AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
1. Clarify PoP of the entire contract, no more than ten (10) years from date of aw ard of the contract and no CLIN/SubCLIN PoP to be more than five (5) years, also clarify key personnel and requirements, Section L.
2. Clarify that electronic (email) proposals w ill not be accepted. Reference FAR 52.215-1(c). All submission must be in accordance w ith instructions to offeror and received no later than the date in block of the solicitation SF33.
3. Identify deleted clauses 52.215-21 ALT III, 52.219-4, 52.219-4 ALT I, and 52.249-2 ALT I as they do not apply to this requirement and are removed in their entirety.
4. Publish answ ers to questions to date as an attachment (Q&A Round 1) to this amendment. Final date for submission of questions changed from ten (10) to no later than fourteen (14) days prior to due date of proposals.
5. This amendment must be acknow ledged, signed, and included w ith the offerors proposal.
6. All other terms and conditions remain unchanged and in full effect.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 122
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 03-Jul-2013
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9128F-13-R-0029
X 9B. DATED (SEE ITEM 11)
21-Jun-2013
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
03-Jul-2013
CODE
U.S. ARMY CORPS OF ENGINEERS, OMAHA DIST
CONTRACTING OFFICE
1616 CAPITOL AVENUE
OMAHA NE 68102-4901
W9128F 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9128F-13-R-0029
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION B - SUPPLIES OR SERVICES AND PRICES
CLIN 0001
The CLIN extended description Period of Performance (PoP) of work to be performed under this contract will not exceed ten (10) years from the date of award of the contract. No FUNDED CONTRACT LINE ITEM PoP will exceed five (5) years in duration. has been added.
The following have been modified:
CONTRACT LINE ITEMS
All questions regarding this solicitation must be submitted to the Contract Specialist, John Tucker at john.h.tucker@usace.army.mil no later than 14 days prior to the date set for receipt of proposals in block 9 of the SF 33. Responses will be addressed in an amendment to the solicitation approximately 7 days prior to the date set for receipt of proposals.
All referenced documents for this solicitation are available at the following web sites:
https://www.portageinc.com/hilldc/transfer.
Contractor User Name: uttrpbr13 Password: password2013 (case sensitive) www.hafbdyndocs.com.
Contractor User Name: uttrpbr13 Password: password2013 (case sensitive)
Updated documents pertaining to current efforts in the concerned areas under this contract may be posted to the above ftp sites during the solicitation process. It is recommended that offerors check the sites regularly for updated documents.
Potential offerors are encouraged to subscribe to http://www.fedbizopps.gov for this solicitation for real-time e-mail notifications when information has been posted to the website for this solicitation.
Number CLIN/SUB-CLIN DESCRIPTION PROJECTED
DATE OF
EXERCISE
NTE
Qty
Unit Unit Price
TOTAL
0001 Environmental Remediation at Hill Air Force Base UTTR in accordance with the PWS.
EXERCISE
NTE
Qty
Unit Unit Price
TOTAL
0001AA Preliminary Project Management Plan, QASP and Time Phased Updates in accordance with Table 1 of the PWS -
FFP
At Award 1 LS
0001AB
OPTION
Final Project Management Plan, QASP and Time Phased Updates in accordance with Table 1 of the PWS -
FFP
4.5 years from award of
0001AA
1 LS
0002 OT103 (only S208 – Ore Processing Site): Achieve Site Closeout (SC) in accordance with Table 1 of the SOO on this Sub-CLIN - FFP
At Award 1 LS
OPTION
AL510 –Aircraft Debris (MRA 208):
Achieve Site Closeout (SC) in accordance with Table 1 of the SOO on this Sub-CLIN - FFP
FY 16 Subject to Availability of Funds
1 LS
OPTION
ST079 - Remnant POL Contamination, Oasis (XN379):
Achieve Site Closeout (SC) in accordance with Table 1 of the SOO on this Sub-CLIN - FFP
FY 16 Subject to Availability of Funds
1 LS
OPTION
OT104 (only N063S – Target Debris Accumulation Area): Achieve Site Closeout (SC) in accordance with Table 1 of the SOO on this Sub-CLIN
- FFP
FY15 Subject to Availability of Funds
1 LS
0006 OT102 UTTR South (OU SR-1)
0006AA OT102 –UTTR South (OU SR-1):
Complete Decision Document (DD) in accordance with Table 1 of the SOO on this Sub-CLIN - FFP
At Award 1 LS
0006AB
OPTION
OT102 –UTTR South (OU SR-1):
Achieve Remedy-in-Place (RIP) in accordance with Table 1 of the SOO on this Sub-CLIN - FFP
Upon Completion of
0006AA
1 LS
0006AC
OPTION
OT102 –UTTR South (OU SR-1):
Mobilize and develop an optimized exit strategy (OES) plan to achieve Site Closeout (SC) while maintaining compliance with current regulatory and binding agreements - FFP.
Upon Completion of
0006AB
1 LS
0006AD
OPTION
OT102 –UTTR South (OU SR-1):
Implement OES strategy and deliver a Final OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements - FFP.
Upon Completion of
0006AC
1 LS
EXERCISE
NTE
Qty
Unit Unit Price
TOTAL
0006AE
OPTION
OT102 –UTTR South (OU SR-1):
Deliver a Final OES Effectiveness Report to achieve SC documenting the completion of the approved strategy that fell within the POP while maintaining compliance with current regulatory and binding agreements -
FFP.
Upon completion of 0006AD
1 LS
0007 OT104 except N063S – UTTR North, North Half (OU NR-2)
0007AA OT104 except N063S – UTTR North, North Half (OU NR-2): Complete Decision Document (DD) in accordance with Table 1 of the SOO on this Sub-CLIN - FFP
At Award 1 LS
0007AB
OPTION
OT104 except N063S – UTTR North, North Half (OU NR-2): Achieve Remedy-in-Place (RIP) in accordance with Table 1 of the SOO on this Sub-
CLIN - FFP.
Upon Completion of
0007AA
1 LS
0007AC
OPTION
OT104 except N063S – UTTR North, North Half (OU NR-2): Mobilize and develop an optimized exit strategy (OES) plan to achieve Site Closeout (SC) while maintaining compliance with current regulatory and binding agreements - FFP.
Upon Completion of
0007AB
1 LS
0007AD
OPTION
OT104 except N063S – UTTR North, North Half (OU NR-2): Implement OES strategy and deliver a Final OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements - FFP.
Upon Completion of
0007AC
1 LS
0007AE
OPTION
OT104 except N063S – UTTR North, North Half (OU NR-2): Deliver a Final OES Effectiveness Report to achieve SC documenting the completion of the approved strategy that fell within the POP while maintaining compliance with current regulatory and binding agreements -
FFP.
