Amendment_0002.pdf

PDF 2 MB Posted

Attached to
Stator Repair and Rewedge Federal contract opportunity
Solicitation number
W9127S18R0009
Issued by
Department of the Army Corps of Engineers Engineering District Little Rock

About this file

Amendment 0004

View the file

Other files for this federal contract opportunity

Other files attached to Stator Repair and Rewedge, newest first.
File Type Posted
Amendment_0001.pdf PDF
W9127S18R0009-plans(12-14).pdf PDF
W9127S18R0009-specs.pdf PDF
W9127S18R0009-plans(5-7).pdf PDF
W9127S18R0009-plans(8-11).pdf PDF
W9127S18R0009-Solicitation.pdf PDF
W9127S18R0009-plans(1-4).pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

See page 2

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9127S18R0009

X 9B. DATED (SEE ITEM 11)

08-May-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

20-Jun-2018

CODE

CONTRACTING DIVISION

USACE, LITTLE ROCK (W9127S)

700 W. CAPITOL AVE, RM 7315

LITTLE ROCK AR 72201-3225

W9127S 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9127S18R0009

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0002

The purpose of this amendment is to:

1) Answer ProjNet inquiries

2) Revise Specification Sections:

48 13 16.02 26 01 45 00.00 10 01 14 00.00 46

3) Revise Solicitation Section 00 21 00 (Changes in bold and italicized)

(End of Summary of Changes)

UNCLASSIFIED\\FOR OFFICIAL USE ONLY

Bid Inquiry Contractor Report All Inquiries

Project: Beaver - Stator Repair and Rewedge Review: Bidder Inquiry RFI Review (00001) (sorted by CommentID ) Displaying 18 inquiries.

Id Discipline Sheet Detail Spec 7468038 Mechanical SF 1442 Site Visit Access W9127S18R0009 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

At the site visit, will our personnel be able to have safe access to the bore of the stator and have safe access to the top and bottom end windings and areas of failure to take measurements? Please confirm that the rotor is out and is accessible for inspection and measurements.

(Attachment: W9127S18R0009-Solicitation.pdf) On: May 14 2018.

Government Response. . The site visit was conducted on May 23, 2018, and contractors were provided safe access to the unit 2 stator area. The rotor for the unit 2 was taken out and placed on the generator bay area. On: Jun 18 2018 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7468092 Hydropower page 4 of 70 Buy American Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

The FAR Clause 52.225-9 BUY AMERICAN-CONSTRUCTION MATERIALS restricts the use of foreign construction materials. Please be aware that some of the materials such as the raw materials of the packing materials for the stator coils in the slot for this project are not manufactured in the United States. Please revise the requirements to allow Free Trade Agreement countries.

On: May 14 2018.

Government Response. . FAR Clause 52.225-9 applies, offerors may request a determination concerning the applicability of the statute for specifically identified construction materials by following the instructions in 52.225-9 and 52.225-10 of the solicitation. On: Jun 20 2018 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7478336 Contracting Section 01 14 00.00

Quality Control inspector 1.5

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Please confirm that a separate designated Quality Control Inspector is not required and that the Contractor's site supervisor can act as Quality Control inspector.

On: May 18 2018.

Government Response. . No dual-hatting of these positions is allowed. The CQC and the site supervisor must be two separate individuals. On: Jun 18 2018 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7478469 Contracting Page 13 of 70 Factor 4 Past Performance PPQ and CPARS

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Can the vendor use already completed PPQs(attachment2) from past Government tenders for the projects identified in Factor 1 experience or are we required to have these completed again by our clients? Can Past CPARS evaluations on specific Factor 1 Experience Projects be used in lieu of PPQs?

On: May 18 2018.

Government Response. . The use of already completed PPQs(attachment2) from past Government tenders for the projects identified in Factor 1 experience is acceptable. CPARS cannot be submitted in lieu of PPQs. The Government will check CPARS in addition to the PPQs. On: Jun 18 2018

Page 1 of 5ProjNet: Logged In User

6/20/2018https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAl...

Current Request Status: Request Closed Information for this report is procurement sensitive.

7478884 Contracting Section 01 11 01 1.1.1 Project Description

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

The Contractor shall allow 365 days between Phase 1 and Phase 2 to allow Government to prepare for the 2nd unit outage. Based on unit 2- 90 day outage time plus submittal preparation before unit # 2 outage, and unit 1 30 day outage, the contract could extend well past 365 days. Two Questions:

1. Contract duration and LD amount on page 38 of 70 are based on 365 calendar days to complete entire work.

Please clarify.

2.Should we assume 365 days between units in our pricing or will Contractor be entitled to any cost increase relief for escalation of Labor rates and materials cost?

