Performance Work Statement
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A.07.23_Amendment_0001_RFQ_W9127S18Q0012.pdf | ||
| A.07.23_Amendment_0002_RFQ_W9127S18Q0012.pdf | ||
| A.07.23_RFP_W9127S18Q0012.pdf | ||
| A.04.36_Wage_Rates.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. ARMY CORPS OF ENGINEERS| 4305 CHARLES WOODEN ROAD PINE BLUFF, ARKANSAS 71601
GENERAL MAINTENANCE
US ARMY COPRS OF ENGINEERS
LITTLE ROCK DISTRICT
PINE BLUFF SITE OFFICE
Table of Contents
PART 1 - GENERAL INFORMATION
1. GENERAL:
1.1 Description of Services/Introduction:
1.2 Background:
1.3 Objectives:
1.4 Scope:
1.5 Period of Performance:
1.6 General Information
1.6.1 Quality Control (QC):
1.6.2 Quality Control Manager:
1.6.3 Quality Assurance:
1.6.4 Recognized Holidays:
1.6.5 Hours of Operation:
1.6.6 Schedule of Work:
1.6.7 Place of Performance:
1.6.8 Type of Contract: IDIQ
1.6.9 Security Requirements:
1.6.10 Post Award Conference/Periodic Progress Meetings:
1.6.11 Contracting Officer Representative (COR):
1.6.12 Special Qualifications:
1.6.13 Key Personnel:
1.6.14 Daily Communication:
1.6.15 Identification of Contractor Employees:
1.6.16 Conduct:
1.6.17 Removal of Contractor's Employees:
1.6.18 Organizational Conflict of Interest:
1.6.19 Environment and OSHA:
1.6.20 Safety Requirements:
1.6.21 Payment:
1.6.22 Lost and Found:
1.6.23 Contractor Recommendations:
1.6.24 Changes to Frequencies or Quantities:
1.6.25 Required Insurance:
1.6.26 CONTRACTOR MANAGEMENT REPORTING (CMR): Not required
1.6.27 Permits and Licenses:
1.6.28 Other Contracts:
1.6.29 Title 36- Rules and Regulations:
1.6.30 Contractor Travel: Not Applicable
1.6.31 Other Direct Costs: Not Applicable
1.6.32 Data Rights: Not Applicable
1.6.33 PHASE IN /PHASE OUT PERIOD: Not Applicable
1.6.34 Required Performance Capability:
1.6.35 Delivery Order:
1.6.36 Work Order:
1.6.37 Normal Service Call:
1.6.38 Disposal of Debris:
1.6.39 Excavation:
1.6.40 Compaction Effort:
1.6.41 Seeding and Mulch:
1.6.42 Dressing of Work Areas:
1.6.43 Back-fill Material:
1.6.44 Excavation Inspections:
1.6.45 Rock Excavation:
1.6.46 Utility Line Bedding Material:
1.6.47 Marking Tape:
1.6.48 Stone Material:
1.6.49 Contractor Furnished Stone:
1.6.50 Stone Tests:
1.6.51 Weight and Absorption:
1.6.52 Soundness (Freezing-Thaw Resistance):
1.6.53 Resistance to Disintegration by Saturated Solutions of Sodium Sulfate or Magnesium Sulfate:
1.6.54 Fill Material:
1.6.55 Materials:
1.6.56 Completion Time:
1.6.57 Warranty Information:
1.6.58 Testing:
1.6.59 Work In Turf and Other Areas:
1.6.60 Contract Labor Requirements:
PART 2 - DEFINITIONS & ACRONYMS
2. DEFINITIONS AND ACRONYMS:
2.1. DEFINITIONS:
2.2. ACRONYMS:
PART 3 - GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND SERVICES
3. GOVERNMENT FURNISHED ITEMS AND SERVICES:
PART 4 - CONTRACTOR FURNISHED ITEMS AND SERVICES
4. CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES:
PART 5 - SPECIFIC TASKS
5. Specific Tasks:
5.1 Basic Services:
5.2 General Maintenance Services:
5.2.1 Service Calls:
5.2.2 Unscheduled Labor Hours:
5.2.3 Materials Costs:
5.2.4 Replace/Install Fire Ring/Grill:
5.2.5 Replace/Install Pedestal BBQ Grill:
5.2.6 Top Soil: (Contractor Purchased/Delivered/Spread)
5.2.7 Fill Material: (Contractor Purchased/Delivered/Spread)
5.2.8 Screening Material: (Contractor Purchased/Delivered/Spread)
5.2.9 Aggregate Base Material: (Contractor Purchased/Delivered/Spread)
5.2.10 Sand: (Contractor Purchased/Delivered/Spread)
5.2.11 Quarry Run Stone: (Contractor Purchased/Delivered/Spread)
5.2.12 B-Stone: (Contractor Purchased/Delivered/Spread)
5.2.13 Four and Six Inch Thick Concrete Slab: All materials shall be furnished by the contractor
5.2.14 Replace/Install Aluminum Picnic Table:
5.2.15 Replace/Install Concrete Wheel Stop:
5.2.16 Debris Removal:
5.2.17 General Painting:
5.2.17.9 Payment For Painting by the Square Foot:
5.2.18 Metal Roofing Installation:
5.2.18 Conventional (Shingle) Roofing Repair/Replace:
5.2.20 General Carpentry for Roofing:
5.2.21 Payment for Roofing:
5.2.22 Civil Engineering Services:
5.3 Electrical Maintenance Services:
5.3.1 Service Calls:
5.3.2 Unscheduled Labor Hours:
5.3.3 Materials Costs:
5.3.4 Replace/Repair RV Electric Pedestal (30 AMP or 50 AMP):
5.3.5 Park Preseason Electric Check:
5.3.6 Repair/Replace Buried Electrical Lines:
