PERFORMANCE WORK STATEMENT (PWS)
R.D. WILLIS GENERATOR STEP-UP TRANSFORMER REMANUFACTURE
B.A. STEINHAGEN LAKE, JASPER COUNTY, TX
1. PROJECT BACKGROUND
R.D. Willis hydroelectric facility is built on the Town Bluff, or Dam “B”, structure at the
South end of B.A. Steinhagen Lake in Jasper County, Texas. The existing 8,900 kVA, 25kV Grd Y / 4,160V Delta R.D. Willis main generator step-up transformer, which also provided station service power, is failed on the high voltage A-phase and diesel is currently being used to power the station service loads. The U.S. Army Corps of Engineers: Fort Worth District intends issue a turn-key contract to remanufacture the existing transformer.
GENERAL: This is a non-personal services contract to provide the remanufacturing of existing 8,900 kVA, 25kV Grd Y / 4,160V Delta, R.D. Willis main generator step-up transformer and services. The Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government:
1. Disconnection, rigging and movement to truck, and shipment of the existing transformer from the R.D. Willis hydroelectric facility to the remanufacturing facility.
2. Contractor shall comply with EM 385-1-1 and OPSEC requirements.
3. Remanufacturing of the transformer to include:
• Engineering services to determine remanufacturing requirements
• Three new low voltage coils
• Three new high voltage coils
• New gaskets
• New tank paint
• New external accessories –
• Bushings will be reused
• Nitrogen regulator will be reused
• All connections and processing
• Testing
4. Return shipment to the R.D. Willis hydroelectric facility, offload, placement, reconnection, and testing ready for service
5. Warranty period of 1 year after energizing at the facility to include all leaks, gassing above IEEE Condition 1 rates, and paint.
STATEMENT OF WORK:
3/19/2019 Page 2 of 13
2. BID SCHEDULE
BID ITEMS UNITS QTY.
UNIT
PRICE TOTAL
0001: Transformer
Remanufacturing:
Disconnection, rigging, transportation to and offloading at the remanufacturing facility;
remanufacture; and transportation to and offloading at the R.D.
Willis facility, placement in operating location, testing for return to service, and completion of all external connections
JOB 1
TOTAL PRICE OF ALL BID ITEMS
3/19/2019 Page 3 of 13
3. MEASUREMENT AND PAYMENT
To meet the requirements of this statement of work, the Contractor shall perform the following in accordance with the bid items listed above:
0001: Transformer Remanufacture: Payment for this item shall be made on a JOB basis to include all temporary protection, materials, tools, labor, and pre-work submittals required to perform all requirements of this Statement of Work at the RD Willis facility for removal
(disconnect the transformer power and control connections, remove the transformer from the vault location, load onto transport truck, transport to and offload at the remanufacturing facility), remanufacture, and reinstallation of the transformer (load onto transport truck, transport to the R.D. Willis facility, unload from the from the transport truck into the final vault location, reconnect all power and control wiring, test all connections, and test the transformer to certify ready for service) and additional work required to remove all temporary features, repair any damage to the facility, and make the installation ready for operation.
4. DETAILED REQUIREMENTS FOR SERVICES
A. Nameplate Information
A nameplate photo is included as an attachment to this scope of work. Key information is included here for bidding purposes.
Transformer Ratings:
Delta Star Serial No. Z490003
3 phase, 60 Hz, 2500 Grd Y / 14434 – 4160 Volts
6,675 / 8,900 kW, class OA / FA cooling
5.6% impedance
150 kV HV BIL
75 kV LV BIL
+3 / -1 @ 2.5% de-energized tap changer
Weights:
13,858 Un-tanking weight, lbs.
9,248 Tank and fittings, lbs.
864 Oil quantity, gallons
29,500 Complete oil-filled weight, lbs.
B. Transportation
The transformer may be transported oil-filled and fully assembled.
130 Length, inches
94 Width, inches
134.75 Height, inches
29,500 Complete oil-filled weight, lbs.