On: May 18 2018.

Government Response. . The 365 day delay between unit #2 and unit #1 work was included to allow the government time to repair the overhead crane should it prove inoperable. Specifications were amended to allow for the possible delay.

1. Yes, duration and LD are based on 365 days.

2. Should a delay occur, the Contractor may request an equitable adjustment if there is a cost or schedule impact. On: Jun 20 2018 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7478909 Contracting Section 10 14 00.0046 1.3.1 Work Hours Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

The work days are different for the two units. Unit 2 allows 6 days 10 hour shifts but Unit # 1 only allows 4 days 10 hour shifts. It is difficult to get needed electrical winding crew for a 30 day outage working only 4/10s. Can unit#1 rewedge scope also allow for 6/10 Hour shifts?

On: May 18 2018.

Government Response. . An amendment will be issued to allow work schedule for Unit 1 similar to Unit

2. On: Jun 18 2018 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7478942 Contracting Page 14 and 15 of 70 Small Business Participation plan 7.8 Factor 5

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Under submission requirement on page 14 of 70 specifications indicates Total SB participation goal of 20% but the rating table on page 15 of 70 indicates commitment to meet 30% SB participation. Please clarify.

On: May 18 2018.

Government Response. . Total SB participation goal of 20% is correct. The evaluation factors will be changed accordingly in Amendment 0002. On: Jun 18 2018 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7478954 Contracting page 6 of 70 Funding Note on Funding Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Can you provide and update Project Funding and if the USACE is confident an award of the contract will be made 90 days after bid due date.

On: May 18 2018.

Government Response. . The solicitation was issued in advance of receipt of funding; however, the Government expects funds to be provided within the 90 days specified. On: Jun 20 2018 Current Request Status: Request Closed

Page 2 of 5ProjNet: Logged In User

Information for this report is procurement sensitive.

7478968 Construction Management

Section 01 32 01.00 10 Project Schedule

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

The scheduler and scheduling requirement seem very high level for a project of this duration and work scope. This requirement will add cost to the project that may not be needed. Would the USACE consider simplifying these requirements?

On: May 18 2018.

Government Response. . No, this is a standard specification per our Construction Office. On: Jun 18 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7479004 Construction Management

Section 01 45 00.00 10 3.4.2 CQC System Manager

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

The requirement for CQC manager is very restrictive i.e. Electrical engineer with 20 years experience in Hydroelectric powerhouse related work. Our site managers on typical USACE projects usually have dual role of Site manager and CQC manager are not Engineers and many do not have 20 years experience in this role. Can the USACE reduce this restrictive requirement to exclude Electrical engineering degree requirement and 5 or 10 years of experience in lieu of 20 years in Hydroelectric powerhouse related work?

On: May 18 2018.

Government Response. . Page 4, paragraph 3.4.2 Will be revised to read "...The CQC System Manager is required to be a graduated electrical engineer with a minimum of 5 years construction experience in hydroelectric generator winding repair and rewedge related work, or a graduated in construction management with a minimum of 10 years construction experience in hydroelectric generator winding repair and rewedge related work, or a master electrician with a minimum of 10 years construction experience in hydroelectric generator winding repair and rewedege related work..." On: Jun 18 2018 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7488255 Hydropower W9127S18R0009 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Based on the evaluation during the site visit, we believe it's highly risky to repair the coils of Unit 2 as described in the specification as to use half-coil splices, taking into consideration that these coils are over 50 years old and are quite fragile. During such repair, the groundwall of the repaired coils and the existing coils around the repairing area can easily be damaged. We strongly recommend to jumper the coils and run unit 2 in a reduced output, in the meantime a complete generator rewind shall be planned in the near future.

On: May 24 2018.

Government Response. . Based on HDC's winding repair experience, we believe the repair approach outlined in the solicitation is not of high risk and is within the capabilities of qualified winding repair companies. The coils contain only three (3) turns each, which is not quite as ambitious as similar repairs on coils with four or more turns. Executing the repair as outlined in the solicitation maximizes the post-repair capacity of Unit 2. A rewind is not planned for the Beaver units at this time, as such, it is the Government's preference to not reduce capacity any more than necessary. There is insufficient risk to pursue an alternative repair that results in a greater de-rate. If the bidder is capable of performing the work, they should bid the scope outlined in the solicitation. On: Jun 20 2018 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7490003 Project Management 1 bid date Solicitation-,Offer, and Award Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Sealed offers due 19 Jun 2018 10:00 a.m. - Can this date be extended?

On: May 25 2018.

