A.02.01_Combined_Synopsis_Solicitation_17Q0007_(2).pdf
PDF 2 MB Posted
- Solicitation number
- W9127S-17-Q-0007
About this file
Combined Synopsis Solicitation W9127S-17-Q-0007 for Millwood Lake Maintenance IDIQ
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A.02.01_Solicitation_Amendment_1_17Q0007.pdf | ||
| A.02.01_Past_Performance_Questionnaire.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR QUOTATION COVER PAGE
US Army Corps of Engineer, Little Rock District Contracting Division
700 W. Capitol Avenue Room 7315 Little Rock, AR 72201
W9127S-17-Q-0007, Millwood Lake Maintenance IDIQ, Millwood Lake Project Office
Submitted by
Offeror Name:
Offeror Address:
Street
City/State
Offeror Email Address:
Cage Code:
DUNS Number:
TIN:
Telephone Number:
Signature:
Date:
This is a combined synopsis/solicitation for commercial items prepared in accordance with the format in Subpart 12.6 as supplemented with additional information in this notice. This announcement constitutes the only solicitation, quotes are being requested and a written solicitation will not be issued.
The solicitation number and a statement that the solicitation is issued as a request for quotation (RFQ)
The solicitation document and incorporated provisions and clauses are those in effect through Federal Acquisition Circular 2005-94.
Set Aside, NAICS Code & Size Standard: This solicitation is set-aside for Small Business. The NAICS Code 561210 and the applicable size standard is $38,500,000.00.
A list of contract line item number(s) and items, quantities and units of measure:
Please see attached quote schedule beginning on page ___4__.
Description of requirements for the items to be acquired: This requirement is to perform electrical, plumbing, carpentry and other maintenance services for the Corps of Engineers Millwood Lake Project Office, Arkansas, Area of Responsibility in accordance with the PWS.
Date(s) and place(s) of delivery/acceptance and FOB point:
Base Year CLINS 0001 through 0103 will be 15 July 2017 (or date of award whichever is later) through 14 July 2018.
Option Year 1 CLINS 1001 through 1103 will be15 July 2018 through 14 July 2019.
Option Year 2 CLINS 2001 through 2103 will be 15 July 2019 through 14 JUly 2020.
The place of performance will be the Corps of Engineers Millwood Lake Project Office, Arkansas, area of responsibility. (Millwood Lake Parks)
The provision at 52.212-1, Instructions to Offerors -- Commercial, applies to this acquisition and a statement regarding any addenda to the provision. Offerors are also required to submit a completed copy of the Request for Quotation cover page on page __1_, and a completed copy of the pricing schedule beginning on page __4___.
The provision at 52.212-2, Evaluation -- Commercial Items, Streamlined Evaluation procedures IAW FAR 12.602 shall be incorporated in this solicitation.
Award shall be made that is most advantageous to the Government based on the factors contained in the solicitation.
http://farsite.hill.af.mil/reghtml/regs/far2afmcfars/fardfars/far/52_000.htm#P1472_202066 http://farsite.hill.af.mil/reghtml/regs/far2afmcfars/fardfars/far/52_000.htm#P1533_213837
Offerors are required to include a completed copy of the provision at 52.212-3 Alt I, Offeror Representations and Certifications -- Commercial Items, with its quote.
The clause at 52.212-4, Contract Terms and Conditions -- Commercial Items, applies to this acquisition.
The clause at 52.212-5 (Deviation), Contract Terms and Conditions Required To Implement Statutes Or Executive Orders -- Commercial Items, applies to this acquisition. Please see the Clauses Incorporated By Reference section for additional FAR Clauses applicable to this acquisition.
A site visit is scheduled for:
Thursday 15 June 2017 at 08:00 A.M. CST at the USACE Millwood Lake Project Office, 1528 Hwy 32 East Ashdown, AR 71822
Contact Brandee Wright at 501-340-1466 for site visit questions.
Quotes are due on 29 June 2017 at 10:00 am CST. Email submission of quotations are preferred in pdf form, however FAX or Mail submissions are allowed.
Required Documents to Submit
1. Request for Quotation cover page (signed)
2. Completed (filled in) Provisions and Clauses as applicable
3. Signed Amendments (if applicable)
4. Factor 1 – 5 Submission Requirements (See Instructions To Offerors)
5. Completed Quote Schedule
FAX: 501-324-5137
EMAIL: vincent.j.tomasi@usace.army.mil
If sending by mail. Please submit your quotes to the following address:
US Army Corps of Engineers, Attn: Vincent Tomasi, 700 W. Capitol Avenue Room 7315, Little Rock, AR 72201
If you have any questions regarding this solicitation, please contact Vincent Tomasi at 501-340-1260 or submit an email to:
vincent.j.tomasi@usace.army.mil http://farsite.hill.af.mil/reghtml/regs/far2afmcfars/fardfars/far/52_000.htm#P1547_215689 http://farsite.hill.af.mil/reghtml/regs/far2afmcfars/fardfars/far/52_000.htm#P1845_256368 http://farsite.hill.af.mil/reghtml/regs/far2afmcfars/fardfars/far/52_000.htm#P2045_297176 mailto:vincent.j.tomasi@usace.army.mil mailto:vincent.j.tomasi@usace.army.mil
CLIN ESTIMATED
NUMBER DESCRIPTION QUANTITY U/M UNIT PRICE AMOUNT
SECTION A
CARPENTRY AND PAINTING
Furnish all necessary management, personnel, materials, supplies, parts, tools, equipment, etc., to provide maintenance services as described in Work Statement Technical Provisions for the period 15 July 2017 or date of award, whichever is later, Through 14 July 2018.
0001 Normal Service Call 30 EA
0002 Emergency Service Call 10 EA
0003 Emergency Debris Removal 50000 EA $1.00 $50,000.00
0004 Estimated Materials Costs 30000 EA $1.00 $30,000.00 for Service, Repair, and parts
CARPENTRY
0005 Remove/Replace Existing Timbers 1500 LF
0006 Remove/Replace Base Timbers 1500 LF
0007 Install Timbers 10000 LF
BASE YEAR
QUOTE SCHEDULE
Millwood Lake Maintenance IDIQ-Millwood Project Office Offeror must fill out all options to be considered.
