RFQ.pdf

PDF 413 KB Posted

Attached to
Well Decommissioning
Solicitation number
W9128F-18-Q-0030
Issued by

About this file

Decommission irrigation wells for the US Army Corps of Engineers, Gavins Point Project

View the file

Other files

File Type Posted
Well_Decomm_Technical_Exhibits.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEE ADDENDUM

(No Collect Calls)

W9128F18Q0030 12-Feb-2018

b. TELEPHONE NUMBER

402-667-2556

8. OFFER DUE DATE/LOCAL TIME

02:00 PM 28 Feb 2018

5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA – FAR (48 CFR) 53.212

(TYPE OR PRINT)

(SIGNATURE OF CONTRACTING OFFICER)

ADDENDA ARE

26. TOTAL AWARD AMOUNT (For Gov t. Use Only )

23.

CODE 10. THIS ACQUISITION IS

SUCH ADDRESS IN OFFER

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT

BELOW IS CHECKED

TELEPHONE NO.

W9128F9. ISSUED BY

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME

MONICA E DWYER

2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER

(TYPE OR PRINT)

30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA

0 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.

25. ACCOUNTING AND APPROPRIATION DATA

1. REQUISITION NUMBER

20.

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

ARE NOT ATTACHED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

. YOUR OFFER ON SOLICITATION

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

% FOR:SET ASIDE:UNRESTRICTED OR X

SMALL BUSINESSX

17a.CONTRACTOR/ CODE FACILITY

OFFEROR CODE

U.S. ARMY CORPS OF ENGINEERS, OMAHA DIST

CONTRACTING OFFICE

1616 CAPITOL AVENUE

OMAHA NE 68102-4901

18a. PAYMENT WILL BE MADE BY CODE

RATED ORDER UNDER

DPAS (15 CFR 700)

13a. THIS CONTRACT IS A

13b. RATING

CODE15. DELIVER TO CODE 968812 16. ADMINISTERED BY

12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

14. METHOD OF SOLICITATION

RFQ IFB RFPX

COE GAVINS POINT PRJT OFC NTR RSC

LINDA FILO

USAED, OMAHACENWO-OD-GP-N

55245 HIGHWAY 121

CROFTON NE 68730

TEL: 402-667-2569 FAX:

FAX:

TEL: SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

8(A)

HUBZONE SMALL

BUSINESS

SIZE STANDARD:

$15,000,000

NAICS:

238910

X

OFFER DATED

29. AWARD OF CONTRACT: REF.

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

EMAIL:

TEL:

31c. DATE SIGNED

SEE SCHEDULE

SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT

24.22.21.19.

WOMEN-OWNED SMALL BUSINESS (WOSB)

ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

EDWOSB

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

(CONTINUED)

PAGE 2 OF40

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

32b. SIGNATURE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

37. CHECK NUMBER

FINALPARTIALCOMPLETE

36. PAYMENT35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER

FINAL

33. SHIP NUMBER

PARTIAL

38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE

42a. RECEIVED BY (Print)

42b. RECEIVED AT (Location)

42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS

STANDARD FORM 1449 (REV. 2/2012) BACK

Prescribed by GSA – FAR (48 CFR) 53.212

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

SEE SCHEDULE

20.

SCHEDULE OF SUPPLIES/ SERVICES

21.

QUANTITY UNIT

22. 23.

UNIT PRICE

24.

AMOUNT

19.

ITEM NO.

W9128F18Q0030

Section SF 1449 - CONTINUATION SHEET

SOLICITATION INSTRUCTIONS

Instructions to Quoters – Commercial Items

This solicitation is being advertised as a BEST VALUE procurement. See FAR 52.212-2 Addendum; Evaluation— Commercial Items for specific information to be submitted with your quote.

(a) North American Industry Classification System (NAICS) code and small business size standard. The NAICS code and small business size standard for this acquisition appear in Block 10 of the solicitation cover sheet (SF 1449). However, the small business size standard for a concern which submits a quotation in its own name, but which proposes to furnish an item which it did not itself manufacture, is 500 employees.

(b) Submission of quotations. Submit quotations to the office specified in this solicitation at or before the exact time specified in this solicitation. Quotations may be submitted on the SF 1449, letterhead stationery, or as otherwise specified in the solicitation.

Quotations are due by February 28, 2018 @ 3:00 P.M. Send your completed quotation package to the attention of monica.e.dwyer@usace.army.mil. Electronic quotations are preferred over paper responses, unless other arrangements have been made with the individual identified above.

As a minimum, quotations must show-

(1) The solicitation number W9128F18Q0030

(2) The time specified in the solicitation for receipt of quotations;

(3) The name, address and telephone number of the quoter;

(4) A technical description of the items being quoted in sufficient detail to evaluate compliance with the requirements in the solicitation. This may include product literature or other documents, if necessary;

(5) Terms of any express warranty;

(6) Price and any discount terms;

(7) “Remit to” address, if different than mailing address;

(8) A completed copy of the representations and certifications at FAR 52.212-3 (see FAR 52.212-3(b) for those representations and certifications that the quoter shall complete electronically);

(9) Acknowledgment of Solicitation Amendments;

(10) Past performance information, when included as an evaluation factor, to include recent and relevant contracts for the same or similar items and other references (including contract numbers, points of contact with telephone numbers and other relevant information); and

(c) Reserved.