B.A. STEINHAGEN LAKE, JASPER COUNTY, TX
3/19/2019 Page 4 of 13
C. Rigging
The transformer is in a 3-sided containment vault with clear access to the front after removing a chain-link fence. A small non-removable curb spans the front of the vault. A permissible loading diagram is included as an attachment to this scope of work. The transformer sits on top of the powerhouse structure, and loading must be strictly observed to prevent structural failure. A lifting / loading plan will be required indicating all trucks, cribbing, cranes, outriggers, and loading prior to work. This plan must be approved before removal can proceed. Note: No outriggers within the service bridge span or hatch.
D. Background Information
The transformer failed in service during a severe weather event in the area. All indications are of a failure in the A-phase high voltage coil or lead structure. All available data regarding the failure is provided in an attachment to this work statement. An inspection of the interior has not been performed. Dissolved gas-in-oil analysis supports arcing event under oil at greater than 700 degrees C. Oil analysis is available upon request.
E. Arrival Inspection
Perform all inspections and tests necessary to determine any deviations from the scope proposed in this document. Notify the Government immediately of any deviations. Upon un-tanking, document with photographs indicating the failure location, arc strikes to the tank wall, and other incident impacts of the in-service failure.
F. Remanufacturing: Active Assembly
Disassemble the top yoke and remove the existing transformer windings. Inspect the transformer core iron for suitability of re-use. Remanufacture new high voltage and low voltage coils of new copper and insulation with materials suitable for a 65 degree C temperature rise transformer rating. Incidental to this is all blocking, leads, spacers, and insulators required to land the remanufactured coils on the core assembly, clamped in place for short circuit strength and reconnected as a complete active assembly rated per the original nameplate.
3/19/2019 Page 5 of 13
G. Bill of Materials
The bill of materials below is for external components. Items numbers correspond with H.K.
Porter Inc. drawing 346142, included as an attachment to this PWS.
No. Item Quantity Requirement
1 HV BUSHING, 25 KV 3
re-use existing, replaced 2016; replace gasket
2 LV BUSHING, 8.7 KV 3
re-use existing, replaced 2016; replace gasket
RADIATORS WITH SHUT-OFF
VALVES AND DRAIN AND VENT
PROVISIONS (DEMOUNTABLE, 5
TOTAL)
Replace 10 butterfly valves, 5 drains, 5 vents, and all gaskets. Inspect, leak-test, repair if necessary, and repaint radiators
BOLTED MANHOLE COVER,
APPROX 12x28 1 Replace gasket
LIFTING EYES FOR LIFTING
COVER ONLY
4 inspect, re-paint with tank
JUNCTION BOX FOR INTERNAL
C.T. LEADS WIRED TO CONTROL
CABINET
1 inspect, replace as-needed
PRESSURE RELIEF DEVICE W/
AUTOMATIC OPERATION AND
SIGNAL FOR INDICATION,
MANUAL RESET WITH ALARM
CONTACTS
replace with new, replace wiring to control cabinet termination
CONTROL CABINET WITH
PRIVISIONS FOR LOCKING,
BOLTED TO THE TANK WALL
1 no work required
3 INCH FLANGED CONNECTION
FOR VACUUM PUMP
1 replace blind flange and gasket
CORE GROUND TO COVER ACCESS
THRU ITEM 4
1 inspect, replace as-needed
ONE INCH DRAIN VALVE AND
FILTER PRESS CONNECTION WITH
3/8 SAMPLING DEVICE
1 replace, new blind flange and gasket
ONE INCH UPPER FILTER PRESS
CONNECTIONS
1 replace, new blind flange and gasket
TRANSFORMER TANK WITH
BOLTED ON COVER
1 inspect, re-paint, ANSI no. 70 grey
TRANSFORMER BASE WITH
PROVSION FOR ROLLING IN
EITHER DIRECTION
1 inspect, re-paint, ANSI no. 70 grey
LIFTING LUGS FOR LIFTING
TRANSFORMER COMPLETE WITH
LIQUID
4 inspect, re-paint with tank
SUDDEN PRESSURE RELAY WITH
CONTACTS WIRED TO ITEM 8
replace with new, replace wiring to control cabinet termination
B.A. STEINHAGEN LAKE, JASPER COUNTY, TX
