Lock Chamber Bulkhead Recesses- 110' Stoplog Cutting, Norrell Lock and Dam, MKARNS
Solicitation number
W9127S21R0005
Issued by

About this file

This solicitation seeks proposals for lock chamber bulkhead recesses and 110-foot stoplog slot cutting at the Norrell Lock and Dam. Work includes diamond wire cutting through solid concrete up to sixty-one feet deep; concrete block removal; three-sided coffer box installation; concrete preparation and stoplog/bulkhead part installation; steel fabrication installation; and underwater concrete placement. The total contract value is estimated between $5 million to $10 million. The NAICS code is 237990 and SBA size standard is $39.5 million. The opportunity is full and open competition. A site visit will take place on June 22, 2021. Proposals are due by August 6, 2021. The small business participation goal is 5% of total contract value.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Amendment 0002 provides Government responses to RFIs submitted in ProjNet, corresponding Specifications/ Draw ings changes, and applicable attachments.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 56

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 22-Jul-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9127S21R0005

X 9B. DATED (SEE ITEM 11)

14-Jun-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

22-Jul-2021

CODE

CONTRACTING DIVISION

USACE, LITTLE ROCK (W9127S)

700 W. CAPITOL AVE, RM 7315

LITTLE ROCK AR 72201-3225

W9127S 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9127S21R0005

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 10 00 - SOLICITATION

The following have been added by full text:

RFI RESPONSES

Bid Inquiry Contractor Report All Inquiries

Project: FY20 O&M Rehab Cntrpst & Insp Miter Gates at Norrell Review: W9127S21R0005 (00001) (sorted by CommentID ) Displaying 84 inquiries.

Id Discipline Sheet Detail Spec

9295859 Contracting n/a n/a N/A

Comment Classification: Controlled Unclassified Information (CUI)

Please forward copy of pictures of lock chamber in dewatered condition

On: Jun 23 2021.

Government Response. . The last dewater occurred in 2002; photos will be posted on SAM.gov alongside Amendment 0002. On: Jul 19 2021

Current Request Status: Request Closed

Information for this report is procurement sensitive.

9295915 Contracting n/a n/a 09 97 02 3.5

Comment Classification: Controlled Unclassified Information (CUI)

There is a paint spec included and identifies the areas to be painted. However I do not see any discussion of lead abatement for existing metals that will have to be coated near the new work.

How will this be handled?

Will the coffer boxes require painting after there use on this project?

On: Jun 23 2021.

Government Response. . The lock chamber armoring is a routinely maintenance item, so the presence of lead based paint is low. The contractor should take all precautions for lead paint testing that are detailed in 09 97. In the event that lead based paint is encountered then it will be disposed of per 01 57.

The coffer boxes will not need to be repainted in their entirety. In the event that the contractor damages the boxes and they need to be repaired before returning them to USACE, then the repair area will need to be painted. On: Jul 19 2021

Current Request Status: Request Closed

Information for this report is procurement sensitive.

9295950 Contracting n/a n/a 01 11 00 para. 1.1

Comment Classification: Controlled Unclassified Information (CUI)

Please provide photographs of the coffer boxes and quantity available. Will the KTR be required to transport from there storage yard (location) and will a KTR be required to provide his own crane for hoisting? Has a quality check been performed on the coffer boxes to ascertain a good fit to new coffer boxes shown in the drawings?

Government Response. . The government has two cofferboxes that will be made available for pick up at the DMT. A crane and operator will be made available for loading and unloading of cofferboxes. Extensions shown in the plans were designed with the intent of a good fit with existing cofferboxes and the lock chamber floor. As addressed in 01 22 00.00 10 para 1.2.2.1, all other requirements are the responsibility of the contractor and should be included in the proposal pricing.

The most recent cofferbox inspection report will be posted on SAM.gov alongside Amendment 0002. On: Jul 19 2021

Current Request Status: Request Closed

Information for this report is procurement sensitive.

9295995 Contracting n/a n/a 01 11 00 para. 1.3 a

(4) & 1.3 e

Comment Classification: Controlled Unclassified Information (CUI)

Is the intent that the KTR is required to perform a full survey prior to the work to ascertain the work can be constructed, both underwater and above? Will the GIS survey be required prior to beginning work?

Government Response. . The contractor is not required to provide a survey report to USACE. Surveys should be conducted as required to complete work accurately.

Costs associated with planned surveys should be included in proposed price.

The most recent side scan sonar survey will be posted on SAM.gov alongside Amendment 0002; see pages 20 and 21. On: Jul 19 2021

9296089 Contracting n/a n/a 01 14 00.00 para. 1.5

Comment Classification: Controlled Unclassified Information (CUI)

Most of the work is inside the lock along the lock wall and underwater. Will KTR be required to vacate the lock when a barge is ready to lock through during daylight hours? This will probably occur June through January.

Government Response. . Spec 01 14 00.0046 paragraph 1.5.2 states "If the lock can be returned to service outside of working hours then the closure period may last up to 1 month. If the lock cannot be returned to service outside of working hours then the closure period may only last up to 14 consecutive days that will be followed by a 10 day period where traffic is not to be impacted."

