Bid_Abstract_W9128F-13-B-0009.pdf

PDF 50 KB Posted

Attached to
SOF MOUNTAINEERING CLIMBING/RAPPELLING TOWER at FT. CARSON, CO
Solicitation number
W9128F13B0009
Issued by

About this file

W9128F-13-B-0009 Bid Abstract

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2. DATE ISSUED 3. DATE OPENED

28-Jun-13 6-Aug-13

I CERTIFY THAT I HAVE OPENED, READ AND

RECORDED ON THIS ABSTRACT ALL OFFERS

RECEIVED IN RESPONSE TO THIS SOLICITATION DATE SIGNED

C. REASONABLE CONTRACT

7A 7B 7C D. E. F. E. F. E. F.

ITEM # DESCRIPTION OF OFFER ITEM EST. QTY UNIT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT

Entire Work Complete to Construct Climbing Tower with Reinforced Concrete Composite Material Climbing System Job LS $1,324,350.00 $1,901,526.00 $2,077,732.00

Entire Work Complete to Construct Precast Concrete Surface as Shown on Drawings

Job LS $133,015.00 $189,438.00 $190,815.00

Enitre Work Complete to Construct Cementitious Coated Plywood Climbing System Job LS $140,155.00 $110,590.00 $132,708.00

Entire Work Complete to Construct 2x6 Wood Climbing Surface

Job LS $31,565.00 $114,108.00 $136,930.00

Entire Work Complete to Construct Additonal 5 Climbing Lanes of Reinforced Concrete Composite Material Climbing System

Job LS $159,715.00 $218,340.00 $204,880.00

Entire Work Complete to Construct Climbing Tower Bridge as Shown on Drawings

Job LS $89,490.00 $94,577.00 $132,613.00

TOTAL AMOUNT $1,878,290.00 $2,628,579.00 $2,875,678.00

9. OFFERS

SIGNATURE

NAME AND TITLE OF CERTIFYING OFFICIAL (Type) Tyler Hegge, Contract Specialist

ABSTRACT OF OFFERS - CONSTRUCTION

1. SOLICITATION NUMBER

W9128F13B0009

4. ISSUING OFFICE

8. GOVERNMENT ESTIMATE5. PROJECT TITLE

OMAHA, NE 68102

1616 Capitol Avenue

CONTRACTING DIVISION (CENWO-CT)

US ARMY CORPS OF ENGINEERS

B. REASONABLE CONTRACT

NO. 1 NO. 2 (Check A, B or C AND COMPLETE D, E AND F)

1015 Fir 240 Mill Dr.

A. HIRED LABOR

Cortez Construction Co., Inc. Mack Mechanical, Inc.

B. BID SECURITY

C. AMENDMENTS ACKNOWLEDGED

C. AMENDMENTS ACKNOWLEDGED

Cookeville, TN 38501

B. BID SECURITY

OPTION ITEMS

6. NUMBER OF AMENDMENTS ISSUED

SOF Mountaineering Climbing/Rapelling Tower

FORT CARSON, CO

20% (Without Profit)

(Including Profit)

Pueblo, CO 81001

20%

I CERTIFY THAT I HAVE OPENED, READ AND

ITEM # DESCRIPTION OF OFFER ITEM EST. QTY UNIT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT

Entire Work Complete to Construct Climbing Tower with Reinforced Concrete Composite Material Climbing System Job LS $1,741,833.66 $1,700,000.00 $1,717,481.00

Entire Work Complete to Construct Precast Concrete Surface as Shown on Drawings

Job LS $211,111.04 $166,700.00 $181,046.00

Enitre Work Complete to Construct Cementitious Coated Plywood Climbing System Job LS $133,793.00 $118,700.00 $105,937.00

Entire Work Complete to Construct 2x6 Wood Climbing Surface

Job LS $108,321.08 $64,000.00 $35,974.00

Entire Work Complete to Construct Additonal 5 Climbing Lanes of Reinforced Concrete Composite Material Climbing System