3/19/2019 Page 6 of 13
HV TAP CHANGER FOR
DEENERGIZED OPERATION,
WHEEL TYPE W/ PROVISION FOR
PADLOCKING
inspect assembly, re-grease, replace springs, replace rollers as-needed
18 STAINLESS STEEL NAMEPLATE 1
add adjacent nameplate for remanufacturing of HV and LV windings, indicating facility name, location, and month / year
GROUND PAD WITH (2) 1/2-13
TAPPED HOLES (2 TOTAL)
2 no work required
20 PRESSURE VACUUM GAUGE 1 replace with new
LIQUID LEVEL GUAGE WITH
ALARM CONTACTS (LOW LEVEL
AND HIGH LEVEL ALARMS)
replace with new, replace wiring to control cabinet termination
DIAL TYPE THERMOMETER WITH
ALARM CONTACTS (REMOTE
DIAL: 10-120 C RANGE
replace with new, replace wiring to control cabinet termination
HV LIGHTING ARRESTER (18KV)
STATION CLASS
3 no work required
WINDING TEMPERATURE
INDICATOR WITH CONTACTS
(REMOTE DIAL)
replace with new, replace wiring to control cabinet termination
HV NEUTRAL COVER MOUNTED
CURRENT TRANSFORMER,
EXTERNAL TYPE, 10:5
replace with new, replace wiring to control cabinet termination
26 FANS - 25 INCH 1/2 HP 4
replace with new (Krenz-vent or equivalent), replace wiring to control cabinet termination
HV BCT 300/5 C50 (2 PER PHASE 6
TOTAL)
replace with new, replace wiring to control cabinet termination
* 28
HV COVER MOUNTED POTENTIAL
TRANSFORMER (3 TOTAL)
3 remove and store at site; reinstall
H0 GROUNDING PROVISIONS 1/4 X
2 COPPER BUS TO ITEM 19
1 inspect hardware and replace as-needed
30 TWO INCH FLANGED GATE VALVE 1 replace, new blind flange and gasket
HV NEUTRAL BUSHING, 15 KV, 600
AMPS
re-use existing, replaced 2016; replace gasket
PORTERAIRE NITROGEN GAS
REGULATING SYSTEM WITH
PURGING VALVE
inspect for leaks, replace components or seals as-needed
OIL LEVEL MARKINGS - 20, 25, & 95
DEG C PERMANENT WELD LINES
1 no work required
* REMOVE FOR SHIPMENT
3/19/2019 Page 7 of 13
H. Testing – Factory
Test the transformer to affirm success of remanufacturing and suitability for return to service prior to shipment from the factory per IEEE and NETA requirements for class of equipment. Government representation for witness testing at the Factory’s final testing is required. Contractor to provide government minimum of 10 working day notice prior to factory test date.
I. Testing – after installation
After offloading from the transportation truck to the final operation location, test the transformer to ensure no damage from transportation and certify for operation per IEEE and
NETA requirements for class of equipment.
J. Installation
Reconnect all external control and power connections. Working with Government personnel, verify that all functions are operating correctly and providing signals to Government equipment in the powerhouse.
K. Warranty
The warranty period shall be for 1 year following 48 hours of successful energized operation after installation. In addition to the active assembly, the warranty shall include all leaks, paint systems, and any gassing conditions beyond Condition 1 defined in IEEE C57.104.
B.A. STEINHAGEN LAKE, JASPER COUNTY, TX
3/19/2019 Page 8 of 13
5. DELIVERABLES
All deliverable products and documents shall be the property of USACE. Submit one paper copy of all non-electronic files. Deliverables for this scope of work are as follows:
A. Schedule. Provide a schedule within 7 calendar days after notice to proceed. The schedule shall specifically note where USACE support is needed onsite. The Schedule shall also include major and minor work elements and stages of the work.
B. Per USACE EM 385-1-1 Section 01.A12 Accident Prevention Plan (APP) shall be submitted and accepted by GDA prior to initiation of any work activity, The APP shall be submitted with in Ten (10) calendar day of NTP.
C. Proposed Site Work Plan - Removal. Provide a written plan of onsite work including deck loading for movement of the transformer and transport truck and personnel information for security clearance.
