2. DATE ISSUED 3. DATE OPENED
28-Jun-13 6-Aug-13
I CERTIFY THAT I HAVE OPENED, READ AND
RECORDED ON THIS ABSTRACT ALL OFFERS
RECEIVED IN RESPONSE TO THIS SOLICITATION DATE SIGNED
C. REASONABLE CONTRACT
7A 7B 7C D. E. F. E. F. E. F.
ITEM # DESCRIPTION OF OFFER ITEM EST. QTY UNIT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT
Entire Work Complete to Construct Climbing Tower with Reinforced Concrete Composite Material Climbing System Job LS $1,324,350.00 $1,901,526.00 $2,077,732.00
Entire Work Complete to Construct Precast Concrete Surface as Shown on Drawings
Job LS $133,015.00 $189,438.00 $190,815.00
Enitre Work Complete to Construct Cementitious Coated Plywood Climbing System Job LS $140,155.00 $110,590.00 $132,708.00
Entire Work Complete to Construct 2x6 Wood Climbing Surface
Job LS $31,565.00 $114,108.00 $136,930.00
Entire Work Complete to Construct Additonal 5 Climbing Lanes of Reinforced Concrete Composite Material Climbing System
Job LS $159,715.00 $218,340.00 $204,880.00
Entire Work Complete to Construct Climbing Tower Bridge as Shown on Drawings
Job LS $89,490.00 $94,577.00 $132,613.00
TOTAL AMOUNT $1,878,290.00 $2,628,579.00 $2,875,678.00
9. OFFERS
SIGNATURE
NAME AND TITLE OF CERTIFYING OFFICIAL (Type) Tyler Hegge, Contract Specialist
ABSTRACT OF OFFERS - CONSTRUCTION
1. SOLICITATION NUMBER
W9128F13B0009
4. ISSUING OFFICE
8. GOVERNMENT ESTIMATE5. PROJECT TITLE
OMAHA, NE 68102
1616 Capitol Avenue
CONTRACTING DIVISION (CENWO-CT)
US ARMY CORPS OF ENGINEERS
B. REASONABLE CONTRACT
NO. 1 NO. 2 (Check A, B or C AND COMPLETE D, E AND F)
1015 Fir 240 Mill Dr.
A. HIRED LABOR
Cortez Construction Co., Inc. Mack Mechanical, Inc.
B. BID SECURITY
C. AMENDMENTS ACKNOWLEDGED
C. AMENDMENTS ACKNOWLEDGED
Cookeville, TN 38501
B. BID SECURITY
OPTION ITEMS
6. NUMBER OF AMENDMENTS ISSUED
SOF Mountaineering Climbing/Rapelling Tower
FORT CARSON, CO
20% (Without Profit)
(Including Profit)
Pueblo, CO 81001
20%
I CERTIFY THAT I HAVE OPENED, READ AND
ITEM # DESCRIPTION OF OFFER ITEM EST. QTY UNIT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT
Entire Work Complete to Construct Climbing Tower with Reinforced Concrete Composite Material Climbing System Job LS $1,741,833.66 $1,700,000.00 $1,717,481.00
Entire Work Complete to Construct Precast Concrete Surface as Shown on Drawings
Job LS $211,111.04 $166,700.00 $181,046.00
Enitre Work Complete to Construct Cementitious Coated Plywood Climbing System Job LS $133,793.00 $118,700.00 $105,937.00
Entire Work Complete to Construct 2x6 Wood Climbing Surface
Job LS $108,321.08 $64,000.00 $35,974.00
Entire Work Complete to Construct Additonal 5 Climbing Lanes of Reinforced Concrete Composite Material Climbing System
Job LS $259,084.38 $234,000.00 $180,714.00
Entire Work Complete to Construct Climbing Tower Bridge as Shown on Drawings
Job LS $138,598.76 $77,000.00 $99,337.00
TOTAL AMOUNT $2,592,741.92 $2,360,400.00 $2,320,489.00
4. ISSUING OFFICE NAME AND TITLE OF CERTIFYING OFFICIAL (Type)
ABSTRACT OF OFFERS - CONSTRUCTION
1. SOLICITATION NUMBER Page 2 of 5
W9128F13B0009
US ARMY CORPS OF ENGINEERS Tyler Hegge, Contract Specialist
CONTRACTING DIVISION (CENWO-CT) SIGNATURE
1616 Capitol Avenue *
OMAHA, NE 68102
5. PROJECT TITLE 9. OFFERS
NO.3 NO. 4 NO. 5
SOF Mountaineering Climbing/Rapelling Tower FORT CARSON, CO CMS Inc. of Colorado Springs White Construction Group J&S Construction Company