(d) Product samples. When required by the solicitation, product samples shall be submitted at or prior to the time specified for receipt of quotations. Unless otherwise specified in this solicitation, these samples shall be submitted at no expense to the Government, and returned at the sender’s request and expense, unless they are destroyed during testing.

(e) Multiple quotations. Quoters are encouraged to submit multiple quotations presenting alternative terms and conditions or commercial items for satisfying the requirements of this solicitation. Each quotation submitted will be evaluated separately.

(f) Late submissions.

(1) Quoters are responsible for submitting quotations so as to reach the Government office designated in the solicitation by the time specified in the solicitation. If no time is specified in the solicitation, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that quotations are due.

(2) Any quotation received at the Government office designated in the solicitation after the exact time specified for receipt of quotations is late and will not be considered unless it is received before purchase order issuance and the

Contracting Officer determines that accepting the late quotation would not unduly delay the acquisition.

(3) If an emergency or unanticipated event interrupts normal Government processes so that quotations cannot be received at the Government office designated for receipt of quotations by the exact time specified in the solicitation, and urgent Government requirements preclude amendment of the solicitation or other notice of an extension of the closing date, the time specified for receipt of quotations will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.

(g) Issuance of purchase order. Quotations should contain the quoter’s best technical and price terms. The Contracting Officer may reject any or all quotations. The Contracting Officer may issue a purchase order to other than the quoter with the lowest priced quotation. After the evaluation of quotations, the Contracting Officer may negotiate final terms with one or more quoters of the Government’s choice before issuing any purchase order. The Contracting Officer will not negotiate with any quoters other than those of the Government’s choice and will not use the formal source selection procedures described in FAR part 15.

(h) Multiple purchase orders. The Government may issue a purchase order for any item or group of items of a quotation, unless the quoter qualifies the quotation by specific limitations. Unless otherwise provided in the Schedule, quotations may not be submitted for quantities less than those specified. The Government reserves the right to issue a purchase order for a quantity less than the quantity quoted, at the unit prices quoted, unless the quoter specifies otherwise in the quotation.

(i) Availability of requirements documents cited in the solicitation.

(1)(i) The GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29, and copies of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained for a fee by submitting a request to-

GSA Federal Supply Service Specifications Section Suite 8100 470 East L’Enfant Plaza, SW Washington, DC 20407 Telephone (202) 619-8925 Facsimile (202) 619-8978

(ii) If the General Services Administration, Department of Agriculture, or Department of Veterans Affairs issued this solicitation, a single copy of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained free of charge by submitting a request to the addressee in paragraph (i)(1)(i) of this provision.

Additional copies will be issued for a fee.

(2) Most unclassified Defense specifications and standards may be downloaded from the following ASSIST websites:

(i) ASSIST (https://assist.dla.mil/online/start/).

(ii) Quick Search (http://quicksearch.dla.mil/).

(iii) ASSISTdocs.com (http://assistdocs.com).

(3) Documents not available from ASSIST may be ordered from the Department of Defense Single Stock Point (DoDSSP) by-

(i) Using the ASSIST Shopping Wizard (https://assist.dla.mil/wizard/index.cfm);

(ii) Phoning the DoDSSP Customer Service Desk (215) 697-2179, Mon-Fri, 0730 to 1600 EST; or

(iii) Ordering from DoDSSP, Building 4, Section D, 700 Robbins Avenue, Philadelphia, PA 19111-5094, Telephone

(215) 697-2667/2179, Facsimile (215) 697-1462.

(4) Nongovernment (voluntary) standards must be obtained from the organization responsible for their preparation, publication, or maintenance.

(j) Data Universal Numbering System (DUNS) Number. (Applies to all quotations exceeding $3,000, and quotations of $3,000 or less if the solicitation requires the Contractor to be registered in the System for Award Management (SAM) database.) The quoter shall enter, in the block with its name and address on the cover page of its quotation, the annotation “DUNS” or “DUNS+4” followed by the DUNS or DUNS+4 number that identifies the quoter’s name and address. The DUNS+4 is the DUNS number plus a 4-character suffix that may be assigned at the discretion of the quoter to establish additional SAM records for identifying alternative Electronic Funds Transfer (EFT) accounts

(see FAR Subpart 32.11) for the same concern. If the quoter does not have a DUNS number, it should contact Dun and Bradstreet directly to obtain one. A quoter within the United States may contact Dun and Bradstreet by calling 1-866-705-5711 or via the internet at http://fedgov.dnb.com/webform. A quoter located outside the United States must contact the local Dun and Bradstreet office for a DUNS number. The quoter should indicate that it is a quoter for a Government contract when contacting the local Dun and Bradstreet office.

(k) System for Award Management. Unless exempted by an addendum to this solicitation, by submission of a quotation, the quoter acknowledges the requirement that a prospective contractor shall be registered in the SAM database prior to purchase order issuance, during performance and through final payment of any contract resulting from this solicitation. If the quoter does not become registered in the SAM database in the time prescribed by the Contracting Officer, the Contracting Officer will proceed to issue the purchase order to the next otherwise successful registered quoter. Quoters may obtain information on registration and annual confirmation requirements via the SAM database accessed through https://www.acquisition.gov.