Page 3 of 5ProjNet: Logged In User

Government Response. . Proposal due date has been extended to July 09, 2018 at 10:00 A.M. On: Jun 18 2018 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7492707 Construction Management Solicitation Form 1442 Section 13

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Can the submittal deadline be extended?

On: May 29 2018.

Government Response. . Proposal due date has been extended to July 09, 2018 at 10:00 A.M. On: Jun 18 2018 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7497581 Contracting 48 13 16.02 26 Pg 4 / 01 57 19 Pg 22 Asbestos W9127S18R0009

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Will the government take responsibility for any discovered asbestos hazard?

If discovered in pre-outage testing will the Government take responsibility to abate any asbestos hazard discovered in this testing or during the course of the work and state that Contractor shall not be responsible for abatement of asbestos if discovered.

On: May 31 2018.

Government Response. . An asbestos test was done around the air housing and the test results indicated that there was no asbestos found. Asbestos samples have been collected around the winding and rotor. If test results indicate asbestos, abatement will be added to the solicitation. On: Jun 18 2018 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7499741 Contracting Page 9 of 70 Preparing Proposal 4.6.2 Page Limitations Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Maximum of 40 printed pages submitted for all four evaluation factors. Is this 40 page limit per each factor or 40 page limit for all factors? We suggest 40 pages per factor as especially technical approach and Management Plan factors requires some details and explanation of many pages for a good evaluation.

On: Jun 01 2018.

Government Response. . The technical proposal page limit is 40 pages total for all factors and will not be increased. On: Jun 18 2018 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7499751 Construction Management Outage time Section 011400.00 46 paragraph

1.3.3 Outage Time

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

30 working days for Stator rewedge, clean and inspection of stator core and winding. Inspect and clean rotor Paint Rotor and stator and test stator winding is very tight. Is there a possibility this can be extended to another 15 work days?

On: Jun 01 2018.

Government Response. . The specification will be revised to show 45 working days for Unit 1. On: Jun 18 2018 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7499842 Contracting Warranty Section 48 13 16.02 26 1.5 Warranty

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Page 4 of 5ProjNet: Logged In User

We noted during the site inspection that these units have never been rewound and the existing winding is over 50 years old. Based on the known breakdown of insulation in these windings and recent failure, we will not be able to provide a 5 year workmanship warranty on half coils splices. We will need to add a comment to this warranty requirement or better definition in the specifications On Warranty requirement. There is High risk there could be more winding failures during testing phase in the old coil insulation. We also agree that the Contractor should provide best solution to get unit back on line at derated output and a complete rewind should be planned in future by the USACE.

On: Jun 01 2018.

Government Response. . The warranty requires the Contractor to be responsible for their work as specified. Any failures during testing of the portions of the existing stator winding not touched by the Contractor are the responsibility of the Government. Failures in splices, bypasses or brazes made by the contractor or damages to the spare coils are the responsibility of the Contractor. The contractor has to strip and apply new insulation to the areas where they make their brazes. On: Jun 18 2018 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7500467 Construction Management Stator Core repair Section 48 13 16.02 26

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Although not explicitly requested in the RFP, a stator core loop test will be required for an adequate quality control of the repair job. At a minimum, a stator loop test would be required during the initial inspection and another one after the repair work.

The initial loop test would be useful to make a first assessment of the core. In addition to the area affected by the fault, other hot spots requiring attention could be detected at other locations around the core.

The second loop test after repair will be required to confirm the repair process was successful.

Hot spots left in the stator can deteriorate over time. The most critical hot spots are the ones located within the stator slot as a hot spot in contact with the winding insulation can contribute to accelerated ageing and, eventually, failure.

Will the USACE consider adding Core loop test to the work scope and schedule?

On: Jun 01 2018.

Government Response. . The majority of the existing stator winding will be installed, before, during and after the repair. Performing an interlaminar insulation (core loop) test with the stator winding would not only heat the stator winding, but also block portions of the stator core of true interest (the inside the slot) and likely result in a higher measured temperature, making such a test inaccurate. The performance of an interlaminar insulation test will not be added to the contract, nor will any Contractor be authorized to perform that test. On: Jun 18 2018 Current Request Status: Request Closed

Information for this report is procurement sensitive.

Report Complete

UNCLASSIFIED\\FOR OFFICIAL USE ONLY

Patent 11/892,984 ProjNet property of ERDC since 2004.