0008 Install Base Timbers 1500 LF
0009 Handrails 2x4x16 Ground Contact 2000 LF
0010 Handrails 2x6x16 Ground Contact 1500 LF
0011 Handrails 4x4x10 Ground Contact Post 500 LF
0012 Handrails 4x4x16 Ground Contact Post 500 LF
0013 Replace/Install Pedestal Grills 30 EA
0014 Install Concrete Fire Pit 25 EA
0015 Replace/Install One Post Signs 40 EA
0016 Replace/Install Two Post Signs 40 EA
0017 Fill Material 5000 TN
0018 Sand Material 700 TN
0019 Screening Material 700 TN
0020 Aggregate Base Material 2000 TN
0021 Aggregate Base Material 3/4" 2000 TN
0022 Rip Rap Stone 6"-12" 2000 TN
0023 Rip Rap Stone 6" and smaller 2000 TN
0024 Replace Metal Entry Doors 10 EA
0025 Replace or Install Shower Bench 10 EA
0026 Replace/Install Utility Table Tops 25 EA
0027 Replace/Install 8 Foot Vinyl Coated Picnic Tables 25 EA
0028 Culvert Replacement – 6” to 12" 10 EA
0029 Culvert Replacement – 13” to 24" 10 EA
0030 Culvert Replacement – 25” to 36" 10 EA
0031 Culvert Replacement - 37" to 48" 10 EA
0032 Headwall 18-48" culverts 20 EA
0033 Concrete 300 CY
0034 Asphalt 2000 TN
0035 Metal Picnic Shelter Canopy 10 EA
0036 Chainlink Fencing 1000 LF
PAINTING
0037 Oil Base, Primer Coat – (4000 SF) 4000 SF
0038 Oil Base, Intermediate or Finish Coat 5000 SF
(5000 SF)
0039 Latex, Primer Coat, (6000 SF) 6000 SF
0040 Latex, Intermediate or Finish Coat 5000 SF
(5000 SF)
0041 Pavement Marking 9000 LF
TOTAL SECTION A BASE YEAR
SECTION B
ELECTRICAL
Furnish all necessary management, personnel, materials, supplies, parts, tools, equipment, etc., to provide maintenance services as described in Work Statement Technical Provisions for the period 15 July 2017 or date of award, whichever is later, Through 14 July 2018.
0042 Normal Service Calls 10 EA
0043 Emergency Service Calls 8 EA
0044 Estimated Material Costs 15000 EA $1.00 $15,000.00
0045 Replace or Install Camper Pedestal (50 amp) 50 EA
0046 Replace Security Light Bulb 40 EA
LED
0047 Replace Security Light Fixture 50 EA
LED
0048 Install/Replace Solar Lights 5 EA
0049 Trenching (Electrical Lines) 5000 LF
0050 Replace Underground Electrical 2000 LF Wiring 2/0 AWG (Up to 2000 LF
0051 Replace Underground Electrical 200 LF
Wiring - #4 AWG
0052 Replace Underground Electrical 200 LF Wiring - #6 AWG
TOTAL SECTION B BASE YEAR
CLIN ESTIMATED
NUMBER DESCRIPTION QUANTITY U/M UNIT PRICE AMOUNT
SECTION C
PLUMBING AND SEPTIC SYSTEM
MAINTENANCE
Furnish all necessary management, personnel, materials, supplies, parts, tools, equipment, etc., to provide maintenance services as described in Work Statement Technical Provisions for the period 15 July 2017 or date of award, whichever is later, Through 14 July 2018.
0053 Normal Service Call 25 EA
0054 Emergency Service Call 15 EA
0055 Estimated Material Costs 10000 EA $1.00 $10,000.00 for Service Call Repair Parts
0056 Trenching and Backfilling (Water Lines) 1500 LF
0057 Replace Sump Pump (10 HP submergible) 3 EA
0058 Replace Lift Station Pump 4 EA
0059 Replace or Install Underground Water Line - 5000 LF
PVC ¾” – 2”
0060 Replace Underground Water Line - 5000 LF PVC over 2” – 4” pipe
0061 Replace Water Heater 40 gal or less 8 EA
0062 Replace Water Heater 85 gallon 3 EA
0063 Replace Water Heater 120 gallon 1 EA
0064 Install Vermiculite (4 CF bag size) 150 Bags
0065 Replace or Install Hydrant Assembly to include 50 EA Valve Box, Riser & Cap, Hydrant,& Vermicelite
0066 Replace Trailer Dump Station Water Tower 4 EA
0067 Septic Tank Pump Out Service 60 EA
TOTAL SECTION C BASE YEAR
CLIN ESTIMATED
NUMBER DESCRIPTION QUANTITY U/M UNIT PRICE AMOUNT
SECTION D
CIVIL ENGINEERING SERVICES
Furnish all necessary management, personnel, materials, supplies, parts, tools, equipment, etc., to provide maintenance services as described in Work Statement Technical Provisions for the period 15 July 2017 or date of award, whichever is later, Through 14 July 2018.
0068 Brush Mulcher 60 HR
0069 Dump Truck, 10 cy 130 HR
0070 Backhoe 250 HR
0071 Tractor w/Blade 40 HR
0072 Skidsteer w/ Auger 25 HR
0073 Tractor w/Front Loader 80 HR
0074 Dozer Work 250 HR
0075 Trackhoe with 30ft boom 250 HR
0076 Road Grader 100 HR
0077 Mini Excavator 250 HR
0078 Bucket Truck 100 HR
0079 Concrete Saw 60 HR
0080 Side Boom Bushhog 200 HR
0081 Crane (up to 100 tons) 60 HR
0082 Compactor (Walk Behind) 120 HR
0083 Rubber Tire Loader 250 HR
TOTAL SECTION D BASE YEAR
SECTION E
TREE REMOVAL/ UNDERBRUSHING
Furnish all necessary management, personnel, materials, supplies, parts, tools, equipment, etc., to provide maintenance services as described in Work Statement Technical Provisions for the period 15 July 2017 or date of award, whichever is later, Through 14 July 2018.
0084 Tree Removal – 6” to 12” Pine 50 EA
0085 Tree Removal – 13” to 20” Pine 50 EA
0086 Tree Removal – 21” to 26” Pine 50 EA
0087 Tree Removal – 27” & Above Pine 50 EA
0088 Tree Removal – 6” to 12” Hardwood 75 EA
0089 Tree Removal – 13’ to 16” Hardwood 75 EA
0090 Tree Removal – 17” to 20’ Hardwood 75 EA
0091 Tree Removal – 21” to 26’ Hardwood 75 EA
0092 Tree Removal – 27” to 32’ Hardwood 60 EA
0093 Tree Removal – 33” and Above Hardwood 50 EA
0094 Stump Grinding 18" and under 400 EA
0095 Stump Grinding 19" and above 250 EA
0096 Underbrushing 80 Acres
TOTAL SECTION E BASE YEAR
NUMBER DESCRIPTION QUANTITY U/M UNIT PRICE AMOUNT
SECTION F
HERBICIDE
Furnish all necessary management, personnel, materials, supplies, parts, tools, equipment, etc., to provide maintenance services as described in Work Statement Technical Provisions for the period 15 July 2017 or date of award, whichever is later, Through 14 July 2018.