The intent of this statement is to give the contractor some flexibility. The contractor can shut to lock down to all traffic 24hrs a day but that type of closure may only last 14 consecutive days followed by a 10 day period were traffic is free to move. If the contractor can reopen the lock to traffic over night then the outage can last 30 consecutive days. If the contractor can open the lock to traffic at night then there will be no need to vacate the lock for barges during the day. On: Jul 19 2021

9296096 Contracting n/a n/a 01 14 00.00 para. 1.5

Comment Classification: Controlled Unclassified Information (CUI)

Will USACE consider adding Item for KTR standby time?

Government Response. . The government has provided anticipated weather delays in its Specifications. A breakdown of lockages per month over the last few years will be posted on SAM.gov alongside Amendment 0002.

Offerors should take this information into consideration when building their proposed schedules. On: Jul 19 2021

9296113 Contracting n/a n/a 01 22 00.00 para.

1.2.4.1 & 1.2.5.1

The CLIN Items specifically state the KTR--SHALL NOT INCLUDE ANY OF THE MARINE SUPPORT--please clarify intent.

On: Jun 23 2021.

Government Response. . The sentence in CLIN 005 and 006 should read: This item shall include any of the marine support activities suck as equipment cost for barges, cranes, tug operation or any other marine operations that the contractor envisions necessary to complete the work.

These items will be corrected and included in Amendment 0002. On: Jul 19 2021

9297225 Other 05 50 04

Comment Classification: Controlled Unclassified Information (CUI)

Spec section 05 50 04 2.4 Bulkhead Recess Assemblies says that the assemblies shall be fabricated and delivered in on piece unless otherwise noted. The drawings show all bulkhead recesses being made in two pieces each and welded together. Can the bulkhead recesses be fabricated and delivered in one piece or are they to be welded in the field at this joint?

On: Jun 24 2021.

Government Response. . Either way is fine so long as proper alignment and embedment is achieved. On: Jul 20 2021

9297235 Other 05 50 04

Comment Classification: Controlled Unclassified Information (CUI)

Spec section 05 50 04 2.2.4 calls for the frame for grating to be Extruded aluminum 6063-T6 with a continuous extruded anchor for embedment on concrete. Drawings BHR S-507 and S- 517 call for the framing to be A36 steel with no anchors. None of the drawings show any weld symbols for the grate framing. Can you clarify these points?

Government Response. . After further review the embedded items are Aluminum.

The welds shall full penetration butt welds. On: Jul 20 2021

9297939 Specifications 03 41 00

Are there any precast concrete panels that are part of the scope of work? If not, what scope of work does Specification Section 03 41 00 apply?

Government Response. . There are no precast concrete panels. This section will be removed. On: Jul 19 2021

Government Response. . There are no precast concrete panels. This section will be removed. On: Jul 19 2021

9297965 Construction Management none none

Comment Classification: Controlled Unclassified Information (CUI)

What is the contractor required to do with the cofferdams after removal? Will the government supply the crane to pick the cofferdams at the final delivery location after the project?

Government Response. . The cofferboxes will be delivered back to the USACE marine terminal from which they were picked up. There will be a crane at the marine terminal to receive the cofferboxes. On: Jul 19 2021

9297967 Construction Management none none none

Comment Classification: Controlled Unclassified Information (CUI)

Can the government supply as-built information for the bulkheads to be used on this project?

More specifically we are requesting dimensions, weight and pictures if available.

Government Response. . The bulkhead design drawings will be posted on SAM.gov alongside Amendment 0002. On: Jul 19 2021

9297970 Construction Management none none none

Can the government supply the pick weights for the cofferdams and any as-built information that is available?

On: Jun 24 2021.

Government Response. . A copy of the shop drawings will be posted on SAM.gov alongside Amendment 0002. Approximate weight of each is 36,500 pounds. On: Jul 19 2021

9297972 Construction Management none none none

Comment Classification: Controlled Unclassified Information (CUI)

Can the government provide reference drawings for the upstream and downstream sill?

Government Response. . Drawings for each Upstream and Downstream will be posted on SAM.gov alongside Amendment 0002. On: Jul 19 2021

9297973 Construction Management none none none

Comment Classification: Controlled Unclassified Information (CUI)

Is this project sales tax exempt on permanent materials?

Government Response. . It should be assumed that this project is not tax exempt.

On: Jul 19 2021

9297977 Construction Management none none none

Comment Classification: Controlled Unclassified Information (CUI)

Would the government extend the bid date by two weeks?

Government Response. . The proposal deadline was extended to 6 August in Amendment 0001, which was issued on 7 July. On: Jul 19 2021

9297989 Construction Management

SD101 &SD110 A! none

Comment Classification: Controlled Unclassified Information (CUI)

Can the government provide reference detailing the corbels to be removed on this project for cofferdam installation?

Government Response. . Reference drawings will be posted on SAM.gov alongside Amendment 0002. See detail N-N. On: Jul 20 2021

9297992 Construction Management none none none

Comment Classification: Controlled Unclassified Information (CUI)

Please confirm that the government will supply the operated crane, rigging, certified riggers and pick plan for loading the cofferdams from their current laydown location.

Government Response. . USACE will supply the crane, crane operator, and rigging to load/unload both cofferboxes from Dardanelle Marine Terminal.

Please note the contractor will be responsible for these items while working at Norrell Lock and Dam. On: Jul 19 2021

9297994 Construction Management none none none

Comment Classification: Controlled Unclassified Information (CUI)

Please confirm the location where the contractor will take delivery of government furnished cofferdams.

