This abstract of offers document summarizes bids received in response to Solicitation Number W9128F-20-B-0018 for a bank stabilization project at the Oahe Dam Outlet Works Channel. Three offers were received for furnishing all plant, labor, materials, and equipment to provide approximately 2,000 cubic yards of earth embankment, 5,000 square yards of geotextile, and 10,000 tons of riprap stone protection at the project site. Offerors provided unit pricing for items including riprap, geotextile fabric, embankment material, and choking material, with total bid prices ranging from $765,675 to $1,268,750. The apparent low offeror was A.G.E. Corporation of Fort Pierre, South Dakota at $765,675. The contracting office for this project is the Department of the Army Corps of Engineers Engineering District Omaha.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| KO Bid Abstract - Force Main Bank Stablization Oahe Dam.pdf | ||
| Site Visit Sign-in Sheet.pdf | ||
| Force Main Bank Stabilization Oahe Dam SD.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2. DATE ISSUED3. DATE OPENED
I CERTIFY THAT I HAVE OPENED, READ AND
AND RECORDED ON THIS ABSTRACT
ALL OFFERS RECEIVED IN RESPONSE DATE SIGNED
X C. REASONABLE CONTRACT
7A 7B 7C D. E. F.
ITEM # DESCRIPTION OF OFFER ITEM EST. QUANTITY UNIT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNTUNIT PRICE ESTIMATED AMOUNT
CLIN 0001
All work complete to supply and install riprap as specified in the specifications and drawings.
8,600
TON
$68.40 $588,240.00 59.00$ $507,400.00 43.50$ $374,100.00
CLIN 0002
All work complete to supply and install geotextile fabric as specified
5,000
SY
2.40$ $12,000.00 5.50$ $27,500.00 3.00$ $15,000
CLIN 0003
All work complete to supply, haul, place, and compact embankment (cut/fill) for bank stabilization as specified.
1,500
CY
27.550$ $41,325.00 21.50$ $32,250.00 20.00$ $30,000.00
CLIN 0004
All work complete to supply and install choking material as specified.
TON
31.15$ $1,557.50 35.00$ $1,750.00 60.00$ $3,000.00
CLIN 0005
All remaining work including but not limited to:
mobilization, demobilization, access road, shaping, and maintenance, and all other work except the work listed in the items above and below. 1
JOB
XXX $96,200.00 $175,000.00 $33,000.00
$739,322.50 $743,900.00 $455,100.00
CLIN 0006
All work complete to supply and install riprap as specified.
2,050
TON
68.40$ $140,220.00 59.00$ $120,950.00 43.50$ $89,175.00
CLIN 0007
All work complete to supply and install geotextile fabric as specified.
1,250
SY
2.40$ $3,000.00 5.50$ $6,875.00 3.00$ $3,750.00
CLIN 0008
All work complete to supply, haul, place, and compact embankment (cut/fill) for bank stabilization as specified.
CY
27.55$ $6,887.50 21.50$ $5,375.00 20.00$ $5,000.00
CLIN 0009
All work complete to supply and install choking material as specified.
TON
31.15$ $311.50 35.00$ $350.00 60.00$ $600.00
CLIN 0010
All Remaing Work
JOB
XXX $11,700.00 $41,400.00 $5,000.00
$162,119.00 $174,950.00 $103,525.00
CLIN 0011
All work complete to supply and install riprap as specified.
2,050
TON
68.40$ $140,220.00 59.00$ $120,950.00 43.50$ $89,175.00
CLIN 0012
All work complete to supply and install geotextile fabric as specified.
1,250
SY
2.40$ $3,000.00 5.50$ $6,875.00 3.00$ $3,750.00
CLIN 0013
All work complete to supply, haul, place, and compact embankment (cut/fill) for bank stabilization as specified.
CY
27.55$ $6,887.50 21.50$ $5,375.00 20.00$ $5,000.00
CLIN 0014
All work complete to supply and install choking material as specified.
TON
31.15$ $311.50 35.00$ $350.00 60.00$ $600.00
CLIN 0015
All remaining work
JOB
XXX $11,700.00 $41,400.00 $5,000.00
$162,119.00 $174,950.00 $103,525.00
CLIN 0016
All work complete to supply and install riprap as specified
2,050
TON
68.40$ $140,220.00 59.00$ $120,950.00 43.50$ $89,175.00
CLIN 0017
All work complete to supply and install geotextile fabric as specified.
1,250
SY
2.40$ $3,000.00 5.50$ $6,875.00 3.00$ $3,750.00
CLIN 0018
All work complete to supply, haul, place, and compact embankment (cut/fill) for bank stabilization as specified
CY
27.55$ $6,887.50 21.50$ $5,375.00 20.00$ $5,000.00
CLIN 0019
All work complete to supply and install choking material as specified
TON
31.15$ $311.50 35.00$ $350.00 60.00$ $600.00
CLIN 0020
All Remaining Work
JOB
XXX $11,700.00 $41,400.00 $5,000.00
$162,119.00 $174,950.00 $103,525.00
TOTAL $1,225,679.50 $1,268,750.00 $765,675.00
OMAHA, NE 68102-1618
1616 CAPITOL AVENUE
CONTRACTING DIVISION (CENWO-CT)
US ARMY CORPS OF ENGINEERS
l PAGES
9. OFFERS
TO THIS SOLICITATION
SIGNATURE
NAME AND TITLE OF CERTIFYING OFFICIAL (Type) Dean Matuszewski - Contracting Officer/ Nicole Parker - Contracting Specialist
NO. 1 NO. 2
ABSTRACT OF OFFERS - CONSTRUCTION
1. SOLICITATION NUMBER
W9128F-20-B-0018
4. ISSUING OFFICE
8. GOVERNMENT ESTIMATE
(Check A, B or C AND COMPLETE D, E AND F)
5. PROJECT TITLE
(Without Profit)
(Including Profit)
A. OFFEROR A. OFFEROR
704 W Highway 14 & 34 PO Box 1162
A. HIRED LABOR
IGE A-G-E corporation Morris Inc
Fort Pierre, SD 57532 Pierre, SD 57501
B. REASONABLE CONTRACT
Bid Security 20%
C. AMENDMENTS ACKNOWLEDGED 2
Bid Security 20%
C. AMENDMENTS ACKNOWLEDGED 2
6. NUMBER OF AMENDMENTS ISSUED 2
Force Main Bank Stablization
Oahe Dam, AD
| 2020-05-07T13:49:03-0500 | |