Bid Abstract - W9127N26BA005 Cottonwood Pile Dike Repairs.pdf
PDF 150 KB Posted
- Attached to
- Cottonwood Pile Dike Repairs
- Solicitation number
- W9127N26BA005CottonwoodPileDikeRepairs-Solicitation
About this file
This is a Standard Form 1419 Abstract of Offers documenting a sealed bid solicitation for construction services related to Cottonwood Pile Dike Repairs. The solicitation number is W9127N26BA005, issued on April 1, 2026, with a bid opening date of May 15, 2026. The issuing office is W071 ENDIST PORTLAND, KO CONTRACTING DIVISION, located at 333 SW First Avenue, Portland, OR 97204-3495.
The contract encompasses 17 mandatory line items (CLINs) valued at a government estimate of $14,060,000, consisting of mobilization/demobilization, timber pile installation work at multiple pile dike locations (ranging from stationing 68.35 to 71.51), rock placement at various pile dike stations, and marker pile installation. All bids required 20 percent bid security and acknowledgment of three amendments. Nine offers were received from the following contractors: Xenturis, Duwwamish Services LLC, M.J. Hughes Construction Inc., T1 Construction LLC, Trade West Construction Inc., HME Construction Inc., Bergerson Construction Inc., and two additional slots. Bid prices ranged significantly, from a low of $7,995,000 (HME Construction Inc., Offer No. 6) to a high of $26,170,083 (Trade West Construction Inc., Offer No. 5). No optional CLINs were included in any of the offers. All offerors acknowledged the contract amendments as required.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2. DATE ISSUED 3. DATE OPENED PAGE 1 OF 3 PAGES
4/1/2026 5/15/2026
4. ISSUING OFFICE
CONTRACT SPECIALIST SIGNATURE CONTRACTING OFFICER SIGNATURE
5. PROJECT TITLE
B. BID SECURITY B. BID SECURITY
20% of bid price 20% of bid price
C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED
Yes 3 of 3 Yes 3 of 3 Yes 3 of 3
MANDATORY CLINS -$
0001 Mobilization and Demobilization 1 Job 2,625,000.00$ 2,625,000.00$ 1,084,583.00$ 1,084,583.00$ 1,980,000.00$ 1,980,000.00$ 1,780,000.00$ 1,780,000.00$ 0002 Timber Pile Installation Pile Dike 68.35 1 Job 270,000.00$ 270,000.00$ 397,680.00$ 397,680.00$ 60,000.00$ 60,000.00$ 95,000.00$ 95,000.00$ 0003 Rock Placement Pile Dike 68.35 1 Job 1,635,000.00$ 1,635,000.00$ 1,626,875.00$ 1,626,875.00$ 1,700,000.00$ 1,700,000.00$ 2,000,000.00$ 2,000,000.00$ 0004 Rock Placement Pile Dike 68.57 1 Job 280,000.00$ 280,000.00$ 813,437.00$ 813,437.00$ 250,000.00$ 250,000.00$ 550,000.00$ 550,000.00$ 0005 Rock Placement Pile Dike 68.79 1 Job 325,000.00$ 325,000.00$ 1,084,583.00$ 1,084,583.00$ 385,000.00$ 385,000.00$ 750,000.00$ 750,000.00$ 0006 Timber Pile Installation Pile Dike 69.01 1 Job 225,000.00$ 