SEE ADDENDUM
(No Collect Calls)
W9128F19Q0021 16-Jan-2019
b. TELEPHONE NUMBER
402-995-2886
8. OFFER DUE DATE/LOCAL TIME
02:00 PM 01 Feb 2019
5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA – FAR (48 CFR) 53.212
(TYPE OR PRINT)
(SIGNATURE OF CONTRACTING OFFICER)
ADDENDA ARE
26. TOTAL AWARD AMOUNT (For Gov t. Use Only )
23.
CODE 10. THIS ACQUISITION IS
SUCH ADDRESS IN OFFER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
TELEPHONE NO.
W9128F9. ISSUED BY
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME
DANIEL D MONAHAN
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER
(TYPE OR PRINT)
30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA
0 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.
25. ACCOUNTING AND APPROPRIATION DATA
1. REQUISITION NUMBER
20.
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
W59XQG83201900
ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
. YOUR OFFER ON SOLICITATION
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
% FOR:SET ASIDE:UNRESTRICTED OR X
SMALL BUSINESSX
17a.CONTRACTOR/ CODE FACILITY
OFFEROR CODE
U.S. ARMY CORPS OF ENGINEERS, OMAHA DIST
CONTRACTING OFFICE
1616 CAPITOL AVENUE
OMAHA NE 68102-4901
18a. PAYMENT WILL BE MADE BY CODE
RATED ORDER UNDER
DPAS (15 CFR 700)
13a. THIS CONTRACT IS A
13b. RATING
CODE15. DELIVER TO CODE G6R0P00 16. ADMINISTERED BY
12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
14. METHOD OF SOLICITATION
RFQ IFB RFPX
OAHE PROJECT OFFICE
PATRICK FEIOCK
USAED, OMAHA CENWO-OD-OA 28563 POWERHOUSE RD
PIERRE SD 57501-6174
TEL: 605-845-2252 FAX:
FAX:
TEL: SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
8(A)
HUBZONE SMALL
BUSINESS
SIZE STANDARD:
$18,000,000
NAICS:
561720
X
OFFER DATED
29. AWARD OF CONTRACT: REF.
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
EMAIL:
TEL:
31c. DATE SIGNED
SEE SCHEDULE
SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT
24.22.21.19.
WOMEN-OWNED SMALL BUSINESS (WOSB)
ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
(CONTINUED)
PAGE 2 OF68
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
37. CHECK NUMBER
FINALPARTIALCOMPLETE
36. PAYMENT35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER
FINAL
33. SHIP NUMBER
PARTIAL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
STANDARD FORM 1449 (REV. 2/2012) BACK
Prescribed by GSA – FAR (48 CFR) 53.212
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
SEE SCHEDULE
20.
SCHEDULE OF SUPPLIES/ SERVICES
21.
QUANTITY UNIT
22. 23.
UNIT PRICE
24.
AMOUNT
19.
ITEM NO.
Section SF 1449 - CONTINUATION SHEET
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job OA-Hazelton Rec Area Cleaning
FFP
HAZELTON AREA AS PER BID SHEDULE.OA2180-60511 OA19 REC FIELD
REC MGMT [464482]
FOB: Destination
MILSTRIP: W59XQG83201900
PURCHASE REQUEST NUMBER: W59XQG83201900
NET AMT
0002 1 Job OA-Beaver Creek Rec Area Cleaning
FFP
BEAVER CREEK AREA AS PER BID SHEDULE.OA2180-60511 OA19 REC
FIELD REC MGMT [464482]
FOB: Destination
0003 1 Job OA-Beaver Creek East Rec Area Cleaning
FFP
BEAVER CREEK EAST AREA AS PER BID SHEDULE.OA2180-60511 OA19
REC FIELD REC MGMT [464482]
0004 1 Job OA-Cattail Bay Rec Area Cleaning
FFP
CATTAIL BAY AREA AS PER BID SHEDULE.OA2180-60511 OA19 REC
FIELD REC MGMT [464482]
1001 1 Job OPTION OA-Hazelton Rec Area Cleaning
FFP
HAZELTON AREA AS PER BID SHEDULE.OA2180-60511 OA19 REC FIELD
REC MGMT [464482]
1002 1 Job OPTION OA-Beaver Creek Rec Area Cleaning
FFP
BEAVER CREEK AREA AS PER BID SHEDULE.OA2180-60511 OA19 REC
FIELD REC MGMT [464482]
1003 1 Job OPTION OA-Beaver Creek East Rec Area Cleaning
FFP
BEAVER CREEK EAST AREA AS PER BID SHEDULE.OA2180-60511 OA19
REC FIELD REC MGMT [464482]
1004 1 Job OPTION OA-Cattail Bay Rec Area Cleaning
FFP
CATTAIL BAY AREA AS PER BID SHEDULE.OA2180-60511 OA19 REC
FIELD REC MGMT [464482]
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government 0002 Destination Government Destination Government 0003 Destination Government Destination Government 0004 Destination Government Destination Government 1001 Destination Government Destination Government 1002 Destination Government Destination Government 1003 Destination Government Destination Government 1004 Destination Government Destination Government
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 POP 01-APR-2019 TO
31-OCT-2019
N/A OAHE PROJECT OFFICE
PATRICK FEIOCK
USAED, OMAHA CENWO-OD-OA 28563
POWERHOUSE RD
PIERRE SD 57501-6174
605-845-2252
G6R0P00
0002 POP 01-APR-2019 TO
31-OCT-2019
N/A (SAME AS PREVIOUS LOCATION)
0003 POP 01-APR-2019 TO
N/A (SAME AS PREVIOUS LOCATION)
0004 POP 01-APR-2019 TO
N/A (SAME AS PREVIOUS LOCATION)
1001 POP 01-APR-2020 TO
31-OCT-2020
N/A (SAME AS PREVIOUS LOCATION)
1002 POP 01-APR-2020 TO
N/A (SAME AS PREVIOUS LOCATION)
1003 POP 01-APR-2020 TO
N/A (SAME AS PREVIOUS LOCATION)
1004 POP 01-APR-2020 TO
N/A (SAME AS PREVIOUS LOCATION)
BID SCHEDULE
BID SHEDULE
BASE YEAR
(PERFORMANCE PERIOD 01 April 19 THRU 31 October 19)
CLIN 0001 - HAZELTON
Line Task Freq. UI Cost/UI Total Cost
0001AA
Campground and Boat Ramp
(1) 61 required cleanups as scheduled and a maximum of 10 additional cleanups as directed by the COR.