SAFE CLEARANCE PROCEDURES:
A Safe Clearance System, as stated in EM 385-1-1, and EM 385-1-31 and the power plant
Safe Clearance procedure, is used by project personnel to insure continuity of service and safety to personnel and equipment. Any work performed which requires taking project operating equipment out of service will be done only after a formal clearance is obtained by the Government with a seven calendar day notice. After the Government clearance tags and locks have been placed on the equipment, the Contractor shall place his own clearance tag and lock on the equipment. Safe Clearance procedures shall not be violated by Contractor personnel, and any violations will be grounds for requesting the removal of the offender(s). A copy of the Safe Clearance Procedure program will be supplied to the Contractor upon request.
D. Receiving Inspection. Provide a written report receiving inspection report of test results, external physical inspections, and internal physical inspections of the transformer. Note any deviations from expected condition that may affect the scope of remanufacturing.
E. Test results - factory. Provide a written report of all test results from the remanufacturing facility. Where digital files, such as with Doble test systems, are available, provide the digital file on a compact disc.
F. Proposed Site Work Plan - Install. Provide a written plan of onsite work including deck loading for movement of the transformer and transport truck and personnel information for security clearance.
G. Test Results - field. Provide a written report of all test results to the USACE within 3 days after completion of tests. Where digital files, such as with Doble test systems, are available, provide the digital file on a compact disc.
3/19/2019 Page 9 of 13
6. SCHEDULE
All services under this agreement shall be completed NLT 360 days after award. Specific milestones are as follows:
MILESTONE COMPLETION DATE
Award
Schedule 7 calendar days after Award
Pre-Work Conference /Site visit 14 days after Award
Proposed Site Work Plan - Removal 14 calendar days prior to work
Receiving Inspection 5 calendar days after inspection
Test Results - Factory 3 calendar days following testing
Test Factory- Prior to shipment [ Government witness Test] 10 work days prior to test [notification required.]
Proposed Site Work Plan - Install 14 calendar days prior to work
Test Results - field 3 calendar days following testing
Job Completion
7. COORDINATION
Coordinate delivery scheduling, offloading location, and site access with the R.D. Willis
Project POC. Make every effort to resolve issues in a timely manner before they become a problem.
Project Manager. The Contractor shall appoint a project manager (PM) to serve as a single point-of-contact (POC) and liaison between USACE and the Contractor. Upon signed agreement, the Contractor shall immediately advise the R.D. Willis Project POC of the individual so designated. The PM shall be responsible for the coordination of all work performed for this contract and may be the site supervisor overseeing the work.
PLANT AND EQUIPMENT IDENTIFICATION. The contractor shall identify major plant and equipment and keep the Superintendent informed of what is on site.
TRASH. All refuse generated by the contractor shall be removed by contractor.
DAMAGED EQUIPMENT OR ABNORMAL CONDITIONS. The Government shall be informed immediately upon finding any damaged equipment or other abnormal conditions.
The failure or abnormality shall not be disturbed until witnessed by the Powerhouse
Superintendent. Prior to proceeding further with work on the unit, the Contractor, Owner, and the Government shall agree in writing as to the responsibility for the damage or abnormality.
3/19/2019 Page 10 of 13
Government Project Personnel Working Hours. The scheduled working hours of the
Project staff at the R.D. Willis power plant are Mondays through Fridays from 7:30 a.m. until
5:00 p.m. Saturdays, Sundays and Federal Holidays are non-work days. All Project support required by the Contractor shall be scheduled during the Project staff working hours.
Contractor's Working Hours. The allowable Contractor's working hours shall be the same as that for the Government project personnel, unless otherwise specifically approved. The schedule of work hours, shifts and days of the week shall be coordinated with the Powerhouse
Superintendent. Notification of any proposed changes of the schedule of regular work hours, overtime work hours, and shifts of work crews and personnel at the site shall be coordinated with the Powerhouse Superintendent.
Sanitation Facilities. The nearest bathroom facilities are offsite at Sandy Creek Park.