CAGE Code ______________________ DUNS Number ___________________ Tax Identification Number (TIN) ______________________________ Company Name and Address: (Should match SAM profile) Point of Contact:

Name _______________________________________ Title ________________________________________ Business Phone _______________________________ Cell Phone (if applicable) _______________________ Fax ________________________________________ E-Mail ______________________________________

(l) Requests for information. The contracting officer will not notify unsuccessful quoters that responded to this solicitation. Quoters may request information on purchase order(s) resulting from this solicitation from the contracting officer.

(m) Insurance Required (FAR 52.228-5):

In accordance with FAR 28.307-2, “Liability,” the contractor shall procure the following minimum insurance:

Type Amount Workman’s Compensation and Employer’s Liability Insurance $100,000 General Liability Insurance $1,000,000 per occurrence

And, when automobiles are used in connection with performing the contract:

Type Amount Automobile Liability Insurance $200,000 per person Bodily Injury $500,000 per occurrence Property Damage $ 20,000 per occurrence

And, when aircraft is used in connection with performing the contract:

Type Amount Aircraft Public and Passenger Liability Insurance $200,000 per person Bodily Injury (other than passenger injury) $500,000 per occurrence Property Damage $200,000 per occurrence Passenger Liability Bodily Injury $200,000 multiplied by the number of seats or passengers, whichever is greater

And, when contract performance involves use of vessels, the Contracting Officer shall require, as determined by the agency, vessel collision liability and protection and indemnity insurance. The contractor is responsible for contacting the state for compliance with its workman’s compensation laws.

(n) State and Local Taxes:

The U.S. Army Corps of Engineers is exempt from paying state and local taxes per Title 4 United States Code 104-

107. The U.S. Army Corps of Engineers Tax ID Number is 62-1642142.

PERFORMANCE WORK STATEMENT

Well Decommissioning Services U.S. Army Corps of Engineers, Gavins Point Project

1.0 General Information

1.1 Scope of Work. The contractor shall provide all personnel, equipment, supplies, transportation, tools, materials, supervision and other items necessary to perform well decommissioning on U.S. Army Corps of Engineers (USACE) lands. This is a fixed priced, performance based service contract where desired outcomes are defined and measured while contractor methods are generally not constrained or directed.

1.1.1. Audubon Bend was purchased by USACE in 2009 as part of the Missouri River Recovery Program. This program is designed, in part, to restore and enhance biological diversity associated with the Missouri River.

Audubon Bend is comprised of 2,372 acres adjacent to the Missouri River with approximately 4 miles of riverfront.

Upon purchase, approximately 80% of the property was cultivated. Each year USACE converts a portion of the cultivated area into native habitat. Currently, approximately 32% of the property is cultivated, 20% is wooded, and 48% is young woodland and prairie restoration plantings.

1.2 Contractor Personnel

1.2.1 The Contractor shall perform all work under this contract with his own forces except as provided in Paragraph

1.2.2.2 Subcontracting. Employees who perform this work shall be qualified persons on the Contractor’s own payroll.

1.2.2 All Contractor vehicles shall be registered, licensed and insured to meet all State and local laws.

1.2.2.1 The Contractor employees shall be skilled in and capable of performing the work under this contract. All employees of the Contractor or subcontractor shall be 18 years of age or older.

1.2.2.2 Subcontracting. No work may be subcontracted without written approval of the COR. Compliance with the provisions of this contract by subcontractors shall be the responsibility of the Contractor.

1.2.3 Security Requirements. Physical security at various project locations is subject to change with very little notice. When advised by the COR, the Contractor employees and subcontractors shall comply with any and all changing requirements. Such changes may reduce access to certain areas under this contract.

1.3 Quality Control

1.3.1 The contractor shall designate, in writing, a member of each work crew who shall serve as the contact for matters involving quality and performance or nonperformance of the required work assigned to that crew. The employee (s) shall be qualified and fully competent with full authority to act for, and on behalf of, the contractor as necessary to insure that the required work is performed in accordance with the specifications and standards contained herein. The contractor shall furnish the above written designation to the Contracting Officer’s Representative at the project no later than the first day of work. The contractor shall include the name(s), address(es), and telephone number(s) of the responsible individual(s).

1.3.2 The Contracting Officer reserves the right to disapprove any individual whom he considers to be incompetent to perform the work required. Such disapproval’s will be given to the contractor by written notice.

1.4 Quality Assurance

1.4.1 The government has the right to inspect all services called for by the contract, to the extent practicable at all times and places during the term of the contract. The government shall perform inspections in a manner that will not unduly delay the work.

1.4.2 If any of the services do not conform to contract requirements, the government may require the contractor to perform the services in conformity with contract requirements and at no increase in cost. If the contract requirements are not met after a second attempt the government may (1) require the contractor to take necessary action to ensure that future performance conforms to contract requirements and (2) reduce the contract price to reflect the reduced value of the services performed.