5.3.7 Repair/Replace Buried Electrical Lines for Utility Company:
5.3.8 Replace/Install Electric Riser/Rack:
5.3.9 Replace/Install Electric Panelboard:
5.3.10 Replace/Install Electric Wireway:
5.3.11 Replace/Install Electric Safety Disconnect:
5.3.12 Replace/Install Electric Meter Base:
5.3.13 Utility Road Crossing:
5.4 Plumbing Maintenance Services:
5.4.1 Service Calls:
5.4.2 Unscheduled Labor Hours:
5.4.3 Materials Costs:
5.4.4 Repair Underground Water Leak:
5.4.5 Water Hydrant Maintenance:
5.4.6 Replace/Install Underground Water Line PVC ¾” to 2” Pipe:
5.4.7 Replace/Install Underground Water Line PVC over 2” to 4” Pipe:
5.4.8 Replace/Install Underground Sewer Line PVC 2” to 4” Pipe:
5.4.9 Replace/Install Freezeless Water Hydrant:
5.4.10 Replace/Install Sewer Lift Station Pump:
5.4.11 Inspect Reduced Pressure Zone Assemblies:
PART 6 - APPLICABLE PUBLICATIONS
6. APPLICABLE PUBLICATIONS (CURRENT EDITIONS)
PART 7 - ATTACHMENT/TECHNICAL EXHIBIT LISTING
7.1 TECHNICAL EXHIBIT 1
7.2 TECHNICAL EXHIBIT 2
7.3 TECHNICAL EXHIBIT 3
7.4 TECHNICAL EXHIBIT 4
7.5 TECHNICAL EXHIBIT 5
7.6 TECHNICAL EXHIBIT 6
7.6 TECHNICAL EXHIBIT 7
7.8 TECHNICAL EXHIBIT 8
7.9 TECHNICAL EXHIBIT 9
7.10 TECHNICAL EXHIBIT 10
7.11 TECHNICAL EXHIBIT 11
7.12 TECHNICAL EXHIBIT 12
7.13 TECHNICAL EXHIBIT 13
7.14 TECHNICAL EXHIBIT 14
7.15 TECHNICAL EXHIBIT 15
7.16 TECHNICAL EXHIBIT 16
7.17 TECHNICAL EXHIBIT 17
7.18 TECHNICAL EXHIBIT 18
7.19 TECHNICAL EXHIBIT 19
7.20 TECHNICAL EXHIBIT 20
7.21 TECHNICAL EXHIBIT 21 ................................................................. Error! Bookmark not defined.
7.22 TECHNICAL EXHIBIT 22
7.23 TECHNICAL EXHIBIT 23
7.24TECHNICAL EXHIBIT 24
7.25 TECHNICAL EXHIBIT 25
7.26 TECHNICAL EXHIBIT 26
7.27TECHNICAL EXHIBIT 27
7.28TECHNICAL EXHIBIT 28
7.29TECHNICAL EXHIBIT 29
7.30TECHNICAL EXHIBIT 30
7.31TECHNICAL EXHIBIT 31
7.32TECHNICAL EXHIBIT 32
7.33TECHNICAL EXHIBIT 33
7.34TECHNICAL EXHIBIT 34
7.35TECHNICAL EXHIBIT 35
7.36TECHNICAL EXHIBIT 36
7.37TECHNICAL EXHIBIT 37
7.38TECHNICAL EXHIBIT 38
7.39TECHNICAL EXHIBIT 39
PERFORMANCE WORK STATEMENT (PWS)
GENERAL MAINTENANCE, ELECTRICAL MAINTENANCE, PLUMBING MAINTENANCE
PINE BLUFF SITE OFFICE
PART 1 - GENERAL INFORMATION
1. GENERAL:
This is a non-personnel services contract to provide general maintenance, electrical maintenance, and plumbing maintenance services. The Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.
1.1 Description of Services/Introduction:
The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform general maintenance, electrical maintenance, and plumbing maintenance services as defined in this Performance Work Statement except for those items specified as Government furnished property and services. The Contractor shall perform to the standards in this contract.
1.2 Background:
The Pine Bluff Site Office is located in Pine Bluff, Arkansas and has authority over facilities on the McClellan-Kerr Arkansas River Navigation System from navigation mile 0.0 in Desha County, Arkansas, at the mouth of the White River to navigation mile 125.0 just downstream of Murray Lock and Dam in Little Rock, Arkansas. The McClellan Kerr Arkansas River Navigation System (MKARNS) is a multipurpose system. It was developed and is maintained for navigation, power generation, environmental stewardship, recreational and water supply purposes.
1.3 Objectives:
Perform general maintenance, electrical maintenance, and plumbing maintenance services in a satisfactorily and timely manner according to the performance work statement.
1.4 Scope:
The intent of this contract is to provide general maintenance, electrical maintenance, and plumbing maintenance services at Pine Bluff Site Office facilities. Services include but not limited to general maintenance, performing electrical and plumbing repairs and installation. The Contractor shall furnish all necessary management, supervision, inspection, personnel, materials, supplies, parts, tools, equipment, transportation, and vehicles, except as otherwise provided for herein, necessary to assure that all services are performed in accordance with the contract specifications, drawings, attachments, exhibits, and all applicable laws, regulations, codes, or directives. The Contractor shall accomplish work in a timely and satisfactorily manner.