0097 Herbicide Application 400 Acres
TOTAL SECTION F BASE YEAR
CLIN DESCRIPTION ESTIMATED
NUMBER QUANTITY U/M UNIT PRICE AMOUNT
SECTION G
GABIONS
Furnish all necessary management, personnel, materials, supplies, parts, tools, equipment, etc., to provide maintenance services as described in Work Statement Technical Provisions for the period 15 July 2017 or date of award, whichever is later, 0098 Gabion Installation 750 CY
TOTAL SECTION G BASE YEAR
CLIN DESCRIPTION ESTIMATED
NUMBER QUANTITY U/M UNIT PRICE AMOUNT
SECTION H
BOUYS
Furnish all necessary management, personnel, materials, supplies, parts, tools, equipment, etc., to provide maintenance services as described in Work Statement Technical Provisions for the period 15 July 2017 or date of award, whichever is later, Through 14 July 2018.
0099 Bouy Installation/Removal 200 EA
0100 Estimated Material Cost 10000 EA $1.00 $10,000.00
TOTAL SECTION H BASE YEAR
CLIN DESCRIPTION ESTIMATED
NUMBER QUANTITY U/M UNIT PRICE AMOUNT
SECTION I
GENERATOR MAINTENANCE
Furnish all necessary management, personnel, materials, supplies, parts, tools, equipment, etc., to provide maintenance services as described in Work Statement Technical Provisions for the period 15 July 2017 or date of award, whichever is later, 0101 Yearly Maintenance 5000 $1.00 $5,000.00
0102 Emergency Service Call 5 EA
0103 Estimated Material Cost 12000 EA $1.00 $12,000.00
TOTAL SECTION I BASE YEAR
TOTAL PRICE BASE YEAR SECTION A-I
(CLINS 0001 - 0103)
CLIN ESTIMATED
NUMBER DESCRIPTION QUANTITY U/M UNIT PRICE AMOUNT
SECTION A –
CARPENTRY AND PAINTING
Furnish all necessary management, personnel, materials, supplies, parts, tools, equipment, etc., to provide maintenance services as described in Work Statement Technical Provisions for the period 15 July 2018 or date of award, whichever is later, Through 14 July 2019.
1001 Normal Service Call 30 EA
1002 Emergency Service Call 10 EA
1003 Emergency Debris Removal 50000 EA $1.00 $50,000.00
OPTION YEAR 1
1004 Estimated Materials Costs 30000 EA $1.00 $30,000.00 for Service, Repair, and parts
CARPENTRY
1005 Remove/Replace Existing Timbers 1500 LF
1006 Remove/Replace Base Timbers 1500 LF
1007 Install Timbers 10000 LF
1008 Install Base Timbers 1500 LF
1009 Handrails 2x4x16 Ground Contact 2000 LF
1010 Handrails 2x6x16 Ground Contact 1500 LF
1011 Handrails 4x4x10 Ground Contact Post 500 LF
1012 Handrails 4x4x16 Ground Contact Post 500 LF
1013 Replace/Install Pedestal Grills 30 EA
1014 Install Concrete Fire Pit 25 EA
1015 Replace/Install One Post Signs 40 EA
1016 Replace/Install Two Post Signs 40 EA
1017 Fill Material 5000 TN
1018 Sand Material 700 TN
1019 Screening Material 700 TN
1020 Aggregate Base Material 2000 TN
1021 Aggregate Base Material 3/4" 2000 TN
1022 Rip Rap Stone 12" and down 2000 TN
1023 Rip Rap Stone 6" and down 2000 TN
1024 Replace Metal Entry Doors 10 EA
1025 Replace or Install Shower Bench 10 EA
1026 Replace/Install Utility Table Tops 25 EA
1027 Replace/Install 8 Foot Vinyl Coated Picnic Tables 25 EA
1028 Culvert Replacement – 6” to 12" 10 EA
1029 Culvert Replacement – 13” to 24" 10 EA
1030 Culvert Replacement – 25” to 36" 10 EA
1031 Culvert Replacement - 37" to 48" 10 EA
1032 Headwall 18-48" culverts 20 EA
1033 Concrete 300 CY
1034 Asphalt 2000 TN
1035 Metal Picnic Shelter Canopy 10 EA
1036 Chainlink Fencing 1000 LF
PAINTING
1037 Oil Base, Primer Coat – (4000 SF) 4000 SF
1038 Oil Base, Intermediate or Finish Coat 5000 SF
(5000 SF)
1039 Latex, Primer Coat, (6000 SF) 6000 SF
1040 Latex, Intermediate or Finish Coat 5000 SF
(5000 SF)
1041 Pavement Marking 9000 LF
TOTAL SECTION A OPTION 1
CLIN ESTIMATED
NUMBER DESCRIPTION QUANTITY U/M UNIT PRICE AMOUNT
SECTION B
ELECTRICAL
Furnish all necessary management, personnel, materials, supplies, parts, tools, equipment, etc., to provide maintenance services as described in Work Statement Technical Provisions for the period 15 July 2018 or date of award, whichever is later, Through 14 July 2019.
1042 Normal Service Calls 10 EA
1043 Emergency Service Calls 8 EA
1044 Estimated Material Costs 15000 EA $1.00 $15,000.00
1045 Replace or Install Camper Pedestal (50 amp) 50 EA
1046 Replace Security Light Bulb 40 EA
LED
1047 Replace Security Light Fixture 50 EA
LED
1048 Install/Replace Solar Lights 5 EA
1049 Trenching (Electrical Lines) 5000 LF
1050 Replace Underground Electrical 2000 LF Wiring 2/0 AWG (Up to 2000 LF
1051 Replace Underground Electrical 200 LF Wiring - #4 AWG
1052 Replace Underground Electrical 200 LF Wiring - #6 AWG
TOTAL SECTION B OPTION 1
CLIN ESTIMATED
NUMBER DESCRIPTION QUANTITY U/M UNIT PRICE AMOUNT
SECTION C
PLUMBING AND SEPTIC SYSTEM
MAINTENANCE
Furnish all necessary management, personnel, materials, supplies, parts, tools, equipment, etc., to provide maintenance services as described in Work Statement Technical Provisions for the period 15 July 2018 or date of award, whichever is later, Through 14 July 2019.
1053 Normal Service Call 25 EA
1054 Emergency Service Call 15 EA
1055 Estimated Material Costs 10000 EA $1.00 $10,000.00 for Service Call Repair Parts
1056 Trenching and Backfilling (Water Lines) 1500 LF
1057 Replace Sump Pump (10 HP submergible) 3 EA
1058 Replace Lift Station Pump 4 EA
1059 Replace or Install Underground Water Line - 5000 LF
PVC ¾” – 2”
1060 Replace Underground Water Line - 5000 LF PVC over 2” – 4” pipe
1061 Replace Water Heater 40 gal or less 8 EA
1062 Replace Water Heater 85 gallon 3 EA
1063 Replace Water Heater 120 gallon 1 EA
1064 Install Vermiculite (4 CF bag size) 150 Bags
1065 Replace or Install Hydrant Assembly to include 50 EA Valve Box, Riser & Cap, Hydrant,& Vermicelite
1066 Replace Trailer Dump Station Water Tower 4 EA
1067 Septic Tank Pump Out Service 60 EA
TOTAL SECTION C OPTION 1
CLIN ESTIMATED
NUMBER DESCRIPTION QUANTITY U/M UNIT PRICE AMOUNT
SECTION D
CIVIL ENGINEERING SERVICES
Furnish all necessary management, personnel, materials, supplies, parts, tools, equipment, etc., to provide maintenance services as described in Work Statement Technical Provisions for the period 15 July 2018 or date of award, whichever is later, Through 14 July 2019.
