Amend_01_Attch1of1_Projnet_Q&A_Small_Business.pdf
PDF 330 KB Posted
- Solicitation number
- W9127S-18-R-6002
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ATTACHMENT_W9127S-18-R-6002_Clauses_to_be_Included_in_IDC_(SB).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project: FY18 AE IDC MATOC Review: Synopsis/Solicitation (SB) (00001)
Id Discipline Sheet Detail Spec
7311200 Engineering Support Page 4 of RFP
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Regarding the position of engineering technician – what type of engineering technician are you looking for?
On: Feb 07 2018.
Government Response. . As stated in the solicitation, the evaluation will consider education, training, registration, overall and relevant experience and longevity with the firm as well as experience in medical planning and design. On:
Feb 08 2018
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7311202 Other Page 4 of RFP
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Are you looking for us to provide resumes for the following administrative positions? Or can we state that we have these positions in-house.
o Administrative Assistant o Technical Writer
On: Feb 07 2018.
Government Response. . Resumes are required for all disciplines listed in the solicitation. On: Feb 08 2018
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7311206 Survey Page 5 of RFP
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
For the position of survey crew, since this is a nationwide contract and surveying is usually done by a local firm in the area of where the work will be performed, do we need to provide resumes?
On: Feb 07 2018.
Government Response. . Resumes are required for all disciplines listed in the solicitation. On: Feb 08 2018
Current Request Status: Request Closed
W9127S-18-R-6002 PROJNET Q&A
https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAll&strReportType=AllCont&RequestTimeout=1000&pagStrRowSort=CommentID https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAll&strReportType=AllCont&RequestTimeout=1000&pagStrRowSort=Discipline https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAll&strReportType=AllCont&RequestTimeout=1000&pagStrRowSort=Sheet https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAll&strReportType=AllCont&RequestTimeout=1000&pagStrRowSort=Detail https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAll&strReportType=AllCont&RequestTimeout=1000&pagStrRowSort=SpecText
Information for this report is procurement sensitive.
7311211 Environmental Page 5 of RFP
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
In regards to the Registered Environmental Design Personnel, since the RFP already lists an environmental engineer, environmental survey personnel, as well as an industrial hygienist – If they all have to capability to provide sampling of asbestos, lead based paints, soils, etc., as well a design services, do we still need to include resume(s) for registered environmental design personnel?
On: Feb 07 2018.
Government Response. . Resumes are required for all disciplines listed in the solicitation. On: Feb 08 2018
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7316516 Other Solicitation Solicitation Solicitation
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Will previous planning and project experience from the Department of Veterans Affairs be considered relevant as long as such experience meets the requirements listed under B.
Specialized Experience and Technical Competence?
On: Feb 11 2018.
Government Response. . Yes. On: Feb 12 2018
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7316518 Other Solicitation Solicitation Solicitation
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
A. Professional Qualifications - may key personnel hold dual roles? If so should specific resumes be submitted for each role (individuals with dual roles may have more than one resume).
On: Feb 11 2018.
Government Response. . Yes. Resumes should be provided for each discipline, even if a specific individual is filling multiple roles, ie. program manager and architect. On: Feb 12 2018
Current Request Status: Request Closed
7321155 Other Page 4 Health Care
Planner Past Experience
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Will alternate but comparable past experience be accepted for the health care planner if we can't show experience with, for example, MEPRS and MCFAS?
On: Feb 14 2018.
Government Response. . The requirements identified will not be waived.
Alternate past experience will not be accepted for the health care planner. On: Feb
20 2018
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7321305 Other
4. Submission
Format
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Solicitation Submission Format requires that fonts should be Times New Roman no smaller than 12 points. We are finding that it is a challenge to format Resumes with qualification details and 5 projects on one page with Times New Roman 12 Point Font on Form E.
Important details may not fit.
We request consideration for allowing other font types of 12 point so that resumes could be formatted with adequate details and 5 projects on one page.
On: Feb 14 2018.
Government Response. . The font type and size is a requirement that will not be waived. On: Feb 20 2018
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7323804 Architectural Page 5 Section B
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
It is stated that projects must be completed in the last five years. Does that mean construction must have been completed in the last 5 years, or are projects where the design work has been completed in the 5 years acceptable?
On: Feb 15 2018.
Government Response. . AE must demonstrate efforts that have been completed within the past 5 years that detail the experience required. On: Feb 20 2018
7323811 Architectural Sheet 6 Section C
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Where would you like CPARS included? Will they count towards the 100 page limit?
On: Feb 15 2018.
Government Response. . CPARS information is not a requirement for inclusion in the SF330. CPARS will be downloaded by the Government. On: Feb 20 2018
7332375 Architectural III. Selection
Criteria
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Would you like the resumes in the same order as they are listed in the solicitation or would you prefer them listed similarly to how they will be organized in the organization chart?
On: Feb 21 2018.
Government Response. . Yes, in alphabetical order by discipline as shown in the solicitation. On: Feb 28 2018
7339489 Other Submission Format
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
In the solicitation, it states the SF330 font should be Times New Roman no smaller than 12 pt.
The SF330 form available for download at the provided link does not allow for this font. It appears the font is set as Arial or another similar sans serif font. Please advise on how to proceed.
On: Feb 27 2018.
Government Response. . The pre-set font and size for the SF330 on the referenced link is acceptable. On: Feb 28 2018
Report Complete
File details come from the government source that posted it.