225,000.00$ 361,528.00$ 361,528.00$ 50,000.00$ 50,000.00$ 95,000.00$ 95,000.00$ 0007 Rock Placement Pile Dike 69.01 1 Job 1,525,000.00$ 1,525,000.00$ 1,988,402.00$ 1,988,402.00$ 1,400,000.00$ 1,400,000.00$ 2,000,000.00$ 2,000,000.00$ 0008 Rock Placement Pile Dike 69.25 1 Job 715,000.00$ 715,000.00$ 903,819.00$ 903,819.00$ 600,000.00$ 600,000.00$ 1,350,000.00$ 1,350,000.00$ 0009 Timber Pile Installation Pile Dike 69.51 1 Job 320,000.00$ 320,000.00$ 488,062.00$ 488,062.00$ 70,000.00$ 70,000.00$ 95,000.00$ 95,000.00$ 0010 Rock Placement Pile Dike 69.51 1 Job 735,000.00$ 735,000.00$ 2,078,784.00$ 2,078,784.00$ 650,000.00$ 650,000.00$ 1,400,000.00$ 1,400,000.00$ 0011 Timber Pile Installation Pile Dike 69.79 1 Job 550,000.00$ 550,000.00$ 813,437.00$ 813,437.00$ 130,000.00$ 130,000.00$ 150,000.00$ 150,000.00$ 0012 Rock Placement Pile Dike 69.79 1 Job 1,250,000.00$ 1,250,000.00$ 1,626,875.00$ 1,626,875.00$ 1,150,000.00$ 1,150,000.00$ 2,300,000.00$ 2,300,000.00$ 0013 Timber Pile Installation Pile Dike 70.07 1 Job 535,000.00$ 535,000.00$ 813,437.00$ 813,437.00$ 125,000.00$ 125,000.00$ 150,000.00$ 150,000.00$ 0014 Rock Placement Pile Dike 70.07 1 Job 700,000.00$ 700,000.00$ 2,078,784.00$ 2,078,784.00$ 595,000.00$ 595,000.00$ 1,150,000.00$ 1,150,000.00$ 0015 Rock Placement Pile Dike 71.17 1 Job 290,000.00$ 290,000.00$ 903,819.00$ 903,819.00$ 250,000.00$ 250,000.00$ 750,000.00$ 750,000.00$ 0016 Rock Placement Pile Dike 71.51 1 Job 1,495,000.00$ 1,495,000.00$ 1,446,111.00$ 1,446,111.00$ 1,250,000.00$ 1,250,000.00$ 2,000,000.00$ 2,000,000.00$ 0017 Marker Pile Installation 1 Job 585,000.00$ 585,000.00$ 1,446,111.00$ 1,446,111.00$ 849,950.00$ 849,950.00$ 1,350,000.00$ 1,350,000.00$
SUB-TOTAL FOR MANDATORY CLINS 14,060,000.00$ 19,956,327.00$ 11,494,950.00$ 17,965,000.00$ KTR Indicates 19,956,331.00$
OPTIONAL CLINS
SUB-TOTAL FOR OPTIONAL CLINS -$ -$ -$ -$
14,060,000.00$ 19,956,327.00$ 11,494,950.00$ 17,965,000.00$
9. OFFERS
B. REASONABLE CONTRACT
(Without Profit)
C. REASONABLE CONTRACT
(including profit)
NO.1 NO.2 NO.3
A. OFFEROR A. OFFEROR A. OFFEROR
A.HIRED LABOR
8. GOVERNMENT ESTIMATE
Check A, B, or C, and Complete D, E, and F.)
Xenturis M.J. Hughes Construction, Inc.
ABSTRACT OF OFFERS
W9127N2BA0005
I CERTIFY THAT I HAVE OPENED, READ, AND RECORDED ON THIS ABSTRACT
ALL BIDS RECEIVED IN RESPONSE TO THIS SOLICITATION.
W071 ENDIST PORTLAND
KO CONTRACTING DIVISION, 333 SW FIRST AVE
PORTLAND, OR 97204-3495
UNITED STATES
1. SOLICITATION NO.
STANDARD FORM 1419 (10-3)
Duwwamish Services LLC
B. BID SECURITY
F. AMOUNT D.UNIT
PRICE
E. AMOUNT D.UNIT
PRICE
E. AMOUNT D.UNIT
PRICE
E. AMOUNT
COTTONWOOD PILE DIKE REPAIRS
TOTAL FOR ALL CLINS
ACCEPTANCE LIMITATIONS - DAYS
INFORMALITIES
X
6. NUMBER OF AMENDMENTS ISSUED: 2
7A.