Upon Completion of
0007AD
1 LS
0008 OT105 – UTTR North, South Half
(OU NR-2)
0008AA OT105 – UTTR North, South Half (OU NR-2): Complete Decision Document (DD) in accordance with Table 1 of the SOO on this Sub-CLIN
At Award 1 LS
EXERCISE
NTE
Qty
Unit Unit Price
TOTAL
- FFP.
0008AB
OPTION
OT105 – UTTR North, South Half (OU NR-2): Achieve Remedy-in- Place (RIP) in accordance with Table 1 of the SOO on this Sub-CLIN - FFP.
Upon Completion of
0008AA
1 LS
0008AC
OPTION
OT105 – UTTR North, South Half (OU NR-2): Mobilize and develop an optimized exit strategy (OES) plan to achieve Site Closeout (SC) while maintaining compliance with current regulatory and binding agreements -
FFP.
Upon Completion of
0008AB
1 LS
0008AD
OPTION
OT105 – UTTR North, South Half (OU NR-2): Implement OES strategy and deliver a Final OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements - FFP.
Upon Completion of
0008AC
1 LS
0008AE
OPTION
OT105 – UTTR North, South Half (OU NR-2): Deliver a Final OES Effectiveness Report to achieve SC documenting the completion of the approved strategy that fell within the POP while maintaining compliance with current regulatory and binding agreements – FFP.
Upon Completion of
0008AD
1 LS
0009 OT103 (only S292 – Post Engineering Salvage Yard)
0009AA OT103 (only S292 – Post Engineering Salvage Yard): Achieve Response Complete (RC) in accordance with Table 1 of the SOO on this Sub-CLIN
- FFP.
At Award 1 LS
0009AB
OPTION
OT103 (only S292 – Post Engineering Salvage Yard): Mobilize and develop an optimized exit strategy (OES) plan to achieve Site Closeout (SC) while maintaining compliance with current regulatory and binding agreements -
FFP.
Upon Completion of
0009AA
1 LS
0009AC
OPTION
OT103 (only S292 – Post Engineering Salvage Yard): Implement OES strategy and deliver a Final OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements - FFP.
Upon Completion of
0009AB
EXERCISE
NTE
Qty
Unit Unit Price
TOTAL
0009AD
OPTION
OT103 (only S292 – Post Engineering Salvage Yard): Deliver a Final OES Effectiveness Report to achieve SC documenting the completion of the approved strategy that fell within the POP while maintaining compliance with current regulatory and binding agreements - FFP.
Upon Completion of
0009AC
1 LS
0010 AL501B – Wendover (MRA 184)
0010AA AL501B - Wendover (MRA 184):
Achieve Remedial Investigation/Feasibility Study (RI/FS) in accordance with Table 1 of the SOO on this Sub-CLIN - FFP.
At Award 1 LS
0010AB
OPTION
AL501B - Wendover (MRA 184):
Achieve Decision Document (DD) in accordance with Table 1 of the SOO on this Sub-CLIN - FFP.
Upon Completion of
0010AA
1 LS
0011 AL501C – Wendover (MRA 184)
0011AA AL501C - Wendover (MRA 184):
Achieve Remedial Investigation/Feasibility Study (RI/FS) in accordance with Table 1 of the SOO on this Sub-CLIN - FFP.
At Award 1 LS
0011AB
OPTION
AL501C - Wendover (MRA 184):
Achieve Decision Document (DD) in accordance with Table 1 of the SOO on this Sub-CLIN - FFP.
Upon Completion of
0011AA
1 LS
0012 AL501D – Wendover (MRA 184)
0012AA AL501D - Wendover (MRA 184):
Achieve Remedial Investigation/Feasibility Study (RI/FS) in accordance with Table 1 of the SOO on this Sub-CLIN- FFP.
At Award 1 LS
0012AB
OPTION
AL501D - Wendover (MRA 184):
Achieve Decision Document (DD) within three (3) years from Obligation date on this Sub-CLIN - FFP.
Upon Completion of
0012AA
1 LS
0013 AL501E – Wendover (MRA 184)
0013AA AL501E - Wendover (MRA 184):
Achieve Remedial Investigation/Feasibility Study
At Award 1 LS
EXERCISE
NTE
Qty
Unit Unit Price
TOTAL
(RI/FS) in accordance with Table 1 of the SOO on this Sub-CLIN - FFP.
0013AB
OPTION
AL501E - Wendover (MRA 184):
Achieve Decision Document (DD) in accordance with Table 1 of the SOO on this Sub-CLIN - FFP.
Upon Completion of
0013AA
1 LS
0014 AL501F – Wendover (MRA 184)
0014AA AL501F - Wendover (MRA 184):
Achieve Remedial Investigation/Feasibility Study (RI/FS) in accordance with Table 1 of the SOO on this Sub-CLIN - FFP.
At Award 1 LS
0014AB
OPTION
AL501F - Wendover (MRA 184):
Achieve Decision Document (DD) in accordance with Table 1 of the SOO on this Sub-CLIN - FFP.
Upon Completion of
0014AA
1 LS
0015 Surface Clearance for Flat/Sparse Vegetation Terrain acreage within MRA/MRSs 205 – Practice Bombing Range, 207 - Practice Bombing Range and Jettison Area, 209 - Practice Bombing Range and Jettison Area, 210 – Scattered Sparse MEC and 513
– South Aragonite Craters and After Action Reports (AAR)
0015AA
OPTION
Complete Surface Clearance for Flat/Sparse Vegetation Terrain acreage within MRA/MRSs 205, 207, 209, 210 and 513 and After Action Reports in accordance with Table 2 of the SOO, 4000 acres – FFP/ FUP.
FY15 Subject to Availability of Funds
4000 acre
0015AB
OPTION
Complete Surface Clearance for Flat/Sparse Vegetation Terrain acreage within MRA/MRSs 205, 207, 209, 210 and 513 and After Action Reports in accordance with Table 2 of the SOO, 1000 acres – FFP/ FUP.
FY15 Subject to Availability of Funds
1000 acre
0015AC
OPTION
Complete Surface Clearance for Flat/Sparse Vegetation Terrain acreage within MRA/MRSs 205, 207, 209, 210 and 513 and After Action Reports in accordance with Table 2 of the SOO, 1000 acres – FFP/ FUP.
FY15 Subject to Availability of Funds
1000 acre
0015AD
OPTION
Complete Surface Clearance for Flat/Sparse Vegetation Terrain acreage within MRA/MRSs 205, 207, 209, 210 and 513 and After Action Reports in accordance with Table 2 of the SOO, 1000 acres – FFP/ FUP.