71 EA $ $
0001AB
Boat Ramp
(2) 17 required cleanups as scheduled and a maximum of 5 additional cleanups as directed by the COR.
22 EA $ $
CLIN 0001 HAZELTON – Total Cost Total $
CLIN 0002 BEAVER CREEK
0002AA
Complete Campground
(1) 68 required cleanups as scheduled and a maximum of 10 additional cleanups with comfort station open as directed by COR
78 EA $ $
0002AB
Campground Partial Closure
(2) 15 required cleanups as scheduled and a maximum of 5 additional cleanups as directed by the COR.
20 EA $ $
0002AC
Boat Ramp
(3) 17 required cleanups as scheduled and a maximum of 5 additional cleanups as directed by the COR.
22 EA $ $
CLIN 0002 BEAVER CREEK – Total Cost Total $
CLIN 0003 BEAVER CREEK EAST
0003AA
(1) 22 required cleanups as scheduled and a maximum of 5 additional cleanups as directed by the COR
27 EA $ $
CLIN 0003 BEAVER CREEK EAST– Total Cost Total $
CLIN 0004 CATTAIL BAY
0004AA
(1) 60 required cleanups as scheduled and a maximum of 10 additional cleanups as directed by the COR.
70 EA $ $
CLIN 0004 CATTAIL BAY – Total Cost Total $
Grand Total
Total Offer for Oahe Janitorial Services – Base Year Grand Total $
BID SCHEDULE
OPTION YEAR 1
(PERFORMANCE PERIOD 01 April 20 THRU 31 October 20)
CLIN 1001 - HAZELTON
Line Task Freq. UI Cost/UI Total Cost
1001AA
Campground and Boat Ramp
(1) 60 required cleanups as scheduled and a maximum of 10 additional cleanups as directed by the COR.
70 EA $ $
1001AB
Boat Ramp
(2) 17 required cleanups as scheduled and a maximum of 5 additional cleanups as directed by the COR.
22 EA $ $
CLIN 1001 HAZELTON – Total Cost Total $
CLIN 1002 BEAVER CREEK
1002AA
Complete Campground
(1) 67 required cleanups as scheduled and a maximum of 10 additional cleanups with comfort station open as directed by COR
77 EA $ $
1002AB
Campground Partial Closure
(2) 14 required cleanups as scheduled and a maximum of 5 additional cleanups as directed by the COR.
19 EA $ $
1002AC
Boat Ramp
(3) 17 required cleanups as scheduled and a maximum of 5 additional cleanups as directed by the COR.
22 EA $ $
CLIN 1002 BEAVER CREEK – Total Cost Total $
CLIN 1003 BEAVER CREEK EAST
1003AA
(1) 21 required cleanups as scheduled and a maximum of 5 additional cleanups as directed by the COR
26 EA $ $
CLIN 1Beaver Creek 003 BEAVER CREEK EAST– Total Cost Total $
CLIN 1004 CATTAIL BAY
1004AA
(1) 60 required cleanups as scheduled and a maximum of 10 additional cleanups as directed by the COR.
70 EA $ $
CLIN 1004 CATTAIL BAY – Total Cost Total $
Grand Total
Total Offer for Oahe Janitorial Services – Option Year Grand Total $
PERFORMANCE WORK STATEMENT
PERFORMANCE WORK STATEMENT (PWS)
COMPLETE CLEANUP SERVICES
NORTH DAKOTA RECREATION AREAS
US ARMY COPRS OF ENGINEERS
(OAHE PROJECT/LAKE OAHE)
28563 Powerhouse Road Pierre, SD 57501
1.0 General Information.
1.1 Background. The Corps of Engineers manages/maintains four (4) recreation areas that are used frequently by the visiting public during April through October. Complete cleaning service are required to provide a quality and safe experience for our visiting public.
1.2 Scope of Work. The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, other items and non-personal services necessary to provide complete cleanup of approximately 79 acres in recreation areas for the Corps of Engineers (Oahe Project/Lake Oahe) as defined in this Performance Work Statement (PWS). The government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the contractor who, in turn is responsible to the government. This is a fixed priced, performance based service contract where the government defines and measures desired outcomes, while contractor methods are generally not constrained or directed.
1.3 Period of Performance. The period of performance shall be for one (1) Base Year of 12 months and one (1) 12-month option years. The Period of Performance reads as follows:
Base Year: 01 April 2019 through 31 March 2020
Active period of performance: 1 April 2019 through 31 October 2019 Inactive period of performance: 1 November 2019 through 31 March 2020
Option Year 1: 01 April 2020 through 31 March 2021
Active period of performance: 1 April 2020 through 31 October 2020 Inactive period of performance: 1 November 2020 through 31 March 2021
*Note: The Contractor is not required to perform any services during the inactive period of performance.