1068 Brush Mulcher 60 HR
1069 Dump Truck, 10 cy 130 HR
1070 Backhoe 250 HR
1071 Tractor w/Blade 40 HR
1072 Skidsteer w/ Auger 25 HR
1073 Tractor w/Front Loader 80 HR
1074 Dozer Work 250 HR
1075 Trackhoe with 30ft boom 250 HR
1076 Road Grader 100 HR
1077 Mini Excavator 250 HR
1078 Bucket Truck 100 HR
1079 Concrete Saw 60 HR
1080 Side Boom Bushhog 200 HR
1081 Crane (up to 100 tons) 60 HR
1082 Compactor (Walk Behind) 120 HR
1083 Rubber Tire Loader 250 HR
TOTAL SECTION D OPTION 1
CLIN ESTIMATED
NUMBER DESCRIPTION QUANTITY U/M UNIT PRICE AMOUNT
SECTION E
TREE REMOVAL/ UNDERBRUSHING
Furnish all necessary management, personnel, materials, supplies, parts, tools, equipment, etc., to provide maintenance services as described in Work Statement Technical Provisions for the period 15 July 2018 or date of award, whichever is later, Through 14 July 2019.
1084 Tree Removal – 6” to 12” Pine 50 EA
1085 Tree Removal – 13” to 20” Pine 50 EA
1086 Tree Removal – 21” to 26” Pine 50 EA
1087 Tree Removal – 27” & Above Pine 50 EA
1088 Tree Removal – 6” to 12” Hardwood 75 EA
1089 Tree Removal – 13’ to 16” Hardwood 75 EA
1090 Tree Removal – 17” to 20’ Hardwood 75 EA
1091 Tree Removal – 21” to 26’ Hardwood 75 EA
1092 Tree Removal – 27” to 32’ Hardwood 60 EA
1093 Tree Removal – 33” and Above Hardwood 50 EA
1094 Stump Grinding 18" and under 400 EA
1095 Stump Grinding 19" and above 250 EA
1096 Underbrushing 80 Acres
TOTAL SECTION E OPTION 1
CLIN ESTIMATED
NUMBER DESCRIPTION QUANTITY U/M UNIT PRICE AMOUNT
SECTION F
HERBICIDE
Furnish all necessary management, personnel, materials, supplies, parts, tools, equipment, etc., to provide maintenance services as described in Work Statement Technical Provisions for the period 15 July 2018 or date of award, whichever is later, Through 14 July 2019.
1097 Herbicide Application 400 Acres
TOTAL SECTION F OPTION 1
CLIN DESCRIPTION ESTIMATED
NUMBER QUANTITY U/M UNIT PRICE AMOUNT
SECTION G
GABIONS
tools, equipment, etc., to provide maintenance services as described in Work Statement Technical Provisions for the period 15 July 2018 or date of award, whichever is later, Through 14 July 2019.
1098 Gabion Installation 750 CY
TOTAL SECTION G OPTION 1
CLIN DESCRIPTION ESTIMATED
NUMBER QUANTITY U/M UNIT PRICE AMOUNT
SECTION H
BOUYS
Furnish all necessary management, personnel, materials, supplies, parts, tools, equipment, etc., to provide maintenance services as described in Work Statement Technical Provisions for the period 15 July 2018 or date of award, whichever is later, Through 14 July 2019.
1099 Bouy Installation/Removal 200 EA
1100 Estimated Material Cost 10000 EA $1.00 $10,000.00
TOTAL SECTION H OPTION 1
CLIN DESCRIPTION ESTIMATED
NUMBER QUANTITY U/M UNIT PRICE AMOUNT
SECTION I
GENERATOR MAINTENANCE
tools, equipment, etc., to provide maintenance services as described in Work Statement Technical Provisions for the period 15 July 2018 or date of award, whichever is later, Through 14 July 2019.
1101 Yearly Maintenance 5000 $1.00 $5,000.00
1102 Emergency Service Call 5 EA
1103 Estimated Material Cost 12000 EA $1.00 $12,000.00
TOTAL SECTION I OPTION 1
TOTAL OPTION 1 SECTION A-I
(CLINs 1001 - 1103)
CLIN ESTIMATED
NUMBER DESCRIPTION QUANTITY U/M UNIT PRICE AMOUNT
SECTION A
CARPENTRY AND PAINTING
Furnish all necessary management, personnel, materials, supplies, parts, tools, equipment, etc., to provide maintenance services as described in Work Statement Technical Provisions for the period 15 July 2019 or date of award, whichever is later, OPTION YEAR 2
Through 14 July 2020.
2001 Normal Service Call 30 EA
2002 Emergency Service Call 10 EA
2003 Emergency Debris Removal 50000 EA $1.00 $50,000.00
2004 Estimated Materials Costs 30000 EA $1.00 $30,000.00 for Service, Repair, and parts
CARPENTRY
2005 Remove/Replace Existing Timbers 1500 LF
2006 Remove/Replace Base Timbers 1500 LF
2007 Install Timbers 10000 LF
2008 Install Base Timbers 1500 LF
2009 Handrails 2x4x16 Ground Contact 2000 LF
2010 Handrails 2x6x16 Ground Contact 1500 LF
2011 Handrails 4x4x10 Ground Contact Post 500 LF
2012 Handrails 4x4x16 Ground Contact Post 500 LF
2013 Replace/Install Pedestal Grills 30 EA
2014 Install Concrete Fire Pit 25 EA
2015 Replace/Install One Post Signs 40 EA
2016 Replace/Install Two Post Signs 40 EA
2017 Fill Material 5000 TN
2018 Sand Material 700 TN
2019 Screening Material 700 TN
2020 Aggregate Base Material 2000 TN
2021 Aggregate Base Material 3/4" 2000 TN
2022 Rip Rap Stone 12" and down 2000 TN
2023 Rip Rap Stone 6" and down 2000 TN
2024 Replace Metal Entry Doors 10 EA
2025 Replace or Install Shower Bench 10 EA
2026 Replace/Install Utility Table Tops 25 EA
2027 Replace/Install 8 Foot Vinyl Coated Picnic Tables 25 EA
2028 Culvert Replacement – 6” to 12" 10 EA
2029 Culvert Replacement – 13” to 24" 10 EA
2030 Culvert Replacement – 25” to 36" 10 EA
2031 Culvert Replacement - 37" to 48" 10 EA
2032 Headwall 18-48" culverts 20 EA
2033 Concrete 300 CY
2034 Asphalt 2000 TN
2035 Metal Picnic Shelter Canopy 10 EA
2036 Chainlink Fencing 1000 LF
PAINTING
2037 Oil Base, Primer Coat – (4000 SF) 4000 SF
2038 Oil Base, Intermediate or Finish Coat 5000 SF
(5000 SF)
2039 Latex, Primer Coat, (6000 SF) 6000 SF
2040 Latex, Intermediate or Finish Coat 5000 SF
(5000 SF)
2041 Pavement Marking 9000 LF
TOTAL SECTION A OPTION 2
CLIN ESTIMATED
NUMBER DESCRIPTION QUANTITY U/M UNIT PRICE AMOUNT
SECTION B
ELECTRICAL
Furnish all necessary management, personnel, materials, supplies, parts, tools, equipment, etc., to provide maintenance services as described in Work Statement Technical Provisions for the period 15 July 2019 or date of award, whichever is later, Through 14 July 2020.
