Redacted_FINAL_JA_ClearCreek_AshlandNE.PDF

PDF 537 KB Posted

Attached to
Clear Creek Levee Emergency Protection Project Federal contract opportunity
Solicitation number
W9128F19B0012
Issued by
Department of the Army Corps of Engineers Engineering District Omaha

About this file

J&A for Clear Creek Levee Project

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOR OFFICIAL USE ONLY

JUSTIFICATION REVIEW DOCUMENT

OTHER THAN FULL AND OPEN COMPETITION

PROJECT/EQUIPMENT: CONTROL NO: CECT-NWO-19-12

After-the-Fact J&A for Western Sarpy/Clear Creek Platte River Right Bank Levee near Ashland, Nebraska AUTHORITY: 10 U.S.C. 2304(c)(2) as implemented by FAR 6.302-2, Unusual and Compelling Urgency.

AMOUNT: $2,348,000

Control No.: CECT-NWO-19-12

AFTER-THE-FACT JUSTIFICATION AND APPROVAL (J&A)

FOR OTHER THAN FULL AND OPEN COMPETITION

WESTERN SARPY/CLEAR CREEK PLATTE RIVER RIGHT BANK LEVEE – ASHLAND, NE

1. CONTRACTING AGENCY: United States Army Corps of Engineers, Northwestern Division, Omaha District (NWO), Contracting Division, Civil Works Branch (CECT-NWO-C), 1616 Capitol Avenue, Omaha, NE 68102.

2. DESCRIPTION OF ACTION: A firm fixed- price contract was executed for the construction of initial levee breach repairs along the Western Sarpy/Clear Creek Platte River Right Bank levee near Ashland, Nebraska. The contract was funded with Flood Control and Coastal Emergency (FCCE) Class 210 and 310 funds.

a verbal approval request was sent to the Office of Senior Contacting Official (SCO) on March 28, 2019 with approval received the same day. The award was in the amount of $2,348,000.

3. DESCRIPTION OF SUPPLIES/SERVICES OR NATURE OF CONSTRUCTION: The project generally consisted of construction of minimal flood protection structures and all ancillary work and features along the Platte River to protect public infrastructure located near Ashland, Nebraska from projected high river stages and the breach in Western Sarpy/Clear Creek Flood Reduction Project Right Bank levee. This levee is located on the right bank of the Platte River in Saunders County, NE. It consists of an earthen levee with a ten foot top width and grassed side slopes. The downstream location ties in with high ground in several housing developments and then extends into the Camp Ashland Training Site. The depth of the breach from the levee crest to the water surface in the scour hole was measured at approximately twelve (12) feet. In addition, there was a scour along the riverside slope at the toe of the riprap protection. The purpose of this action was to provide initial flood protection at the specified breached areas of the levee. The solicitation for this requirement had no options and neither did the contract award. The period of performance was advertised as 7 calendar days.

4. AUTHORITY CITED: 10 U.S.C. 2304(c)(2), as implemented by FAR 6.302-2, DFARS 206.302-2(b) and PGI 206.302-2(b)(i) – Unusual and compelling urgency.

5. REASON FOR AUTHORITY CITED: Expedited contracting procedures using limited competition was necessary to advertise, award, and perform a time-critical initial levee breach repair along the Platte River system, a tributary to the Missouri River.

a. Background.

A bomb cyclone storm dumped one (1) to three (3) inches (with localized higher amounts) of warm rainfall on a heavy wet snowpack across the region between Tuesday, March 12 and Thursday, March 14. The rain fell on a plains snowpack that held 3 or more inches of snow water equivalent in Nebraska and Iowa with event higher amounts in southeastern South Dakota. In north central South Dakota and North Dakota that snowmelt is forecast to occur in the coming weeks. A frost depth of up to 2 feet across the region resulted in significant runoff from the snowmelt and rainfall. Waters from this flood event came from tributaries that enter the Missouri River below the large main stem storage reservoirs. Mountain snowpack is at or slightly above normal (99% in the Garrison reach and 102% in the Fort Peck reach), Plains soils are very saturated and frost depths of up to 5 feet remains across the northern plains. Plains snowpack in South Dakota and North Dakota has a snow water equivalent 3-8 inches with some places reporting higher levels. More flooding is forecasted on the James, Vermillion and Big Sioux River basins from snowmelt. These three rivers flow unregulated in South Dakota to the Missouri River. This flooding will cause the Missouri River stages from Sioux City to Rulo, Nebraska to remain high with slight increases possible. These second peaks are not forecasted to be higher than the recent peak stages we have witnessed.

The issue at hand is widespread unregulated flows across western Iowa, eastern Nebraska and southeastern South Dakota which have caused devastating flooding on multiple tributary streams and extensive overtopping and breaching of the Missouri River levees south of Omaha.

The Missouri River levee system has been severely compromised. Emergency management teams continue to support local, state, and county flood fight actions and the district is establishing a 2019 Omaha System Restoration Team to expedite advanced interim measures as well as overall restoration of the federal levee system along the Missouri River.

A significant portion of the more than 500 miles of levees on the Missouri, Platte, and Elkhorn rivers have experienced flood damaged. USACE Omaha is currently tracking more than fifty

(50) breaches to address. The Platte, Niobrara and Elkhorn Rivers along with other unregulated tributaries overwhelmed the Missouri River levee systems. The record river levels exceeded the levee systems’ design capacity from Omaha to Rulo, Nebraska and into the Kansas City District AOR. The enormous river flows severely compromised Federal and Non-Federal levee systems downstream of Omaha on the Missouri River as well as south of Fremont, NE on the Platte River.