Government Response. . The contractor will receive the cofferboxes behind the Lock at:

Dardanelle Marine Terminal 1656 Lock & Dam Road Russellville, Arkansas 72802 On: Jul 19 2021

9297999 Construction Management none none 03 31 00, subpart

3.3.5

Section 03 31 00, Subpart 3.3.5 Time Interval Between Mixing and Placing states:

"Concrete shall be placed within 30 minutes after discharge into non-agitating equipment.

When concrete is truck-mixed or when a truck mixer or agitator is used for transporting concrete mixed by a concrete plant mixer, the concrete shall be delivered to the site of the work, and discharge shall be completed within 1-1/2 hours after introduction of the cement to the aggregates. When the length of haul makes it impossible to deliver truck-mixed concrete within these time limits, batching of cement and a portion of the mixing water shall be delayed until the truck mixer is at or near the construction site."

The current wording is saying to add the aggregates to the truck and most of the water at the plant and then add the cement and remaining water to the truck once it's on site. Was the intention of this paragraph to say it is allowable to add the aggregates and cement to the mixer truck at the plant and then add the water to the truck once it arrives on site?

Government Response. . We will change the specifications to note that the water shall not be added until the truck arrives to the jobsite. The contractor shall provide a water tank with a gauge to measure the water added and a high range water reducer must be added for workability. On: Jul 20 2021

9298003 Construction Management

SD110 none none

Comment Classification: Controlled Unclassified Information (CUI)

Can the corbels shown on Contract Drawing SD110 be removed during the fall of 2021?

Government Response. . This may be a possibility, provided that only a partial closure is requested and all the notifications to industry that are in the plans and specified are completed and operations and the industry can accommodate this option. On: Jul 20 2021

9298018 Construction Management

S-101 none none

Comment Classification: Controlled Unclassified Information (CUI)

What are the installation tolerances of the horizontal location and elevation of the steel bulkhead bearing pads that are shown in Contract Drawings S-101 and S-110?

Government Response. . All requirements from paragraph 3.1.1.1 of specification 05 50 03 shall apply to the fabrication.

All requirements of paragraph 1.7 of specification 03 31 00 shall apply to the installation of the fabrication. On: Jul 20 2021

9298021 Construction Management none none none

Comment Classification: Controlled Unclassified Information (CUI)

How much freeboard does the design of the existing cofferdam require?

Government Response. . The top of the box has a design height of 140.5 with one foot of freeboard. The current boxes are 30'-8" with new fabricated extensions of 16'-6". On: Jul 19 2021

9298023 Construction Management none none none

Comment Classification: Controlled Unclassified Information (CUI)

How many cofferboxes does the USACE have scheduled for this project? It appears one upstream coffer box and one downstream cofferbox based on the material quantities.

Government Response. . You are correct; one upstream and one downstream. On:

Jul 19 2021

9298025 Construction Management none none none

Comment Classification: Controlled Unclassified Information (CUI)

Are the cofferboxes that are scheduled for this project location specific, or can they be installed at any of the four bulkhead slot locations?

Government Response. . The boxes themselves are only specific to upstream and downstream. With the proper lip extensions these boxes can be used at multilple different projects on the MKARNS system. On: Jul 20 2021

9298027 Construction Management none none 03 41 00

Comment Classification: Controlled Unclassified Information (CUI)

Specification Section 03 41 00 "PLANT-PRECAST STRUCTURAL CONCRETE" addresses the requirements of precast structural concrete items. We did not see any precast concrete that was included in the contract drawings. Are there any precast concrete items that are required in this project?

Government Response. . There are no precast items in this requirement. This section will be removed. On: Jul 19 2021

9298030 Construction Management

S-506 none none

Comment Classification: Controlled Unclassified Information (CUI)

Contract drawing S-506 provides weld details for the wall armor splices at the wire saw cut lines. The details imply a PJP weld is required. Was this the intention of the weld detail or is the intention to provide a CJP weld?

Government Response. . This is not a critical weld and PJP will be sufficient. On:

Jul 20 2021

9298037 Construction Management none none 03 32 00

Comment Classification: Controlled Unclassified Information (CUI)

Specification Section 03 32 00 "CAST-IN-PLACE STRUCTURAL CONCRETE"; Subpart

1.2 Concrete Finishing Personnel states:

"... Minimum of two ACI-certified Concrete Flatwork Finishers on-site at all times during placement of concrete."

There is very little flatwork associated with this project. Can this requirement be waved?

Government Response. . This requirement may be waived by the COR or ACO after award; however, please submit your proposal in accordance with the solicitation requirements. On: Jul 20 2021

9298040 Construction Management none none none

Comment Classification: Controlled Unclassified Information (CUI)

On similar jobs, USACE has provided dredging services prior to sill work. Does USACE plan to provide any type of dredging service prior to sill work?

Government Response. . SWL has no mechinisim to dredge at this location. On:

9298624 Other 1

Comment Classification: UNCLASSIFIED (U) this ProjNet site is entitled: Project: (485533) FY20 O&M Rehab Cntrpst & Insp Miter Gates at Norrell; Review: W9127S21R0005 and is dated: (Jun 13 2021 - Jun 29 2021) However, the RFP shows the name as "Lock Chamber Bulkhead Recesses - 110' stoplog slot cutting". Please verify these are the same solicitations. Also, the RFP shows a deadline for questions on 6/30 and a final due date July 16, 2021. Please confirm.

On: Jun 25 2021.

