) | ||||
| A. Home Office Personnel | Fully Burdened Binding Capped Labor Rate (Hourly) | Units | Quantity | Subtotal |
| Program Manager | Hrs. | 60 | $ - 0 | |
| Project Manager | Hrs. | 220 | $ - 0 | |
| Senior Contract Manager | Hrs. | 80 | $ - 0 | |
| Procurement Specialist | Hrs. | 140 | $ - 0 | |
| Safety & Health Manager (SHM) | Hrs. | 100 | $ - 0 | |
| Clerical | Hrs. | 100 | $ - 0 | |
| Total Section A- Home Office Personnel | $ - 0 | |||
| B. Field Office Personnel | Fully Burdened Binding Capped Labor Rate (Hourly) | Units | Quantity | Subtotal |
| Site Superintendent / On-Site Supervisor | Hrs. | 170 | $ - 0 | |
| Environmental Engineer | Hrs. | 170 | $ - 0 | |
| Chemist | Hrs. | 150 | $ - 0 | |
| Site Safety & Health Officer | Hrs. | 170 | $ - 0 | |
| Contractor Quality Control Supervisor | Hrs. | 170 | $ - 0 | |
| Regulatory Specialist | Hrs. | 170 | $ - 0 | |
| Hazardous Waste/Transportation Specialist | Hrs. | 170 | $ - 0 | |
| Process Engineer | Hrs. | 110 | $ - 0 | |
| Total Section B- Field Office Personnel | $ - 0 | |||
| C. Other Direct Costs | Units | Quantity | Subtotal | |
| Materials, supplies, equipment, and other ODCs (plugged number) | Each | 15,000.00 | $ 15,000.00 | |
| Markup Rate (Base Period Year 2) | 0% | |||
| Markup Amount (Base Period Year 2) | $ - 0 | |||
| Subtotal | $ 15,000.00 | |||
| Subcontract effort (plugged number) | Each | 125,000.00 | $ 125,000.00 | |
| Markup Rate (Base Period Year 2) | 0% | |||
| Markup Amount (Base Period Year 2) | $ - 0 | |||
| Subtotal | $ 125,000.00 | |||
| Total Section C | $ 140,000.00 | |||
| Total Estimated Cost (A+B+C) | ||||
| Total Estimated Cost | $ 140,000.00 | |||
| Profit | ||||
| Profit Rate | 0% | |||
| Profit Amount | $ - 0 | |||
| Year 2 Total | $ 140,000.00 |
| Year 3- (Base Period) | ||||
| A. Home Office Personnel | Fully Burdened Binding Capped Labor Rate (Hourly) | Units | Quantity | Subtotal |
| Program Manager | Hrs. | 60 | $ - 0 | |
| Project Manager | Hrs. | 220 | $ - 0 | |
| Senior Contract Manager | Hrs. | 80 | $ - 0 | |
| Procurement Specialist | Hrs. | 140 | $ - 0 | |
| Safety & Health Manager (SHM) | Hrs. | 100 | $ - 0 | |
| Clerical | Hrs. | 100 | $ - 0 | |
| Total Section A- Home Office Personnel | $ - 0 | |||
| B. Field Office Personnel | Fully Burdened Binding Capped Labor Rate (Hourly) | Units | Quantity | Subtotal |
| Site Superintendent / On-Site Supervisor | Hrs. | 170 | $ - 0 | |
| Environmental Engineer | Hrs. | 170 | $ - 0 | |
| Chemist | Hrs. | 150 | $ - 0 | |
| Site Safety & Health Officer | Hrs. | 170 | $ - 0 | |
| Contractor Quality Control Supervisor | Hrs. | 170 | $ - 0 | |
| Regulatory Specialist | Hrs. | 170 | $ - 0 | |
| Hazardous Waste/Transportation Specialist | Hrs. | 170 | $ - 0 | |
| Process Engineer | Hrs. | 110 | $ - 0 | |
| Total Section B- Field Office Personnel | $ - 0 | |||
| C. Other Direct Costs | Units | Quantity | Subtotal | |
| Materials, supplies, equipment, and other ODCs (plugged number) | Each | 15,000.00 | $ 15,000.00 | |
| Markup Rate (Base Period Year 3) | 0% | |||