FY15 Subject to Availability of Funds
1000 acre
EXERCISE
NTE
Qty
Unit Unit Price
TOTAL
0015AE
OPTION
Complete Surface Clearance for Flat/Sparse Vegetation Terrain acreage within MRA/MRSs 205, 207, 209, 210 and 513 and After Action Reports in accordance with Table 2 of the SOO, 500 acres – FFP/ FUP.
FY15 Subject to Availability of Funds
500 acre
0015AF
OPTION
Complete Surface Clearance for Flat/Sparse Vegetation Terrain acreage within MRA/MRSs 205, 207, 209, 210 and 513 and After Action Reports in accordance with Table 2 of the SOO, 500 acres – FFP/ FUP.
FY15 Subject to Availability of Funds
500 acre
0015AG
OPTION
Complete Surface Clearance for Flat/Sparse Vegetation Terrain acreage within MRA/MRSs 205, 207, 209, 210 and 513 and After Action Reports in accordance with Table 2 of the SOO, 500 acres – FFP/ FUP.
FY15 Subject to Availability of Funds
500 acre
0015AH
OPTION
Complete Surface Clearance for Flat/Sparse Vegetation Terrain acreage within MRA/MRSs 205, 207, 209, 210 and 513 and After Action Reports in accordance with Table 2 of the SOO, 500 acres – FFP/ FUP.
FY15 Subject to Availability of Funds
500 acre
OPTION
Complete Surface Clearance for Steep/Rocky/Sparse Vegetation Terrain acreage within MRA/MRSs 205, 207, 209, 210 and 513 and After Action Reports in accordance with Table 2 of the SOO, 800 acres -
FFP/FUP.
FY15 Subject to Availability of Funds
800 acre
0017 Surface Clearance for Dunes Terrain acreage within MRA/MRSs 205, 207, 209, 210 and 513 and AAR
0017AA
OPTION
Complete Surface Clearance for Dunes Terrain acreage within MRA/MRSs 205, 207, 209, 210 and 513 and After Action Report in accordance with Table 2 of the SOO, 3000 acres - FFP/FUP.
FY15 Subject to Availability of Funds
3000 acre
0017AB
OPTION
Complete Surface Clearance for Dunes Terrain acreage within MRA/MRSs 205, 207, 209, 210 and 513 and After Action Report in accordance with Table 2 of the SOO, 2000 acres - FFP/FUP.
FY15 Subject to Availability of Funds
1000 acre
0017AC
OPTION
Complete Surface Clearance for Dunes Terrain acreage within MRA/MRSs 205, 207, 209, 210 and 513 and After Action Report in accordance with Table 2 of the SOO, FY15 Subject to Availability of
1000 acre
EXERCISE
NTE
Qty
Unit Unit Price
TOTAL
1000 acres - FFP/FUP.
0017AD
OPTION
Complete Surface Clearance for Dunes Terrain acreage within MRA/MRSs 205, 207, 209, 210 and 513 and After Action Report in accordance with Table 2 of the SOO, 500 acres - FFP/FUP.
FY15 Subject to Availability of Funds
1500 acre
OPTION
205 – Practice Bombing Range:
Achieve Remedial Investigation (RI) in accordance with Table 2 of the SOO on this Sub-CLIN – FFP.
FY20 Subject to Availability of Funds
1 LS
OPTION
206 – Open Detonation Operation:
Achieve Remedial Investigation (RI) in accordance with Table 2 of the SOO on this Sub-CLIN - FFP.
FY17 Subject to Availability of Funds
1 LS
OPTION
207 – Practice Bombing Range and Jettison Area: Achieve Remedial Investigation (RI) in accordance with Table 2 of the SOO on this Sub-CLIN
- FFP.
FY19 Subject to Availability of Funds
1 LS
OPTION
209 – Practice Bombing Range and Jettison Area: Achieve Remedial Investigation (RI) in accordance with Table 2 of the SOO on this Sub-CLIN
- FFP.
FY19 Subject to Availability of Funds
1 LS
OPTION
210 – Scattered Sparse MEC: Achieve Remedial Investigation (RI) in accordance with Table 2 of the SOO on this Sub-CLIN – FFP.
FY19 Subject to Availability of Funds
1 LS
OPTION
513 – South Aragonite Craters:
Achieve Remedial Investigation (RI) in accordance with Table 2 of the SOO on this Sub-CLIN - FFP.
FY19 Subject to Availability of Funds
1 LS
OPTION
203 (MRS MU505 only) –50 Cal Strafing Target & Sparse Scattered MEC: Achieve Remedial Investigation (RI) in accordance with Table 1 of the SOO on this Sub-CLIN
- FFP.
FY17 Subject to Availability of Funds
1 LS
OPTION
204 – Practice Bombing Range:
Achieve Remedial Investigation (RI) in accordance with Table 1 of the SOO on this Sub-CLIN - FFP.
FY19 Subject to Availability of Funds
1 LS
0026 LF007 – Landfill 5
0026AA*
OPTION
LF007 –Landfill 5: Achieve Remedy-in-Place (RIP) in accordance with Table 1 of the SOO on this Sub-
CLIN- FFP.
Within 6 months of award
EXERCISE
NTE
Qty
Unit Unit Price
TOTAL
0026AB*
OPTION
LF007 – Landfill 5: Achieve Remedy-in-Place (RIP) and primary source removal in accordance with Table 1 of the SOO on this Sub-
CLIN- FFP.
Within 6 months of award
1 LS
0026AC
OPTION
LF007 – Landfill 5: Mobilize and develop an optimized exit strategy (OES) plan to achieve Site Closeout (SC) while maintaining compliance with current regulatory and binding agreements - FFP.
Upon Completion of 0026AA or
0026AB
1 LS
0026AD
OPTION
LF007 – Landfill 5: Implement OES strategy and deliver a Final OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements - FFP.
Upon Completion of
0026AC
1 LS
0026AE
OPTION
LF007 –Landfill 5: Deliver a Final OES Effectiveness Report to achieve SC documenting the completion of the approved strategy that fell within the POP while maintaining compliance with current regulatory and binding agreements- FFP.
Upon Completion of
0026AD
1 LS
0027 MRS MU505a: Achieve Site Closeout (SC) in accordance with Table 1 of the SOO on this Sub-
CLIN- FFP.
At Award 1 LS
OPTION
MRA 204 (NFA portion only):
Achieve Site Closeout (SC) in accordance with Table 1 of the SOO on this Sub-CLIN- FFP.
FY15 Subject to Availability of Funds
1 LS
OPTION
MRA 205 (NFA portion only):
Achieve Site Closeout (SC) in accordance with Table 1 of the SOO on this Sub-CLIN- FFP.