Page 5 of 5ProjNet: Logged In User

SECTION 01 14 00.00 46

WORK RESTRICTIONS (SWL)

PART 1 GENERAL

1.1 PROTECTION OF GOVERNMENT PROPERTY

1.1.1 Protection of Government Facilities

Take whatever measures are necessary or required for protection of the existing buildings, grounds, parking area and other Government facilities.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

1.3 WORK SCHEDULE

1.3.1 Work Hours

Arrange work schedule so that the work performed at the Government installation will be as following: Unit 1 normal day shift established as 6:30 a.m. to 5:00 p.m., Monday through (AM0002) Saturday , except Federal holidays. Unit 2 normal day shift established as 6:30 a.m. to 5:00 p.m., Monday through Saturday, except Federal holidays.

1.3.2 Inspection Hours

The contract requires that certain tests be performed in the presence of the Contracting Officer or his representative. These tests will be scheduled between 10:30 a.m. and 03:00 p.m., Monday through Thursday, excluding Federal holidays; the Government shall be given 72 hours advance notice.

1.3.3 Outage Time

Installation activity shall be planned and scheduled so that all the installation and operational testing shall not exceed 90 working days for unit 2 stator repair and rewedge and (AM0002) 45 working days for rewedge unit 1. Unit #2 is currently out of service and work can be commensed without restriction of no outage. There maybe a waiting of 365 days between the work for Phase I (Unit #2 work) and Phase II (Unit #1 work)to allow the Government to coordinate the usage of the crane and to remove unit #1 cover and rotor out of the main unit. At anytime within the 365 days, the Contractor may receive a notice to proceed on Phase II. The Contractor shall have 60 days to mobilize to the site and start Phase II work. Critical load maximum outage period shall be no more than 1 hour.

SECTION 01 14 00.00 46 Page 1

Stator Repair and Rewedge Beaver Powerhouse Beaver Lake, White River Carroll County, Arkansas SOLICITATION NUMBER W9127S18R0009

AMENDMENT 0002 TO SOLICITATION W9127S18R0009 on 06/12/2018 m4ecdtdd Highlight

See paragraph Special Scheduling Requirements for a list of critical loads. As much as possible preparatory work shall be accomplished prior to unit outages to minimize downtime. The Contractor shall assure that an adequate number of personnel are present during unit outages to assure that the specified outage time is not exceeded. Main generator unit outages for power plant work are not permitted 15 June – 15 September and 15 December – 15 March. The Contractor shall provide a detailed sequence of outages in the construction schedule. Outages shall be detailed to the day level.

1.3.4 Special Scheduling Requirements

a. Contractor shall be ready for operation of the repaired main unit generators as approved by Contracting Officer noting work restrictions in this section. Before work is started on the project coordinate with Contracting Officer since this work will interfere with normal operation.

b. Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work.

c. The Powerhouse will remain in operation during the entire construction period. The Contractor shall conduct his operations so as to avoid interference with the powerhouse daily operations of the activity.

d. Permission to interrupt any generator units and/or utility service shall be requested in writing a minimum of 21 calendar days prior to the desired date of interruption.

e. The work under this contract requires special attention to the scheduling and conduct of the work in connection with existing operations. Identify on the construction schedule each factor which constitutes a potential interruption to operations.

The following conditions apply:

(1) No generation unit outages will be allowed during the following periods: December 15th through March 15th and June 15th through September 15th.

(2) All outages of the main units or related systems that could effect the plant operation shall be coordinated 21 days in advance with the Contracting Officer. Some shutdowns will require more prep time by the powerhouse personnel than others. All outages shall be listed in the Contractor's schedule and be continuously updated. Once a outage period is scheduled with the powerhouse, Contractor shall not delay or postpone the outage. A detailed outage plan shall be submitted and approved before outage work can start and shall include outage schedule as well as detailed information on the methodology and procedure for performing the work.

(3) The Contractor shall perform prep work to minimize period of the unit outage. Duration of shutdown varies with number of turbines in operation.

(4) Contracting Officer will provide a notice of which unit and date to allow Contractor access.

(5) Sequence of work may vary due to lake water level, number of turbines generating, Contractor's approach, and current plant

SECTION 01 14 00.00 46 Page 2

Stator Repair and Rewedge Beaver Powerhouse Beaver Lake, White River Carroll County, Arkansas SOLICITATION NUMBER W9127S18R0009

AMENDMENT 0002 TO SOLICITATION W9127S18R0009 on 06/12/2018 operations. At Pre-Con meeting, sequence shall be discussed to determine best approach to complete work.

1.4 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER (AM0002) CONDITION AND

SPECIAL CONDITIONS

1.4.1 Procedure for Determination

This provision specifies the procedure for determination of time extensions for unusually severe weather in accordance with the contract clause entitled "Default (Fixed Price Construction)". In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:

a. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

b. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.

(AM0002) c. In the event the government owned government operated bridge crane become inoperable, the Contractor shall submit a request for time extension to the COR for review and approval.