ITEM
NO.
7B. DESCRIPTION OF OFFERED ITEM
7C. EST
QUANTITY
D.
UNIT
E. UNIT
PRICE
2. DATE ISSUED 3. DATE OPENED PAGE 2 OF 3 PAGES
4. ISSUING OFFICE
CONTRACT SPECIALIST SIGNATURE CONTRACTING OFFICER SIGNATURE
5. PROJECT TITLE
B. BID SECURITY B. BID SECURITY
20% of bid price 20% of bid price 20% of bid price
C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED
Yes 3 of 3 Yes 3 of 3 Yes 3 of 3
MANDATORY CLINS -$
0001 Mobilization and Demobilization 1 Job 2,625,000.00$ 2,625,000.00$ 6,744,061.00$ 6,744,061.00$ 5,090,000.00$ 5,090,000.00$ 680,000.00$ 680,000.00$ 0002 Timber Pile Installation Pile Dike 68.35 1 Job 270,000.00$ 270,000.00$ 805,541.00$ 805,541.00$ 260,000.00$ 260,000.00$ 85,000.00$ 85,000.00$ 0003 Rock Placement Pile Dike 68.35 1 Job 1,635,000.00$ 1,635,000.00$ 1,960,773.00$ 1,960,773.00$ 1,130,000.00$ 1,130,000.00$ 1,400,000.00$ 1,400,000.00$ 0004 Rock Placement Pile Dike 68.57 1 Job 280,000.00$ 280,000.00$ 811,786.00$ 811,786.00$ 1,130,000.00$ 1,130,000.00$ 170,000.00$ 170,000.00$ 0005 Rock Placement Pile Dike 68.79 1 Job 325,000.00$ 325,000.00$ 855,497.00$ 855,497.00$ 1,130,000.00$ 1,130,000.00$ 265,000.00$ 265,000.00$ 0006 Timber Pile Installation Pile Dike 69.01 1 Job 225,000.00$ 225,000.00$ 805,541.00$ 805,541.00$ 260,000.00$ 260,000.00$ 45,000.00$ 45,000.00$ 0007 Rock Placement Pile Dike 69.01 1 Job 1,525,000.00$ 1,525,000.00$ 1,873,350.00$ 1,873,350.00$ 1,130,000.00$ 1,130,000.00$ 1,050,000.00$ 1,050,000.00$ 0008 Rock Placement Pile Dike 69.25 1 Job 715,000.00$ 715,000.00$ 1,211,434.00$ 1,211,434.00$ 1,130,000.00$ 1,130,000.00$ 500,000.00$ 500,000.00$ 0009 Timber Pile Installation Pile Dike 69.51 1 Job 320,000.00$ 320,000.00$ 805,541.00$ 805,541.00$ 260,000.00$ 260,000.00$ 70,000.00$ 70,000.00$ 0010 Rock Placement Pile Dike 69.51 1 Job 735,000.00$ 735,000.00$ 1,152,110.00$ 1,152,110.00$ 1,130,000.00$ 1,130,000.00$ 500,000.00$ 500,000.00$ 0011 Timber Pile Installation Pile Dike 69.79 1 Job 550,000.00$ 550,000.00$ 805,541.00$ 805,541.00$ 260,000.00$ 260,000.00$ 90,000.00$ 90,000.00$ 0012 Rock Placement Pile Dike 69.79 1 Job 1,250,000.00$ 1,250,000.00$ 1,586,103.00$ 1,586,103.00$ 1,130,000.00$ 1,130,000.00$ 850,000.00$ 850,000.00$ 0013 Timber Pile Installation Pile Dike 70.07 1 Job 535,000.00$ 535,000.00$ 805,541.00$ 805,541.00$ 260,000.00$ 260,000.00$ 90,000.00$ 90,000.00$ 0014 Rock Placement Pile Dike 70.07 