Government Response. . Confirmed the title of these two projects are one in the same project; the ProjNet site is listed (485533) FY20 Rehab Cntrpst & Insp Miter Gates at Norrell; Review: W9127S21R0005 and the RFP is listed at Lock Chamber Bulkhead Recesses 110' Stoplog Slot Cutting are the same project.

The ProjNet Title (485533) FY20 O&M Rehab Cntrpst & Insp Miter Gates at Norrell, is how the project is titled in the President's Budget. The RFP Title, Lock Chamber Bulkhead Recesses 110' Stoplog Slot Cutting, is specific to the type of work that will be done at Norrell with those funds. They are the same project. The name just allows USACE to link the work back to the Presidents Budget.

The deadline for RFIs was 30 June.

The proposal deadline was extended to 6 August in Amendment 0001, which was issued on 7 July. On: Jul 19 2021

9298626 Other 11 of 58

Comment Classification: UNCLASSIFIED (U)

Per RFP Factor 1 Technical Approach #10 – letter of commitment – can that letter be excluded from the page count?

On: Jun 25 2021.

Government Response. . Letters of commitment shall be included in the page limit. On: Jul 19 2021

9298628 Other RFP p.12 of 58

Comment Classification: UNCLASSIFIED (U)

How many pages are allowed for Factor 3 containing the schedule, the narrative explaining the schedule, and the project management/risk plan discussion?

Government Response. . Limit the Gantt chart schedule to no more than 85 individual items/tasks.

Limit the Project Management Plan to no more than 10 pages. On: Jul 20 2021

Information for this report is procurement sensitive.

9298630 Other RFP p.11 of 58

Comment Classification: UNCLASSIFIED (U)

On 2 of our relevant projects, our main client contact is no longer with that company. Will you accept the submission of an older PPQ signed survey with an updated first page?

Government Response. . The submission of an older PPQ signed survey with an updated first page will be acceptable. On: Jul 19 2021

9299377 Other RFP p.11 of 58

Comment Classification: UNCLASSIFIED (U)

Factor 1 – Technical Approach (limit: 4 pages) The RFP has asked bidders at a minimum to address 10 specific elements regarding the work as identified by the Government, in addition to other information the bidder feels necessary to address within our technical approach. It is our strong opinion that it would require considerably more than 4 pages of text in order to satisfactorily address each of these major bullet points identified by the Government. Would the USACE please consider increasing the page limit for the Technical Approach section of the proposal to 20 pages?

Government Response. . The Technical Approach's page limit will be increased to 10 pages. This will be included in Amendment 0002. On: Jul 20 2021

9299380 Other RFP p.13 of 58

Comment Classification: UNCLASSIFIED (U)

Factor 3 – Work Plan: Project Management Plan (limit: 5 pages) For bidders to provide complete and sufficient detail to satisfy the information requested by the government within the Project Management Plan of the proposal, would you please consider increasing the page limit for this section to 10 pages?

Government Response. . The Project Management Plan's page limit will be increased to 10 pages. This will be included in Amendment 0002. On: Jul 19 2021

9299653 Other RFP Factor 2 (p. 11 &

12)

Factor 2 reads as to ONLY include PPQ's. Are we allowed to either expand Block 4 in the Attachment B (which would require us to recreate the form) to provide a detailed project description or note "See attached" in Block 4 and add a full project page along with the PPQ.

Government Response. . Attachments/appendices are not permitted. Offerors should provide as much project description information to show its relevance to the work required under this solicitation. On: Jul 19 2021

9299658 Other RFP Document

Comment Classification: Controlled Unclassified Information (CUI)

Are Final CPARS allowed in place of the Attachment B (Form PPQ-03)?

Government Response. . No; the requirement states offerors shall submit PPQs.

9301083 Contracting None None 00 22 16

Comment Classification: Controlled Unclassified Information (CUI)

Section 00 22 16 – Supplementary Instructions to Proposers, Submission Format, Page 9 of 58, specifies file format and names for submission. However, the specified file name for Volume II contains an invalid character (/). Can a different/modified file name be provided?

On: Jun 28 2021.

Government Response. . A (-) may be used in place of (/). On: Jul 19 2021

9301086 Contracting None None 00 22 16

Section 00 22 16 – Supplementary Instructions to Proposers, Factor 1 – Technical Approach (Vol 1, Bookmark B), Page 11 of 58, specifies a four-page limit for narrative to include a wide range of information (to name a few: dive plan, personnel/work force management, employees and certifications, and letters of commitment signed by both subcontractor and prime contractor). Can the page limit be increased to 10 pages to better address all requirements?

Government Response. . The Technical Approach's page limit will be increased to 10 pages. This will be included in Amendment 0002. On: Jul 19 2021

9301087 Contracting None None 00 22 16

Comment Classification: Controlled Unclassified Information (CUI)

Section 00 22 16 – Supplementary Instructions to Proposers, Factor 2 – Past Performance (Vol 1, Bookmark C), specifies PPQs. Can previously submitted PPQs be utilized?

Government Response. . PPQs previously completed by the example project's POC may be submitted in lieu of requesting the POC to recomplete the form;

however, Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs. On: Jul 19 2021

9301267 Other S-301

Comment Classification: Controlled Unclassified Information (CUI)

Are there any specifications for the Neoprene seals for the bottom of the Cofferdam Extension Assemblies? The drawings in multiple locations say 2"x3". How are they to be attached? What is the durometer? What are the leakage acceptance standards? Does there need to be any allowance figured for compression?