2042 Normal Service Calls 10 EA
2043 Emergency Service Calls 8 EA
2044 Estimated Material Costs 15000 EA $1.00 $15,000.00
2045 Replace or Install Camper Pedestal (50 amp) 50 EA
2046 Replace Security Light Bulb 40 EA
LED
2047 Replace Security Light Fixture 50 EA
LED
2048 Install/Replace Solar Lights 5 EA
2049 Trenching (Electrical Lines) 5000 LF
2050 Replace Underground Electrical 2000 LF Wiring 2/0 AWG (Up to 2000 LF
2051 Replace Underground Electrical 200 LF Wiring - #4 AWG
2052 Replace Underground Electrical 200 LF Wiring - #6 AWG
TOTAL SECTION B OPTION 2 $15,000.00
CLIN ESTIMATED
NUMBER DESCRIPTION QUANTITY U/M UNIT PRICE AMOUNT
SECTION C
PLUMBING AND SEPTIC SYSTEM
MAINTENANCE
Furnish all necessary management, personnel, materials, supplies, parts, tools, equipment, etc., to provide maintenance services as described in Work Statement Technical Provisions for the period 15 July 2019 or date of award, whichever is later, 2053 Normal Service Call 25 EA
2054 Emergency Service Call 15 EA
2055 Estimated Material Costs 10000 EA $1.00 $10,000.00 for Service Call Repair Parts
2056 Trenching and Backfilling (Water Lines) 1500 LF
2057 Replace Sump Pump (10 HP submergible) 3 EA
2058 Replace Lift Station Pump 4 EA
2059 Replace or Install Underground Water Line - 5000 LF
PVC ¾” – 2”
2060 Replace Underground Water Line - 5000 LF PVC over 2” – 4” pipe
2061 Replace Water Heater 40 gal or less 8 EA
2062 Replace Water Heater 85 gallon 3 EA
2063 Replace Water Heater 120 gallon 1 EA
2064 Install Vermiculite (4 CF bag size) 150 Bags
2065 Replace or Install Hydrant Assembly to include 50 EA Valve Box, Riser & Cap, Hydrant,& Vermicelite
2066 Replace Trailer Dump Station Water Tower 4 EA
2067 Septic Tank Pump Out Service 60 EA
TOTAL SECTION C OPTION 2
NUMBER DESCRIPTION QUANTITY U/M UNIT PRICE AMOUNT
SECTION D
CIVIL ENGINEERING SERVICES
Furnish all necessary management, personnel, materials, supplies, parts, tools, equipment, etc., to provide maintenance services as described in Work Statement Technical Provisions for the period 15 July 2019 or date of award, whichever is later, Through 14 July 2020.
2068 Brush Mulcher 60 HR
2069 Dump Truck, 10 cy 130 HR
2070 Backhoe 250 HR
2071 Tractor w/Blade 40 HR
2072 Skidsteer w/ Auger 25 HR
2073 Tractor w/Front Loader 80 HR
2074 Dozer Work 250 HR
2075 Trackhoe with 30ft boom 250 HR
2076 Road Grader 100 HR
2077 Mini Excavator 250 HR
2078 Bucket Truck 100 HR
2079 Concrete Saw 60 HR
2080 Side Boom Bushhog 200 HR
2081 Crane (up to 100 tons) 60 HR
2082 Compactor (Walk Behind) 120 HR
2083 Rubber Tire Loader 250 HR
TOTAL SECTION D OPTION 2
CLIN ESTIMATED
NUMBER DESCRIPTION QUANTITY U/M UNIT PRICE AMOUNT
SECTION E
TREE REMOVAL/ UNDERBRUSHING
Furnish all necessary management, personnel, materials, supplies, parts, tools, equipment, etc., to provide maintenance services as described in Work Statement Technical Provisions for the period 15 July 2019 or date of award, whichever is later, Through 14 July 2020.
2084 Tree Removal – 6” to 12” Pine 50 EA
2085 Tree Removal – 13” to 20” Pine 50 EA
2086 Tree Removal – 21” to 26” Pine 50 EA
2087 Tree Removal – 27” & Above Pine 50 EA
2088 Tree Removal – 6” to 12” Hardwood 75 EA
2089 Tree Removal – 13’ to 16” Hardwood 75 EA
2090 Tree Removal – 17” to 20’ Hardwood 75 EA
2091 Tree Removal – 21” to 26’ Hardwood 75 EA
2092 Tree Removal – 27” to 32’ Hardwood 60 EA
2093 Tree Removal – 33” and Above Hardwood 50 EA
2094 Stump Grinding 18" and under 400 EA
2095 Stump Grinding 19" and above 250 EA
2096 Underbrushing 80 Acres
TOTAL SECTION E OPTION 2 $0.00
CLIN ESTIMATED
NUMBER DESCRIPTION QUANTITY U/M UNIT PRICE AMOUNT
SECTION F
HERBICIDE
Furnish all necessary management, personnel, materials, supplies, parts, tools, equipment, etc., to provide maintenance services as described in Work Statement Technical Provisions for the period 15 July 2019 or date of award, whichever is later, 2097 Herbicide Application 400 Acres
TOTAL SECTION F OPTION 2
NUMBER QUANTITY U/M UNIT PRICE AMOUNT
SECTION G
GABIONS
Furnish all necessary management, personnel, materials, supplies, parts, tools, equipment, etc., to provide maintenance services as described in Work Statement Technical Provisions for the period 15 July 2019 or date of award, whichever is later, Through 14 July 2020.
2098 Gabion Installation 750 CY
TOTAL SECTION G OPTION 2
CLIN DESCRIPTION ESTIMATED
NUMBER QUANTITY U/M UNIT PRICE AMOUNT
SECTION H
BOUYS
Furnish all necessary management, personnel, materials, supplies, parts, tools, equipment, etc., to provide maintenance services as described in Work Statement Technical Provisions for the period 15 July 2019 or date of award, whichever is later, Through 14 July 2020.