1.4.1.1 Schedule of Anticipated Adverse Weather Days

The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY

WORK DAYS BASED ON (4) DAY WORK WEEK

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

6 3 3 2 2 1 1 1 1 1 1 4

1.4.1.2 Reporting Adverse Weather Delays

Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled workday. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the

SECTION 01 14 00.00 46 Page 3

Stator Repair and Rewedge Beaver Powerhouse Beaver Lake, White River Carroll County, Arkansas SOLICITATION NUMBER W9127S18R0009

AMENDMENT 0002 TO SOLICITATION W9127S18R0009 on 06/12/2018 m4ecdtdd Highlight m4ecdtdd last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph (b), above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the contract clause entitled "Default (Fixed Price Construction)".

1.5 QUALITY CONTROL

1.5.1 General

The Contractor shall establish and maintain quality control for his operations to assure compliance with contract requirements and maintain records of his quality control for all construction operations under the contract as specified in SECTION 01 45 00.00 10 QUALITY CONTROL

1.5.2 Technical Provisions

This requirement shall apply equally to each section of the Technical Provisions, except where the QUALITY CONTROL requirements set forth critical items of work requiring special attention by the Contractor.

1.5.3 Control Inspector Safety Responsibilities

Each Contractor quality control inspector shall be responsible for inspecting the work under his surveillance for compliance with EM 385-1-1 , and shall immediately bring to the attention of the Contractor's supervisory personnel all unsafe working conditions, unsafe work practices, unsafe tools or equipment and instances of noncompliance with the Safety and Health Requirements Manual.

1.5.4 Quality Control Inspector Environmental Responsibilities

The Contractor quality control inspector shall be responsible for quality control for environment protection specified in SECTION 01 57 19 TEMPORARYENVIRONMENTAL CONTROLS, and shall immediately bring to the attention of the Contractor's supervisory personnel all instances of noncompliance.

1.5.5 Records and Tests

A copy of the records and tests, as well as the records of corrective action taken, will be furnished the Government as directed by the Contracting Officer.

1.6 GOVERNMENT-FURNISHED UTILITIES

Utilities will be furnished by the Government to the Contractor free of charge as specified below. The Contractor shall carefully conserve any utilities furnished by the Government.

1.6.1 Water

Government furnished raw or non-potable water will be available at existing hydrants or outlets that are located near the work area. The Contractor shall furnish all piping, hoses, valves, fittings and all other incidentals necessary to convey the water from the existing hydrants or outlets to the work site. Backflow preventers are required when using water from a fire hydrant. The backflow preventer must be tested for

SECTION 01 14 00.00 46 Page 4

Stator Repair and Rewedge Beaver Powerhouse Beaver Lake, White River proper operation each time that it's moved. The contractor must have documentation of the testing in-hand to demonstrate that the backflow preventer was tested in its current location.

1.6.2 Electricity

Government furnished electricity will be available at existing electrical outlets, 120 volt at 15 amp or 480 volt, that are located near the work area. The Contractor shall furnish all panels, circuit breakers, wiring, transformers and all other incidentals necessary to meet the needs of the equipment used in the work.

1.6.3 Compressed Air

Government furnished compressed air will be available at existing outlets, 20 cfm at 125 psi, that are located near the work area. The Contractor shall furnish all hoses, regulators, connectors, tools, water separators, and all other incidentals necessary to meet the needs of the equipment used in the work.

1.6.4 Work Area and Storage Area

The Contractor's work and storage area will be assigned by the Contracting Officer.

1.6.5 Sanitary Facilities

Existing sanitary facilities and drinking water fountains will not be available for use by the Contractor's personnel. The Contractor shall be responsible for sanitary facilities and drinking water.

1.6.6 Use of Powerhouse Crane

1.6.6.1 Use of Crane

The Contractor shall coordinate with the Government, 24 hours in advance, for the use of the crane during the Contractor's scheduled on-site work.

The Government will have priority use of the crane in emergency conditions.

1.6.6.2 Operator(s) and Rigger(s)

The Government will provide the crane operator(s). The Contractor shall provide crane rigger(s) and rigging during Contractor requested crane use through the duration of the on-site work.