1.4.3 If the contractor fails to promptly perform the services again or to take the necessary action to ensure future performance is in conformity with the contract requirements, the government may (1) by contract, or otherwise, perform the services and charge to the contractor any cost incurred by the government that is directly related to the performance of such service or (2) terminate the contract in whole or in part.

1.5 Pre-Work Meeting. Prior to commencing any activities, the Contractor shall arrange a Pre-work Meeting with the COR. The Meeting shall discuss the work to be performed, scheduling, submittal process, review of the Activity Hazard Analysis (AHA), and abbreviated Accident Prevention Plan (APP). At least two (2) days prior to commencing work, the Contractor shall coordinate their proposed work schedule with the COR.

1.6. Submittals. Prior to commencement of services, the Contractor shall submit the following documents to the COR for review and approval:

a. Activity Hazard Analysis (AHA);

b. Abbreviated Accident Prevention Plan (APP)

c. List of who will perform work on this contract;

d. Proof of Insurance for Contractors and Subcontractors;

1.7 Hours of Operation

1.7.1 The Contractor is responsible for conducting business, Monday thru Friday, except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings, unless approved in advance by the COR.

1.8 Standards and Regulations. The Contractor shall perform to the standards in the contract and comply with all Local, State, and Federal Regulations during the services performed. The Contractor is responsible for ascertaining the extent to which these regulations affect the operations resulting from this contract and to comply therewith.

Applicable regulations to this work included, but are not limited to the following:

a. The State of Nebraska, Title 178, Chapter 12 Standards (http://www.sos.ne.gov/rules-and-regs/regsearch/Rules/Health_and_Human_Services_System/Title-178/Chapter-12.pdf).

b. Code of Federal Regulations (CFR), Title 36, Chapter III, Part 327, Rules and Regulations Governing Public Use on Corps of Engineers Water Resource Development Projects EP 1165-2-316 (http://www.publications.usace.army.mil/Portals/76/Publications/EngineerPamphlets/EP_1165-2- 316.pdf?ver=2013-08-22-104526-670)

c. Engineering Manual (EM) 385-1-1 (USACE – Safety and Health Requirements Manual), dated November 2014;

1.9 Safety. The local emergency phone numbers will be furnished to the Contractor by the COR. In addition to applicable Local, State, and Federal laws, the Contractor and their subcontractors are required to adhere to all provisions of the EM 385-1-1. Where safety standards conflict, the most stringent standard shall apply. A copy of the EM 385-1-1 can be found electronically at the following link:

http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf

1.9.1 Activity Hazard Analysis (AHA). The Contractor shall prepare AHAs IAW Paragraph 01.A.14 or 01.A.15 of the EM 385-1-1. If using Paragraph 01.A.15, prepare AHAs IAW Figure 1-2.

1.9.2 Abbreviated Accident Prevention Plan (APP). It is understood that the EM 385-1-1 in its entirety may be too complex for the type of work being performed under these contracts, Contractors may reference Appendix A, for abbreviated Accident Prevention Plan (APP). The contractor shall only need to submit items in Appendix A that are pertinent to the contract. The contractor shall use a qualified person to prepare the site-specific Abbreviated Accident Prevention Plan (AAPP). Prepare the AAPP in accordance with the format and requirements of the EM 385-1-1 and supplemented herein. The Contractor shall sign and submit the APP for Government approval prior to the start of work onsite.

1.10 Environmental Protection. The Contractor shall perform all work in such a manner as to minimize the polluting of air, water, or land, and shall, within reasonable limits, control noise and the disposal of solid waste materials, as well as other pollutants.

1.10.1 Protection of Resources. The Contractor shall not pollute streams, lakes or reservoirs with fuels, oils, bitumens, calcium chloride, acids, insecticides, herbicides or other harmful materials. The Contractor shall investigate and comply with all applicable Federal, State, County and Municipal laws concerning pollution of rivers and streams.

1.10.2 Spillage. Special measures shall be taken to prevent chemicals and other materials from entering public waters. If any spillage occurs, the Contractor shall remove the material and restore the area to its original condition.

If necessary, contaminated ground shall be excavated and disposed of as directed by the Contracting Officer, and replaced with suitable fill material, compacted and finished with topsoil and planted as required to reestablish vegetation all at the expense of the Contractor.

1.10.2.1 Disposal. Disposal of all materials shall be at the appropriate locations as directed by the COR. Disposal of any materials, wastes, effluent, trash, garbage, fuel, chemicals, etc., in areas adjacent to streams shall not be permitted. If any waste material is dumped in unauthorized areas, the Contractor shall remove the material and restore the area to the original condition before being disturbed. If necessary, contaminated ground shall be excavated and disposed of as directed by the Contracting Officer, and replaced with suitable fill material, compacted and finished with topsoil and planted as required to reestablish vegetation all at the expense of the Contractor.

1.10.3 Equipment Accountability. The Contractor shall clean all equipment prior to entering Corps property. The equipment shall have not visible soil, roots, vegetative material, seeds, or other debris that could contain seeds.

1.10.4 Protection of Fish and Wildlife. The Contractor shall at all times perform work and take such steps required to minimize interference with or disturbance to fish and wildlife. The Contractor will not be permitted to alter water flows or otherwise disturb native habitat adjacent to the project area that, in the opinion of the Contracting Officer, are critical to fish or wildlife.