FY15 Subject to Availability of Funds
1 LS
OPTION
MRA 206 (NFA portion only):
Achieve Site Closeout (SC) in accordance with Table 1 of the SOO on this Sub-CLIN- FFP.
FY15 Subject to Availability of Funds
1 LS
OPTION
MRA 207 (NFA portion only):
Achieve Site Closeout (SC) in accordance with Table 1 of the SOO on this Sub-CLIN- FFP.
FY15 Subject to Availability of Funds
1 LS
OPTION
MRA 209 (NFA portion only):
Achieve Site Closeout (SC) in accordance with Table 1 of the SOO on this Sub-CLIN- FFP.
FY15 Subject to Availability of Funds
1 LS
OPTION
MRA 210 (NFA portion only):
Achieve Site Closeout (SC) in accordance with Table 1 of the SOO
FY15 Subject to Availability of
EXERCISE
NTE
Qty
Unit Unit Price
TOTAL
on this Sub-CLIN – FFP.
OPTION
MRA 513 (NFA portion only):
Achieve Site Closeout (SC) in accordance with Table 1 of the SOO on this Sub-CLIN- FFP.
FY15 Subject to Availability of Funds
1 LS
0035 OW004 – OWS Eagle Tower (N004)
0035AA OW004 – OWS Eagle Tower (N004):
Mobilize and develop an optimized exit strategy (OES) plan to achieve Site Closeout (SC) while maintaining compliance with current regulatory and binding agreements - FFP.
At Award 1 LS
0035AB
OPTION
OW004 – OWS Eagle Tower (N004):
Implement OES strategy and deliver a Final OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements - FFP.
Upon completion of 0035AA
1 LS
0035AC
OPTION
OW004 – OWS Eagle Tower (N004):
Deliver a Final OES Effectiveness Report to achieve SC documenting the completion of the approved strategy that fell within the POP while maintaining compliance with current regulatory and binding agreements -
FFP.
Upon completion of 0035AB
1 LS
0036 AT014 – Oasis Fire Training Area (N014)
0036AA AT014 – Oasis Fire Training Area (N014): Mobilize and develop an optimized exit strategy (OES) plan to achieve Site Closeout (SC) while maintaining compliance with current regulatory and binding agreements -
FFP.
At Award 1 LS
0036AB
OPTION
AT014 – Oasis Fire Training Area (N014): Implement OES strategy and deliver a Final OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements - FFP.
Upon completion of 0036AA
1 LS
0036AC
OPTION
AT014 – Oasis Fire Training Area (N014): Deliver a Final OES Effectiveness Report to achieve SC documenting the completion of the approved strategy that fell within the POP while maintaining compliance with current regulatory and binding
Upon completion of 0036AB
EXERCISE
NTE
Qty
Unit Unit Price
TOTAL
agreements - FFP.
0037 WM015 – Oasis MWR Yard (N015)
0037AA WM015 – Oasis MWR Yard (N015):
Mobilize and develop an optimized exit strategy (OES) plan to achieve Site Closeout (SC) while maintaining compliance with current regulatory and binding agreements - FFP.
At Award 1 LS
0037AB
OPTION
WM015 – Oasis MWR Yard (N015):
Implement OES strategy and deliver a Final OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements - FFP.
Upon completion of 0037AA
1 LS
0037AC
OPTION
WM015 – Oasis MWR Yard (N015):
Deliver a Final OES Effectiveness Report to achieve SC documenting the completion of the approved strategy that fell within the POP while maintaining compliance with current regulatory and binding agreements -
FFP.
Upon completion of 0037AB
1 LS
0038 SA020 – Satellite Accumulation Site
TE-06 (N020)
0038AA SA020 – Satellite Accumulation Site TE-06 (N020): Mobilize and develop an optimized exit strategy (OES) plan to achieve Site Closeout (SC) while maintaining compliance with current regulatory and binding agreements -
FFP.
At Award 1 LS
0038AB
OPTION
SA020 – Satellite Accumulation Site TE-06 (N020): Implement OES strategy and deliver a Final OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements - FFP.
Upon completion of 0038AA
1 LS
0038AC
OPTION
SA020 – Satellite Accumulation Site TE-06 (N020): Deliver a Final OES Effectiveness Report to achieve SC documenting the completion of the approved strategy that fell within the POP while maintaining compliance with current regulatory and binding agreements - FFP.
Upon completion of 0038AB
EXERCISE
NTE
Qty
Unit Unit Price
TOTAL
0039 SA021 – Satellite Accumulation Site
TM-04 (N021)
0039AA SA021 – Satellite Accumulation Site TM-04 (N021): Mobilize and develop an optimized exit strategy (OES) plan to achieve Site Closeout (SC) while maintaining compliance with current regulatory and binding agreements -
FFP.
At Award 1 LS
0039AB
OPTION
SA021 – Satellite Accumulation Site TM-04 (N021): Implement OES strategy and deliver a Final OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements - FFP.
Upon completion of 0039AA
1 LS
0039AC
OPTION
SA021 – Satellite Accumulation Site TM-04 (N021): Deliver a Final OES Effectiveness Report to achieve SC documenting the completion of the approved strategy that fell within the POP while maintaining compliance with current regulatory and binding agreements - FFP.
Upon completion of 0039AB
1 LS
0040 SA024 – Satellite Accumulation Site
TU-05 (N024)
0040AA SA024 – Satellite Accumulation Site TU-05 (N024): Mobilize and develop an optimized exit strategy (OES) plan to achieve Site Closeout (SC) while maintaining compliance with current regulatory and binding agreements -
FFP.
At Award 1 LS
0040AB
OPTION
SA024 – Satellite Accumulation Site TU-05 (N024): Implement OES strategy and deliver a Final OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements - FFP.
Upon completion of 0040AA
1 LS
0040AC
OPTION
SA024 – Satellite Accumulation Site TU-05 (N024): Deliver a Final OES Effectiveness Report to achieve SC documenting the completion of the approved strategy that fell within the POP while maintaining compliance with current regulatory and binding agreements - FFP.
Upon completion of 0040AB
EXERCISE
NTE
Qty
Unit Unit Price
TOTAL
0041 PP027 – LM Missile Motor Test Pads (N027-1 and N027-2)
0041AA PP027 – LM Missile Motor Test Pads (N027-1 and N027-2): Mobilize and develop an optimized exit strategy (OES) plan to achieve Site Closeout (SC) while maintaining compliance with current regulatory and binding agreements - FFP.
At Award 1 LS
0041AB
OPTION
PP027 – LM Missile Motor Test Pads (N027-1 and N027-2): Implement OES strategy and deliver a Final OES Implementation Completion Plan while maintaining compliance with current regulatory and binding agreements - FFP.