1.4 Contractor Personnel
1.4.1 The contractor shall perform all work under this contract using his or her own forces except as provided in Paragraph 1.4.2 Subcontracting. Employees who perform this work shall be qualified persons on the contractor’s own payroll. One individual is required to perform the services stated in this PWS. All contractor personnel and regular subcontractors shall maintain a neat and clean appearance. All contractor vehicles shall be registered, licensed, and insured to meet all State and local laws. The contractor employees shall be skilled in and capable of performing the work under this contract. All employees of the contractor or subcontractor shall be at least 16 years of age or older.
1.4.2 Subcontracting. The contractor shall not subcontract any work without written approval of the Contracting Officer. Compliance with the provisions of this contract by subcontractors shall be the responsibility of the contractor.
1.5 Quality Control
1.5.1 The contractor shall designate, in writing, an employee who shall serve as the contact for matters involving quality and performance or nonperformance of the required work stated in this PWS. The employee(s) shall be qualified and fully competent with full authority to act for, and on behalf of, the contractor as necessary to insure that the required work is performed in accordance with the standards contained herein. The contractor shall furnish the above written designation to the Contracting Officer’s Representative (COR) no later than the first day of work. The contractor shall include the name(s), address(s), and telephone number(s) of the responsible individual(s).
1.5.2 The Contracting Officer reserves the right to disapprove any individual whom he considers incompetent to perform the work required. The Contracting Officer will provide a written notice of any disapproval to the contractor.
1.6 Quality Assurance. The government will provide a Quality Assurance Surveillance Plan (QASP) to ensure that the Contractor is performing the services required by this PWS in an acceptable manner. The Government may use Quality Assurance Evaluators (QAE(s)) to provide assistance with the quality assurance methods.
1.6.1 The government has the right to inspect all services called for by the contract, to the extent practicable at all times and places during the term of the contract. The government shall perform inspections in a manner that will not delay the work.
1.6.2 If any of the services do not conform to contract requirements, the government may require the contractor to perform the services in conformity with contract requirements and at no increase in cost. If the contract requirements are not met after a second attempt the government may (1) require the contractor to take necessary action to ensure that future performance conforms to contract requirements and (2) reduce the contract price to reflect the reduced value of the services performed.
1.6.2.1 Upon verification of a validated customer complaint or corrective action report, the COR will notify the contractor that they are required to re-perform specific services. The Contractor shall notify the COR within 24 hours of completion and a re-inspection shall be conducted.
1.6.3 The government may take action, if the contractor fails to perform the services again or to take the necessary action to ensure future performance is in conformity with the contract requirements. The government may (1) by contract, or otherwise, perform the services and charge to the contractor any cost incurred by the government that related to the performance of such service or (2) terminate the contract in whole or in part
1.6.4 The contractor is responsible to replace/repair any damage to government property due to negligence, at his or her own cost. The government may take action, if the contractor fails to replace/repair any damage to government property. The government may (1) by contract, or otherwise, replace/repair damaged government property and charge to the contractor any cost incurred by the government to replace/repair any damage or (2) make a determination to not exercise any future option periods on the contract.
1.7 Hours of Operation. The contractor is responsible for conducting business, between the hours of 8:00 a.m. to 6:00 p.m. Sunday thru Saturday to include Memorial Day, 4th of July, Labor Day, and Columbus Day. The contractor is not required to work on any other Federal holiday or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. The Contractor must maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential.
1.8 Pre-Work Meeting. Prior to commencing any activities, the contractor shall arrange a Pre-work Meeting with the COR. The Meeting shall discuss the work requirements, scheduling, submittal process, review of the Activity Hazard Analysis (AHA), and Abbreviated Accident Prevention Plan (AAP). At least one (1) week prior to commencing work, the Contractor shall coordinate their proposed work schedule with the COR.
1.9. Submittals. Prior to commencement of services, the Contractor shall submit the following documents to the COR for review and approval:
a. Activity Hazard Analysis (AHA);
b. Abbreviated Accident Prevention Plan (APP);
c. List of who will perform work on this contract;
d. Proof of Insurance for Contractors and Subcontractors;
e. Safety Data Sheets (SDS): The Contractor shall supply SDS’s for all cleaning solutions, detergents, and materials used on the project.
1.10 Standards and Regulations. The Contractor shall perform to the standards in the contract and comply with all Local, State, and Federal Regulations during the services performed. The Contractor is responsible for ascertaining the extent to which these regulations affect the operations resulting from this contract. The Contractor shall comply will all applicable regulations. Applicable regulations include, but are not limited to the following:
a. Code of Federal Regulations (CFR), Title 36, Chapter III, Part 327, Rules and Regulations Governing Public Use on Corps of Engineers Water Resource Development Projects EP 1165-2-316 (http://www.publications.usace.army.mil/Portals/76/Publications/EngineerPamphlets/EP_1165-2- 316.pdf?ver=2013-08-22-104526-670)
b. Engineering Manual (EM) 385-1-1 (USACE – Safety and Health Requirements Manual), dated November 2014; http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf
c. Occupational Safety and Health Standards (29 CFR 1910);
1.10.1 Activity Hazard Analysis (AHA). The contractor shall prepare the AHA in accordance with Paragraph 01.A.14 or 01.A.15 of the EM 385-1-1. If using Paragraph 01.A.15, prepare the AHA IAW Figure 1-2.
Note: Contractors and other individual employer’s typically use Job Safety Analyses (JSAs), Job Hazard Analyses (JHAs), or similar Risk Management assessment tools. The government considers equivalent to, and acceptable substitutes for, the USACE’s AHA provided the data collected is the same as that required by the AHA, commensurate with the type of services the contractor is performing.
1.10.2 Abbreviated Accident Prevention Plan (APP). EM 385-1-1 in its entirety may be too complex for the type of work performed under these contracts; contractors may reference Appendix A, for abbreviated Accident Prevention Plan (APP). The contractor shall only need to submit items in Appendix A that are pertinent to the contract. The contractor shall use a qualified person to prepare the site-specific abbreviated Accident Prevention Plan (APP). The contractor shall prepare the APP in accordance with the format and requirements of the EM 385-1-1 and supplemented herein. The contractor shall sign and submit the APP for approval prior to the start of work onsite.