1.5 Period of Performance:
The period of performance shall be for one (1) Base Year of approximately 12 months and two (2) 12-month option years. The Period of Performance reads as follows:
Base Year – February 1, 2018 or date of award whichever is later through January 31, 2019 Option Year I – February 1, 2019 through January 31, 2020 Option Year II – February 1, 2020 through January 31, 2021
1.6 General Information
1.6.1 Quality Control (QC):
In order to assure that the desired level of performance of a service is achieved, the contractor shall establish and implement a quality control plan to ensure contract compliance, establish procedures for inspection and monitor and control the quality of the service. The QC Plan shall include the identification of all contractor personnel, organizational structure, lines of authority and services to be performed. Contractor shall provide a Daily Quality Control Inspection schedule to the Government Representative to determine if services meet the contract requirements and specifications. It is the contractor’s responsibility to correct deficiencies and check the consistency of quality throughout each service, and the plan shall outline whatever actions the contractor deems necessary to provide contract standards for quality control throughout all areas of responsibility. The Quality Control Plan shall be submitted to the COR at the Pine Bluff Site Office. An electronic copy of the plan must be submitted and accepted within 2 weeks of award of the contract. Revisions of the QCP shall be submitted to the COR within 5 working days when changes are made thereafter. After acceptance of the quality control plan the contractor shall receive the COR’s acceptance in writing of any proposed change to his QC system.
1.6.1.1 Contractor Quality Control Plan (CQCP):
The contractor shall assume full responsibility for the quality of all services performed under this contract. The contractors’ quality control plan shall provide an effective level of quality control to ensure that all services are performed in accordance with the specifications and requirements, instructions, provisions, drawings and maps herein, of this contract. The contractor shall establish and implement procedures to identify, prevent, and ensure non-recurrence of defective services.
1.6.1.1.1 CQCP Contents:
Contractors Quality Control Plan shall include, as a minimum, the following items:
1. Contractor organizational structure
2. Contractor personnel and qualifications
3. Work schedule
4. Submittals schedule
5. Inspection requirements and schedule
6. Contractors Quality Control Procedures
7. Documentation of quality control activities
8. Requirements for corrective action when quality control and/or acceptance criteria are not met.
1.6.1.1.2 QC Inspection System:
An inspection system covering all the services listed on the Performance Requirements Summary, must specify the areas to be inspected on either a scheduled or unscheduled basis, how often inspections will be accomplished, and the name and title of the individual(s) who will perform the inspection. It must specify the methods and procedures for identifying and preventing a cleanup service deficiency before the level of performance has become unacceptable.
1.6.1.1.3 Daily Quality Control Inspections/Reports:
Daily QC inspections shall be conducted by the contractor and corrective action(s) shall be taken to address noted deficiencies observed by QC. A record of all daily inspections conducted by the contractor and necessary corrective action taken shall be prepared. Daily reports shall detail the inspection methods and procedures that were utilized to assure that all required services produced an end product that complies with the Specifications and requirements of the contract.
The contractor shall establish a Daily Quality Control Inspection schedule, listing parks/services to be inspected, routes, times, and the person’s name performing the service. The contractor shall provide to the COR a written daily quality control inspection report for each daily service performed. All reports shall be completed daily and submitted on a weekly basis by email, no later than 02:00PM on Friday, to the Pine Bluff Site Office.
The written quality control reports shall contain the following items as a minimum:
a. Contractor's name.
b. Service date, starting time and ending time.
c. Contract, Delivery Order, and Work Order numbers.
d. Statement and description of services performed.
e. Location of services performed.
f. Description of services not performed and reasons for non-performance.
g. Certification Statement that all services performed was in accordance with the specifications.
h. Accidents/damages to Government property.
i. Man-hours worked on Government property.
j. Signature of the contractor's quality control representative.
1.6.2 Quality Control Manager:
The contractor shall designate in writing a quality control manager with full knowledge of the contract specifications/standards, this individual is required to have a copy of the contract in their possession at all times for referral concerning questions of contractor’s responsibility. The contractors’ quality control manager shall be present and available whenever work is being performed, and shall have full authority and power to act for the contractor on items pertaining to overall work performance, management, coordination, and supervision to assure that job performance in each category meets the contract specifications and requirements. The quality control manager may be a working member of a crew performing any of the scheduled services to be inspected. Designated individual(s) will be the primary point of contact with the Government Representative for the performance of services and is responsible for communicating all completed services, delays, failures, and remedies in timely manner to avoid an inspection failure that could result in a deduction of payment for that service.
1.6.3 Quality Assurance:
The Government shall evaluate the Contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan. This plan is primarily focused on what the Government must do to ensure that the Contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the maximum acceptable defect rate(s).
1.6.3.1. The contractor’s work will be inspected within 2 days of the time for completing the work as identified in the contractor’s schedule. If the work has not been performed, or has not been performed satisfactorily, the inspector will notify the contractor of that fact within one working day of the inspection. Work may be performed or re-performed within 2 working days of notice of nonperformance or unsatisfactory performance. If the contractor fails to perform or to re-perform work within 2 working days of notice of nonperformance or unsatisfactory performance, the contractor has failed to promptly perform the services again, and the defects cannot be corrected by re-performance. Deductions will be made for nonperformance or failure to re-perform.