Government Response. . The typical USACE rubber seal has a durometer between 60 and 70. The tensile strength is 2800 psi. A perfect seal will not be achieved, rags cork, pool noodles and foam rubber will have to be installed in order to limit the leakage. 2" and 3"pumps will have to used continually to keep the area workable. Plastic sheeting may be required as well. On: Jul 20 2021

9302745 Other S-506 05 50 04

Comment Classification: Controlled Unclassified Information (CUI)

Upstream Bulkhead Recess Drawing S-506 Section A9 of part S-506-C5 calls out an "AT8" of material ASTM A36. AT8 is not a shape listed under ASTM A36. Where can this shape be found?

Government Response. . The AT8 Material was a casting shape used in the original project back in the 1970's. Use the plate option ASTM A36 steel. On: Jul 20

9302839 Other As-Builts

Comment Classification: Controlled Unclassified Information (CUI)

Can the government provide any and all as-built drawings they have associated with the existing lock and dam structure.

Government Response. . The most accurate set of drawings will be posted on SAM.gov alongside Amendment 0002. Please use this as reference only and the contractor will still be responsible to verify all dimensions and layout in the field.

On: Jul 21 2021

9303625 Other 1442 form

Comment Classification: UNCLASSIFIED (U)

On the 1442 form in the RFP, it indicates ProjNet will accept questions through Wednesday, June 30, 2021. However, ProjNet shows an end date of June 29, 2021. Can you clarify a deadline for questions to USACE?

On: Jun 29 2021.

Government Response. . ProjNet closed to inquiries on 30 June 2021. On: Jul 19

9304245 Other None

Because this is a complex project and there is an upcoming holiday we would like to request a two week extension to the due date.

Government Response. . The proposal deadline was extended to 6 August in Amendment 0001, which was issued on 7 July. On: Jul 19 2021

9304561 Engineering Management

S-504 A1 &A3 none

Comment Classification: Controlled Unclassified Information (CUI)

Details A1 & A3 of sheet S-504 do not provide a material thickness. Please provide the required material thickness.

Government Response. . The steel plate requirement is 1/2" thick. On: Jul 20

9304566 Engineering Management

S-312 A8 none

Comment Classification: Controlled Unclassified Information (CUI)

Detail A8 on sheet S-312 says aluminum rabbet angle (Installed by others). Who is providing the rabbet angle and who install this rabbet angle.

Government Response. . The note on drawing S-312 detail A8 will be removed that states the installed by others. These will be installed buy the contractor. On: Jul 20 2021

9304602 Engineering Management

None none none

Please provide installation instruction for the government provided cofferboxes.

Government Response. . Installation instructions will be posted on SAM.gov alongside Amendment 0002. On: Jul 20 2021

9304611 Engineering Management

S-516 A8 & C8 none

Comment Classification: Controlled Unclassified Information (CUI)

Will the government consider allowing a field weld between the corner armor and the recess.

Government Response. . The government will consider field welding between the corner armor and recess as an alternative proposal. On: Jul 20 2021

9304747 Other RFP p.14 of 58

Comment Classification: UNCLASSIFIED (U)

Q1. Page 14 of 58 of the solicitation states under the Submission Requirements – Part 1: "A mandatory minimum Total Small Business Participation goal of 5% of the total contract value". However, it is stated on the same page under the Evaluation Criteria – Part 2: "A mandatory minimum Total Small Business Participation Plan goal of 8% of the total contract value". Can the Government please clarify the Total Small Business Participation goal for this project?

Government Response. . The correct percentage is 5%. This correction will be included in Amendment 0002. On: Jul 19 2021

9304758 Other RFP p.3 of 58 00 01 10

Comment Classification: UNCLASSIFIED (U)

Can the government please provide the existing record drawings or As-Built drawings showing the existing conditions of the lock and dam structures that are relevant to the scope of work being performed for this contract?

On: Jun 29 2021.

Government Response. . The most accurate set of drawings will be posted on SAM.gov alongside Amendment 0002. Please use this as reference only and the contractor will still be responsible to verify all dimensions and layout in the field.

On: Jul 21 2021

9305128 Other S-509

Comment Classification: Controlled Unclassified Information (CUI)

Bulkhead Recess Drawings S-509 and S-518 show that there is to be no paint on the portion that is embedded in concrete. Are all items that are partially embedded in concrete to be painted this way?

On: Jun 30 2021.

Government Response. . Yes, the embedded potions of all assemblies should be uncoated. On: Jul 20 2021

9305320 Structural

SD201, SD301, S-201,

S-301, S-506

Please reference attachment labeled "B.08.02 Att 2 – Plans (concrete demo clarification).pdf:

Sheets SD201, SD301, S-201, S-301, and S-506 all show the concrete demo scope in elevation and plan views as well as showing details for replaced sections of the Wall Armor Rubbing Bars. I've attempted to use green and blue boxes to show possible conflicts in defining hatching and demolition limits that appear to conflict between the elevation and plan views.

For the Landwall demolition shown on elevation A1 of SD201 the green box is to the left of the slot and the blue box is to the right of the slot, both are shown as "to be removed". Plan Detail A1 on SD301 only shows hatching on the left (green). Please confirm that a similar shape must be removed on the right side of this slot (blue) in order to create room for the embedded rubbing bar for wall armor tie-in piece. Plan Detail A6 on S-301 also appears to only show reinforcement details for the left side (green) with missing details for the right side (blue). When scaling dimensions from the sheets mentioned above they exactly match the dimensions given on S-506 details C3 (green) & C5 (blue).