Job LS $259,084.38 $234,000.00 $180,714.00

Entire Work Complete to Construct Climbing Tower Bridge as Shown on Drawings

Job LS $138,598.76 $77,000.00 $99,337.00

TOTAL AMOUNT $2,592,741.92 $2,360,400.00 $2,320,489.00

4. ISSUING OFFICE NAME AND TITLE OF CERTIFYING OFFICIAL (Type)

ABSTRACT OF OFFERS - CONSTRUCTION

1. SOLICITATION NUMBER Page 2 of 5

W9128F13B0009

US ARMY CORPS OF ENGINEERS Tyler Hegge, Contract Specialist

CONTRACTING DIVISION (CENWO-CT) SIGNATURE

1616 Capitol Avenue *

OMAHA, NE 68102

5. PROJECT TITLE 9. OFFERS

NO.3 NO. 4 NO. 5

SOF Mountaineering Climbing/Rapelling Tower FORT CARSON, CO CMS Inc. of Colorado Springs White Construction Group J&S Construction Company

6 N. Tejon St. 18 S Wilcox St. 1843 Foreman Dr.

Colorado Springs, CO Castle Rock, CO 80104 Cookville, TN

B. BID SECURITY B. BID SECURITY B. BID SECURITY

20% 20% 20%

6. NUMBER OF AMENDMENTS ISSUED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGEDC. AMENDMENTS ACKNOWLEDGED

3 3 3 3

OPTION ITEMS

I CERTIFY THAT I HAVE OPENED, READ AND

ITEM # DESCRIPTION OF OFFER ITEM EST. QTY UNIT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT

Entire Work Complete to Construct Climbing Tower with Reinforced Concrete Composite Material Climbing System Job LS $1,750,604.00 $1,702,498.00 $1,518,000.00

Entire Work Complete to Construct Precast Concrete Surface as Shown on Drawings

Job LS $174,207.00 $202,350.00 $141,000.00

Enitre Work Complete to Construct Cementitious Coated Plywood Climbing System Job LS $109,840.00 $125,662.00 $120,000.00

Entire Work Complete to Construct 2x6 Wood Climbing Surface

Job LS $56,294.00 $81,257.00 $26,000.00

Entire Work Complete to Construct Additonal 5 Climbing Lanes of Reinforced Concrete Composite Material Climbing System

Job LS $233,682.00 $243,570.00 $219,000.00

Entire Work Complete to Construct Climbing Tower Bridge as Shown on Drawings

Job LS $133,844.00 $68,129.00 $69,000.00

TOTAL AMOUNT $2,458,471.00 $2,423,466.00 $2,093,000.00

4. ISSUING OFFICE NAME AND TITLE OF CERTIFYING OFFICIAL (Type)

ABSTRACT OF OFFERS - CONSTRUCTION

1. SOLICITATION NUMBER Page 3 of 5

W9128F13B0009

US ARMY CORPS OF ENGINEERS Tyler Hegge, Contract Specialist

CONTRACTING DIVISION (CENWO-CT) SIGNATURE

1616 Capitol Avenue *

OMAHA, NE 68102

5. PROJECT TITLE 9. OFFERS

NO.6 NO. 7 NO. 8

SOF Mountaineering Climbing/Rapelling Tower FORT CARSON, CO Ayuda Management Corporation Bristol General Contractors, LLC Iron Mike Construction

11800 Ridge Parkway, Ste. 550 111 W. 16th Ave 6950 S. Tucson Way Ste A Broomfield, CO 80021 Anchorage, Alaska 99501 Centennial, CO 80112

B. BID SECURITY B. BID SECURITY B. BID SECURITY

20% 20% 20%

6. NUMBER OF AMENDMENTS ISSUED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGEDC. AMENDMENTS ACKNOWLEDGED

I CERTIFY THAT I HAVE OPENED, READ AND

ITEM # DESCRIPTION OF OFFER ITEM EST. QTY UNIT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT

Entire Work Complete to Construct Climbing Tower with Reinforced Concrete Composite Material Climbing System Job LS $ 1,335,646.00 $1,877,200.00 $1,712,109.00