1.6.4 Recognized Holidays:
The Contractor is not required to perform services on holidays, except for in emergency situations or when approved in advance by the COR.
New Year’s Day Labor Day Martin Luther King Jr.’s Birthday Columbus Day President’s Day Veteran’s Day Memorial Day Thanksgiving Day Independence Day Christmas Day
1.6.5 Hours of Operation:
The Contractor is responsible for conducting business, between the hours of 7:00 a.m. and 5:00 p.m. Monday thru Friday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. Work shall not be performed on Saturdays, Sundays, Federal Holidays, or the day preceding Federal Holidays, except as approved in advance by the COR. For other than firm fixed price contracts, the Contractor will not be reimbursed when the Government facility is closed for the above reasons. The Contractor must at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential.
1.6.6 Schedule of Work:
The contractor shall submit and obtain approval of required documentation as identified in Technical Exhibit 2 prior to commencing work. The Contractor shall commence work to provide services on the date specified on the written order or within the required start time after receipt of telephone order in emergency situations. Work Order will indicate areas where services are required. Work shall be completed within the time limits stated on the delivery order, work order, or agreed upon schedule unless previously authorized by the COR. In case of inclement weather, additional work days may be allowed.
1.6.6.1 The Contractor shall develop a work schedule identifying all contract work and locations.
The Contractor shall submit the work schedules to the COR for review and approval prior to beginning work. The Contractor’s schedule shall include all items of work required by the delivery order or work order. It shall set forth the item of work, locations, and the time/date of beginning and completion. The work schedule shall not be changed without the written approval of the
COR.
1.6.6.2 When the Contractor cannot complete services due to construction debris or Government interference, the Contractor shall perform services within reasonable distance of obstruction and report in writing to the COR the reason for failure to complete the service within 24 hours (verbal notification should be made within 4 hours). The report shall identify type of interference, location and date of interference.
1.6.6.3 Work delays due to federal holidays, inclement weather, and/or other causes beyond the Contractor’s control will not constitute any requirement not being completed as specified herein.
When the Contractor experiences delays due to circumstances beyond his control, the Government may allow the Contractor to work additional hours beyond normal duty hours (7:00 a.m. to 5:00 p.m., Monday through Friday) and on non-scheduled days, i.e. federal holidays, and weekends, with prior approval from the COR on a case by case basis. In the event that weather or other conditions, over which the Contractor has no control, prevent the Contractor from completing an item of work as required by these specifications, the Contractor shall notify the COR of such conditions as soon as they arise. The Contractor may request a weather time extension.
1.6.7 Place of Performance:
The work to be performed under this contract will be performed at all parks and property under the responsibility of the Pine Bluff Site Office.
1.6.8 Type of Contract: IDIQ
The Government will award an Indefinite Delivery Indefinite Quantity Contract. This contract type provides a not to exceed (NTE) estimate of the work required to be performed over the contract period. The actual quantities of services ordered under this contract may be significantly less or possibly more, with contract modification, than the contract quantity. Estimated quantities and/or the work to be performed are described herein as Contract Line Items (CLINS) and/or listed on separate sheets as Bid Schedules. These quantities are approximate and are provided only for the Contractor's information to assist in preparation of bids. They are not guaranteed and the actual quantities may be less or more than shown. Variations in these estimated quantities shall not be justification for a request for additional payment.
1.6.9 Security Requirements
This is a Security Level One, Table A Contract.
1. General Overview
a. The security provisions of this contract and/or applicable task order apply to all Contractor and Subcontractor Employees (CSEs) physically working on federally controlled property or requiring access to a Department of Defense (DoD) network.
b. Prime Contractors (PCs) are responsible for subcontractor compliance with the security provisions of this contract and shall coordinate all security requirements on the behalf of the subcontractors and their employees.
c. PCs will notify the Southwestern Little Rock District Security Office (SWL-DSO) within 5 business days of the contract award of the primary and alternate security Points of Contacts (POC) for this contract. This notification will be in the form of an email sent to m4xslceswlcontracts@usace.army.mil with the following information for each individual:
Full Name:
Email Address:
Work Phone:
Work Cell:
Time Zone of their work location:
NOTE: Only primary and alternate security POCs are authorized to contact the SWL-DSO to inquire about a contract employee.
d. PCs security POCs shall submit the appropriate security investigation package for EACH CSE based on the Security Level listed above.
e. The SWL-DSO reserves the right to upgrade the security level background check/investigation requirement of any contract and/or applicable task order; this includes upgrading the investigation standards for specific CSEs. If required, badges will be issued to all clearedi personnel and are to be worn at all times while working on U.S. Army Corps of Engineers (USACE) property. Any CSE working on USACE property without the proper identification badge will be escorted off site.
NOTE: Proposed foreign contractors seeking to work on a USACE contract must be cleared through the Department of State prior to having site access. To obtain approval, each individual must complete and submit the appropriate documents for processing. The required procedure takes approximately 45 business days to process once all documentation is completed properly and submitted.
2. Security Investigation Package Requirements for each CSE.
a. Security Level One Requirements (processing time is approximately five business days)
(1) SWL form 487 dated 2016, Contractor Required Information Form.
(2) A copy of the CSE’s driver’s license or government issued identification card.