| Markup Amount (Base Period Year 3) | $ - 0 | |||
| Subtotal | $ 15,000.00 | |||
| Subcontract effort (plugged number) | Each | 125,000.00 | $ 125,000.00 | |
| Markup Rate (Base Period Year 3) | 0% | |||
| Markup Amount (Base Period Year 3) | $ - 0 | |||
| Subtotal | $ 125,000.00 | |||
| Total Section C | $ 140,000.00 | |||
| Total Estimated Cost (A+B+C) | ||||
| Total Estimated Cost | $ 140,000.00 | |||
| Profit Rate | ||||
| Profit Rate | 0% | |||
| Profit Amount | $ - 0 | |||
| Year 3 Total | $ 140,000.00 |
| Year 4- (Option Period Year 1) | ||||
| A. Home Office Personnel | Fully Burdened Binding Capped Labor Rate (Hourly) | Units | Quantity | Subtotal |
| Program Manager | Hrs. | 60 | $ - 0 | |
| Project Manager | Hrs. | 220 | $ - 0 | |
| Senior Contract Manager | Hrs. | 80 | $ - 0 | |
| Procurement Specialist | Hrs. | 140 | $ - 0 | |
| Safety & Health Manager (SHM) | Hrs. | 100 | $ - 0 | |
| Clerical | Hrs. | 100 | $ - 0 | |
| Total Section A- Home Office Personnel | $ - 0 | |||
| B. Field Office Personnel | Fully Burdened Binding Capped Labor Rate (Hourly) | Units | Quantity | Subtotal |
| Site Superintendent / On-Site Supervisor | Hrs. | 170 | $ - 0 | |
| Environmental Engineer | Hrs. | 170 | $ - 0 | |
| Chemist | Hrs. | 150 | $ - 0 | |
| Site Safety & Health Officer | Hrs. | 170 | $ - 0 | |
| Contractor Quality Control Supervisor | Hrs. | 170 | $ - 0 | |
| Regulatory Specialist | Hrs. | 170 | $ - 0 | |
| Hazardous Waste/Transportation Specialist | Hrs. | 170 | $ - 0 | |
| Process Engineer | Hrs. | 110 | $ - 0 | |
| Total Section B- Field Office Personnel | $ - 0 | |||
| C. Other Direct Costs | Units | Quantity | Subtotal | |
| Materials, supplies, equipment, and other ODCs (plugged number) | Each | 15,000.00 | $ 15,000.00 | |
| Markup Rate (Option Period Year 1) | 0% | |||
| Markup Amount (Option Period Year 1) | $ - 0 | |||
| Subtotal | $ 15,000.00 | |||
| Subcontract effort (plugged number) | Each | 125,000.00 | $ 125,000.00 | |
| Markup Rate (Option Period Year 1) | 0% | |||
| Markup Amount (Option Period Year 1) | $ - 0 | |||
| Subtotal | $ 125,000.00 | |||
| Total Section C | $ 140,000.00 | |||
| Total Estimated Cost (A+B+C) | ||||
| Total Estimated Cost | $ 140,000.00 | |||
| Profit | ||||
| Profit Rate | 0% | |||
| Profit Amount | $ - 0 | |||
| Year 4 (Option Period Year 1) Total | $ 140,000.00 |
| Year 5- (Option Period Year 2) | ||||
| A. Home Office Personnel | Fully Burdened Binding Capped Labor Rate (Hourly) | Units | Quantity | Subtotal |
| Program Manager | Hrs. | 60 | $ - 0 | |
| Project Manager | Hrs. | 220 | $ - 0 | |
| Senior Contract Manager | Hrs. | 80 | $ - 0 | |
| Procurement Specialist | Hrs. | 140 | $ - 0 | |
| Safety & Health Manager (SHM) | Hrs. | 100 | $ - 0 | |
| Clerical | Hrs. | 100 | $ - 0 | |
| Total Section A- Home Office Personnel | $ - 0 | |||
| B. Field Office Personnel | Fully Burdened Binding Capped Labor Rate (Hourly) | Units | Quantity | Subtotal |
| Site Superintendent / On-Site Supervisor | Hrs. | 170 | $ - 0 | |
| Environmental Engineer | Hrs. | 170 | $ - 0 | |