1.11 Physical Security
1.11.1 The contractor shall be responsible for safeguarding all government facilities, property, and materials provided for contractor use. The contractor shall secure at all times all government facilities, property, and materials. Specific security conditions may change based on threats to national defense, and based on the risk of specific facilities to these threats. The contractor shall abide by these changing conditions at all times, as applicable.
1.11.2 Key Control. The contractor shall ensure all keys issued by the government are not lost, stolen, duplicated, or used by unauthorized persons.
1.11.2.1 The Contractor shall immediately report to the COR any occurrences of lost or stolen keys.
1.11.2.2 In the event keys, other than master keys are lost or stolen, the contractor may be required, upon written direction of the COR, to re-key or replace the affected lock or locks without cost to the government. The government may, however, at its option, replace the affected lock or locks or perform re-keying and deduct the cost of such from the monthly payment due the contractor. If a master key is lost or stolen, the government may need to replace all locks and keys for that system. The government will deduct the total cost to replace the locks and keys from the contractor’s monthly invoice.
1.11.2.3 The contractor shall prohibit the use of keys issued by the government by any persons other than the contractor’s employees. The contractor shall not facilitate access of secured areas to persons other than contractor personnel or subcontractors engaged in performance of contract work requirements.
1.12 Antiterrorism/Operation Security Requirements
1.12.1. Access and General Protection/Security Policy and Procedures. All contractor and all associated subcontractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.
1.12.1 Pre-screen candidates using E-Verify Program. The Contractor must pre‐screen candidates using the E‐ verify Program (http://www.dhs.gov/E‐Verify) website to meet the established employment eligibility requirements.
The vendor must ensure that the candidate has two valid forms of government issued identification to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible candidates must be provided to the COR no later than three (3) business days after the initial contract award.
1.13 Payment
1.13.1 The government will make payment monthly, after the government has inspected and accepted the services, and the government has reviewed, approved, and processed the contractor’s invoice. The contractor shall submit the invoice to the COR and/or any other person that has been designated in the contract to receive the invoice.
1.13.2 The contractor must provide the contractor’s name, address, contract number, period of services completed (i.e., for the month of January or for the period of performance of January 1 through February 23), CLIN number and specific quantities of work performed (i.e., 1 Month, 40 days, 100 acres, etc.), and total requested, for an invoice to be considered proper. The contractor shall submit the invoice by the fifth (5th) of the month for services completed the previous month or submit the invoice upon completion of all services, in accordance with the period of performance stated in the CLIN. The invoice shall be sent to John Voeller 3319 University Drive, Bismarck ND 58504.
2.0 Definitions. The following definitions and descriptions apply wherever the word(s) or phrase(s) is/are stated in this PWS:
Acceptable Level of Performance (ALP): The maximum percent defective, the maximum number of defects per hundred units, or the number of defects in a lot considered satisfactory on the average. The allowable leeway or variance from a standard before the government will reject the specific service.
Contracting Officer’s Representative (COR): means an individual designated an authorized in writing by the Contracting Officer to perform specific technical or administrative functions.
Performance-Based Contract (FAR 2.101): Structuring all aspects of an acquisition around the purpose of the work to be performed with the contract requirements set forth in clear, specific, and objective terms with measurable outcomes as opposed to either the manner by which the work is to be performed or broad and imprecise.
Performance Requirements Summary (PRS): The PRS shows contract requirements, the component requirements related to each contract requirement, the price of each work requirement as a percentage of the associated contract requirement (Fixed Price Contracts), the standard of performance, and the acceptable level of performance (ALP) for each work requirement.
Quality Assurance Surveillance Plan (QASP): An organized written document used by the Government for quality assurance surveillance. Document contains sampling/evaluation guides, checklists, and the performance requirements summary (PRS).
3.0 Government Furnished Items and Services
3.1 Services. The Government will provide garbage hauling service for contractor. All garbage will need to be taken to the Beaver Creek Recreation Area where there will be dumpsters for the Contractor to place trash. The Contractor will not be responsible for payment of dumpsters. Dumpsters will also be placed in the Beaver Creek Recreation Area for users to throw trash.
3.2 Facilities. The Government shall NOT make available to the Contractor any space or facilities for storage of equipment or supplies.
3.3 Utilities. The Government will provide water for cleaning at no extra cost to the contractor while the water system is working or may be obtained from other sources approved by the COR. If obtained from sources other than the Government water supply systems, all arrangements and payments, if any, will be made by the Contractor. The Contractor shall instruct employees in utilities conservation practices. The contractor shall be responsible for operating under conditions that preclude the waste of utilities, which include turning off the water faucets or valves after using the required amount to accomplish cleaning vehicles and equipment.
3.4 Equipment. The government shall provide dumpsters for disposal of refuse.
3.5 Materials. N/A
4.0 Contractor Furnished Items and Responsibilities
4.1 General. The Contractor shall furnish all supplies, equipment, facilities and services required to perform work under this contract that are not listed under Section 3 of this PWS.
4.2 Materials. The Contractor shall provide toilet paper, liquid hand soap, detergent, disinfectants, cleaners, solvents, insecticides, and germicidal solutions to meet the requirements under this PWS. The Contractor must supply the COR with Material Data Safety Sheets for any product used on the contract.
4.3 Equipment. The contractor shall provide mops, brooms, buckets, cleaning cloths, scrub brushes, pressure washer, etc. to meet the requirements under this PWS.