Upon completion of 0041AA
1 LS
0041AC
OPTION
PP027 – LM Missile Motor Test Pads (N027-1 and N027-2): Deliver a Final OES Effectiveness Report to achieve SC documenting the completion of the approved strategy that fell within the POP while maintaining compliance with current regulatory and binding agreements - FFP.
Upon completion of 0041AB
1 LS
0042 SWMU 11 - Thermal Treatment Unit:
0042AA
OPTION
SWMU 11 - Thermal Treatment Unit:
Conduct required annual groundwater monitoring and reporting in accordance with Table 2 of the SOO (Year 1) – FFP/FUP
FY14 Subject to Availability of Funds
1 year
0042AB
OPTION
SWMU 11 - Thermal Treatment Unit:
Conduct required annual groundwater monitoring and reporting in accordance with Table 2 of the SOO (Year 2) - FFP/FUP
Upon completion of 00042AA.
1 year
0042AC
OPTION
SWMU 11 - Thermal Treatment Unit:
Conduct required annual groundwater monitoring and reporting in accordance with Table 2 of the SOO (Year 3) - FFP/FUP
Upon completion of 00042AB
1 year
0042AD
OPTION
SWMU 11 - Thermal Treatment Unit:
Conduct required annual groundwater monitoring and reporting in accordance with Table 2 of the SOO (Year 4) - FFP/FUP
Upon completion of 00042AC.
1 year
0042AE
OPTION
SWMU 11 - Thermal Treatment Unit:
Conduct required annual groundwater monitoring and reporting in
Upon completion of 00042AD.
1 year
EXERCISE
NTE
Qty
Unit Unit Price
TOTAL
accordance with Table 2 of the SOO (Year 5) - FFP/FUP
0042AF
OPTION
SWMU 11 - Thermal Treatment Unit:
Conduct required annual groundwater monitoring and reporting in accordance with Table 2 of the SOO (Year 6) - FFP/FUP
Upon completion of 00042AE
1 year
0042AG
OPTION
SWMU 11 - Thermal Treatment Unit:
Conduct required annual groundwater monitoring and reporting in accordance with Table 2 of the SOO (Year 7) - FFP/FUP
Upon completion of 00042F
1 year
0042AH
OPTION
SWMU 11 - Thermal Treatment Unit:
Conduct required annual groundwater monitoring and reporting in accordance with Table 2 of the SOO (Year 8) - FFP/FUP
Upon completion of 00042AG
1 year
0042AJ
OPTION
SWMU 11 - Thermal Treatment Unit:
Conduct required annual groundwater monitoring and reporting in accordance with Table 2 of the SOO (Year 9) - FFP/FUP
Upon completion of 00042AH
1 year
0042AK
OPTION
SWMU 11 - Thermal Treatment Unit:
Conduct required annual groundwater monitoring and reporting in accordance with Table 2 of the SOO (Year 10) - FFP/FUP
Upon completion of 00042AJ
1 year
0043 WP025 – UTTR Chemical Pit 4 (OU NR-1) (N012): Abandon all groundwater monitoring infrastructure in accordance with Table 2 of the
SOO – FFP.
At Award 1 LS
0044 SWMU 2, SWMU 9, SWMU 10,
SWMU 17, SWMU 30, SWMU 33,
SWMU 34. SWMU 36, SWMU 37,
SWMU 39, SWMU 43, SWMU 44,
SWMU 48, SWMU 60, SWMU 61,
SWMU 62, SWMU 65, SWMU 67,
and SWMU 92:
0044AA SWMU 2, SWMU 9, SWMU 10,
SWMU 17, SWMU 30, SWMU 33,
SWMU 34. SWMU 36, SWMU 37,
SWMU 39, SWMU 43, SWMU 44,
SWMU 48, SWMU 60, SWMU 61,
SWMU 62, SWMU 65, SWMU 67,
and SWMU 92: Meet Site Management Plan (SMP) requirements in accordance with Table 2 of the SOO (Year 1) – FFP/FUP.
FY14 Subject to Availability of
EXERCISE
NTE
Qty
Unit Unit Price
TOTAL
0044AB
OPTION
SWMU 2, SWMU 9, SWMU 10,
SWMU 17, SWMU 30, SWMU 33,
SWMU 34. SWMU 36, SWMU 37,
SWMU 39, SWMU 43, SWMU 44,
SWMU 48, SWMU 60, SWMU 61,
SWMU 62, SWMU 65, SWMU 67,
and SWMU 92: Meet Site Management Plan (SMP) requirements in accordance with Table 2 of the SOO (Year 2) – FFP/FUP.
Upon completion of 0044AA
1 year
0044AC
OPTION
SWMU 2, SWMU 9, SWMU 10,
SWMU 17, SWMU 30, SWMU 33,
SWMU 34. SWMU 36, SWMU 37,
SWMU 39, SWMU 43, SWMU 44,
SWMU 48, SWMU 60, SWMU 61,
SWMU 62, SWMU 65, SWMU 67,
and SWMU 92: Meet Site Management Plan (SMP) requirements in accordance with Table 2 of the SOO (Year 3) – FFP/FUP.
Upon completion of 0044AB
1 year
0044AD
OPTION
SWMU 2, SWMU 9, SWMU 10,
SWMU 17, SWMU 30, SWMU 33,
SWMU 34. SWMU 36, SWMU 37,
SWMU 39, SWMU 43, SWMU 44,
SWMU 48, SWMU 60, SWMU 61,
SWMU 62, SWMU 65, SWMU 67,
and SWMU 92: Meet Site Management Plan (SMP) requirements in accordance with Table 2 of the SOO (Year 4) – FFP/FUP.
Upon completion of 0044AC
1 year
0044AE
OPTION
SWMU 2, SWMU 9, SWMU 10,
SWMU 17, SWMU 30, SWMU 33,
SWMU 34. SWMU 36, SWMU 37,
SWMU 39, SWMU 43, SWMU 44,
SWMU 48, SWMU 60, SWMU 61,
SWMU 62, SWMU 65, SWMU 67,
and SWMU 92: Meet Site Management Plan (SMP) requirements in accordance with Table 2 of the SOO (Year 5) – FFP/FUP.
Upon completion of 0044AD
1 year
0044AF
OPTION
SWMU 2, SWMU 9, SWMU 10,
SWMU 17, SWMU 30, SWMU 33,
SWMU 34. SWMU 36, SWMU 37,
SWMU 39, SWMU 43, SWMU 44,
SWMU 48, SWMU 60, SWMU 61,
SWMU 62, SWMU 65, SWMU 67,
and SWMU 92: Meet Site Management Plan (SMP) requirements in accordance with Table 2 of the SOO (Year 6) – FFP/FUP.