| Chemist | Hrs. | 150 | $ - 0 | |
| Site Safety & Health Officer | Hrs. | 170 | $ - 0 | |
| Contractor Quality Control Supervisor | Hrs. | 170 | $ - 0 | |
| Regulatory Specialist | Hrs. | 170 | $ - 0 | |
| Hazardous Waste/Transportation Specialist | Hrs. | 170 | $ - 0 | |
| Process Engineer | Hrs. | 110 | $ - 0 | |
| Total Section B- Field Office Personnel | $ - 0 | |||
| C. Other Direct Costs | Units | Quantity | Subtotal | |
| Materials, supplies, equipment, and other ODCs (plugged number) | Each | 15,000.00 | $ 15,000.00 | |
| Markup Rate (Option Period Year 2) | 0% | |||
| Markup Amount (Option Period Year 2) | $ - 0 | |||
| Subtotal | $ 15,000.00 | |||
| Subcontract effort (plugged number) | Each | 125,000.00 | $ 125,000.00 | |
| Markup Rate (Base Period Year 2) | 0% | |||
| Markup Amount (Base Period Year 2) | $ - 0 | |||
| Subtotal | $ 125,000.00 | |||
| Total Section C | $ 140,000.00 | |||
| Total Estimated Cost (A+B+C) | ||||
| Total Estimated Cost | $ 140,000.00 | |||
| Profit | ||||
| Profit Rate | ||||
| Profit Amount | $ - 0 | |||
| Year 5 (Option Period Year 2) Total | $ 140,000.00 |
| 6 Month Extension | ||||
| A. Home Office Personnel | Fully Burdened Binding Capped Labor Rate (Hourly) | Units | Quantity | Subtotal |
| Program Manager | Hrs. | 30 | $ - 0 | |
| Project Manager | Hrs. | 100 | $ - 0 | |
| Senior Contract Manager | Hrs. | 30 | $ - 0 | |
| Procurement Specialist | Hrs. | 60 | $ - 0 | |
| Safety & Health Manager (SHM) | Hrs. | 40 | $ - 0 | |
| Clerical | Hrs. | 40 | $ - 0 | |
| Total Section A- Home Office Personnel | $ - 0 | |||
| B. Field Office Personnel | Fully Burdened Binding Capped Labor Rate (Hourly) | Units | Quantity | Subtotal |
| Site Superintendent / On-Site Supervisor | Hrs. | 80 | $ - 0 | |
| Environmental Engineer | Hrs. | 80 | $ - 0 | |
| Chemist | Hrs. | 70 | $ - 0 | |
| Site Safety & Health Officer | Hrs. | 80 | $ - 0 | |
| Contractor Quality Control Supervisor | Hrs. | 80 | $ - 0 | |
| Regulatory Specialist | Hrs. | 80 | $ - 0 | |
| Hazardous Waste/Transportation Specialist | Hrs. | 80 | $ - 0 | |
| Process Engineer | Hrs. | 60 | $ - 0 | |
| Total Section B- Field Office Personnel | $ - 0 | |||
| C. Other Direct Costs | Units | Quantity | Subtotal | |
| Materials, supplies, eqpt, and other ODCs (plugged number) | Each | 7,500.00 | $ 7,500.00 | |
| Markup Rate (Option Period Year 2) | 0.00% | |||
| Markup Amount (Option Period Year 2) | $ - 0 | |||
| Subtotal | $ 7,500.00 | |||
| Subcontract effort (plugged number) | Each | 62,500.00 | $ 62,500.00 | |
| Markup Rate (Option Period Year 2) | 0.00% | |||
| Markup Amount (Option Period Year 2) | $ - 0 | |||
| Subtotal | $ 62,500.00 | |||
| Total Section C | $ 70,000.00 | |||
| Total Estimated Cost (A+B+C) | ||||
| Total Estimated Cost | $ 70,000.00 | |||
| Fixed Fee | ||||
| Fixed Fee Rate | 0.00% | |||
| Fixed Fee Amount | $ - 0 | |||
| 6-Month Extension Total | $ 70,000.00 |
Total (All 5 Years & Extension) >>>> $ 770,000.00
W9128F-20-R-0038 PRAC IGE
24 FEB 2020
File details come from the government source that posted it. Updated .