4.4 Monthly Submittals. The Contractor shall, on a monthly basis and not later than the fifth (5th) day of the month, submit to the Natural Resource Specialist an invoice (Attachment 4) for cleaning services provided the preceding month. The Contractor shall, on a monthly basis also submit a monthly summary of weekly logs or immediately upon request of the COR. This log will indicate the date and time cleanup was completed; any vandalism, maintenance problems, or etc.; will be noted on the log. All work recorded on invoices that cannot be substantiated by the daily log reports will not be paid. Daily log sheets much be returned to the COR at the end of the month or as often as the COR deems necessary. Attachment 2 is the only acceptable format that will be used for submission of the daily log reports.
5.0 Specific Tasks
5.1 Basic Services. The contractor shall provide services as outlined in this contract. The Contractor shall follow the attached schedule for complete cleanup (Attachment 1). Additional cleanups shall be determined by current condition of the indicated areas with approval received from the COR. The Contractor shall submit and changes to the work schedule on Thursday by 1300, for work being done the next week.
5.2 Complete Cleanup. Specific Services to be performed as One Complete Cleanup. Any valuable items found during the cleaning will be turned into the Park Ranger Office by 10:00 a.m. the day after the item was found.
Hazelton Boat Ramp – (Vault Toilet Cleaning, Refuse Collection (includes Garbage Cans and Fish Cans), Litter Pickup, Cleaning Fish-Cleaning Tables, and Picnic Table and/or Park Bench Cleaning).
Hazelton Campground and Boat Ramp - (Vault Toilet Cleaning, Refuse Collection (includes Garbage Cans and Fish Cans), Litter Pickup, Cleaning Fish-Cleaning Tables, Campfire Ring-Grill and /or Pedestal Grill Cleaning, Picnic Table and/or Park Bench Cleaning, and Camp Pad Post Cleaning).
Beaver Creek Complete Campground - (Vault Toilet Cleaning, Refuse Collection (includes Garbage Cans and Fish Cans), Litter Pickup, Cleaning Fish-Cleaning Tables, Comfort Station Cleaning, Campfire Ring-Grill and /or Pedestal Grill Cleaning, Picnic Table and/or Park Bench Cleaning, Camp Pad Post Cleaning, Picnic Shelter and Trailer Dump Station Cleaning).
Beaver Creek Partial Closure - (Vault Toilet Cleaning, Refuse Collection (includes Garbage Cans and Fish Cans), Litter Pickup, Cleaning Fish-Cleaning Tables, Campfire Ring-Grill and /or Pedestal Grill Cleaning, Picnic Table and/or Park Bench Cleaning, Camp Pad Post Cleaning, Picnic Shelter and Trailer Dump Station Cleaning).
Beaver Creek Boat Ramp - (Vault Toilet Cleaning, Refuse Collection (includes Garbage Cans and Fish Cans), Litter Pickup, and Cleaning Fish-Cleaning Tables).
Beaver Creek East - (Vault Toilet Cleaning, Litter Pickup, Campfire Ring-Grill and /or Pedestal Grill Cleaning, and Picnic Table and/or Park Bench Cleaning).
Cattail Bay - (Vault Toilet Cleaning, Refuse Collection (includes Garbage Cans and Fish Cans), Litter Pickup, Cleaning Fish-Cleaning Tables, Campfire Ring-Grill and /or Pedestal Grill Cleaning, and Picnic Table and/or Park Bench Cleaning).
5.2.1 Vault toilet cleaning. The contractor shall clean all vault toilets in a sanitary, presentable, and usable manner.
The fixtures, stools, walls, doors, ceilings, floors, window sills, concrete apron in and around of vault toilets will be cleaned. Upon completion of the cleaning operation, the vault toilet shall have an appearance free of dirt, cleaning solution, disinfectant, standing water, water spots and be left ready for the public to use. The contractor shall re-fill all toilet tissue, so that it does not run out prior to the next scheduled service. The contractor shall apply germicide and disinfectant on appropriate surfaces. The contractor shall apply deodorizer in the toilets after cleaning. If a stain, mark or substance cannot be removed by reasonable cleaning efforts, the COR shall be advised. The Contractor shall promptly report any mechanical or maintenance problems encountered so that they may be corrected by the Government.
5.2.2 Refuse collection. All refuse containers (a container that is up to 32 gallons in size) and lids will be cleaned inside and outside. All trash, litter, debris or residue (including but not limited to cigarette butts, match books, bottle caps, snap tabs and paper) within or immediately adjacent to the facility being serviced shall be removed. The cleaned refuse containers will be returned to its original position and a new plastic liner shall be installed in containers (as needed) and the lids reinstalled on the containers. The location of refuse containers will be determined by the COR; the Contractor will be responsible to ensure that the refuse containers are in their assigned location after cleaning. Refuse container racks will be cleaned. The Contractor shall promptly report any mechanical or maintenance problems encountered so that they may be corrected by the Government.
5.2.3 Litter pickup. These areas surround and include vault toilets, picnic and day use areas, picnic shelters/gazebos, boat ramps, parking areas, ditch lines within 50 feet of access and/or circulation roads, trails, mowed areas, turnarounds, dumpsters, etc. The Contractor will not be required to clean up fallen trees resulting from wind storms, nor will they be required to remove timber or other drift deposited ashore during high water or by high winds. The Contractor will be required to clean up litter, trash and debris from the refuse containers and dumpsters that may get scattered over the areas by high winds or animals.
5.2.4 Waterborne Fish Cleaning Tables and Fish Cleaning Tables. The tables with approximate dimensions of up to five (5) x eight (8) feet tops, area under and around the tables (includes concrete pad), fish refuse container (a container that is up to 24 gallons in size) and lids, protective shelter and fixtures shall be kept free of dirt, debris, stains, residue, spider webs, insect nests, bird nests, bird droppings, fish remains, and shall be left ready for the public to use. The cleaned fish refuse containers will be returned to its original position and a new plastic liner shall be installed in containers and the lids reinstalled on the containers. If a stain, mark or substance cannot be removed by reasonable cleaning efforts, the COR shall be advised. The Contractor shall promptly report any mechanical or maintenance problems encountered so that they may be corrected by the Government.