(3) A copy of the CSE’s proof of citizenship document or proof of authorization to work in the United States. Acceptable documents are:
(a) U.S. Birth Certificate
(b) U.S. Passport
(c) U.S. Certificate of Citizenship-INS
(d) U.S. Certification of Naturalization
(e) FS-545, Certificate of Birth Abroad
(f) U.S. Certificate of Report of Birth
(g) U.S. Consular Report of Birth Abroad
(h) Workers visa
(i) Permanent Resident card
(4) One (1) digital passport-styled photo to be used for the USACE badge. Photos will be transmitted to the Security Office by means of CD or Email m4xslceswlcontracts@usace.army.mil. Each digital photo shall be stored in a file labeled by the name of the CSE. If transmitted through email, the subject line of the email must be the name of individual pictured. Photo requirements are as follows:
(a) In color.
(b) Taken within the last six months to reflect your current appearance.
(c) Taken in front a plain white or off-white background.
(d) Taken in full face viewed directly facing the camera.
(e) Taken with a neutral expression (preferred) or a natural smile, and with both eyes open.
(f) No hats or sunglasses are authorized in this photo; face must be clearly displayed with no distracters
(5) PCs must ensure each CSE is prescreened using the E-Verify program to meet the established employment eligibility requirements. The PC must ensure that the applicant has two valid forms of government issued identification, in order to ensure the correct information is entered in to the E-verify system. The CSE will provide the SWL-DSO with a list of verified employees to include their registration number from E-Verify. This list will be transmitted or mailed in the package along with the other required documents for CSEs. The E-Verify system can be located at the following URL (http://www.dhs.gov/e-verify).
(6) PCs must train each CSE on the iWatch/core watch suspicious activity reporting requirements (see paragraph 5).
b. Security Level Two Requirements (processing time is approximately 6 months once all documents are submitted electronically and accepted by the Personnel Security Investigation–Center of Excellence (PSI-COE) via the Personnel Security Investigation Portal (PSIP). Work Authorization/Site Access shall be denied until this background investigation is completed and favorably adjudicated. Automatic disqualifying factors that apply to all contractors being vetted at this level can be found in Table A.
(1) All requirements of the Security Level One package apply.
(2) Optional Form (OF) 306, Declaration for Federal Employment. This form shall be affixed with original date and signature; signature must be hand written-electronic signatures will not be accepted. The OF-306 can be found at the following web site:
http://www.opm.gov/forms/pdf_fill/of306.pdf.
(3) Fingerprint: Must be captured on an FD-258 electronically at an approved government site or manually (hard-copy) by a law enforcement or designated government security official.
(a) Hard-copy fingerprint submission can be captured by a law enforcement official local to the individual. CSE’s shall ensure that fingerprints are captured on a true/original FD-258 fingerprint card. No other form will be accepted. Card may be mailed through USPS to: U.S. Army Corps of Engineers, P.O. Box 867, Attn: Security, Little Rock, AR 72201. Use of the commercial delivery service such as Federal Express or UPS shall use following address: US Army Corps of Engineers, Attn: Security Office, Suite 6116, Little Rock, AR, 72201.
(b) CSEs can request to be fingerprinted electronically at the SWL-DSO. If this option is chosen, the individual must contact the SWL-DSO to schedule an appointment. Electronic fingerprinting is the quickest way to receive the results.
(c) CSE will have a background investigation requested by the SWL-DSO. The
CSE will receive an email from PSI-COE with a link to complete the SF 85 online through e-QIP. It is the CSE’s responsibility to read each email thoroughly and complete all tasks given by PSI-COE to ensure the investigation will not be terminated. The CSE will receive an information email stating no further documentation or revisions are required. See Standard Form (SF) 85 for required data input information at http://www.opm.gov/forms/pdf_fill/sf85.pdf. This is to be used as a guide (only) when completing the online equivalent and submitting direct to OPM.
c. Security Level Three Requirements (processing time is approximately 9 months once all documents are submitted electronically and accepted by the Personnel Security Investigation – Center of Excellence (PSI-COE) via the Personnel Security Investigation Portal (PSIP). Work Authorization/Site Access shall be denied until this background investigation is complete and favorably adjudicated. Automatic disqualifying factors that apply to all contractors being vetted at this level can be found in Table A.
(1) All requirements of the Security Level One and Two packages apply except the SF 85 is replaced with the SF 86. See Standard Form (SF) 86 for required data input information at http://www.opm.gov/forms/pdf_fill/sf86.pdf.
d. Multi-Level Security Requirement. (Processing time varies) This level requires the use of “escorts”, which shall be provided by the contractor. Escorts are contractor employees who have met Security Level Two requirements (this takes approximately 6 months once all documents are submitted. Refer to section 2-b.) Escorts will be provided at a 5:1 ratio, this means for every five contractor employees there will be one approved escort that is to remain within close proximity to those they are escorting at all times. All employees that will not be designated as escorts shall meet Security Level One, Table A requirements (this takes approximately 5 business days. Refer to section 2-a.).
3. Personnel Security Investigation Package Transmission
Mailing Address:
USACE SWL
Attn: Security Office 700 West Capitol Ave (room 6116) P.O. Box 867 Little Rock, AR 72201
a. If mailed- the investigation package will be transmitted in a sealed envelope together with a transmittal letter attached to the outside of the envelope for each applicant with the following information:
(1) Contract Number and Title
(2) Contracting Officer’s representative name, office number, and cellular number
(3) CSE’s full name and contact information
(4) PC name, address, and telephone number
b. Investigation packages can be faxed to (501) 324-5471. Faxed packages must have coversheet with contract information. Documents that contain personally identifiable information (such as social security number) must have coversheet stating “Page contains PII follows”.
c. Email transmission- email packages to m4xslceswlcontracts@usace.army.mil Documents must be password protected if they contain personally identifiable information (such as social security number). Passwords to documents must be sent in separate email.
d. Investigation packages will be submitted to the SWL-DSO for processing and adjudication.