Please provide dimensions & reinforcing details that are to be used in the apparent missing scopes (blue).

On sheet SD201 the left side (green) demolition stops at Elev. 132.04 at the bottom of the Wall Armor Rubbing Bar, but the right side (blue) continues down to Elev. 121.5. Please also confirm that no demolition in these "wings" (green & blue) is required below the 132.04 elevation as there is no need to re-embed a Wall Armor Rubbing Bar below this elevation for all locations on Landwall and Riverwall slot modification locations.

(This question has an attachement)

(Attachment: B.08.02_Att_2-_Plans_(concrete_demo_clarification).pdf) On: Jun 30 2021.

Government Response. . -For the question: "Please confirm that a similar shape must be removed on the right side of this slot (blue) in order to create room for the embedded rubbing bar for wall armor tie-in piece."

-Answer: No, a similar demo section is not to be removed on the DS side of the bulkhead recess.

-For the question: "Please also confirm that no demolition in these "wings" (green & blue) is required below the 132.04 elevation as there is no need to re-embed a Wall Armor Rubbing Bar below this elevation for all locations on Landwall and Riverwall slot modification locations."

-Answer: The demo on the US side of the monolith joint only extends to EL 132.04' while the demo DS of the monolith joint extends to the sill for the installation of the bulkhead recess assembly as shown. On: Jul 20 2021

9305322 Specifications RFP Page 14 of 58

Comment Classification: Controlled Unclassified Information (CUI)

There appears to be a discrepancy in the required Small Business Participation percentage called out in the RFP document. Reference page 14 of 58 of the RFP document, "Small Business Participation Plan (Vol 2, Bookmark A) section 1.b (Second paragraph) says "A mandatory minimum Total Small Business Participation goal of 5% of the total contract value...is required based on the nature of the work for this project." Also, reference next section of same page "Evaluation Criteria" under section 2. first paragraph, it states, "A mandatory minimum Total Small Business Participation Plan goal of 8% of the total contract value is assigned to this acquisition." The next paragraph lists the percentage of each individual socioeconomic category that makes up the required percentage and when summed these equal 5%. Please confirm that the minimum goal for Total Small Business Participation for this project is 5%.

Government Response. . The correct percentage is 5%. This correction will be included in Amendment 0002. On: Jul 19 2021

9305344 Other G-004

Comment Classification: Controlled Unclassified Information (CUI)

Reference Plan Sheet G-004, General Note #8 states "No work involving open flames, sparks, or other operations deemed dangerous by the contracting officer will be allowed during lockage of tows containing flammable products." Is it known approximately how many loads of flammable products come through the lock per day, week, or month, and can the government share that information?

Government Response. . Historical data pertaining to these types of barges are inconsistent. In general the lock encounters this situation once to twice a week. On:

9305347 Other RFP Page 12-13

Comment Classification: Controlled Unclassified Information (CUI)

Reference RFP Document pages 12 & 13 of 58, Factor 3 (Schedule vis Gantt Chart). The first paragraph states to limit the Gantt chart schedule to no more than 50 individual items / tasks.

The section goes on the list numerous items of detail to include in the schedule including:

design, submittals, procurement, fabrication, permitting, mob / demob, etc., as well as an additional 12 key tasks that are identified to be included. We are finding it difficult to include the requested amount of detail in the schedule and keep it to no more than 50 individual items.

We request the government change the schedule requirements to allow up to 85 individual items.

Government Response. . The Schedule's limit will be increased to 85 tasks. This will be included in Amendment 0002. On: Jul 19 2021

9305349 Specifications 01 41 00.00 46

Comment Classification: Controlled Unclassified Information (CUI)

Reference Specification Section 01 14 00.00 46 page 2 section 1.5 paragraph 2 states that as long as the contractor can keep a continuous lane through the lock that is a minimum of 80 feet wide then a partial closure will be permitted in lieu of a full closure. When working within the coffer-box we believe this can be done, however when the coffer-box is in place at the downstream - landside location, will the coffer-box cause conflict with the passing barge and the lock trolley system?

On: Jun 30 2021.

Government Response. . This configuration will conflict with the use of the Tow Haulage. This will simply be another restriction that we detail in our notice to navigation. This additional requirement on industry should not affect the contractor.

On: Jul 20 2021

9305356 Other none

Comment Classification: Controlled Unclassified Information (CUI)

Is contractor responsible for protecting cofferboxes from barge strikes or is the barge operator responsible for avoiding contact with the cofferboxes?

Government Response. . The tow boat operator is responsible for barge strikes to the coffer boxes. On: Jul 20 2021

9305406 Contracting 1 1 1

Comment Classification: Controlled Unclassified Information (CUI)

Will the government please extend the due date for ProjNet questions.

Government Response. . ProjNet closed for RFI submission on 30 June 2021. On:

Jul 19 2021

9305409 Contracting n n n

Comment Classification: Controlled Unclassified Information (CUI)

Please supply the historical barge traffic logs.