USACE POCs
ASSIGNMENT PERSONNEL PHONE EMAIL
R.D. Willis Project POC Tom Webb (409) 384-5292 thomas.r.webb@usace.army.mil
Invoices POC
8. R.D. WILLIS POWERHOUSE COORDINATION AND ACCESS
R.D. Willis is a remote unmanned powerhouse West of Jasper, TX accessed via County
Road 154. The approximate location is shown on the map below. Personnel and equipment accessing the powerhouse will be escorted by USACE Personnel to the site.
mailto:thomas.r.webb@usace.army.mil
3/19/2019 Page 11 of 13
Coordinate access with:
Tom Webb
Superintendent
Piney Woods Hydropower Business Line Manager
Sam Rayburn / RD Willis Power Plants
(409) 384-5292 or (409) 384-9368
Thomas.r.webb@usace.army.mil
OPSEC REQUIREMENTS:
AT Level I Training. This provision/contract text is for contractor employees with an area of performance within an Army controlled installation, facility or area. Proposed language:
"All contractor employees, to include subcontractor employees, requiring access to Army installations, facilities, controlled access areas, or require network access, shall complete AT
Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Upon request, the contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website:
http://jko.jten.mil/courses/atl1/launch.html; or it can be provided by the RA ATO in presentation form which will be documented via memorandum."
Access and General Protection/Security Policy and Procedures. This standard language text is for contractor employees with an area of performance within an Army controlled installation, facility or area. Proposed language: "All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office.
Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by
DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes."
mailto:Thomas.r.webb@usace.army.mil
3/19/2019 Page 12 of 13
For contractors who do not require CAC, but require access to a DoD facility or installation. Proposed language: Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime
Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening
Database (TSDB) (Army Directive 2014-05 / AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures
(provided by government representative, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
Suspicious Activity Reporting Training (e.g. iWATCH, CorpsWatch, or See Something, Say Something). This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. Proposed language:
"The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training."
Will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas. The contractor will coordinate with the
COR and/or the facility security office for access when required. (Use when security clearances are not required, i.e. facility repair or construction). Proposed language: "All contract employees, including subcontractor employees who are not in possession of the appropriate security clearance or access privileges, will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas."
(FOR CLASSIFIED CONTRACTS ONLY) Contractor Company to obtain a Facility
Clearance and individual clearances at the appropriate level. Proposed language: "The
Prime Contractor Company must have a Facility Clearance (FCL) at the appropriate level
(IAW the NISPOM DOD 5220.22-M and AR 380-49) prior to the start of the contract awarded period of performance. Contractor personnel performing work under this contract must have the required security clearance, per AR 380-67, at the appropriate level at the start of the period of performance. Security Clearances and FCL requirements are required to be maintained for the life of the contract IAW the DD Form 254 attached to the contract. If no
FCL, the supporting Government Contracting Activity will sponsor the prime contract company in obtaining the FCL."
3/19/2019 Page 13 of 13
Pre-screen candidates using E-Verify Program. Proposed language: "The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award." *When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, with the designated Government representative. This Form will be provided to the Contracting
Officer and shall become part of the official contract file.
REFERENCES. All work shall comply with the requirements of these publications. The publications are referenced to in the text by basic definition only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 Safety and Health Requirements Manual
EM 385-1-31The Control of Hazardous Energy
UNIFIED FACILITIES GUIDE SPECIFICATIONS (UFGS)
UFGS 01 57 19 Temporary Environmental Controls
U.S. DEPARTMENT OF THE ARMY (DA)
ARMY REGULATION (AR) DA AR 200-1 Environmental Protection and Enhancement
9. ATTACHMENTS
1. Map – Regional
2. Map – Local
3. Map – Satellite view of facility
4. Drawing – Plan – El 85.0 – powerhouse deck loading limits
5. Drawing – El 85.0 – powerhouse deck
6. Drawing – GSU vault and tower
7. Drawing – 346142 – Transformer outline and assembly
8. Drawing – 345150 – Transformer wiring diagram
9. Drawing – Transformer LV terminal cover box
10. Photo – El 85.0 Back of vault
11. Photo – El 85.0 Access area
12. Photo – El. 85.0 Front of vault