1.11 Physical Security

1.11.1 The Contractor shall be responsible for safeguarding all Government facilities, property and materials provided for Contractor use. All Government facilities, property and materials shall be appropriately secured at all times. Specific security conditions may change based on threats to national defense, and based on the risk of specific facilities to these threats. The Contractor shall abide by these changing conditions at all times. The Government is not responsible for the Contractor’s equipment when stored on Government property administered by the USACE Gavins Point Project.

1.11.2 Key Control. The Contractor shall ensure all keys issued to the Contractor by the Government are not lost, stolen or duplicated and are not used by unauthorized persons.

1.11.2.1 The Contractor shall immediately report to the COR any occurrences of lost or stolen keys.

1.11.2.2 In the event keys, other than master keys are lost or stolen, the Contractor may be required, upon written direction of the COR, to re-key or replace the affected lock or locks without cost to the Government. The Government may, however, at its option, replace the affected lock or locks or perform re-keying and deduct the cost of such from the monthly payment due the Contractor. If a master key is lost or stolen, the Government may need to replace all locks and keys for that system. The total cost of such replacement will be deducted from the monthly payment due the Contractor.

1.11.2.3 The Contractor shall prohibit the use of keys issued by the Government by any persons other than the Contractor’s employees. The Contractor shall not facilitate access of secured areas to persons other than Contractor personnel or subcontractors engaged in performance of contract work requirements.

2.0 Definitions. The following definitions and descriptions apply wherever the word, phrase, or acronym is used in this performance work statement.

Acceptable Level of Performance (ALP): The maximum percent defective, the maximum number of defects per hundred units, or the number of defects in a lot that can be considered satisfactory on the average. The allowable leeway or variance from a standard before the government will reject the specific service.

Contracting Officer’s Representative (COR): means an individual designated an authorized in writing by the Contracting Officer to perform specific technical or administrative functions.

Daily Duties: To be performed each day facilities are serviced.

Performance-Based Contract (FAR 2.101): Structuring all aspects of an acquisition around the purpose of the work to be performed with the contract requirements set forth in clear, specific, and objective terms with measurable outcomes as opposed to either the manner by which the work is to be performed or broad and imprecise.

Performance Requirements Summary (PRS): The PRS shows contract requirements, the component requirements related to each contract requirement, the price of each work requirement as a percentage of the associated contract requirement (Fixed Price Contracts), the standard of performance, and the acceptable level of performance (ALP) for each work requirement.

3.0 Specific Tasks

3.1 Basic Services. The Contractor shall provide well decommissioning services for six (6) irrigation wells at Audubon Bend. Wells are located within or along the edges of natural areas (Technical Exhibit 2). The Contractor shall make every effort to minimize damage to surrounding habitat in natural areas when accessing and decommissioning the wells. The Contractor will complete all services between May 14, 2018 and September 30, 2018. Site inspections are encouraged prior to submitting a quote and can be arranged by contacting Linda Filo at

(402) 667-2569.

3.1.1. Audubon Bend is located near Wynot, Nebraska in Cedar County.

3.1.2 Irrigation Well Related Equipment. In the case that pumps, switches, pivots, or any other irrigation related equipment are still attached to a well or located in the immediate area surrounding a well that the Contractor needs to access, the Contractor is responsible for coordinating removal of the equipment by the property owners through the COR.

3.2 Description of Work Areas

3.2.1 Well Location A. Location A is a covered well along the edge of a dirt road. See Attachment 1 (Technical Exhibit 3).

3.2.2 Well Location B. Location B is a sealed well within a grassland that contains scattered young cottonwood trees. The area is mostly flat ground with a few gentle slopes. See Attachment 1 (Technical Exhibit 4).

3.2.3 Well Location C. Location C is a sealed well within a grassland. The area is mostly flat ground. See Attachment 1 (Technical Exhibit 5).

3.2.4 Well Location D. Location D is a covered well within a grassland, within about 30 feet of location C. See Attachment 1 (Technical Exhibit 6).

3.2.5 Well Location E. Location E is a covered well within a grassland. The area is flat ground with a few gentle slopes. See Attachment 1 (Technical Exhibit 7).

3.2.6 Well Location F. Location F is a covered well within a crop field that will be planted to prairie in the spring of 2018. The area is mostly flat ground. See Attachment 1 (Technical Exhibit 8).

4.0 Performance Requirements Summary

The Contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.

Performance Objective

Standard Performance Threshold Method of Surveillance

PRS # 1.

The Contractor shall provide well decommissioning services for 6 irrigation wells at Audubon Bend in accordance with the PWS.

Contractor shall decommission all wells in accordance with The State of Nebraska, Title 178, Chapter 12 Standards.

Zero deviation from standard.

Random direct inspection.