Upon completion of 0044AE
EXERCISE
NTE
Qty
Unit Unit Price
TOTAL
0044AG
OPTION
SWMU 2, SWMU 9, SWMU 10,
SWMU 17, SWMU 30, SWMU 33,
SWMU 34. SWMU 36, SWMU 37,
SWMU 39, SWMU 43, SWMU 44,
SWMU 48, SWMU 60, SWMU 61,
SWMU 62, SWMU 65, SWMU 67,
and SWMU 92: Meet Site Management Plan (SMP) requirements in accordance with Table 2 of the SOO (Year 7) – FFP/FUP.
Upon completion of 0044AF
1 year
0044AH
OPTION
SWMU 2, SWMU 9, SWMU 10,
SWMU 17, SWMU 30, SWMU 33,
SWMU 34. SWMU 36, SWMU 37,
SWMU 39, SWMU 43, SWMU 44,
SWMU 48, SWMU 60, SWMU 61,
SWMU 62, SWMU 65, SWMU 67,
and SWMU 92: Meet Site Management Plan (SMP) requirements in accordance with Table 2 of the SOO (Year 8) – FFP/FUP.
Upon completion of 0044AG
1 year
0044AJ
OPTION
SWMU 2, SWMU 9, SWMU 10,
SWMU 17, SWMU 30, SWMU 33,
SWMU 34. SWMU 36, SWMU 37,
SWMU 39, SWMU 43, SWMU 44,
SWMU 48, SWMU 60, SWMU 61,
SWMU 62, SWMU 65, SWMU 67,
and SWMU 92: Meet Site Management Plan (SMP) requirements in accordance with Table 2 of the SOO (Year 9) – FFP/FUP.
Upon completion of 0044AH
1 year
0044AK
OPTION
SWMU 2, SWMU 9, SWMU 10,
SWMU 17, SWMU 30, SWMU 33,
SWMU 34. SWMU 36, SWMU 37,
SWMU 39, SWMU 43, SWMU 44,
SWMU 48, SWMU 60, SWMU 61,
SWMU 62, SWMU 65, SWMU 67,
and SWMU 92: Meet Site Management Plan (SMP) requirements in accordance with Table 2 of the SOO (Year 10) – FFP/FUP.
Upon completion of 0044AJ
1 year
[additional Sub-CLINs beyond minimum performance objectives to be proposed consistent with the contractors approach]
TOTAL
Note: If additional Sub-CLINS are created prior to award pursuant to Sub-CLIN restructuring, some or all could be re-numbered to be sequential. Projected dates of exercise are the anticipated award dates for the Sub-CLINS, but will be subject to the availability of funding and to the bona fide needs rule. No FUNDED CONTRACT LINE
ITEM will exceed a five (5) year period of performance. The contract in its entirety will not exceed a ten (10) year period of performance from date of contract award.
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
The following have been modified:
STATEMENT OF OBJECTIVES
STATEMENT OF OBJECTIVES (SOO)
FOR
PERFORMANCE-BASED REMEDIATION (PBR)
AT
UTAH TEST AND TRAINING RANGE, HILL AIR FORCE BASE
CONTRACT NUMBER: TBD
19 Jun 2013
Table of Contents
1.0 SCOPE
1.1 INTRODUCTION
1.2 SITE HISTORY
1.3 GENERAL PBR SCOPE AND REQUIREMENTS
1.4 KEY PERSONNEL
2.0 APPLICABLE DOCUMENTS
3.0 GOVERNMENT FURNISHED INFORMATION, EQUIPMENT, AND PROPERTY (GFI, GFE,
GFP)
4.0 MANAGEMENT, PLANNING, AND REPORTING REQUIREMENTS
4.1 MILESTONE PAYMENT SCHEDULE (MPS)
4.2 PROJECT MANAGEMENT PLAN (PMP)
4.3 PBR DOCUMENT REPOSITORY
4.4 WORK BREAKDOWN STRUCTURE
4.5 SCHEDULE AND PLANNING REQUIREMENTS
4.5.1 Project Planning Chart and/or Construction Planning Chart
4.5.2 Integrated Master Schedule (IMS)
4.6 COST AND STATUS REPORTING
4.6.1 Contractor’s Progress, Status, and Management Report (CPSMR)
4.7 MEETING AND CONFERENCE REQUIREMENTS
4.7.1 Meeting/Teleconference Support
4.7.2 Public Meetings and Hearings
4.8 CONTRACTOR DOCUMENTATION
4.9 SPATIAL DATA (MAP) REQUIREMENTS
4.10 NOTIFICATION REQUIREMENTS
4.11 PERMITS
4.11.1 Environmental Permits
4.11.2 Rights of Access to Non-AF Real Property
4.11.3 New Rights-of-Entry and Leases
4.12 PHOTO DOCUMENTATION
4.13 REMOTE AND/OR AUSTERE SITES
4.14 SITE ACCESS BADGES
4.14.1 On-Base Identification Badge
4.14.2 Authorized Escorts
4.15 WORKSITE ACTIVITIES AND COORDINATION
4.15.1 Coordination of Activities
4.15.2 Hazardous Material and Hazardous Waste Permitting and Reporting
5.0 CHEMISTRY REQUIREMENTS
5.1 QUALITY CONTROL
5.2 LABORATORY SELECTION
5.3 ANALYTICAL DATA MANAGEMENT
5.4 RECORD KEEPING
6.0 PLANS AND REPORTS
6.1 QUALITY PROGRAM PLANS (QPP)
6.2 TECHNICAL PLANS AND REPORTS
6.2.1 Technical Plans
6.2.2 Technical Reports
7.0 SITE WORK
7.1 CONSERVATION
7.1.1 Natural Resources Protection on DoD Property
7.1.2 Cultural Resources Management on DoD Property
7.2 DEMOBILIZATION
7.3 SITE CHARACTERIZATION
7.4 SITE PREPARATION
7.5 DEMOLITION
8.0 ENVIRONMENTAL REQUIREMENTS
8.1 PERFORMANCE-BASED REMEDIATION (PBR)
8.1.1 Scope Discussion and Limits
8.1.2 Environmental Liabilities
8.1.3 Transition of Work
8.1.4 Guarantee Limit (and Option of Environmental Insurance)
8.2 ENVIRONMENTAL CONSTRUCTION
8.2.1 Completion of Conceptual Design
8.2.2 Study Effort Incidental to Remedy or Corrective Action
8.2.3 Construction
8.2.4 Pre-Final Inspection
8.2.5 Final Inspection
8.2.6 Delivery and Warranty
8.3 ENVIRONMENTAL RESOURCES PROGRAM INFORMATION MANAGEMENT SYSTEM (ERPIMS)
8.4 INNOVATIVE AND PROVEN TECHNOLOGIES
8.5 OPERATIONS AND MAINTENANCE
8.6 MILITARY MUNITIONS RESPONSE AND SUPPORT
8.7 PRESUMPTIVE AND OTHER REMEDIES
8.7.1 Requirements
8.7.2 Regulatory Site Closeout
8.8 HAZARDOUS WASTE REMOVAL AND SUPPORT
9.0 ADDITIONAL REQUIREMENTS
10.0 POINTS OF CONTACT
11.0 ABBREVIATIONS, ACRONYMS, AND TERMS
ATTACHMENTS
ATTACHMENT 1 – Reserved ATTACHMENT 2 – Site List & Escort Requirements ATTACHMENT 3 – Recurring Report Deadlines List ATTACHMENT 4 – Reserved ATTACHMENT 5 – Format for Metadata ATTACHMENT 6 – Public Affairs Support Requirements
1.0 SCOPE
This requirement is for environmental remediation activities at the Utah Test and Training Range (UTTR), Hill Air Force Base (HAFB). This Statement of Objectives (SOO) defines the scope for a Performance-Based Remediation (PBR) requirement which includes a full range of environmental remediation activities necessary to achieve minimum performance objectives, and support progress to Site Closeout (SC) at 18 Installation Restoration Program (IRP) sites, and 15 Military Munitions Response Program (MMRP) Munitions Response Areas (MRAs)). This SOO also includes 29 RCRA Compliance Solid and Hazardous Waste Management Units (SWMUs) (see Attachment 2, Managed IRP Site ID/SWMU [RCRA] column).