1 Job 700,000.00$ 700,000.00$ 1,086,544.00$ 1,086,544.00$ 1,130,000.00$ 1,130,000.00$ 475,000.00$ 475,000.00$ 0015 Rock Placement Pile Dike 71.17 1 Job 290,000.00$ 290,000.00$ 824,274.00$ 824,274.00$ 1,130,000.00$ 1,130,000.00$ 190,000.00$ 190,000.00$ 0016 Rock Placement Pile Dike 71.51 1 Job 1,495,000.00$ 1,495,000.00$ 1,907,071.00$ 1,907,071.00$ 1,130,000.00$ 1,130,000.00$ 1,050,000.00$ 1,050,000.00$ 0017 Marker Pile Installation 1 Job 585,000.00$ 585,000.00$ 2,129,375.00$ 2,129,375.00$ 200,000.00$ 200,000.00$ 485,000.00$ 485,000.00$
SUB-TOTAL FOR MANDATORY CLINS 14,060,000.00$ 26,170,083.00$ 17,890,000.00$ 7,995,000.00$
OPTIONAL CLINS
SUB-TOTAL FOR OPTIONAL CLINS -$ -$ -$ -$
14,060,000.00$ 26,170,083.00$ 17,890,000.00$ 7,995,000.00$
D.UNIT
PRICE
E. AMOUNT D.UNIT
PRICE
E. AMOUNT
TOTAL FOR ALL CLINS
ACCEPTANCE LIMITATIONS - DAYS
INFORMALITIES
STANDARD FORM 1419 (10-3)
D.UNIT
PRICE
E. AMOUNT
C. REASONABLE CONTRACT
(including profit)
6. NUMBER OF AMENDMENTS ISSUED: 2
7A.
ITEM
NO.
7B. DESCRIPTION OF OFFERED ITEM
7C. EST
QUANTITY
D.
UNIT
E. UNIT
PRICE
F. AMOUNT
COTTONWOOD PILE DIKE REPAIRS A. OFFEROR
T1 Construction, LLC Trade West Construction, Inc. HME Construction, Inc.
X B. REASONABLE CONTRACT
(Without Profit)
B. BID SECURITY
A.HIRED LABOR A. OFFEROR A. OFFEROR
8. GOVERNMENT ESTIMATE
Check A, B, or C, and Complete D, E, and F.)
9. OFFERS
NO.4 NO.5 NO.6
ABSTRACT OF OFFERS 1. SOLICITATION NO.
W9127N26BA005
I CERTIFY THAT I HAVE OPENED, READ, AND RECORDED ON THIS ABSTRACT
ALL BIDS RECEIVED IN RESPONSE TO THIS SOLICITATION.
W071 ENDIST PORTLAND
KO CONTRACTING DIVISION, 333 SW FIRST AVE
PORTLAND, OR 97204-3495
UNITED STATES
2. DATE ISSUED 3. DATE OPENED PAGE 3 OF 3 PAGES
4. ISSUING OFFICE
CONTRACT SPECIALIST SIGNATURE CONTRACTING OFFICER SIGNATURE
5. PROJECT TITLE
B. BID SECURITY B. BID SECURITY
20% of bid price 20% of bid price 20% of bid price
C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED
Yes 3 of 3
MANDATORY CLINS -$
0001 Mobilization and Demobilization 1 Job 2,625,000.00$ 2,625,000.00$ 2,725,000.00$ 2,725,000.00$ -$ -$ 0002 Timber Pile Installation Pile Dike 68.35 1 Job 270,000.00$ 270,000.00$ 98,500.00$ 98,500.00$ -$ -$ 0003 Rock Placement Pile Dike 68.35 1 Job 1,635,000.00$ 1,635,000.00$ 1,588,700.00$ 1,588,700.00$ -$ -$ 0004 Rock Placement Pile Dike 68.57 1 Job 280,000.00$ 280,000.00$ 315,000.00$ 315,000.00$ -$ -$ 0005 Rock Placement Pile Dike 68.79 1 Job 325,000.00$ 325,000.00$ 307,000.00$ 307,000.00$ -$ -$ 0006 Timber Pile Installation Pile Dike 69.01 1 Job 225,000.00$ 225,000.00$ 86,000.00$ 86,000.00$ -$ -$ 0007 Rock Placement Pile Dike 69.01 1 Job 1,525,000.00$ 1,525,000.00$ 1,348,000.00$ 1,348,000.00$ -$ -$ 0008 Rock Placement Pile Dike 69.25 1 Job 715,000.00$ 715,000.00$ 579,000.00$ 579,000.00$ -$ -$ 0009 Timber Pile Installation Pile Dike 69.51 1 Job 320,000.00$ 320,000.00$ 89,100.00$ 89,100.00$ -$ -$ 0010 Rock Placement Pile Dike 69.51 1 Job 735,000.00$ 735,000.00$ 857,650.00$ 857,650.00$ -$ -$ 0011 Timber Pile Installation Pile Dike 69.79 1 Job 550,000.00$ 550,000.00$ 132,950.00$ 132,950.00$ -$ -$ 0012 Rock Placement Pile Dike 69.79 1 Job 1,250,000.00$ 1,250,000.00$ 1,312,000.00$ 1,312,000.00$ -$ -$ 0013 Timber Pile Installation Pile Dike 70.07 1 Job 535,000.00$ 535,000.00$ 132,450.00$ 132,450.00$ -$ -$ 0014 Rock Placement Pile Dike 70.07 1 Job 700,000.00$ 700,000.00$ 775,750.00$ 775,750.00$ -$ -$ 0015 Rock Placement Pile Dike 71.17 1 Job 290,000.00$ 290,000.00$ 330,300.00$ 330,300.00$ -$ -$ 0016 Rock Placement Pile Dike 71.51 1 Job 1,495,000.00$ 1,495,000.00$ 1,095,000.00$ 1,095,000.00$ -$ -$ 0017 Marker Pile Installation 1 Job 585,000.00$ 585,000.00$ 392,400.00$ 392,400.00$ -$ -$
SUB-TOTAL FOR MANDATORY CLINS 14,060,000.00$ 12,164,800.00$ -$ -$
OPTIONAL CLINS
SUB-TOTAL FOR OPTIONAL CLINS -$ -$ -$ -$
14,060,000.00$ 12,164,800.00$ -$ -$
W071 ENDIST PORTLAND
KO CONTRACTING DIVISION, 333 SW FIRST AVE
PORTLAND, OR 97204-3495
UNITED STATES
ABSTRACT OF OFFERS 1. SOLICITATION NO.
W9127N26BA005
I CERTIFY THAT I HAVE OPENED, READ, AND RECORDED ON THIS ABSTRACT
ALL BIDS RECEIVED IN RESPONSE TO THIS SOLICITATION.
A. OFFEROR
8. GOVERNMENT ESTIMATE
Check A, B, or C, and Complete D, E, and F.)
9. OFFERS
NO.7 NO.8 NO.9
B. REASONABLE CONTRACT
(Without Profit)
B. BID SECURITY
A.HIRED LABOR A. OFFEROR
C. REASONABLE CONTRACT
(including profit)
6. NUMBER OF AMENDMENTS ISSUED: 2
7A.
ITEM
NO.
7B. DESCRIPTION OF OFFERED ITEM
7C. EST
QUANTITY
D.
UNIT
E. UNIT
PRICE
F. AMOUNT
COTTONWOOD PILE DIKE REPAIRS A. OFFEROR
Bergerson Construction, Inc.
X
D.UNIT
PRICE
E. AMOUNT D.UNIT
PRICE
E. AMOUNT
TOTAL FOR ALL CLINS
ACCEPTANCE LIMITATIONS - DAYS
INFORMALITIES
STANDARD FORM 1419 (10-3)
D.UNIT
PRICE
E. AMOUNT
| Offers 1-3 |
| Offers 4-6 |
| Offerors 7-9 |