Government Response. . A breakdown of lockages per month over the last few years will be posted on SAM.gov alongside Amendment 0002. On: Jul 20 2021

9305415 Engineering Management

SD201 & SD210 A1 & A6 n

Comment Classification: Controlled Unclassified Information (CUI)

Is the KTR expected to remove concrete behind the existing armor so that the new wall armor can be welded to the existing armor?

Government Response. . These sections can be used if the contractor can save the parts. The shape mold cannot be found for this steel shape. On: Jul 20 2021

9305417 Engineering Management

V301 A7 n

Comment Classification: Controlled Unclassified Information (CUI)

Dwg V-301 detail A7 what does the E and F of this section supposed to portray?

Government Response. . See note 9. a) on the same sheet. E and F are points to be surveyed to set line AB. On: Jul 20 2021

9305420 Construction Management n n 01 14 00.00-1.14

Comment Classification: Controlled Unclassified Information (CUI)

01 14 00.00-1.4.1 Does the 7 am to 7 pm mean a full closure with no barge traffic or partial closure that is just restricted to traffic 80 feet wide or less?

Government Response. . That statement is pertaining to all work. It is our assumption that the contractor will ask for differing work hours for special activities like the dive and cofferbox operations. This is request is allowed in the same paragraph in the next sentence. "Work at the installation during other periods of time will be permitted only on the specific approval of the Contracting Officer or his authorized representative for each specified time." On: Jul 20 2021

9305441 Contracting 1 1 1

With the market being so volatile when it comes to materials (both permanent and construction) in price hikes and long lead times, is there an economic price adjustment clause that can be added to this contract so that the KTR doesn't have to put such a high contingency fund in the bid to cover this high risk?

Government Response. . 252.243-7002 Requests for Equitable Adjustment (DEC 2012) is included in this solicitation and resulting contract. See page 41 of SF1442.

9306301 Survey V-104 and 105 A1 Note 1

Comment Classification: UNCLASSIFIED (U)

Please verify the intent of theoretical vs. actual measurements and survey procedure for V, W, X, Y, and Z.

Government Response. . These survey points will be used to set the new bulkhead sill modification elevation points. On: Jul 20 2021

9306302 Contracting n n 01 14 00 Subpart

1.5.2

Section 01 14 00; Subpart 1.5.2 Bulkhead Sill Installation states:

"..The contractor shall confirm the notice a minimum of 1 month before beginning any activities that will impact free navigation. Impacts shall not excessively impact the flow of traffic. If the lock can be returned to service outside of working hours then the closure period may last up to 1 month. If the lock cannot be returned to service outside of working hours then the closure period may only last up to 14 consecutive days that will be followed by a 10 day period where traffic is not to be impacted."

Please define what is meant by "..Impacts shall not excessively impact the flow of traffic."

Does the statement ""..Impacts shall not excessively impact the flow of traffic." include the cofferboxes attached to the side of the lock if they are located only on one side of the lock?

On: Jun 30 2021.

Government Response. . That is just a clarifying statement to let the contractor know why we are asking for durations on certain activities. We know that certain activities will impact traffic and in an effort to be accommodating to industry we need to restrict those activates to reasonable periods. On: Jul 20 2021

9306315 Construction Management

1 1 1

Comment Classification: Controlled Unclassified Information (CUI)

How much dredging does the USACE assume will need to take place in the sill area? what type of sediment does the USACE think will be in the sill area?

Government Response. . Pages 1 and 2 of the Hydrographic Survey for Norrell will be posted on SAM.gov alongside Amendment 0002. On: Jul 20 2021

9306320 Construction Management

1 1 1

Comment Classification: Controlled Unclassified Information (CUI)

What type of aggregate is the existing concrete made from? Is it granite, river rock, sand stone, limestone, etc.?

What is the compressive strength of the existing concrete.

Government Response. . The original lock specifications did not state whether the concrete the aggregate is granite or limestone. Assumed the aggregate to be Granite.

The estimate size is 3" maximum aggregate. The assumed compressive strength 3,500 psi. On: Jul 20 2021

9306324 Engineering Management n n n

Can drawings be provided that show the layout and size of the reinforcing steel that is in the existing concrete where the bulk head slots are to be installed?

On: Jun 30 2021.

Government Response. . Drawings will be posted on SAM.gov alongside Amendment 0002. On: Jul 20 2021

9306327 Contracting n n n

Comment Classification: Controlled Unclassified Information (CUI)

The link included in the Contract Documents ( https://www.swl-wc.usace.army.mil/pages/arkansas_river_projects.htm) does not provide a hydrographs for the upper or lower pools at Norrell Lock. Please provide a hydrograph for the average upper and lower pools on either a daily or weekly basis.

Government Response. . The gauges for the headwater monitoring is not very reliable at Norrell. Spreadsheet will be posted on SAM.gov alongside Amendment 0002.

Overall the pool around Norrell is relatively static unless the structure is impacted by a high water event. On: Jul 20 2021

9306330 Engineering Management n n n

Comment Classification: Controlled Unclassified Information (CUI)

Is it acceptable to use power hand tools to prep surfaces for touch up field painting existing metal and weld areas instead of field blasting?

Government Response. . The use of power hand tools is acceptable. On: Jul 20

9306334 Contracting n n 01 14 00 Subpart

1.4.1

Section 01 14 00; Subpart 1.4.1 Work Hours states:

Arrange work schedule so that the work performed at the Government installation will be during the normal day shift established as 7:00 a.m.

to 7:00 p.m., Monday through Friday, except Federal holidays, with the option of working weekends only with the approval of the Contracting Officer's Representative.

