Grounds_Keeping_Responses_to_Questions.pdf

PDF 97 KB Posted

Attached to
Grounds Keeping Services, Mountain Home Project Office, Norfork and Bull Shoals Lakes
Solicitation number
W9127S-16-T-0008
Issued by

About this file

Grounds Keeping Responses to Questions

View the file

Other files

File Type Posted
Attendance_Record_9Feb16.pdf PDF
Pre_Bid_Agenda_9Feb16.pdf PDF
Combined_Synopsis_Solicitation.pdf PDF
Grounds_Keeping_Bid_Schedule.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation: W9127S-16-T-0008

Grounds Keeping Services, Mountain Home Project Office, Norfork and Bull Shoals Lakes

Responses to Questions

1Q: What was last year's awarded bid total amount for this contract?

1A: Contract history has been provided in FedBizOps on 8Feb16. If you require anything extra, you will have to submit a FOIA (Freedom of Information Act) request to our legal office.

2Q: Is this a follow-on requirement? If so, could you please provide the incumbent contract number for this opportunity? If not, is this a new requirement?

2A: This is not a new requirement; contract history has been provided in FedBizOps on 8Feb16.

3Q: In regards to the Modification you released earlier this evening, you provided three incumbent contractors. Are these services being consolidated? I understand that a FIOA is needed for additional information, but if these services are being consolidated, are there only three contracts being performed for this new effort?

3A: Services are not consolidated.

4Q: The Statement of Work indicates all mowing is to be completed within 14 calendar days with additional language that restricts mowing on weekends, federal holidays and days proceeding federal holidays. So, in a 14 calendar day cycle, the contractor only has 10 "allowable" days in which to complete mowing? And should a federal holiday similarly fall within this time frame, less "allowable" days? Accordingly, does the same apply to leaf removal in a 4 calendar day cycle?

4A: Wording is correct. Yes, the performance cycle basically amounts to 10 schedulable workdays. If a federal holiday, administrative decision, or major weather delay further restricts performance it shall not count against the 14 days. Yes, this pattern would apply to all tasks.