Contractor Q&A for W9128F-15-B-0028:
Question: Will the haul route remain as originally suggested or will a new haul route be required?
Answer: The haul route as shown on the drawings for the C5+00 Repair Area will remain intact, though the contractor potentially may need to perform some re-grading to ensure the safe travel of construction equipment in accordance with what is called for in the specifications.