5.2.5 Comfort Station Cleaning. The fixtures, walls, partitions, ceilings, floors, floor drains, ledges, rafters, roof supports, showers, toilets, stool lids, waterborne facilities, mirrors, sinks, soap trays, faucets, handicap bars, plumbing fixtures, metal louvers, water fountain, sidewalks and concrete apron in and around the Comfort Station shall be free of dirt, spider webs, bird and insect nests, debris, and trash. All surfaces should have a condition free of all dirt, oil, lotions, soap residue, calcium deposits, or other foreign matter. All surfaces shall be free of standing water and water spots. Soap dispensers shall be filled. The contractor shall re-fill all toilet tissue, so that it does not run out prior to the next scheduled service. The contractor shall apply germicide and disinfectant on appropriate surfaces. If a stain, mark or substance cannot be removed by reasonable cleaning efforts, the COR shall be advised.
The Contractor shall promptly report any mechanical or maintenance problems encountered so that they may be corrected by the Government.
5.2.6 Trailer Dump Station Cleaning. The fixtures, sidewalks and concrete apron in and around the Trailer Dump Station shall be cleaned to remove all cobwebs, litter, and debris from the fixtures and from the immediate vicinity.
If a stain, mark or substance cannot be removed by reasonable cleaning efforts, the COR shall be advised. The Contractor shall promptly report any mechanical or maintenance problems encountered so that they may be corrected by the Government.
5.2.7 Picnic Table and Park Bench Cleaning. The picnic tables and park benches, areas under and around the tables or benches shall be kept free of dirt, debris, stains, residue, spider webs, insect nests, bird droppings, and shall be left ready for the public to use. The cleaned tables and benches will be returned to their original position. There should be one (1) picnic table at every numbered camp pad. If a stain, mark or substance cannot be removed by reasonable cleaning efforts, the COR shall be advised. The Contractor shall promptly report any mechanical or maintenance problems encountered so that they may be corrected by the Government.
5.2.8 Camp Pad Post Cleaning. Camp pad posts will be cleaned so that all insects, insect nests, bird nests, cobwebs, dirt and any debris or residue left from insects or animals will be removed from the front and back of camp pad post. The camp pad post shall be dried of any water and shall be left ready for public use. The Contractor shall promptly report any mechanical or maintenance problems encountered so that they may be corrected by the Government.
5.2.9 Campfire Ring-Grill and Pedestal Grill Cleaning. All ashes and unburned material (including nails) will be removed from grills and surrounding ground and disposed of in an approved refuse site. All grated grill tops will be cleaned to remove all foreign matter including but not limited to food particles, paper, trash, ashes, grease, and etc. The grills shall be left clean and ready for the public to use. This cleanup task does not preclude the Contractor from normal litter pickup around or in the Campfire Ring-Grills and Pedestal Grills. The Contractor shall promptly report any mechanical or maintenance problems encountered so that they may be corrected by the Government.
5.2.10 Picnic Shelter cleaning. The fixtures, walls, ceilings, floors, ledges, rafters, roof supports, sidewalks and concrete apron in and around the Picnic Shelters will be cleaned. Upon completion of the cleaning operation, the Picnic Shelters shall be free of dirt, spider webs, insect nests, bird droppings, bird nests, cleaning solution, disinfectant, water spots, and will be left ready for the public to use, which will include that all picnic tables assigned to Shelters shall be arranged in the facilities. If a stain, mark or substance cannot be removed by reasonable cleaning efforts, the Government Representative shall be advised. The Contractor shall promptly report any mechanical or maintenance problems encountered so that they may be corrected by the Government.
5.2.11 Re-performance: Contractor shall be notified when re-performance is required by a validated customer complaint or corrective action report. The contractor shall re-perform grounds maintenance operations within 8 hours of notification and shall notify the COR within 24 hours of completion and a re-inspection shall be conducted.
6.0 Performance Requirements Summary. The contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.
Performance Objective
(The Service required— usually a shall statement)
Standard Performance Threshold (This is the maximum error rate. It could possibly be “Zero deviation from standard”)
Method of Surveillance
PRS # 1.
The contractor shall clean all areas in a sanitary, presentable, and usable manner in accordance with Paragraph 5.2.
a. The contractor shall complete all cleanups to maintain a clean and presentable manner in accordance with Paragraphs 5.2.1-5.2.10
Areas are cleaned and maintained to customer satisfaction at 100% of visits. No more than (2) validated customer complaints per month.
Periodic surveillance by the Government and Validated Customer Complaint received by the
COR.
PRS # 2
The contractor shall be required to report and replace/repair any damage to government property due to Contractor’s negligence in accordance with Paragraph 1.6.4
a. Report and replace/repair and damage to Government Property as specified in Paragraph 1.6.4
No more than 1 valid discrepancies and/or 1 legitimate complaint from the public within a 30 day period can be cause for contract termination.
Periodic surveillance by the Government and Validated Customer Complaint received by the
COR.