1.7 BULLETIN BOARD, PROJECT SIGN, SAFETY SIGN

1.7.1 Bulletin Board

The Contractor shall furnish, install, and maintain for the duration of the contract, a weather tight bulletin board, having hinged or sliding glazed doors, on which shall be displayed legible copies of (1) the poster entitled "equal employment opportunity is the law" (OFCCP Publication 1420) as required by CONTRACT CLAUSES: EQUAL OPPORTUNITY, AFFIRMATIVE

ACTION COMPLIANCE REQUIREMENTS FOR CONSTRUCTION, AFFIRMATIVE ACTION FOR

SPECIAL DISABLED AND VIETNAM ERA VETERANS, AND AFFIRMATIVE ACTION FOR

HANDICAPPED WORKERS; (2) the Notice to Employees Poster (WH Publication 1321); (3) the schedule of minimum wage rates for the contract as required by CONTRACT CLAUSE: DAVIS-BACON ACT; and (4) current safety posters. The

SECTION 01 14 00.00 46 Page 5

Stator Repair and Rewedge Beaver Powerhouse Beaver Lake, White River bulletin board shall be mounted where and as approved by the Contracting Officer, in a prominent place accessible to all employees of the Contractor and subcontractors, and to applicants for employment. The bulletin board shall remain the property of the Contractor and shall be removed by him upon completion of the contract work.

1.7.2 Project and Safety Signs

The requirements for the signs (see Section 01 00 50 Forms and Attachments), their content, and location shall be as shown on the drawings. Exact location and name of sponsor, to be placed on the sign, shall be determined by the Contracting Officer. Verify with the Contracting Officer, the exact text to be placed on the signs prior to construction of the signs.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used.

-- End of Section --

SECTION 01 14 00.00 46 Page 6

Stator Repair and Rewedge Beaver Powerhouse Beaver Lake, White River

SECTION 01 45 00.00 10

QUALITY CONTROL

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM D3740 (2012a) Minimum Requirements for Agencies Engaged in the Testing and/or Inspection of Soil and Rock as Used in Engineering Design and Construction

ASTM E329 (2014a) Standard Specification for Agencies Engaged in the Testing and/or Inspection of Materials Used in Construction

1.2 PAYMENT

Separate payment will not be made for providing and maintaining an effective Quality Control program. Include all associated costs in the applicable Bid Schedule unit or lump-sum prices.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Contractor Quality Control (CQC) Plan; G

SECTION 01 45 00.00 10 Page 1

Stator Repair and Rewedge Beaver Powerhouse Beaver Lake, White River

AMENDMENT 0002 TO SOLICITATION W9127S18R0009 ON 06/12/2018

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

Establish and maintain an effective quality control (QC) system that complies with the Contract Clause titled "Inspection of Construction." QC consist of plans, procedures, and organization necessary to produce an end product which complies with the contract requirements. The QC system covers all work operations, both onsite and offsite, and shall be keyed to the proposed work sequence. The project superintendent will be held responsible for the quality of work and is subject to removal by the Contracting Officer for non-compliance with the quality requirements specified in the contract. In this context the highest level manager responsible for the overall construction activities at the site, including quality and production is the project superintendent. The project superintendent shall maintain a physical presence at the site at all times and is responsible for all construction and related activities at the site, except as otherwise acceptable to the Contracting Officer.

3.2 CONTRACTOR QUALITY CONTROL (CQC) PLAN

Submit no later than 10 days after receipt of notice to proceed, the Contractor Quality Control (CQC) Plan proposed to implement the requirements of the Contract Clause titled "Inspection of Construction."

The Government will consider an interim plan for the first 10 days of operation. Work will be permitted to begin only after acceptance of the CQC Plan or acceptance of an interim plan applicable to the particular feature of work to be started. Work outside of the accepted interim plan will not be permitted to begin until acceptance of a CQC Plan or another interim plan containing the additional work.

3.2.1 Content of the CQC Plan

Include, as a minimum, the following to cover all work operations, both onsite and offsite, including work by subcontractors, fabricators, suppliers, and purchasing agents:

a. A description of the quality control organization, including a chart showing lines of authority and acknowledgment that the CQC staff will implement the three phase control system for all aspects of the work specified. Include a CQC System Manager that reports to the project superintendent.

b. The name, qualifications (in resume format), duties, responsibilities, and authorities of each person assigned a CQC function.

c. A copy of the letter to the CQC System Manager signed by an authorized official of the firm which describes the responsibilities and delegates sufficient authorities to adequately perform the functions of the CQC System Manager, including authority to stop work which is not in compliance with the contract. Letters of direction to all other various quality control representatives outlining duties, authorities, and responsibilities will be issued by the CQC System Manager. Furnish copies of these letters to the Contracting Officer.