Will the USACE provide additional working time if a tow is still locking through the chamber at 7:00 AM? If so, when will the additional working time be provided, later in the schedule or at the end of the day of the occurrence. Note, at the end of the day the KTR will incur additional overtime cost and might infringe on the fatigue management plan for work worker safety.

Does Subpart 01 14 00 mean that no traffic will be allowed in the lock from 7:00 AM to 7:00 PM or just restricted traffic?

Government Response. . Propose as if no traffic will be in the lock from 0700 AM to 0700 PM. On: Jul 20 2021

9306346 Structural Cofferdam S-101 and

A-1 & 4

Comment Classification: UNCLASSIFIED (U)

Cofferdam details show padeyes on exterior and angle on interior. Please confirm securement method including anchor sizing, spec, etc. and how to handle setting the anchors if they align with existing armor plating on lock wall.

Government Response. . The rigging configurations needs to be able pick 60,000 lbs. or 30 tons. The holes can be reamed for larger shackles up to 2" diameter if required. On: Jul 20 2021

9306348 Other None

Please provide all barge counts, and lock traffic information available for the last five years. It was mentioned during the site visit that this information could be provided.

On: Jun 30 2021.

Government Response. . A breakdown of lockages per month over the last few years will be posted on SAM.gov alongside Amendment 0002. On: Jul 20 2021

9306351 Structural S-501,S-505,S-507

Comment Classification: Controlled Unclassified Information (CUI)

Please reference Bulkhead Sill plan sheet S-505 Section A7 it calls for an ASTM F1554 GR.

36 Galvanized leveling rod 1"x1'6" but on S-501 A7 the same bolt is called out as a S-507-A9 which is detailed on sheet S-507 detail A9 as a 1"x1' 2-1/4" threaded rod anchor. Please clarify which detail is correct.

Government Response. . We will change the S-507 detail A9 detail to show 1" diameter 1'-6" long threaded anchor. On: Jul 20 2021

9306352 Other S-101

Comment Classification: Controlled Unclassified Information (CUI)

Reference Sheet S-101 (Bulkhead Sill), General Note N, which reads "After concrete has cured and the Government has set a bulkhead on the sill, divers verify and visually record with photo or video that the bulkhead is bearing on each lock floor support. Please confirm that the government will set the bulkhead with their own labor, supervision, cranes, barges, and any other necessary equipment, and load/unload and haul bulkhead and any other necessary material.

Government Response. . The government will set the bulkhead. This bulkhead with lifting beam weighs 110,000 lbs and is 110' long. It takes a 300 to 600 ton crane and floating plant to install. Yes, this is USACE equipment and USACE installed. On: Jul 20 2021

9306355 Contracting RFP p.11 of 58

Reference RFP Document p. 11 of 58 (Factor 2 – Past Performance) the document states for the contractor to submit up to five relevant projects that were completed within the past seven years. Would the government accept submission of relevant projects that would be currently over 85% complete?

Government Response. . Only 100% complete projects are acceptable for this factor. On: Jul 19 2021

9306357 Civil V-001, V-102, V-103

Comment Classification: Controlled Unclassified Information (CUI)

Reference plan sheet V-001 General Note 1 says "The contractor shall reset the survey position monuments." Is this referring to the 8 new monuments to be installed shown on sheets V-102 and V-103? Or is there additional survey monument the contractor is supposed to reset?

Government Response. . The contractor shall reset the monuments shown on V- 102 and V-103. On: Jul 20 2021

9306358 Sedimentation Bulkhead Sill S-101 Sequence A

Comment Classification: UNCLASSIFIED (U)

What are the disposal requirements of any siltation in the lock and sill work area; can it be discharged downstream?

Government Response. . Yes; it may be discharged downstream. On: Jul 20 2021

Information for this report is procurement sensitive.

9306360 Specifications 01 22 00.00 10

Comment Classification: Controlled Unclassified Information (CUI)

In reference to spec section 01 22 00.00 10 page 2, section 1.2.4.1 and 1.2.5.1, both sections say "This item shall not include any of the marine support activities such as equipment cost for barges, cranes, tug operation or any other marine operations that the contractor envisions necessary to complete the work." If the contractor does not include those items here where are they supposed to be included? Is the government going to provide these services for the contractor? Please clarify.

On: Jun 30 2021.

Government Response. . The sentence should read "This item shall include any of the marine support activities such as equipment cost for barges, cranes, tug operation or any other marine operations that the contractor envisions necessary to complete the work."

A correction will be made to the section in Amendment 0002. On: Jul 20 2021

9310905 Specifications General Structural

Notes

We cannot find any call-outs for epoxy coated rebar or any other special rebar coatings. Please confirm black rebar per ASTM 615 is acceptable.

On: Jul 05 2021.

Government Response. . That is acceptable. On: Jul 20 2021

Information for this report is procurement sensitive.

9310906 Specifications 01 14 00.00 46

Comment Classification: Controlled Unclassified Information (CUI)

Please confirm per specification 01 14 00.00 46 section 1.5 Navigation Restrictions, if the contractor can provide a continuous lane through the lock that is a minimum of 80 feet wide then the contractor can work inside coffer-boxes while barges are simultaneously passing through the lock.

On: Jul 05 2021.

Government Response. . If a barge hits the three sided coffer box/coffer dam,…