6 N. Tejon St. 18 S Wilcox St. 1843 Foreman Dr.
Colorado Springs, CO Castle Rock, CO 80104 Cookville, TN
B. BID SECURITY B. BID SECURITY B. BID SECURITY
20% 20% 20%
6. NUMBER OF AMENDMENTS ISSUED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGEDC. AMENDMENTS ACKNOWLEDGED
3 3 3 3
OPTION ITEMS
I CERTIFY THAT I HAVE OPENED, READ AND
ITEM # DESCRIPTION OF OFFER ITEM EST. QTY UNIT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT
Entire Work Complete to Construct Climbing Tower with Reinforced Concrete Composite Material Climbing System Job LS $1,750,604.00 $1,702,498.00 $1,518,000.00
Entire Work Complete to Construct Precast Concrete Surface as Shown on Drawings
Job LS $174,207.00 $202,350.00 $141,000.00
Enitre Work Complete to Construct Cementitious Coated Plywood Climbing System Job LS $109,840.00 $125,662.00 $120,000.00
Entire Work Complete to Construct 2x6 Wood Climbing Surface
Job LS $56,294.00 $81,257.00 $26,000.00
Entire Work Complete to Construct Additonal 5 Climbing Lanes of Reinforced Concrete Composite Material Climbing System
Job LS $233,682.00 $243,570.00 $219,000.00
Entire Work Complete to Construct Climbing Tower Bridge as Shown on Drawings
Job LS $133,844.00 $68,129.00 $69,000.00
TOTAL AMOUNT $2,458,471.00 $2,423,466.00 $2,093,000.00
4. ISSUING OFFICE NAME AND TITLE OF CERTIFYING OFFICIAL (Type)
ABSTRACT OF OFFERS - CONSTRUCTION
1. SOLICITATION NUMBER Page 3 of 5
W9128F13B0009
US ARMY CORPS OF ENGINEERS Tyler Hegge, Contract Specialist
CONTRACTING DIVISION (CENWO-CT) SIGNATURE
1616 Capitol Avenue *
OMAHA, NE 68102
5. PROJECT TITLE 9. OFFERS
NO.6 NO. 7 NO. 8
SOF Mountaineering Climbing/Rapelling Tower FORT CARSON, CO Ayuda Management Corporation Bristol General Contractors, LLC Iron Mike Construction
11800 Ridge Parkway, Ste. 550 111 W. 16th Ave 6950 S. Tucson Way Ste A Broomfield, CO 80021 Anchorage, Alaska 99501 Centennial, CO 80112
B. BID SECURITY B. BID SECURITY B. BID SECURITY
20% 20% 20%
6. NUMBER OF AMENDMENTS ISSUED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGEDC. AMENDMENTS ACKNOWLEDGED
I CERTIFY THAT I HAVE OPENED, READ AND
ITEM # DESCRIPTION OF OFFER ITEM EST. QTY UNIT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT
Entire Work Complete to Construct Climbing Tower with Reinforced Concrete Composite Material Climbing System Job LS $ 1,335,646.00 $1,877,200.00 $1,712,109.00
Entire Work Complete to Construct Precast Concrete Surface as Shown on Drawings
Job LS $252,000.00 $205,000.00 $183,708.00
Enitre Work Complete to Construct Cementitious Coated Plywood Climbing System Job LS $105,325.00 $120,000.00 $123,084.00
Entire Work Complete to Construct 2x6 Wood Climbing Surface
Job LS $64,320.00 $120,000.00 $66,501.00