SECTION 01 45 00.00 10 Page 2

Stator Repair and Rewedge Beaver Powerhouse Beaver Lake, White River

d. Procedures for scheduling, reviewing, certifying, and managing submittals, including those of , . These procedures must be in accordance with Section 01 33 00 SUBMITTAL PROCEDURES.

e. Control, verification, and acceptance testing procedures for each specific test to include the test name, specification paragraph requiring test, feature of work to be tested, test frequency, and person responsible for each test. (Laboratory facilities approved by the Contracting Officer are required to be used.)

f. Procedures for tracking preparatory, initial, and follow-up control phases and control, verification, and acceptance tests including documentation.

g. Procedures for tracking deficiencies from identification through acceptable corrective action. Establish verification procedures that identified deficiencies have been corrected.

h. Reporting procedures, including proposed reporting formats.

i. A list of the definable features of work. A definable feature of work is a task which is separate and distinct from other tasks, has separate control requirements, and is identified by different trades or disciplines, or it is work by the same trade in a different environment. Although each section of the specifications can generally be considered as a definable feature of work, there are frequently more than one definable features under a particular section. This list will be agreed upon during the coordination meeting.

3.2.2 Acceptance of Plan

Acceptance of the Contractor's plan is required prior to the start of cons. Acceptance is conditional and will be predicated on satisfactory performance during the. The Government reserves the right to require the Contractor to make changes in the Constractor Quality Control(CQC) Plan and operations including removal of personnel, as necessary, to obtain the quality specified.

3.2.3 Notification of Changes

After acceptance of the CQC Plan, notify the Contracting Officer in writing of any proposed change. Proposed changes are subject to acceptance by the Contracting Officer.

3.3 COORDINATION MEETING

After the and prior to acceptance by the Government of the CQC Plan, meet with the Contracting Officer and discuss the Contractor's quality control system. Submit the CQC Plan a minimum of seven (7) calendar days prior to the Coordination Meeting. During the meeting, a mutual understanding of the system details must be developed, including the forms for recording the CQC , control activities, testing, administration of the system for both onsite and offsite work, and the interrelationship of Contractor's Management and control with the Government's Quality Assurance. Minutes of the meeting will be prepared by the Government, signed by both the Contractor and the Contracting Officer and will become a part of the contract file. There can be occasions when subsequent conferences will be called by either party to reconfirm mutual understandings and/or address

SECTION 01 45 00.00 10 Page 3

Stator Repair and Rewedge Beaver Powerhouse Beaver Lake, White River deficiencies in the CQC system or procedures which can require corrective action by the Contractor.

3.4 QUALITY CONTROL ORGANIZATION

3.4.1 Personnel Requirements

The requirements for the CQC organization are a Safety and Health Manager, and sufficient number of additional qualified personnel to ensure safety and contract compliance. The Safety and Health Manager reports directly to a senior project (or corporate) official independent from the CQC System Manager. The Safety and Health Manager will also serve as a member of the CQC Staff Personnel identified in the technical provisions as requiring specialized skills to assure the required work is being performed properly will also be included as part of the CQC organization.

The Contractor's CQC staff maintains a presence at the site at all times during progress of the work and have complete authority and responsibility to take any action necessary to ensure contract compliance. The CQC staff will be subject to acceptance by the Contracting Officer. Provide adequate office space, filing systems and other resources as necessary to maintain an effective and fully functional CQC organization. Promptly complete and furnish all letters, material submittals, shop drawing submittals, schedules and all other project documentation to the CQC organization. The CQC organization is responsible to maintain these documents and records at the site at all times, except as otherwise acceptable to the Contracting Officer.

3.4.2 CQC System Manager

Identify as CQC System Manager an individual within the onsite work organization that is responsible for overall management of CQC and has the authority to act in all CQC matters for the Contractor. The CQC System Manager is required to be a graduate electrical engineer with a minimum of (AM0002) 5 years construction experience in hydroelectric (AM0002) generator winding repair and rewedg e related work, or a graduate of construction management with a minimum of (AM0002) ten (10) years construction experience in hydroelectric (AM0002) generator winding repair and rewedge related work, or a master electrician with a minimum of (AM0002) ten (10) years construction experience in hydroelectric (AM002) generator winding repair and rewedge related work. This CQC System Manager is on the site at all times during construction and is employed by the prime Contractor. The CQC System Manager is assigned as CQC System Manager but can have duties as project superintendent in addition to quality control. Identify in the plan an alternate to serve in the event of the CQC System Manager's absence. The requirements for the alternate are the same as the CQC System Manager.

3.4.3 Additional Requirement

In addition to the above experience and education requirements the CQC System Manager must have completed the course entitled "Construction Quality Management For Contractors" in the past five years. Contact the Little Rock District Construction Office, 501-324-7356, for information about this course.