1.1 Introduction
The UTTR is an approximately one-million acre test and training range comprised of the North Range, South Range and Wendover Parcel. It has been used since the 1940s and is presently an active range with strict coordination, access and escort requirements. The Wendover Parcel is located in both Utah and Nevada and is a closed range. The Nevada portion of the Wendover Parcel is currently being considered for transfer.
Environmental remediation activities at the UTTR are being conducted pursuant to the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) under an Integration Agreement (IA) with the Utah Department of Environmental Quality (UDEQ) with oversight from U.S. Environmental Protection Agency (EPA) Region 8. The Nevada Division of Environmental Protection (NDEP) provides regulatory oversight for UTTR sites in Nevada (including sites managed under CERCLA and the MMRP). EPA Region 9 has delegated oversight authority to NDEP for the sites within Nevada. Some environmental remediation activities at the UTTR North Range are being conducted pursuant to the Resource Conservation and Recovery Act (RCRA) under a Part B Permit, with regulatory oversight provided by the UDEQ, Division of Solid and Hazardous Waste (DSHW).
The open IRP sites are currently managed in four operable units (OUs) as follows: North Range OU NR-1 (Site WP025) and OU NR-2 (Sites OT104 and OT105); and South Range OU SR-1 (Site OT102) and OU SR-2 (Site OT103). Sites ST079, OT013, OT098, OT099, and OT0101 are managed outside of these OUs, but are also included in this SOO. There are 37 sites included in this SOO that are managed under the RCRA Permit. Included in these 37 sites are eight IRP sites (OW004, LF007, AT014, WM015, SA020, SA021, SA024, and PP027) and 29 RCRA Compliance SWMUS. Of the 29 RCRA Compliance SWMUs, only 28 require inspections and reporting; one SWMU is the Thermal Treatment Unit (SWMU 11) which will be visited in order to conduct groundwater sampling.
Fifteen (15) MRAs are currently being managed under the MMRP.
MRA 184 Wendover AF Auxiliary Range Nevada, located on Department of Defense (DoD) property in Nevada and Utah and includes five (5) MRSs; AL501B, AL501C, AL501D, AL501E, and AL501F.
MRA 203, 50 Cal Strafing Target and Sparse Scattered Munitions and Explosives of Concern (MEC), located on Bureau of Land Management (BLM) land in Utah and Nevada and Utah School and Institutional Trust Land Administration (SITLA) land in Utah and includes the following MRSs: MU505, MU505a, MU505b.
No Further Action (NFA) is being pursued for MU505b under separate contract.
Based on the preliminary results of the comprehensive site evaluation (CSE) Phase II, the following MRAs are anticipated to be divided into separate MRSs.
MRA 204, Practice Bombing Range, located on BLM and SITLA land in Utah and includes MRS TG506.
MRA 205, Practice Bombing Range, located on BLM land in Utah and includes MRS
TG507.
MRA 206, Open Detonation Operation, located on BLM land in Utah and includes MRS
OD508.
MRA 207, Practice Bombing Range and Jettison Area, located on BLM and SITLA land in Utah and includes MRS TG509.
MRA 208, Plane Crash, located on BLM land in Utah and includes MRS AL510.
MRA 209, Practice Bombing Range and Jettison Area, located on BLM and SITLA land in Utah and includes MRS TG511.
MRA 210, Scattered Sparse MEC, located on BLM and SITLA land in Utah and includes
MRS XU512.
MRA 513, South Aragonite Craters, located on BLM land in Utah and includes MRS
OD513.
1.2 RESERVED
1.3 General PBR Scope and Requirements
The contractor shall perform all the necessary environmental construction and engineering activities as required to achieve the performance objectives of this SOO.
Table 1 and Table 2 show the sites included in the scope of this requirement. Attachment 2 provides more information on these sites, particularly with respect to how they are identified and tracked by the Government.
The Air Force (AF) is required to implement remedies as necessary to protect human health and the environment. The intent of the PBR initiative is to maximize the number of SCs or advance sites as close to SC as practicable during the period of performance (POP) in a cost effective manner. It is desirable to the AF that life-cycle costs (LCC) be reduced. The AF is interested in substantial reduction of long-term environmental liabilities and LCC through accelerated achievement of SC and optimization of environmental restoration activities for all sites included in this contract while complying with applicable federal, state and local laws and regulations;
and applicable U.S. Army Corps of Engineers (USACE), AF, and base-specific orders, agreements, or rules. General performance objectives pursuant to the AF’s overarching goals are listed below in order of priority:
1) Achieve SC during the POP.
2) For any site not achieving SC during the POP, achieve:
a. Response Complete (RC)
b. Remedy in Place (RIP)
c. The furthest objective within the regulatory structure for each site (e.g. Decision
Document (DD), Preliminary Assessment/Site Inspection (PA/SI), etc.)