Attachments

Technical Exhibit 1 – Audubon Bend Technical Exhibit 2 – Well locations Technical Exhibit 3 – Well location A Technical Exhibit 4 – Well location B Technical Exhibit 5 – Well location C Technical Exhibit 6 – Well location D Technical Exhibit 7 – Well location E Technical Exhibit 8 – Well location F

PWS

PERFORMANCE WORK STATEMENT (PWS)

Well Decommissioning Services U.S. Army Corps of Engineers, Gavins Point Project

1.0 General Information

1.1 Scope of Work. The contractor shall provide all personnel, equipment, supplies, transportation, tools, materials, supervision and other items necessary to perform well decommissioning on U.S. Army Corps of Engineers (USACE) lands. This is a fixed priced, performance based service contract where desired outcomes are defined and measured while contractor methods are generally not constrained or directed.

1.1.1. Audubon Bend was purchased by USACE in 2009 as part of the Missouri River Recovery Program. This program is designed, in part, to restore and enhance biological diversity associated with the Missouri River.

Audubon Bend is comprised of 2,372 acres adjacent to the Missouri River with approximately 4 miles of riverfront.

Upon purchase, approximately 80% of the property was cultivated. Each year USACE converts a portion of the cultivated area into native habitat. Currently, approximately 32% of the property is cultivated, 20% is wooded, and 48% is young woodland and prairie restoration plantings.

1.2 Contractor Personnel

1.2.1 The Contractor shall perform all work under this contract with his own forces except as provided in Paragraph

1.2.2.2 Subcontracting. Employees who perform this work shall be qualified persons on the Contractor’s own payroll.

1.2.2 All Contractor vehicles shall be registered, licensed and insured to meet all State and local laws.

1.2.2.1 The Contractor employees shall be skilled in and capable of performing the work under this contract. All employees of the Contractor or subcontractor shall be 18 years of age or older.

1.2.2.2 Subcontracting. No work may be subcontracted without written approval of the COR. Compliance with the provisions of this contract by subcontractors shall be the responsibility of the Contractor.

1.2.3 Security Requirements. Physical security at various project locations is subject to change with very little notice. When advised by the COR, the Contractor employees and subcontractors shall comply with any and all changing requirements. Such changes may reduce access to certain areas under this contract.

1.3 Quality Control

1.3.1 The contractor shall designate, in writing, a member of each work crew who shall serve as the contact for matters involving quality and performance or nonperformance of the required work assigned to that crew. The employee (s) shall be qualified and fully competent with full authority to act for, and on behalf of, the contractor as necessary to insure that the required work is performed in accordance with the specifications and standards contained herein. The contractor shall furnish the above written designation to the Contracting Officer’s Representative at the project no later than the first day of work. The contractor shall include the name(s), address(es), and telephone number(s) of the responsible individual(s).

1.3.2 The Contracting Officer reserves the right to disapprove any individual whom he considers to be incompetent to perform the work required. Such disapproval’s will be given to the contractor by written notice.

1.4 Quality Assurance

1.4.1 The government has the right to inspect all services called for by the contract, to the extent practicable at all times and places during the term of the contract. The government shall perform inspections in a manner that will not unduly delay the work.

1.4.2 If any of the services do not conform to contract requirements, the government may require the contractor to perform the services in conformity with contract requirements and at no increase in cost. If the contract requirements are not met after a second attempt the government may (1) require the contractor to take necessary action to ensure that future performance conforms to contract requirements and (2) reduce the contract price to reflect the reduced value of the services performed.

1.4.3 If the contractor fails to promptly perform the services again or to take the necessary action to ensure future performance is in conformity with the contract requirements, the government may (1) by contract, or otherwise, perform the services and charge to the contractor any cost incurred by the government that is directly related to the performance of such service or (2) terminate the contract in whole or in part.

1.5 Pre-Work Meeting. Prior to commencing any activities, the Contractor shall arrange a Pre-work Meeting with the COR. The Meeting shall discuss the work to be performed, scheduling, submittal process, review of the Activity Hazard Analysis (AHA), and abbreviated Accident Prevention Plan (APP). At least two (2) days prior to commencing work, the Contractor shall coordinate their proposed work schedule with the COR.

1.6. Submittals. Prior to commencement of services, the Contractor shall submit the following documents to the COR for review and approval:

e. Activity Hazard Analysis (AHA);

f. Abbreviated Accident Prevention Plan (APP)

g. List of who will perform work on this contract;

h. Proof of Insurance for Contractors and Subcontractors;

1.7 Hours of Operation

1.7.1 The Contractor is responsible for conducting business, Monday thru Friday, except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings, unless approved in advance by the COR.

1.8 Standards and Regulations. The Contractor shall perform to the standards in the contract and comply with all Local, State, and Federal Regulations during the services performed. The Contractor is responsible for ascertaining the extent to which these regulations affect the operations resulting from this contract and to comply therewith.