3.4.4 Organizational Changes

Maintain the CQC staff at full strength at all times. When it is necessary to make changes to the CQC staff, revise the CQC Plan to reflect the

SECTION 01 45 00.00 10 Page 4

Stator Repair and Rewedge Beaver Powerhouse Beaver Lake, White River Carroll County, Arkansas SOLICITATION NUMBER W9127S18R0009

AMENDMENT 0002 TO SOLICITATION W9127S18R0009 ON 06/12/2018

M4ECDMDL

Highlight

M4ECDMDL

Highlight

M4ECDMDL

Highlight

M4ECDMDL

Highlight

M4ECDMDL

Highlight

M4ECDMDL

Highlight

M4ECDMDL

changes and submit the changes to the Contracting Officer for acceptance.

3.5 SUBMITTALS AND DELIVERABLES

Submittals, if needed, shall comply with the requirements in Section 01 33 00 SUBMITTAL PROCEDURES. The CQC organization is responsible for certifying that all submittals and deliverables are in compliance with the contract requirements.

3.6 CONTROL

Contractor Quality Control (CQC) is the means by which the Contractor ensures that the construction, to include that of subcontractors and suppliers, complies with the requirements of the contract. At least three phases of control are required to be conducted by the CQC System Manager for each definable feature of the construction work as follows:

3.6.1 Preparatory Phase

This phase is performed prior to beginning work on each definable feature of work, after all required plans/documents/materials are approved/accepted, and after copies are at the work site. This phase includes:

a. A review of each paragraph of applicable specifications, reference codes, and standards. Make available during the preparatory inspection a copy of those sections of referenced codes and standards applicable to that portion of the work to be accomplished in the field. Maintain and make available in the field for use by Government personnel until final acceptance of the work.

b. Review of the contract drawings.

c. Check to assure that all materials and/or equipment have been tested, submitted, and approved.

d. Review of provisions that have been made to provide required control inspection and testing.

e. Examination of the work area to assure that all required preliminary work has been completed and is in compliance with the contract.

f. Examination of required materials, equipment, and sample work to assure that they are on hand, conform to approved shop drawings or submitted data, and are properly stored.

g. Review of the appropriate activity hazard analysis to assure safety requirements are met.

h. Discussion of procedures for controlling quality of the work including repetitive deficiencies. Document construction tolerances and workmanship standards for that feature of work.

i. Check to ensure that the portion of the plan for the work to be performed has been accepted by the Contracting Officer.

j. Discussion of the initial control phase.

k. The Government must be notified at least 24 hours in advance of beginning the preparatory control phase. Include a meeting conducted

SECTION 01 45 00.00 10 Page 5

Stator Repair and Rewedge Beaver Powerhouse Beaver Lake, White River by the CQC System Manager and attended by the superintendent, other CQC personnel (as applicable), and the foreman responsible for the definable feature. Document the results of the preparatory phase actions by separate minutes prepared by the CQC System Manager and attach to the daily CQC report. Instruct applicable workers as to the acceptable level of workmanship required in order to meet contract specifications.

3.6.2 Initial Phase

This phase is accomplished at the beginning of a definable feature of work. Accomplish the following:

a. Check work to ensure that it is in full compliance with contract requirements. Review minutes of the preparatory meeting.

b. Verify adequacy of controls to ensure full contract compliance.

Verify required control inspection and testing are in conpliance with the contract.

c. Establish level of workmanship and verify that it meets minimum acceptable workmanship standards. Compare with required sample panels as appropriate.

d. Resolve all differences.

e. Check safety to include compliance with and upgrading of the safety plan and activity hazard analysis. Review the activity analysis with each worker.

f. The Government need to be notified at least 24 hours in advance of beginning the initial phase for definable feature of work. Prepare separate minutes of this phase by the CQC System Manager and attach to the daily CQC report. Indicate the exact location of initial phase for definable feature of work for future reference and comparison with follow-up phases.

g. The initial phase for each definable feature of work is repeated for each new crew to work onsite, or any time acceptable specified quality standards are not being met.

3.6.3 Follow-up Phase

Perform daily checks to assure control activities, including control testing, are providing continued compliance with contract requirements, until completion of the particular feature of work. Record the checks in the CQC documentation. Conduct final follow-up checks and correct all deficiencies prior to the start of additional features of work which may be affected by the deficient work. Do not build upon nor conceal non-conforming work.

3.6.4 Additional Preparatory and Initial Phases

Conduct additional preparatory and initial phases on the same definable features of work if: the quality of on-going work is unacceptable; if there are changes in the applicable CQC staff, onsite production supervision or work crew; if work on a definable feature is resumed after a substantial period of inactivity; or if other problems develop.

SECTION 01 45 00.00 10 Page 6

Stator Repair and Rewedge Beaver Powerhouse Beaver Lake, White River

3.7 TESTS

3.7.1 Testing Procedure

Perform specified or required tests to verify that control measures are…