PRS # 3
The contractor shall re-perform grounds maintenance operations within 8 hours of notification and shall notify the COR within 24 hours of completion in accordance with Paragraph 5.2.11
a. The Contractor shall preform re-performance and notify the COR as specified in Paragraph 5.2.11
Zero deviation from standard 100 percent inspection
7.0 Attachments
7.1 Attachment 1 – Cleanup Inventory and schedule
7.2 Attachment 2 – Contractors Daily Cleanup Worksheet
7.3 Attachment 3 – Contractors Safety Meeting Worksheet
7.4 Attachment 4 – Invoice
7.5 Attachment 5 – Equipment and Work Experience Log
7.6 Attachment 6 – Estimated Workload Data
7.7 Attachment 7 – Maps of Areas
ATTACHMENT 1
OAHE RECREATION CLEANING NORTH DAKOTA INVENTORY
Area Vault Toilets
Garbage Cans
Fish Cans
Litter Pickup Acres
Fish Cleaning Tables
Grills Picnic Shelters/ Gazebos
Picnic Tables/Park Benches
Camp Pad Posts
Comfort Stations
Dump Station
Hazelton Boat Ramp
Single
2 8 3.5 1 -- -- 3 -- -- --
Hazelton Campground and Boat Ramp
Single
14 8 18 1 30 -- 33 30 -- --
Beaver Creek Complete Campground
Single
6 10 43 1 65 1 75 62 1 1
Beaver Creek Partial Closure
Single
-- 10 14.5 1 21 1 30 21 -- 1
Beaver Creek Boat Ramp
Single
-- 10 10 1 -- -- 2 -- -- --
Beaver Creek East
Single
- -- 10 -- 20 -- 10 -- -- --
Cattail Bay 4 Single
6 8 8 1 10 -- 13 -- -- --
FREQUENCY SCHEDULE FOR CLEANUP SERVICES
Area 04/01 –4/30, 10/01-10/31
05/01 –05-11, 09/08-09/30
05/12 – 09/07
Hazelton Boat Ramp
M, F -- --
Hazelton Campground and
Boat Ramp
-- M,TH M, TH, SA
Beaver Creek Complete
Campground
-- -- SU, M, TH, SA
Beaver Creek Campground
Partial Closure
-- M,TH,SA --
Beaver Creek Boat Ramp
M,F -- --
Beaver Creek East -- TH TH
Cattail Bay -- M, TH M, TH, SA
LEGEND
SU - SUNDAY M - MONDAY TU - TUESDAY W – WEDNESDAY TH - THURSDAY
F - FRIDAY SA - SATURDAY
ATTACHMENT 2
OAHE RECREATION CLEANING ND CONTRACTOR DAILY LOG - CLEANUP SERVICES
CONTRACTOR_______________________ DATE_________________
AREA START TIME STOP TIME
HAZELTON _____________ _____________
BEAVER CREEK
CAMPGROUND _____________ _____________
BEAVER CREEK
EAST _____________ _____________
CATTAIL BAY _____________ _____________
AREA THAT WORK WAS PERFORMED
AREAS WITH ANY PROBLEMS OR VANDALISM__________________________________
WEATHER CONDITIONS____________________________________________________
CONTRACTOR'S SIGNATURE___________________________________________________
ATTACHMENT 3
OAHE RECREATION CLEANING ND CONTRACTOR SAFETY MEETING MINUTES
DATE:___________
TIME:___________
EMPLOYEES PRESENT: TOPICS DISCUSSED:
1.______________________________ 1.________________________
2.______________________________ 2.________________________
3.______________________________ 3.________________________
4.______________________________ 4.________________________
5.______________________________ 5.________________________
6.______________________________ 6.________________________
MINUTES OF THE MEETING:
CONTRACTOR'S SIGNATURE:___________________________
DATE:___________________________
ATTACHMENT 4
CONTRACT NUMBER: W9128F19
FROM__________THRU__________
OAHE ND RECREATION CLEANING INVOICE
AREAS REQ COMPLETE CLEANUPS ADDITIONAL WORK CLEANUPS TOTAL
# $ TOTAL # $ TOTAL
HAZELTON BOAT
RAMP
HAZELTON COMPLETE
BEAVER CREEK EAST
BEAVER CREEK BOAT
RAMP
BEAVER CREEK
PARTIAL
CAMPGROUND
BEAVER CREEK
CAMPGROUND
CATTAIL BAY
GRAND TOTAL
MAN HOURS ___________
DATE INVOICE RECEIVED _________________
PAYMENT TO BE MADE TO:
W9128F19Q0021
ATTACHMENT 5
EQUIPMENT AND WORK EXPERIENCE
TYPE CAPACITY MANUFACTURER AGE AND LOCATION
CONDITION
EXPERIENCE RECORD
ATTACHMENT 6
ESTIMATED WORKLOAD DATA
BASE YEAR
ITEM NAME
ESTIMATED QUANTITY
0001AA Hazelton Campground and Boat Ramp 61 Cleanup
0001AA Hazelton Campground and Boat Ramp Additional 10 Cleanup
0001AB Hazelton Boat Ramp 17 Cleanup
0001AB Hazelton Boat Ramp Additional 5 Cleanup
0002AA Beaver Creek Complete Campground 68 Cleanup
0002AA Beaver Creek Complete Campground Additional 10 Cleanup
0002AB Beaver Creek Campground Partial Closure 15 Cleanup
0002AB Beaver Creek Campground Partial Closure Additional 5 Cleanup
0002AC Beaver Creek Boat Ramp 17 Cleanup
0002AC Beaver Creek Boat Ramp Additional 5 Cleanup
0003AA Beaver Creek East 22 Cleanup
0003AA Beaver Creek East Additional 5 Cleanup
0004AA Cattail Bay 60 Cleanup
0004AA Cattail Bay Additional 10 Cleanup
ESTIMATED WORKLOAD DATA
OPTION YEAR
ITEM
NAME
ESTIMATED QUANTITY
1001AA Hazelton Campground and Boat Ramp
60 Cleanup
1001AA Hazelton Campground and Boat Ramp Additional 10 Cleanup
1001AB Hazelton Boat Ramp 17 Cleanup
1001AB Hazelton Boat Ramp Additional 5 Cleanup
1002AA Beaver Creek Complete Campground 67 Cleanup
1002AA Beaver Creek Complete Campground Additional 10 Cleanup
1002AB Beaver Creek Campground Partial Closure 15 Cleanup
1002AB Beaver Creek Campground Partial Closure Additional 5 Cleanup
1002AC Beaver Creek Boat Ramp 17 Cleanup
1002AC Beaver Creek Boat Ramp Additional 5 Cleanup
1003AA Beaver Creek East 21 Cleanup
1003AA Beaver Creek East Additional 5 Cleanup
1004AA Cattail Bay 60 Cleanup
1004AA Cattail Bay Additional 10 Cleanup
ATTACHMENT 7
MAPS OF AREAS
MAP 1 Overview
MAP 2 Hazelton Cleaning
MAP 3 Beaver Creek Campground Cleaning
MAP 4 Beaver Creek North East
MAP 5 Beaver Creek South East
MAP 6 Cattail Bay
CLAUSES INCORPORATED BY REFERENCE
52.204-7 System for Award Management OCT 2018 52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-13 System for Award Management Maintenance OCT 2018 52.204-16 Commercial and Government Entity Code Reporting JUL 2016 52.204-18 Commercial and Government Entity Code Maintenance JUL 2016 52.212-4 Contract Terms and Conditions--Commercial Items OCT 2018 52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011 52.225-25 Prohibition on Contracting with Entities Engaging in Certain
Activities or Transactions Relating to Iran-- Representation and Certifications.