Applicable regulations to this work included, but are not limited to the following:

d. The State of Nebraska, Title 178, Chapter 12 Standards (http://www.sos.ne.gov/rules-and-regs/regsearch/Rules/Health_and_Human_Services_System/Title-178/Chapter-12.pdf).

e. Code of Federal Regulations (CFR), Title 36, Chapter III, Part 327, Rules and Regulations Governing Public Use on Corps of Engineers Water Resource Development Projects EP 1165-2-316 (http://www.publications.usace.army.mil/Portals/76/Publications/EngineerPamphlets/EP_1165-2- 316.pdf?ver=2013-08-22-104526-670)

f. Engineering Manual (EM) 385-1-1 (USACE – Safety and Health Requirements Manual), dated November 2014;

1.9 Safety. The local emergency phone numbers will be furnished to the Contractor by the COR. In addition to applicable Local, State, and Federal laws, the Contractor and their subcontractors are required to adhere to all provisions of the EM 385-1-1. Where safety standards conflict, the most stringent standard shall apply. A copy of the EM 385-1-1 can be found electronically at the following link:

http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf

1.9.1 Activity Hazard Analysis (AHA). The Contractor shall prepare AHAs IAW Paragraph 01.A.14 or 01.A.15 of the EM 385-1-1. If using Paragraph 01.A.15, prepare AHAs IAW Figure 1-2.

1.9.2 Abbreviated Accident Prevention Plan (APP). It is understood that the EM 385-1-1 in its entirety may be too complex for the type of work being performed under these contracts, Contractors may reference Appendix A, for abbreviated Accident Prevention Plan (APP). The contractor shall only need to submit items in Appendix A that are pertinent to the contract. The contractor shall use a qualified person to prepare the site-specific Abbreviated Accident Prevention Plan (AAPP). Prepare the AAPP in accordance with the format and requirements of the EM 385-1-1 and supplemented herein. The Contractor shall sign and submit the APP for Government approval prior to the start of work onsite.

1.10 Environmental Protection. The Contractor shall perform all work in such a manner as to minimize the polluting of air, water, or land, and shall, within reasonable limits, control noise and the disposal of solid waste materials, as well as other pollutants.

1.10.1 Protection of Resources. The Contractor shall not pollute streams, lakes or reservoirs with fuels, oils, bitumens, calcium chloride, acids, insecticides, herbicides or other harmful materials. The Contractor shall investigate and comply with all applicable Federal, State, County and Municipal laws concerning pollution of rivers and streams.

1.10.2 Spillage. Special measures shall be taken to prevent chemicals and other materials from entering public waters. If any spillage occurs, the Contractor shall remove the material and restore the area to its original condition.

If necessary, contaminated ground shall be excavated and disposed of as directed by the Contracting Officer, and replaced with suitable fill material, compacted and finished with topsoil and planted as required to reestablish vegetation all at the expense of the Contractor.

1.10.2.1 Disposal. Disposal of all materials shall be at the appropriate locations as directed by the COR. Disposal of any materials, wastes, effluent, trash, garbage, fuel, chemicals, etc., in areas adjacent to streams shall not be permitted. If any waste material is dumped in unauthorized areas, the Contractor shall remove the material and restore the area to the original condition before being disturbed. If necessary, contaminated ground shall be excavated and disposed of as directed by the Contracting Officer, and replaced with suitable fill material, compacted and finished with topsoil and planted as required to reestablish vegetation all at the expense of the Contractor.

1.10.3 Equipment Accountability. The Contractor shall clean all equipment prior to entering Corps property. The equipment shall have not visible soil, roots, vegetative material, seeds, or other debris that could contain seeds.

1.10.4 Protection of Fish and Wildlife. The Contractor shall at all times perform work and take such steps required to minimize interference with or disturbance to fish and wildlife. The Contractor will not be permitted to alter water flows or otherwise disturb native habitat adjacent to the project area that, in the opinion of the Contracting Officer, are critical to fish or wildlife.

1.11 Physical Security

1.11.1 The Contractor shall be responsible for safeguarding all Government facilities, property and materials provided for Contractor use. All Government facilities, property and materials shall be appropriately secured at all times. Specific security conditions may change based on threats to national defense, and based on the risk of specific facilities to these threats. The Contractor shall abide by these changing conditions at all times. The Government is not responsible for the Contractor’s equipment when stored on Government property administered by the USACE Gavins Point Project.

1.11.2 Key Control. The Contractor shall ensure all keys issued to the Contractor by the Government are not lost, stolen or duplicated and are not used by unauthorized persons.

1.11.2.1 The Contractor shall immediately report to the COR any occurrences of lost or stolen keys.

1.11.2.2 In the event keys, other than master keys are lost or stolen, the Contractor may be required, upon written direction of the COR, to re-key or replace the affected lock or locks without cost to the Government. The Government may, however, at its option, replace the affected lock or locks or perform re-keying and deduct the cost of such from the monthly payment due the Contractor. If a master key is lost or stolen, the Government may need to replace all locks and keys for that system. The total cost of such replacement will be deducted from the monthly payment due the Contractor.

1.11.2.3 The Contractor shall prohibit the use of keys issued by the Government by any persons other than the Contractor’s employees. The Contractor shall not facilitate access of secured areas to persons other than Contractor personnel or subcontractors engaged in performance of contract work requirements.

2.0 Definitions. The following definitions and descriptions apply wherever the word, phrase, or acronym is used in this performance work statement.

Acceptable Level of Performance (ALP): The maximum percent defective, the maximum number of defects per hundred units, or the number of defects in a lot that can be considered satisfactory on the average. The allowable leeway or variance from a standard before the government will reject the specific service.

Contracting Officer’s Representative (COR): means an individual designated an authorized in writing by the Contracting Officer to perform specific technical or administrative functions.