2099 Bouy Installation/Removal 200 EA
2100 Estimated Material Cost 10000 EA $1.00 $10,000.00
TOTAL SECTION H OPTION 2
NUMBER QUANTITY U/M UNIT PRICE AMOUNT
SECTION I
GENERATOR MAINTENANCE
Furnish all necessary management, personnel, materials, supplies, parts, tools, equipment, etc., to provide maintenance services as described in Work Statement Technical Provisions for the period 15 July 2019 or date of award, whichever is later, Through 14 July 2020.
2101 Yearly Maintenance 5000 $1.00 $5,000.00
2102 Emergency Service Call 5 EA
2103 Estimated Material Cost 12000 EA $1.00 $12,000.00
TOTAL SECTION I OPTION 2
TOTAL OPTION 2 SECTION A-I
(CLINS 2001 - 2103)
GRAND TOTAL
(Total of Base year, Option year 1 and Option year 2)
W9127S-17-Q-0007
CLAUSES INCORPORATED BY REFERENCE
52.202-1 Definitions NOV 2013 52.203-3 Gratuities APR 1984 52.203-5 Covenant Against Contingent Fees MAY 2014 52.203-6 Alt I Restrictions On Subcontractor Sales To The Government
(Sep 2006) -- Alternate I
OCT 1995
52.203-12 Limitation On Payments To Influence Certain Federal Transactions
OCT 2010
52.203-17 Contractor Employee Whistleblower Rights and Requirement To Inform Employees of Whistleblower Rights
APR 2014
52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper
MAY 2011
52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First-Tier
Subcontract Awards
OCT 2016
52.204-16 Commercial and Government Entity Code Reporting JUL 2016 52.204-19 Incorporation by Reference of Representations and
Certifications.
DEC 2014
52.207-1 Notice Of Standard Competition MAY 2006 52.212-1 Instructions to Offerors--Commercial Items JAN 2017 52.217-5 Evaluation Of Options JUL 1990 52.219-6 Notice Of Total Small Business Set-Aside NOV 2011 52.219-8 Utilization of Small Business Concerns NOV 2016 52.219-14 Limitations On Subcontracting JAN 2017 52.222-3 Convict Labor JUN 2003 52.222-19 Child Labor -- Cooperation with Authorities and Remedies OCT 2016 52.222-21 Prohibition Of Segregated Facilities APR 2015
52.223-6 MAY 2001
52.223-18 AUG 2011
52.225-13 JUN 2008
52.225-25 OCT 2015
52.228-5 JAN 1997
52.232-8 FEB 2002
52.232-40 DEC 2013
52.233-3 AUG 1996
52.233-4 OCT 2004
52.237-1 APR 1984
52.237-2 APR 1984
52.237-3 JAN 1991
52.242-13 JUL 1995
52.242-17 52.245-1
APR 1984
JAN 2017
52.253-1
Drug-Free Workplace Encouraging Contractor Policies To Ban Text Messaging While Driving Restrictions on Certain Foreign Purchases Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran-- Representation and Certifications.
Insurance - Work On A Government Installation Discounts For Prompt Payment Providing Accelerated Payments to Small Business Subcontractors Protest After Award Applicable Law for Breach of Contract Claim Site Visit Protection Of Government Buildings, Equipment, And Vegetation Continuity Of Services Bankruptcy Government Delay Of Work Government Property Computer Generated Forms JAN 1991
252.201-7000 Contracting Officer's Representative DEC 1991 252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.203-7005 Representation Relating to Compensation of Former DoD
Officials
NOV 2011
252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7004 Alt A System for Award Management Alternate A FEB 2014
252.204-7008 Compliance With Safeguarding Covered Defense Information Controls
OCT 2016
252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting
OCT 2016
252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support
MAY 2016
252.205-7000 Provision Of Information To Cooperative Agreement Holders DEC 1991 252.209-7004 Subcontracting With Firms That Are Owned or Controlled By
The Government of a Country that is a State Sponsor of Terrorism
OCT 2015
252.225-7048 Export-Controlled Items JUN 2013
252.226-7001 SEP 2004
252.227-7000 OCT 1966
252.232-7003 JUN 2012
252.232-7004 OCT 2014
252.232-7010 DEC 2006
252.243-7001 DEC 1991
252.243-7002 DEC 2012
252.244-7000 252.245-7001 252.245-7002 252.245-7003 252.245-7004
Utilization of Indian Organizations and Indian-Owned Economic Enterprises, and Native Hawaiian Small Business Concerns Non-estoppel Electronic Submission of Payment Requests and Receiving Reports DOD Progress Payment Rates Levies on Contract Payments Pricing Of Contract Modifications Requests for Equitable Adjustment Subcontracts for Commercial Items Tagging, Labeling and Marking Gov Property Reporting Loss of Gov Property Contractor Property Management Reporting, Reutilization and Disposal
JUN 2013
APR 2012
APR 2012
APR 2012
SEP 2016
CLAUSES INCORPORATED BY FULL TEXT
52.209-12 CERTIFICATION REGARDING TAX MATTERS (FEB 2016)
(a) This provision implements section 523 of Division B of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-235), and similar provisions, if contained in subsequent appropriations acts.
(b) If the Offeror is proposing a total contract price that will exceed $5,000,000 (including options), the Offeror shall certify that, to the best of its knowledge and belief, it--
(1) Has [ ] filed all Federal tax returns required during the three years preceding the certification;
(2) Has not [ ] been convicted of a criminal offense under the Internal Revenue Code of 1986; and
(3) Has not [ ], more than 90 days prior to certification, been notified of any unpaid Federal tax assessment for which the liability remains unsatisfied, unless the assessment is the subject of an installment agreement or offer in compromise that has been approved by the Internal Revenue Service and is not in default, or the assessment is the subject of a non-frivolous administrative or judicial proceeding.
(End of provision)
52.212-2 EVALUATION--COMMERCIAL ITEMS (OCT 2014)
(a) The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered. The following factors shall be used to evaluate offers:
Factor 1 - Qualifications and Experience Factor 2 – Technical Approach and Understanding of the Work
Factor 3 - Equipment Owned/Rental Available Factor 4 - Past Performance Factor 5 – Price The approach to the source selection for this procurement will be pursuant to a best value concept. The objective is to select the quote that offers the best value for the Government, not necessarily the lowest price. However, as quotes become more equal technically, cost may become a determining factor in award selection.
(b) Options. The Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. The Government may determine that an offer is unacceptable if the option prices are significantly unbalanced. Evaluation of options shall not obligate the Government to exercise the option(s).
(c) A written notice of award or acceptance of an offer, mailed or otherwise furnished to the successful offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party.