Entire Work Complete to Construct Additonal 5 Climbing Lanes of Reinforced Concrete Composite Material Climbing System
Job LS $100,525.00 $235,000.00 $255,158.00
Entire Work Complete to Construct Climbing Tower Bridge as Shown on Drawings
Job LS $77,200.00 $120,000.00 $133,027.00
TOTAL AMOUNT $1,935,016.00 $2,677,200.00 $2,473,587.00
4. ISSUING OFFICE NAME AND TITLE OF CERTIFYING OFFICIAL (Type)
ABSTRACT OF OFFERS - CONSTRUCTION
1. SOLICITATION NUMBER Page 4 of 5
W9128F13B0009
US ARMY CORPS OF ENGINEERS Tyler Hegge, Contract Specialist
CONTRACTING DIVISION (CENWO-CT) SIGNATURE
1616 Capitol Avenue *
OMAHA, NE 68102
5. PROJECT TITLE 9. OFFERS
NO.9 NO. 10 NO. 11
SOF Mountaineering Climbing/Rapelling Tower FORT CARSON, CO Timus-NASCO JV Growling Bear Co., Inc. Medvolt, LLC
8131 Baymeadows Circle 2330 4th Ave 5045 List Drive Jacksonville, FL 32256 Greely, CO 80631 Colorado Springs, CO 80919
B. BID SECURITY B. BID SECURITY B. BID SECURITY
20% 20% 20%
6. NUMBER OF AMENDMENTS ISSUED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGEDC. AMENDMENTS ACKNOWLEDGED
I CERTIFY THAT I HAVE OPENED, READ AND
7A 7B 7C D. E. F. E. F.
ITEM # DESCRIPTION OF OFFER ITEM EST. QTY UNIT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT
Entire Work Complete to Construct Climbing Tower with Reinforced Concrete Composite Material Climbing System Job LS $1,998,000.00 $1,598,065.00
Entire Work Complete to Construct Precast Concrete Surface as Shown on Drawings
Job LS $203,000.00 $160,981.00
Enitre Work Complete to Construct Cementitious Coated Plywood Climbing System Job LS $164,000.00 $95,899.00
Entire Work Complete to Construct 2x6 Wood Climbing Surface
Job LS $167,000.00 $58,175.00
Entire Work Complete to Construct Additonal 5 Climbing Lanes of Reinforced Concrete Composite Material Climbing System
Job LS $275,000.00 $208,212.00
Entire Work Complete to Construct Climbing Tower Bridge as Shown on Drawings
Job LS $158,000.00 $61,712.00
TOTAL AMOUNT $2,965,000.00 $2,183,044.00
4. ISSUING OFFICE NAME AND TITLE OF CERTIFYING OFFICIAL (Type)
ABSTRACT OF OFFERS - CONSTRUCTION
1. SOLICITATION NUMBER Page 5 of 5
W9128F13B0009
US ARMY CORPS OF ENGINEERS Tyler Hegge, Contract Specialist
CONTRACTING DIVISION (CENWO-CT) SIGNATURE
1616 Capitol Avenue *
OMAHA, NE 68102
5. PROJECT TITLE 9. OFFERS
NO. 12 NO. 13
SOF Mountaineering Climbing/Rapelling Tower
B. BID SECURITY B. BID SECURITY
FORT CARSON, CO Mass Service & Supply Mountain West Constuction Group 820 West 10th St 2006 S 1900 West
3 3 3
OPTION ITEMS
20% 20%
6. NUMBER OF AMENDMENTS ISSUED C. AMENDMENTS ACKNOWLEDGEDC. AMENDMENTS ACKNOWLEDGED
Pueblo, CO 81003 Ogden, UT 84412
File details come from the government source that posted it. Updated .