Incomplete forms, illegible forms, etc., will be returned for correction and/ or completion and can delay the CSE from beginning work. The SWL-DSO address can be found in paragraph 2.b (3) (a) above.
e. Any change in personnel (whether an addition or replacement) at any time throughout the duration of the contract, will require the new personnel or replacement personnel to be vetted and approved by the SWL-DSO, in accordance with the requirements contained herein, prior to being granted Work Authorization/Site Access to any USACE property.
4. Onsite Access Approval
The CSE is responsible for contacting either the COR or the SWL Security Office, prior to the first day of work, to receive a list of approved individuals to be onsite, and their badges for identification purposes while onsite. All individuals on USACE property are required to wear identification badge. CSEs must be aware that COR representatives, project office personnel, and/or Security Office personnel can and will conduct identification checks on all persons onsite at USACE property. Any person found onsite without proper identification will be escorted offsite.
5. IWATCH/ Corps Watch Suspicious Activity Reporting (AT/OPSEC Cover Sheet, pg. 2, Section G, 4)
a. Security is simply EVERYONE’s responsibility. We owe it to our organization, our families, and ourselves to constantly be vigilant about what goes on around us. Trust your instincts. We rely on our senses every day of our lives. If a behavior or activity makes you feel uncomfortable, report it. If it doesn’t look, sound, or smell right, report it. The simple rule is, “If you see something, say something!”
b. The contractor and all associated subcontractors will brief all employees on the local iWATCH, Corps Watch, or See Something, Say Something program (training standards provided by the requiring activity ATO-contained herein, below). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. The CSE will provide the SWL Security Office with a list of employees who have been provided this training. This list will be transmitted in the package along with the other required documents for employees.
c. If you see something suspicious, provided below is the type of information to report:
(1) What you witnessed (the suspicious activity) including the date, time, and location.
(2) Description of who was involved
(3) Gender of person(s) involved
(4) Height, build, hair/skin color, and approx. age of person(s) involved
(5) Language spoken (if known)
(6) Vehicle description/ license number (if known)
(7) Have you seen this activity before?
d. How to report:
(1) In an emergency- call 911
(2) Notify your immediate supervisor and COR
6. Disqualifying Factors
Background check/investigation disqualifying factors are included in Tables A and B of this document.
i The term cleared refers to an individual granted authority to work on U.S. Army Corps of Engineers Property. This authorization comes through the Little Rock District Security Office to the Contracting Officer’s Representative (COR).
Table A. Disqualifying Factors
CRIMINAL HISTORY/ CRIMINAL INFORMATION
CHARGED* OR CONVICTED
< 5 Yrs < 10 Yrs > 10 Yrs
Inability to verify claimed identity DENY DENY DENY Individual submitted fraudulent identity information
DENY DENY DENY
Active wants or warrants DENY DENY DENY Barred from any Federal installation or facility DENY DENY DENY Kidnapping, hostage taking, human trafficking, or human smuggling, or conspiracy or attempt to commit offense
DENY DENY DENY
Rape, forcible sodomy, or sexual assault, or conspiracy or attempt to commit offense
DENY DENY DENY
Any sexual offense involving a minor or child, including child molestation, or child pornography; or conspiracy or attempt to commit offense
DENY DENY DENY
Distribution of, or possession with intent to distribute a controlled substance, or conspiracy or attempt to commit offense
DENY DENY DENY
Armed Robbery or conspiracy or attempt to commit offense DENY DENY DENY Espionage, sabotage, treason, or terrorism (not terroristic threats); or conspiracy or attempt to commit offense
DENY DENY DENY
Criminal homicide, murder, manslaughter, or negligent homicide
DENY DENY DENY
Registered Sex Offender DENY DENY DENY Any felony conviction DENY DENY DENY Felony charge involving unlawful distribution, sale, use, possession, or manufacture of and explosive, explosive device, or firearm; or conspiracy or attempt to commit offense
DENY DENY DENY
Knowingly/willfully engaged in acts or activities to overthrow the U.S. Government by force in any jurisdiction or any country; or conspiracy or attempt to commit offense
DENY DENY DENY
Table A. Disqualifying Factors Continued
CRIMINAL HISTORY/ CRIMINAL INFORMATION
CHARGED* OR CONVICTED
<5 Yrs <10 Yrs >10 Yrs
Known/suspected terrorist or belongs to known/suspected terrorist organization
DENY DENY DENY
Mayhem, maiming DENY DENY DENY Child abuse involving serious bodily injury to a child or minor
DENY DENY DENY
Importation or manufacture of a controlled substance DENY DENY DENY Any type of arson DENY DENY ALLOW Any type of burglary or robbery DENY DENY ALLOW Any type of possession or distribution of stolen property DENY DENY ALLOW Any time of willful destruction of property DENY DENY ALLOW
Any type of threat or disruption to the public (terroristic threat, inciting a riot, etc.)