Entire Work Complete to Construct Precast Concrete Surface as Shown on Drawings

Job LS $252,000.00 $205,000.00 $183,708.00

Enitre Work Complete to Construct Cementitious Coated Plywood Climbing System Job LS $105,325.00 $120,000.00 $123,084.00

Entire Work Complete to Construct 2x6 Wood Climbing Surface

Job LS $64,320.00 $120,000.00 $66,501.00

Entire Work Complete to Construct Additonal 5 Climbing Lanes of Reinforced Concrete Composite Material Climbing System

Job LS $100,525.00 $235,000.00 $255,158.00

Entire Work Complete to Construct Climbing Tower Bridge as Shown on Drawings

Job LS $77,200.00 $120,000.00 $133,027.00

TOTAL AMOUNT $1,935,016.00 $2,677,200.00 $2,473,587.00

4. ISSUING OFFICE NAME AND TITLE OF CERTIFYING OFFICIAL (Type)

ABSTRACT OF OFFERS - CONSTRUCTION

1. SOLICITATION NUMBER Page 4 of 5

W9128F13B0009

US ARMY CORPS OF ENGINEERS Tyler Hegge, Contract Specialist

CONTRACTING DIVISION (CENWO-CT) SIGNATURE

1616 Capitol Avenue *

OMAHA, NE 68102

5. PROJECT TITLE 9. OFFERS

NO.9 NO. 10 NO. 11

SOF Mountaineering Climbing/Rapelling Tower FORT CARSON, CO Timus-NASCO JV Growling Bear Co., Inc. Medvolt, LLC

8131 Baymeadows Circle 2330 4th Ave 5045 List Drive Jacksonville, FL 32256 Greely, CO 80631 Colorado Springs, CO 80919

B. BID SECURITY B. BID SECURITY B. BID SECURITY

20% 20% 20%

6. NUMBER OF AMENDMENTS ISSUED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGEDC. AMENDMENTS ACKNOWLEDGED

I CERTIFY THAT I HAVE OPENED, READ AND

7A 7B 7C D. E. F. E. F.

ITEM # DESCRIPTION OF OFFER ITEM EST. QTY UNIT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT

Entire Work Complete to Construct Climbing Tower with Reinforced Concrete Composite Material Climbing System Job LS $1,998,000.00 $1,598,065.00

Entire Work Complete to Construct Precast Concrete Surface as Shown on Drawings

Job LS $203,000.00 $160,981.00

Enitre Work Complete to Construct Cementitious Coated Plywood Climbing System Job LS $164,000.00 $95,899.00

Entire Work Complete to Construct 2x6 Wood Climbing Surface

Job LS $167,000.00 $58,175.00

Entire Work Complete to Construct Additonal 5 Climbing Lanes of Reinforced Concrete Composite Material Climbing System

Job LS $275,000.00 $208,212.00

Entire Work Complete to Construct Climbing Tower Bridge as Shown on Drawings

Job LS $158,000.00 $61,712.00

TOTAL AMOUNT $2,965,000.00 $2,183,044.00

4. ISSUING OFFICE NAME AND TITLE OF CERTIFYING OFFICIAL (Type)

ABSTRACT OF OFFERS - CONSTRUCTION

1. SOLICITATION NUMBER Page 5 of 5

W9128F13B0009

US ARMY CORPS OF ENGINEERS Tyler Hegge, Contract Specialist

CONTRACTING DIVISION (CENWO-CT) SIGNATURE

1616 Capitol Avenue *

OMAHA, NE 68102

5. PROJECT TITLE 9. OFFERS

NO. 12 NO. 13

SOF Mountaineering Climbing/Rapelling Tower

B. BID SECURITY B. BID SECURITY

FORT CARSON, CO Mass Service & Supply Mountain West Constuction Group 820 West 10th St 2006 S 1900 West

3 3 3

OPTION ITEMS

20% 20%

6. NUMBER OF AMENDMENTS ISSUED C. AMENDMENTS ACKNOWLEDGEDC. AMENDMENTS ACKNOWLEDGED

Pueblo, CO 81003 Ogden, UT 84412