AUG 2018
52.232-40 Providing Accelerated Payments to Small Business Subcontractors
DEC 2013
52.245-9 Use And Charges APR 2012 252.203-7000 Requirements Relating to Compensation of Former DoD
Officials
SEP 2011
252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.203-7005 Representation Relating to Compensation of Former DoD
Officials
NOV 2011
252.204-7000 Disclosure Of Information OCT 2016 252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7008 Compliance With Safeguarding Covered Defense Information
Controls
OCT 2016
252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting
OCT 2016
252.223-7008 Prohibition of Hexavalent Chromium JUN 2013 252.232-7003 Electronic Submission of Payment Requests and Receiving
Reports
JUN 2012
252.232-7010 Levies on Contract Payments DEC 2006 252.237-7000 Notice Of Special Standards Of Responsibility DEC 1991 252.237-7001 Compliance With Audit Standards MAY 2000 252.237-7010 Prohibition on Interrogation of Detainees by Contractor
Personnel
JUN 2013
252.243-7001 Pricing Of Contract Modifications DEC 1991
CLAUSES INCORPORATED BY FULL TEXT
52.204-17 OWNERSHIP OR CONTROL OF OFFEROR (JUL 2016)
(a) Definitions. As used in this provision--
Commercial and Government Entity (CAGE) code means—
(1) An identifier assigned to entities located in the United States or its outlying areas by the Defense Logistics Agency (DLA) Commercial and Government Entity (CAGE) Branch to identify a commercial or government entity;
or
(2) An identifier assigned by a member of the North Atlantic Treaty Organization (NATO) or by the NATO Support and Procurement Agency (NSPA) to entities located outside the United States and its outlying areas that the DLA Commercial and Government Entity (CAGE) Branch records and maintains in the CAGE master file. This type of code is known as a NATO CAGE (NCAGE) code.
Highest-level owner means the entity that owns or controls an immediate owner of the offeror, or that owns or controls one or more entities that control an immediate owner of the offeror. No entity owns or exercises control of the highest level owner.
Immediate owner means an entity, other than the offeror, that has direct control of the offeror. Indicators of control include, but are not limited to, one or more of the following: Ownership or interlocking management, identity of interests among family members, shared facilities and equipment, and the common use of employees.
(b) The Offeror represents that it [ ___ ] has or [ ___ ] does not have an immediate owner. If the Offeror has more than one immediate owner (such as a joint venture), then the Offeror shall respond to paragraph (c) and if applicable, paragraph (d) of this provision for each participant in the joint venture.
(c) If the Offeror indicates ``has'' in paragraph (b) of this provision, enter the following information:
Immediate owner CAGE code:
Immediate owner legal name: ___
(Do not use a ``doing business as'' name)
Is the immediate owner owned or controlled by another entity?:
[ ___ ] Yes or [ ___ ] No.
(d) If the Offeror indicates ``yes'' in paragraph (c) of this provision, indicating that the immediate owner is owned or controlled by another entity, then enter the following information:
Highest-level owner CAGE code:
Highest-level owner legal name:
(Do not use a ``doing business as'' name)
(End of provision)
52.212-1 Addendum; Instructions to Quoters—Commercial Items
This solicitation is being advertised as a Best Value procurement. See FAR 52.212-2 Addendum; Evaluation— Commercial Items for specific information to be submitted with your quote.
Please provide the following information with your quote:
Company’s Name as it appears on SAM:
Company’s Address as it appears on SAM:
CAGE CODE:
DUNS:
TIN:
(a) North American Industry Classification System (NAICS) code and small business size standard. The NAICS code and small business size standard for this acquisition appear in Block 10 of the solicitation cover sheet (SF 1449). However, the small business size standard for a concern which submits a quotation in its own name, but which proposes to furnish an item which it did not itself manufacture, is 500 employees.
(b) Submission of quotations. Submit quotations to the office specified in this solicitation at or before the exact time specified in this solicitation. Electronic quotations are preferred over paper responses, unless other arrangements have been made. Send completed quotation to Daniel Monahan at daniel.monahan@usace.army.mil .
Quotations may be submitted on the SF 1449, letterhead stationery, or as otherwise specified in the solicitation. As a minimum, offers must show --
(1) The solicitation number;
(2) The time specified in the solicitation for receipt of quotations;
(3) The name, address, and telephone number of the quoter;
(4) A technical description of the items being quoted in sufficient detail to evaluate compliance with the…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.