DENY DENY ALLOW
Any type of extortion, bribery, or fraud DENY DENY DENY Operation of a motor vehicle while intoxicated by alcohol or drugs in any jurisdiction (1 conviction)
ALLOW ALLOW ALLOW
5 or more offenses for any crime (excluding minor traffic violations)
DENY DENY DENY
2 or more offenses for any crime (excluding minor traffic violations)
DENY ALLOW ALLOW
Any type of assault or violent crime DENY DENY ALLOW Illegal possession or use of a controlled substance DENY ALLOW ALLOW
LEGEND/NOTES
DENY Individual(s) are not cleared to work on USACE property under any circumstance
* Individual must be completely finished through legal processes of being charged with a crime, and will be required to provide documentation
Table B. Disqualifying Factors
CRIMINAL HISTORY/ CRIMINAL INFORMATION
CHARGED* OR CONVICTED
< 5 Yrs < 10 Yrs > 10 Yrs
Inability to verify claimed identity DENY DENY DENY Individual submitted fraudulent identity information DENY DENY DENY Active wants or warrants DENY DENY DENY Barred from any Federal installation or facility DENY DENY DENY Kidnapping, hostage taking, human trafficking, or human smuggling, or conspiracy or attempt to commit offense
DENY DENY DENY
Rape, forcible sodomy, or sexual assault, or conspiracy or attempt to commit offense
DENY DENY DENY
Any sexual offense involving a minor or child, including child molestation, or child pornography; or conspiracy or attempt to commit offense
DENY DENY DENY
Distribution of, or possession with intent to distribute a controlled substance, or conspiracy or attempt to commit offense
DENY DENY DENY
Armed Robbery or conspiracy or attempt to commit offense DENY DENY DENY Espionage, sabotage, treason, or terrorism (not terroristic threats); or conspiracy or attempt to commit offense
DENY DENY DENY
Criminal homicide, murder, manslaughter, or negligent homicide
DENY DENY DENY
Registered Sex Offender DENY DENY DENY Felony conviction not specified individually in this document DENY DENY ALLOW Felony charge involving unlawful distribution, sale, use, possession, or manufacture of and explosive, explosive device, or firearm; or conspiracy or attempt to commit offense
DENY DENY DENY
Table B. Disqualifying Factors Continued Knowingly/willfully engaged in acts or activities to overthrow the U.S. Government by force in any jurisdiction or any country; or conspiracy or attempt to commit offense
DENY DENY DENY
Known/suspected terrorist or belongs to known/suspected terrorist organization
DENY DENY DENY
Mayhem, maiming DENY DENY DENY Child abuse involving serious bodily injury to a child or minor
DENY DENY DENY
Importation or manufacture of a controlled substance DENY DENY DENY Any type of arson DENY DENY ALLOW Any type of burglary or robbery DENY DENY ALLOW Any type of possession or distribution of stolen property DENY DENY ALLOW Any time of willful destruction of property DENY DENY ALLOW Any type of threat or disruption to the public (terroristic threat, inciting a riot, etc.)
DENY ALLOW ALLOW
Any type of extortion, bribery, or fraud DENY DENY ALLOW Operation of a motor vehicle while intoxicated by alcohol or drugs in any jurisdiction (1 conviction)
ALLOW ALLOW ALLOW
5 or more offenses for any crime (excluding minor traffic violations)
DENY DENY ALLOW
2 or more offenses for any crime (excluding minor traffic violations)
DENY ALLOW ALLOW
Any type of assault or violent crime DENY DENY ALLOW Illegal possession or use of a controlled substance DENY ALLOW ALLOW
LEGEND/NOTES
DENY Individual(s) are not cleared to work on USACE property under any circumstance
* Individual must be completely finished through legal processes of being charged with a crime, and will be required to provide documentation
1.6.9.2 Key Control:
The Contractor shall establish and implement methods of making sure all keys/key cards issued to the Contractor by the Government are not lost or misplaced and are not used by unauthorized persons. NOTE: All references to keys include key cards. No keys issued to the Contractor by the Government shall be duplicated. The Contractor shall develop procedures covering key control that shall be included in the Quality Control Plan. Such procedures shall include turn-in of any issued keys by personnel who no longer require access to locked areas. The Contractor shall immediately report any occurrences of lost or duplicate keys/key cards to the Contracting Officer.
1.6.9.2.1 In the event keys, other than master keys, are lost or duplicated, the Contractor shall, upon direction of the Contracting Officer, re-key or replace the affected lock or locks; however, the Government, at its option, may replace the affected lock or locks or perform re-keying. When the replacement of locks or re-keying is performed by the Government, the total cost of re-keying or the replacement of the lock or locks shall be deducted from the monthly payment due the Contractor. In the event a master key is lost or duplicated, all locks and keys for that system shall be replaced by the Government and the total cost deducted from the monthly payment due the Contractor.
1.6.9.2.2 The Contractor shall prohibit the use of Government issued keys/key cards by any persons other than the Contractor’s employees. The Contractor shall prohibit the opening of locked areas by Contractor employees to permit entrance of persons other than Contractor employees engaged in the performance of assigned work in those areas, or personnel authorized entrance by the Contracting Officer.
1.6.9.3 The Contractor shall take special care to protect Government Property including buildings, grounds, roads, and any other surfaces from materials not intended. Return areas damaged as a result of work under this contract to their original condition, to include painting, refinishing, or replacement, as necessary. The Contractor shall report all damages of Government property on the quality control program report. Contractor shall be liable for any and all damages or losses, public or private, caused through fault or negligence of his agents and/or employees.
1.6.10 Post Award Conference/Periodic Progress Meetings:
The Contractor agrees to attend any post award conference convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation Subpart 42.5.