Rapid melting caused ice jams on the Platte River, coupled with excessive rain caused rapid increases in stages on the Platte River from 7.1 ft. to 12.6 ft. in a period of hours. This resulted in overtopping of the Clear Creek levee and a breach in the area that was overtopped. Record high flows occurred which adversely affected the general population in the surrounding area.

Consequently, emergency levee repairs were required to be constructed at Western Sarpy/Clear Creek Platte River Right Bank levee on an urgent basis to prevent additional flooding events. The project generally consisted of time-critical construction/repair of emergency flood protection structures and all ancillary work and features along the Platte River to protect public infrastructure located near Ashland, Nebraska from projected high river stages.

The States of Iowa and Nebraska recently declared a local state of emergency, allowing the states to seek assistance from the federal government. Impact of further flooding would be catastrophic. USACE must provide expeditious contracting solutions to ensure prompt and comprehensive emergency operations to fulfill this critical levee protection mission. Damaged communities will face additional serious health and safety hazards, both personal and ecological, and devastating economic loss if repair efforts are delayed.

b. Justification.

Overtopping and a breach occurred at the Western Sarpy/Clear Creek Platte River Right Bank levee. The depth of the breach from the levee crest to the water surface in the scour hole was measured at approximately twelve (12) feet. In addition, there was a scour along the riverside slope at the toe of the riprap protection. Plans and specifications for these levee repairs were completed on March 28, 2019 allowing just a few days to advertise, award and construct the initial levee breach repairs. Since there was an open breach in the levee, even a moderate rainfall event could have flooded additional residential housing areas on the Platte River downstream from the breach. Consequently, expedited contracting procedures were utilized.

Solicitation was issued via email to all interested vendors on March 28th. A site visit was held at 9:00 A.M. on March 29th with bid opening occurring later that day at 5:00 P.M. Amendment 0001 was issued to replace Davis Bacon Wage Decision rates from Douglas County to Saunders County and update the statement of work to clarify Fill Borrow Source requirements.

Due to the total amount of funding not being available on the 29th, award was postponed until the next day, March 30th to a small business concern, Pruss Excavation of Dodge, NE in the amount of $2,348,000.

c. Impact.

Based upon the breach of the existing Western Sarpy/Clear Creek Platte River Right Bank levee, further flooding could have continued to pose a significant threat to human life, infrastructure, property, and damage to surrounding environment near Ashland, Nebraska.

If no action was taken, the next high water event would have flooded several housing developments along the Platte River downstream of the impacted area. That area includes approximately 583 residences with a population of 500. In addition, flooding often requires emergency rescues and endangers those who are vulnerable, especially those that are located in the local hospital and schools. Flood waters also can contaminate water treatment plants which pollutes drinking water. Flood waters can also cause the growth and spread of disease and mold. If the breach in Clear Creek had not been repaired immediately, the threat and damages as stated above could have increased significantly.

d. Alternatives.

Competitive sealed bidding procedures were utilized as there was a defined scope of work, quantities, and time to contact interested parties. The only alternatives were issuing a task order under the Rapid Disaster Infrastructure (RDI) or use of a letter contract. RDI is a MATOC requiring a source selection process. The prime contractors under RDI are not local to eastern Nebraska and would have taken longer to mobilize and establish local contacts. A letter contract could have been awarded to a local contractor, but it would be undefinitized and also put the contracting officer in weak negotiating position, possibly resulting in an unreasonable price. A competitively bid contract that allows maximum participation of local contractors is the most expeditious acquisition strategy and it realizes the benefit of competition as envisioned by the Competition in Contracting Act.

6. EFFORTS TO OBTAIN COMPETITION: Competition was sought to the maximum extent possible given the circumstances. Contracting personnel contacted approximately seventy-five

(75) firms in the Nebraska area by email to advise them of the site visit and bid opening time on March 29, 2019. Approximately twenty-six (26) companies attended the site visit on March 29, 2019. Five (5) bids were ultimately received.

7. ACTIONS TO INCREASE COMPETITION: Approximately seventy-five (75) companies received e-mail notifications of the contracting opportunity. See Paragraphs 6 and 8 for additional explanation.

8. MARKET RESEARCH: Market research consisted of one contract specialist conducting market research to identify interesting sources using FBO, internet searches, and recommendations from the local levee sponsor. At the time market research was conducted, there were seventy-five (75) firms identified as being interested parties. To date, over ninety

(90) interested parties are included in the Omaha District’s 2019 Interested Vendor listing and the list continues to grow daily. All parties capable of performing specific requirements continue to receive e-mail notifications of contracting opportunities.

9. INTERESTED SOURCES: This action was not synopsized due to the time critical nature of the requirement and is covered by an exception under FAR 5.202(a)(2). Efforts were made to ensure that bids were solicited from as many potential sources as practicable. Twenty-six (26) construction companies attended the pre-bid conference and site visit. It is possible that other interested sources existed, but were not able to respond on the short notice provided.

10. OTHER FACTORS: Due to the unusual and compelling urgency of threatening life, health, and safety, the contracting officer waived the following: synopsis; small business coordination;

legal review; bid guarantee; performance and payment bonds; small business subcontracting plan; and several clauses that are not practical or enforceable under the emergency circumstances. These activities or contract features were not feasible to accomplish in the short duration available for this acquisition, especially considering a deployed contracting officer utilizing paper copies. The typical sealed bid procurement takes approximately 90 days to complete once a requirement is received, including 45 days for pre-award activities and 30 days for advertisement. By using these expedited contracting processes, the contracting officer went from requirement to award in less than 3 days. If this expedited process was not used, Ashland, NE would still incur significant damages as the Missouri River and its tributaries continue to rise due to snowmelt and spring rainfall.