Before the offer's specified expiration time, the Government may accept an offer (or part of an offer), whether or not there are negotiations after its receipt, unless a written notice of withdrawal is received before award.
(End of provision)
52.212-3 OFFEROR REPRESENTATIONS AND CERTIFICATIONS--COMMERCIAL ITEMS (JAN 2017)
ALTERNATE I (OCT 2014)
The offeror shall complete only paragraphs (b) of this provision if the Offeror has completed the annual representations and certification electronically via the System for Award Management (SAM) Web site located at https://www.sam.gov/portal . If the Offeror has not completed the annual representations and certifications electronically, the Offeror shall complete only paragraphs (c) through (u) of this provision.
(a) Definitions. As used in this provision--
“Administrative merits determination” means certain notices or findings of labor law violations issued by an enforcement agency following an investigation. An administrative merits determination may be final or be subject to appeal or further review. To determine whether a particular notice or finding is covered by this definition, it is necessary to consult section II.B. in the DOL Guidance.
“Arbitral award or decision” means an arbitrator or arbitral panel determination that a labor law violation occurred, or that enjoined or restrained a violation of labor law. It includes an award or decision that is not final or is subject to being confirmed, modified, or vacated by a court, and includes an award or decision resulting from private or confidential proceedings. To determine whether a particular award or decision is covered by this definition, it is necessary to consult section II.B. in the DOL Guidance.
“Civil judgment” means--
(1) In paragraph (h) of this provision: A judgment or finding of a civil offense by any court of competent jurisdiction.
(2) In paragraph (s) of this provision: Any judgment or order entered by any Federal or State court in which the court determined that a labor law violation occurred, or enjoined or restrained a violation of labor law. It includes a https://www.sam.gov/portal judgment or order that is not final or is subject to appeal. To determine whether a particular judgment or order is covered by this definition, it is necessary to consult section II.B. in the DOL Guidance.
“DOL Guidance” means the Department of Labor (DOL) Guidance entitled: ``Guidance for Executive Order 13673, `Fair Pay and Safe Workplaces' ''. The DOL Guidance, dated August 25, 2016, can be obtained from www.dol.gov/fairpayandsafeworkplaces.
“Economically disadvantaged women-owned small business (EDWOSB) concern” means a small business concern that is at least 51 percent directly and unconditionally owned by, and the management and daily business operations of which are controlled by, one or more women who are citizens of the United States and who are economically disadvantaged in accordance with 13 CFR part 127. It automatically qualifies as a women-owned small business eligible under the WOSB Program.
“Enforcement agency” means any agency granted authority to enforce the Federal labor laws. It includes the enforcement components of DOL (Wage and Hour Division, Office of Federal Contract Compliance Programs, and Occupational Safety and Health Administration), the Equal Employment Opportunity Commission, the occupational Safety and Health Review Commission, and the National Labor Relations Board. It also means a State agency designated to administer an OSHA-approved State Plan, but only to the extent that the State agency is acting in its capacity as administrator of such plan. It does not include other Federal agencies which, in their capacity as contracting agencies, conduct investigations of potential labor law violations. The enforcement agencies associated with each labor law under E.O. 13673 are--
(1) Department of Labor Wage and Hour Division (WHD) for--
(i) The Fair Labor Standards Act;
(ii) The Migrant and Seasonal Agricultural Worker Protection Act;
(iii) 40 U.S.C. chapter 31, subchapter IV, formerly known as the Davis-Bacon Act;
(iv) 41 U.S.C. chapter 67, formerly known as the Service Contract Act;
(v) The Family and Medical Leave Act; and
(vi) E.O. 13658 of February 12, 2014 (Establishing a Minimum Wage for Contractors);
(2) Department of Labor Occupational Safety and Health Administration (OSHA) for--
(i) The Occupational Safety and Health Act of 1970; and
(ii) OSHA-approved State Plans;
(3) Department of Labor Office of Federal Contract Compliance Programs (OFCCP) for--
(i) ) Section 503 of the Rehabilitation Act of 1973;
(ii) The Vietnam Era Veterans' Readjustment Assistance Act of 1972 and the Vietnam Era Veterans' Readjustment Assistance Act of 1974; and
(iii) E.O. 11246 of September 24, 1965 (Equal Employment Opportunity);
(4) National Labor Relations Board (NLRB) for the National Labor Relations Act; and
(5) Equal Employment Opportunity Commission (EEOC) for--http://www.dol.gov/fairpayandsafeworkplaces
(i) Title VII of the Civil Rights Act of 1964;
(ii) The Americans with Disabilities Act of 1990;
(iii) The Age Discrimination in Employment Act of 1967; and
(iv) Section 6(d) of the Fair Labor Standards Act (Equal Pay Act).
“Forced or indentured child labor” means all work or service—
(1) Exacted from any person under the age of 18 under the menace of any penalty for its nonperformance and for which the worker does not offer himself voluntarily; or
(2) ) Performed by any person under the age of 18 pursuant to a contract the enforcement of which can be accomplished by process or penalties.
“Highest-level owner” means the entity that owns or controls an immediate owner of the offeror, or that owns or controls one or more entities that control an immediate owner of the offeror. No entity owns or exercises control of the highest level owner.
“Immediate owner” means an entity, other than the offeror, that has direct control of the offeror. Indicators of control include, but are not limited to, one or more of the following: Ownership or interlocking management, identity of interests among family members, shared facilities and equipment, and the common use of employees.
“Inverted domestic corporation,” means a foreign incorporated entity that meets the definition of an inverted domestic corporation under 6 U.S.C. 395(b), applied in accordance with the rules and definitions of 6 U.S.C. 395(c).
“Labor compliance agreement” means an agreement entered into between a contractor or subcontractor and an enforcement agency to address appropriate remedial measures, compliance assistance, steps to resolve issues to increase compliance with the labor laws, or other related matters.
“Labor laws” means the following labor laws and E.O.s:
(1) The Fair Labor Standards Act.
(2) The Occupational Safety and Health Act (OSHA) of 1970.
(3) The Migrant and Seasonal Agricultural Worker Protection Act.
(4) The National Labor Relations Act.
(5) 40 U.S.C. chapter 31, subchapter IV, formerly known as the Davis-Bacon Act.
(6) 41 U.S.C. chapter 67, formerly known as the Service Contract Act.
(7) E.O. 11246 of September 24, 1965 (Equal Employment Opportunity).
(8) ) Section 503 of the Rehabilitation Act of 1973.
(9) The Vietnam Era Veterans' Readjustment Assistance Act of 1972 and the Vietnam Era Veterans' Readjustment Assistance Act of 1974.
(10) The Family and Medical Leave Act.
(11) Title VII of the Civil Rights Act of 1964.
(12) The Americans with Disabilities Act of 1990.
(13) The Age Discrimination in Employment Act of 1967.
(14) E.O. 13658 of February 12, 2014 (Establishing a Minimum Wage for Contractors).