3) The contractor shall develop an Optimized Exit Strategy (OES) for sites identified in Table 1 of this SOO that have an approved DD prior to, or during the POP, but do not achieve SC. OES compendium provides additional detail. The contractor shall describe the strategy in an OES Plan to meet the following objectives:
Maintain compliance with all DDs and plans (currently in place or to be approved) until no longer required or an alternate approach is approved.
Implement recommendations presented in five year reviews.
Apply innovative technologies to minimize the cost and period of operating, monitoring and treatment.
Improve the understanding of the Conceptual Site Model (CSM), existing systems, and contamination sources to support optimization.
Provide an analysis of alternatives for each site to aggressively accelerate treatment and progress to expedite SC. Alternatives shall include technical approach, cost estimates and a business case analysis.
Develop performance indicators, decision criteria, and objectives consistent with the performance model described below that will be used to optimize remedial efficiency, quantify how the response is progressing and demonstrate when the objective has been reached. The following are the minimum required OES deliverables: an OES Plan shall be delivered within one year from either date of award or exercise of the option of the SubCLIN, whichever is applicable. An OES Implementation Completion Report shall be delivered upon completion of the implementation of the optimization efforts in the approved OES Plan, and one of the final milestones shall be an OES Effectiveness Report.
o The OES Effectiveness Report shall include:
a) Documentation of what remedial strategies were implemented, what remains to be implemented, and any modifications to the OES arising from performance to date.
b) A realistic schedule to achieve SC or RC after the POP (the contractor shall identify which performance objective is the optimal endpoint). For sites with an indeterminate project completion date, a schedule for 30 years beyond the POP is required.
c) The remaining definable and measurable milestones after the POP.
4) For all sites listed in Table 1 of this SOO that have an approved DD prior to or during the POP and are not being proposed to SC during the POP, the contractor shall develop performance models that describe the expected course of the remediation process (i.e.
how conditions are expected to change over time as measured using appropriate performance indicators from the current state until the performance objective is achieved). For all sites being proposed to SC during the POP, the work planning documents are expected to contain the performance model. The contractor shall provide monitoring reports that demonstrate whether or not the remedial approach is performing in accordance with the performance model. For purposes of reporting contractor progress and status, these conditions shall be quantified by performance indicators relevant to the proposed remedial approach. A performance model is a graphic representation of a performance indicator value over time until a performance objective is achieved. Several indicators may be needed to adequately reflect performance. The contractor shall report the actual remedy performance compared to projected. The contractor shall ensure consistency and continuity of information regarding performance between the Project Management Plan (PMP), Integrated Master Schedule (IMS)/Milestone Payment Schedule (MPS), and OES Plan. The OES plan must include the performance model.
Within the construct of the goals and objectives above, the minimum performance objectives and specific performance objectives to be achieved for each site during the POP for this contract are outlined in Table 1 and Table 2 of the SOO. The sites listed in Table 2 are not closed per the AF SC definition; however, they are located within the active range and the AF does not plan to do additional actions at these sites. If the contractor anticipates the ability to achieve a stretch goal during the POP, the contractor is encouraged to propose that stretch goal, which will then become the requirement (applicable to sites in Table 1 of this SOO only). The contractor shall specify, for each site, the performance objective to include at least the minimum objective as listed for sites in Table 1 of this SOO, and the specific performance objectives of sites in Table 2 of this SOO (with no stretch goal proposed) and date they intend to achieve it for each site within the POP. Contractors shall explain why the selected performance objective (including the minimum performance objective if that is what is proposed) is an optimum solution for the Government for sites in Table 1. It should be noted that the Government reserves the right not to exercise all options not awarded at the time of contract award.
Table 1: Minimum Performance Objectives and Standards
Minimum Performance Objectives Minimum Performance Standards
All Sites
Approved PMP:
Preliminary PMP within 45 calendar days of contract award.
Final PMP expected approximately 4.5 years after award of the Preliminary PMP.
Time-phased updates, submitted annually (at minimum) or more frequently, as appropriate to maintain accuracy and completeness.
Government approval through the Contracting Officer’s Representative (COR).
Provide support (supply documents to independent reviewers, participate in meetings/interviews, etc.) for Five- Year Reviews required for all site(s) identified in the contract for the duration of the contract. Correct any remedy or site deficiencies noted in Five-Year Reviews.
The first Five-Year Review is projected to be completed in 2017.
Government approval through the COR and Regulatory approval (e.g., formal documentation accepting correction of deficiencies).
Beginning at Date of Award, or upon achievement of RIP or RC, or any performance objective that is not SC, conduct, as appropriate, Remedial Action-Operation (RA-O) and/or Long-Term Management (LTM) and develop an OES to achieve SC and implement the elements of the approved strategy that fall within the POP. RA-O/LTM and implementation of the OES shall continue through the duration of the POP or until 1) no longer required based on Government and regulatory concurrence that SC has been achieved or 2) Government, through the COR, and regulators have approved implementation of an alternative approach. This MPO applies only to those sites addressed in Table 1. Unless otherwise indicated, the development and implementation of an OES will not be required for MRS/MRAs.
COR for RA-O/LTM reports and Regulatory approval (e.g., formal regulator documentation accepting the RA-O/LTM report).
Government approval through the COR for OES Plan and OES Effectiveness Report and approval of Regulatory required document.
Achieve Site Closeout (SC) within three (3) years from Date of Award for the following sites:
OT103 (only S208 – Ore Processing Site) AL510 –Aircraft Debris (MRA 208) ST079 – Remnant POL Contamination, Oasis
(XN379)
OT104 (only N063S – Target Debris Accumulation
Area)
COR and Regulatory approval of unrestricted use of the site (e.g.
written confirmation of acceptance of SC documentation).
Complete Decision Document (DD) within two (2) years from Date of Award for the following sites:
OT102 –UTTR South (OU SR-1) OT104 except N063S – UTTR North, North Half
(OU NR-2)
OT105 – UTTR North, South Half (OU NR-2)
Government approval through the COR and Regulatory approval site (e.g. written confirmation of acceptance of DD documentation).
Achieve Response Complete (RC) within three (3) years from Date of Award for the following site:
OT103 (only S292 – Post Engineering Salvage Yard)
(e.g., written confirmation of acceptance of documentation demonstrating RC).
Achieve Remedy-In-Place (RIP) within three (3) years of Date of Award for the following sites:
OT102 –UTTR South (OU SR-1) OT104 except N063S – UTTR North, North Half
(OU NR-2)
OT105 – UTTR North, South Half (OU NR-2)
(e.g., written confirmation of acceptance of documentation demonstrating RIP).
Complete Remedial Investigation (RI)/Feasibility Study (FS) within two (2) years from Date of Award for the following MRSs:
AL501B - Wendover (MRA 184) AL501C - Wendover (MRA 184) AL501D -…