Daily Duties: To be performed each day facilities are serviced.

Performance-Based Contract (FAR 2.101): Structuring all aspects of an acquisition around the purpose of the work to be performed with the contract requirements set forth in clear, specific, and objective terms with measurable outcomes as opposed to either the manner by which the work is to be performed or broad and imprecise.

Performance Requirements Summary (PRS): The PRS shows contract requirements, the component requirements related to each contract requirement, the price of each work requirement as a percentage of the associated contract requirement (Fixed Price Contracts), the standard of performance, and the acceptable level of performance (ALP) for each work requirement.

3.0 Specific Tasks

3.1 Basic Services. The Contractor shall provide well decommissioning services for six (6) irrigation wells at Audubon Bend. Well decommissioning will meet State of Nebraska standards. Wells are located within or along the edges of natural areas (Technical Exhibit 2). The Contractor shall make every effort to minimize damage to surrounding habitat in natural areas when accessing and decommissioning the wells. The Contractor will complete all services between May 14, 2018 and September 30, 2018.

3.1.1. Audubon Bend is located near Wynot, Nebraska in Cedar County.

3.1.2 Irrigation Well Related Equipment. In the case that pumps, switches, pivots, or any other irrigation related equipment are still attached to a well or located in the immediate area surrounding a well that the Contractor needs to access, the Contractor is responsible for coordinating removal of the equipment by the property owners through the COR.

3.2 Description of Work Areas

3.2.1 Well Location A. Location A is a covered well along the edge of a dirt road. See Attachment 1 (Technical Exhibit 3).

3.2.2 Well Location B. Location B is a sealed well within a grassland that contains scattered young cottonwood trees. The area is mostly flat ground with a few gentle slopes. See Attachment 1 (Technical Exhibit 4).

3.2.3 Well Location C. Location C is a sealed well within a grassland. The area is mostly flat ground. See Attachment 1 (Technical Exhibit 5).

3.2.4 Well Location D. Location D is a covered well within a grassland, within about 30 feet of location C. See Attachment 1 (Technical Exhibit 6).

3.2.5 Well Location E. Location E is a covered well within a grassland. The area is flat ground with a few gentle slopes. See Attachment 1 (Technical Exhibit 7).

3.2.6 Well Location F. Location F is a covered well within a crop field that will be planted to prairie in the spring of 2018. The area is mostly flat ground. See Attachment 1 (Technical Exhibit 8).

4.0 Performance Requirements Summary

The Contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.

Performance Objective

Standard Performance Threshold Method of Surveillance

PRS # 1.

The Contractor shall provide well decommissioning services for 6 irrigation wells at Audubon Bend in accordance with the PWS.

Contractor shall decommission all wells in accordance with The State of Nebraska, Title 178, Chapter 12 Standards.

Zero deviation from standard.

Random direct inspection.

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job GP - Decommissioning of six irrigation

FFP

Gavins Point Project- Audubon Bend near Wynot, Nebraska in Cedar County.

Provide all personnel, equipment, supplies, transportation, tools, materials, supervision and other items necessary to perform the well decommissioning IAW the attached PWS.

FOB: Destination

NET AMT

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 POP 14-MAY-2018 TO

30-SEP-2018

N/A COE GAVINS POINT PRJT OFC NTR RSC

LINDA FILO

USAED, OMAHACENWO-OD-GP-N

55245 HIGHWAY 121

CROFTON NE 68730

402-667-2569 FOB: Destination

968812

CLAUSES INCORPORATED BY REFERENCE

52.203-3 Gratuities APR 1984 52.203-6 Alt I Restrictions On Subcontractor Sales To The Government

(Sep 2006) -- Alternate I

OCT 1995

52.203-11 Certification And Disclosure Regarding Payments To Influence Certain Federal Transactions

SEP 2007

52.203-12 Limitation On Payments To Influence Certain Federal Transactions

OCT 2010

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements

JAN 2017

52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper

MAY 2011

52.204-7 System for Award Management OCT 2016 52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First-Tier

Subcontract Awards

OCT 2016

52.204-16 Commercial and Government Entity Code Reporting JUL 2016

52.204-17 Ownership or Control of Offeror JUL 2016 52.208-9 Contractor Use of Mandatory Sources of Supply or Services MAY 2014 52.209-2 Prohibition on Contracting with Inverted Domestic

Corporations--Representation

NOV 2015

52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment

OCT 2015

52.212-1 Instructions to Offerors--Commercial Items JAN 2017 52.212-4 Contract Terms and Conditions--Commercial Items JAN 2017 52.219-28 Post-Award Small Business Program Rerepresentation JUL 2013 52.222-41 Service Contract Labor Standards MAY 2014 52.222-50 Combating Trafficking in Persons MAR 2015 52.222-55 Minimum Wages Under Executive Order 13658 DEC 2015 52.223-1 Biobased Product Certification MAY 2012 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts

SEP 2013

52.223-3 Hazardous Material Identification And Material Safety Data JAN 1997 52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011 52.223-6 Drug-Free Workplace MAY 2001 52.223-10 Waste Reduction Program MAY 2011 52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts

MAY 2008

52.225-13…