(15) Equivalent State laws as defined in the DOL Guidance. (The only equivalent State laws implemented in the FAR are OSHA-approved State Plans, which can be found at www.osha.gov/dcsp/osp/approved_state_plans.html).
“Labor law decision” means an administrative merits determination, arbitral award or decision, or civil judgment, which resulted from a violation of one or more of the laws listed in the definition of ``labor laws''.
“Manufactured end product” means any end product in product and service codes (PSCs) 1000-9999, except—
(1) PSC 5510, Lumber and Related Basic Wood Materials;
(2) Product or Service Group (PSG) 87, Agricultural Supplies;
(3) PSG 88, Live Animals;
(4) PSG 89, Subsistence;
(5) PSC 9410, Crude Grades of Plant Materials;
(6) PSC 9430, Miscellaneous Crude Animal Products, Inedible;
(7) PSC 9440, Miscellaneous Crude Agricultural and Forestry Products;
(8) PSC 9610, Ores;
(9) PSC 9620, Minerals, Natural and Synthetic; and
(10) PSC 9630, Additive Metal Materials.
“Place of manufacture” means the place where an end product is assembled out of components, or otherwise made or processed from raw materials into the finished product that is to be provided to the Government. If a product is disassembled and reassembled, the place of reassembly is not the place of manufacture.
“Restricted business operations” means business operations in Sudan that include power production activities, mineral extraction activities, oil-related activities, or the production of military equipment, as those terms are defined in the Sudan Accountability and Divestment Act of 2007 (Pub. L. 110-174). Restricted business operations do not include business operations that the person (as that term is defined in Section 2 of the Sudan Accountability and Divestment Act of 2007) conducting the business can demonstrate—
(1) Are conducted under contract directly and exclusively with the regional government of southern Sudan;
(2) Are conducted pursuant to specific authorization from the Office of Foreign Assets Control in the Department of the Treasury, or are expressly exempted under Federal law from the requirement to be conducted under such authorization;
http://www.osha.gov/dcsp/osp/approved_state_plans.html
(3) Consist of providing goods or services to marginalized populations of Sudan;
(4) Consist of providing goods or services to an internationally recognized peacekeeping force or humanitarian organization;
(5) Consist of providing goods or services that are used only to promote health or education; or
(6) Have been voluntarily suspended.
Sensitive technology—
(1) Means hardware, software, telecommunications equipment, or any other technology that is to be used specifically—
(i) To restrict the free flow of unbiased information in Iran; or
(ii) To disrupt, monitor, or otherwise restrict speech of the people of Iran; and
(2) Does not include information or informational materials the export of which the President does not have the authority to regulate or prohibit pursuant to section 203(b)(3) of the International Emergency Economic Powers Act (50 U.S.C. 1702(b)(3)).
“Service-disabled veteran-owned small business concern”—
(1) Means a small business concern—
(i) Not less than 51 percent of which is owned by one or more service-disabled veterans or, in the case of any publicly owned business, not less than 51 percent of the stock of which is owned by one or more service-disabled veterans; and
(ii) The management and daily business operations of which are controlled by one or more service-disabled veterans or, in the case of a service-disabled veteran with permanent and severe disability, the spouse or permanent caregiver of such veteran.
(2) ) Service-disabled veteran means a veteran, as defined in 38 U.S.C. 101(2), with a disability that is service- connected, as defined in 38 U.S.C. 101(16).
“Small business concern” means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR Part 121 and size standards in this solicitation.
“Small disadvantaged business concern, consistent with 13 CFR 124.1002,” means a small business concern under the size standard applicable to the acquisition, that--
(1) Is at least 51 percent unconditionally and directly owned (as defined at 13 CFR 124.105) by--
(i) One or more socially disadvantaged (as defined at 13 CFR 124.103) and economically disadvantaged (as defined at 13 CFR 124.104) individuals who are citizens of the United States; and
(ii) Each individual claiming economic disadvantage has a net worth not exceeding $750,000 after taking into account the applicable exclusions set forth at 13 CFR 124.104(c)(2); and
(2) The management and daily business operations of which are controlled (as defined at 13.CFR 124.106) by individuals, who meet the criteria in paragraphs (1)(i) and (ii) of this definition.
“Subsidiary” means an entity in which more than 50 percent of the entity is owned—
(1) Directly by a parent corporation; or
(2) Through another subsidiary of a parent corporation.
“Veteran-owned small business concern” means a small business concern—
(1) Not less than 51 percent of which is owned by one or more veterans(as defined at 38 U.S.C. 101(2)) or, in the case of any publicly owned business, not less than 51 percent of the stock of which is owned by one or more veterans; and
(2) The management and daily business operations of which are controlled by one or more veterans.
“Women-owned business concern” means a concern which is at least 51 percent owned by one or more women; or in the case of any publicly owned business, at least 51 percent of the its stock is owned by one or more women; and whose management and daily business operations are controlled by one or more women.
“Women-owned small business concern” means a small business concern --
(1) That is at least 51 percent owned by one or more women or, in the case of any publicly owned business, at least 51 percent of the stock of which is owned by one or more women; and
(2) Whose management and daily business operations are controlled by one or more women.
“Women-owned small business (WOSB) concern eligible under the WOSB Program (in accordance with 13 CFR part 127),” means a small business concern that is at least 51 percent directly and unconditionally owned by, and the management and daily business operations of which are controlled by, one or more women who are citizens of the United States.
Note to paragraph (a): By a court order issued on October 24, 2016, the following definitions in this paragraph (a) are enjoined indefinitely as of the date of the order: ``Administrative merits determination'', ``Arbitral award or decision'', paragraph (2) of ``Civil judgment'', ``DOL Guidance'', ``Enforcement agency'', ``Labor compliance agreement'', ``Labor laws'', and ``Labor law decision''. The enjoined definitions will become effective immediately if the court terminates the injunction. At that time, DoD, GSA, and NASA will publish a document in the Federal Register advising the public of the termination of the injunction.
(b)
(1) Annual Representations and Certifications. Any changes provided by the offeror in paragraph (b)(2) of this provision do not automatically change the representations and certifications posted on the SAMwebsite.
(2) The offeror has completed the annual representations and certifications electronically via the SAM website accessed through https://www.acquisition.gov. After reviewing the SAM database information, the offeror verifies by submission of this offer that the representation and certifications currently posted electronically at FAR 52.212-3, Offeror Representations and Certifications—Commercial Items, have been entered or updated in the last 12 months, are current, accurate, complete, and applicable to this solicitation (including the business size standard applicable to the NAICS code referenced for this solicitation), as of the date of this offer and are incorporated in this offer by reference (see FAR 4.1201), except for paragraphs . [Offeror to identify the applicable paragraphs at (c) https://www.acquisition.gov/ through (u) of this provision that the offeror has completed for the purposes of this solicitation only, if any.
This is the start of the file's text. The full file is on GovTribe.