The Contracting Officer, Contracting Officers Representative (COR), and other Government personnel, as appropriate, may meet periodically with the Contractor to review the Contractor's performance. At these meetings the Contracting Officer will apprise the Contractor of how the Government views the Contractor's performance and the Contractor will apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the Government.
1.6.11 Contracting Officer Representative (COR):
The COR will be identified by separate letter. The COR monitors all technical aspects of the contract and assists in contract administration The COR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract: perform inspections necessary in connection with contract performance: maintain written and oral communications with the Contractor concerning technical aspects of the contract: issue written interpretations of technical requirements, including Government drawings, designs, specifications:
monitor Contractor's performance and notifies both the Contracting Officer and Contractor of any deficiencies; coordinate availability of Government furnished property, and provide site entry of Contractor personnel. A letter of designation issued to the COR, a copy of which is sent to the Contractor, states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order.
1.6.12 Special Qualifications:
A copy of all licenses required by state and federal regulations shall be submitted to the COR within 2 weeks of award of the contract, and within 5 working days when changes are made thereafter. The following licenses are required to perform work under this contract but not limited to: electrician’s license to perform electrical work, plumber’s license to perform work on plumbing and sewer pumps, septic tank installer’s license to work on septic system components, and CDL to operate trucks as required by the State of Arkansas.
Only properly trained and qualified personnel shall be used in the performance of this contract, they shall have the education, experience or knowledge as evidenced by license, certificate, diploma, etc., to provide a comprehensive understanding of the systems, components, equipment, and facilities to be serviced, operated, maintained, repaired, renovated and constructed under this contract. All employees shall be subject to such Government regulations as are applicable during the time spent performing work under this contract. The contractor shall maintain a file containing the qualifications, certification, diplomas and/or licenses of all personnel (including subcontractor personnel). These files shall be submitted to the COR and will be used as part of the basis for determining the qualifications of personnel. In the event the Contractor does not have a qualified employee to perform the specific work, the Contractor will be required to immediately provide qualified personnel or to subcontract the work to a specialist familiar with the type of work to be accomplished.
1.6.13 Key Personnel:
The following personnel are considered key personnel by the Government: Contract Manager and Quality Control Inspector. The Contractor shall provide a contract manager who shall be responsible for the performance of the work. The name of this person and an alternate who shall act for the Contractor when the manager is absent shall be designated in writing to the Contracting Officer prior to commencing work. The Contract Manager or alternate shall have full authority to act for the Contractor on all contract matters relating to daily operation of this contract. The Contract Manager or alternate shall be available between 7:00 a.m. and 5:00 p.m., Monday thru Friday except for Federal holidays or when the Government facility is closed for administrative reasons. This individual may also serve as a Quality Control Inspector and can be a working member of a crew, provided that job performance in each category is maintained at an acceptable level to the COR. For the purpose of this contract, it is intended that these shall be administrative positions whose responsibility is to ensure compliance with contract specifications.
The Contract Manager and Quality Control Inspector shall be required to communicate, verbal and written, in English and have a copy of the contract in their possession at all times for referral concerning questions of Contractor responsibility. In addition, the Contractor shall designate a responsible employee to act as work leader, and to complete a daily activity report.
1.6.14 Daily Communication:
The Contractor must communicate daily with the designated Government representative assigned to this contract between the hours of 8:00 and 9:00 a.m. Monday through Friday, excluding Federal Holidays while work is being performed. Communications shall cover work accomplished, ongoing work and issuance of new work orders and/or delivery orders. Daily communication is extremely important and must be either by telephone or E-mail, although in person visits may be required in order to exchange or discuss paperwork associated with the performance of this contract.
1.6.15 Identification of Contractor Employees:
All contract personnel attending meetings, answering Government telephones, and working in other situations where their Contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression in the minds of members of the public that they are Government officials. They must also ensure that all documents or reports produced by Contractors are suitably marked as Contractor products or that Contractor participation is appropriately disclosed. The Contractor shall provide ball caps/hats or shirts with the company name or logo to be worn by all employees and subcontractors while working on public recreational areas.
1.6.16 Conduct:
All individuals involved in providing services under this contract shall not be under the influence of drugs or alcoholic beverages. The Contractor shall, at all times, be responsible for the conduct and discipline of his employees and all subcontractors and their employees. Contractor personnel shall present a neat appearance and shall conduct themselves in a proper manner at all times while in the performance of this contract. All individuals involved in providing services shall be dressed neatly and fully to include shoes, pants, and shirts with sleeves that shall be closed or buttoned. Personal Protective Equipment shall fully comply with the current edition of EM-385-1-1 at the time of award. Since a significant portion of the work will be performed in the presence of the public, the conduct of all employees and/or subcontractors is critical and will be closely monitored.
1.6.17 Removal of Contractor's Employees:
The Contracting Officer may require the Contractor to immediately remove from the work site any employee who endangers persons or property, or whose physical or mental condition would impair the employee's ability to satisfactorily perform the required work. Notification to the Contractor will be verbal and in writing if time and circumstances permit. Otherwise, notification shall be verbal or by telephone, and shall be in writing as soon as possible. No such removal, however, shall reduce the Contractor’s obligation to perform all work required under this contract, and immediate replacement shall be made as required. This requirement shall not be the basis of any claim for compensation or damages against the Government.
1.6.18 Organizational Conflict of Interest:
Contractor and subcontractor personnel performing work under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent Organizational Conflict of Interests (OCI) as defined in FAR Subpart 9.5. The Contractor shall notify the Contracting Officer immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the Contracting Officer to avoid or mitigate any such OCI.