This document is a combined synopsis and solicitation for commercial services to renew two sets of port or starboard propeller controllable pitch (CPP) blades and hubs with shafts and anodes for the dredge Yaquina. The U.S. Army Corps of Engineers, Portland District is requesting quotes to complete the work in accordance with the attached performance work statement, which specifies replacing propeller blades, hubs, shafts, and other components. The anticipated period of performance is 90 days after receipt of order. Interested vendors must complete the pricing section of Attachment 1 by the response date. This solicitation is set aside for small businesses under NAICS code 336611 with a size standard of 1,250 employees.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MAIN PROPULSION CPP BLADES HUBS & SHAFTING; RENEW
01. General
Renew two (2) set of port or starboard propeller CPP blades and hub with shafts anodes as specified below.
02. References
Drawings: Hundested 0-002-020932-2 – MP700 Propeller Hoved Samling (Port Hub)
Hundested 0-002-020933-2 – MP700 Propeller Hoved Samling (Starboard Hub)
Hundested 1-022-020409-9 – MP700 / CPG120 Installation of Unit 6330 / G1177 (Port Shaft)
Hundested 1-022-021126-2 – MP700/CPG120i Installation of Unit 6331 / G1178 (Starboard Shaft)
Hundested 2-140-021135-1 – MP700 / CPG120 Flange Coupling Assembly
Authorized Hundested Propeller A/S Technical Representative:
Pacific Marine Equipment, LLC
Hundested Propeller US, LLC
925 NW 49th Street, Unit B
Seattle, WA 98107
Office: (206) 281-9841
Cell: (206) 300-2353
Email: todd@pmeseattle.com
Manuals: Hundested Propeller Marine Gear Manual (Manufacturing Number G1177-78)
Standards AWS A5.9, Specification for Bare Stainless Steel Welding Electrodes and Rods
03. GFM
Controllable Pitch Propeller Blades,Port & Starboard Controllable Pitch Propeller Hubs,Port & Starboard Controllable Pitch Propeller Shafts,Port & Starboard
04. Safety Precautions
Follow all applicable state local and federal requirements including those specified in EM-385-1-1 latest revision.
Prior to commencing work, follow vessel’s LOTO policy and procedures.
05. Specifications
Controllable Pitch Propeller Blades Repair
Contractor shall procure the services of a factory authorized Hundested Propeller A/S Technical Representative.
Technical Representative shall have direct supervision for all work performed under this work item
Contractor shall furnish the following materials for propeller blade replacement. Foot seals shall be compatible and certified for use by the OEM and have an ABS Certificate of Inspection and Class Approval.
a. Blade Foot Seals (x 8)
Use care to not damage or scratch the propeller blade and sealing surfaces.
Technical Representative shall inspect all sealing surfaces. Inspect blade foot seals with each blade.
Removed blades shall be protected so they will not be damaged. Bolt the removed blades to the pallets provided with rubber pads from which the replacement blades are removed. Return the removed blades to the U.S. Moorings Logistics Warehouse.
Controllable Pitch Propeller Tail Shaft Repair
Regarding the USACOE Yaquina spare tail shaft. The shaft inspection and repair details are as are as follows:
1. Contractor will transport each tail shaft from the moorings to shop and back again upon completion.
2. Unload and set the shaft up in Lathe.
3. Measure diameter and Total run out.
4. Document all measurements, provide access for ABS, Vigor or ships representative to witness results.
5. Provide a report upon completion of the work.
6. Machine remove four liners on each shaft.
7. NDT Magnaflux inspect the entire shaft.
8. Prepare shaft liner fits for new liners
9. Machine finish ID of four new IPS provided 316 SS liners and install onto shaft
10. Finish machine liners to specified size.
11. Contract with fiberglass application company and apply to three areas on each shaft
12. Inspect document outside diameter and total run out and ship.
Remove and scrap existing shaft sleeves and fiberglass cladding. Remove all paint, rust or other surface coatings to bare metal. Provide magnetic particle or dye penetrant inspection of shafts to ABS standards.
Verify existing shaft dimensions including OD / total indicated run out (TIR) and provide a CFRPT.
Skim cut liner surfaces to remove existing run outs and achieve required surface finish in accordance with
CFRPT.
Fabricate and install new bearing shaft sleeves IAW measured shaft dimensions and dimensions as shown on Drawings 0-002-020932-2 (Port) and 0-002-020933-2 (Starboard).
NOTE: Forward bearing liner location has been modified from original print with new location, 40 mm forward of original with no change to LOA.
Shaft sleeves shall be constructed of 316L SS and pressure tested as required by ABS. Sleeves shall be turned and ground to achieve a concentric surface with a roughness of not more than 12-16 micro inches root-mean square (RMS).
Interference fit of sleeves shall not exceed 0.003”. Machine sleeves for fiberglass seal areas on liners.
Prepare shaft surface, as necessary, and install new Glass Reinforced Plastic (GRP) coating on shafts with a minimum of 4 wraps. GRP shall be spark tested as required by ABS.
Upon final acceptance of shaft assembly, all sleeve areas and hub shall be coated with a preservative coating meeting MIL-C-11796C Class.
Controllable Pitch Propeller Hubs Port & Starboard Repair
Contractor shall procure the services of a factory authorized Hundested Propeller A/S Technical Representative.
Technical Representative shall have direct supervision for all work performed under this work item. Supervise disassembly, repairs, reassembly and testing of hubs and tie rods. Contractor shall provide machinist labor. At a minimum, repairs include the replacement of the following parts:
a. O-ring 259.3 mm x 5.7 mm, Part #201318F (x2);
b. O-ring 439.3 mm x 5.7 mm, Part #205111F (x2);
c. O-ring 59.3 mm x 5.7 mm, Part #201216F (x2);
d. O-ring 69.3 mm x 5.7 mm, Part #201222F (x2);
e. Stainless Steel Lock Wire (x2);
f. Bronze Plugs for Fill / Vent Hub Flange Cover (x4);
g. Blade Feet (x8); and
h. Slipper Blocks (x8);
i. Cross Head (x2); and
j. Tie Rod Head (x2).
The repairs shall also include weld build-up and re-machining of hub bodies (x2) and hub end plates (x2) to manufacturer’s acceptable tolerance.
Hub shall be reassembled with factory-approved grease, approximately 105 lbs per shaft. Complete assembly shall be operated through the full range of motion.
Contractor shall furnish and install the following:
2ea. Enclosed MP700 Hub End Covers
Consisting of:
New, modified, original end cover with relief valve
Additional enclosed end cover with air bladder
Zinc Anode
All mounting hardware and required sealings
Contractor will transport propeller blades, hubs and shafting from the moorings to shop and back again upon completion
06. Testing
Submit ABS-approved certification / statement for proposed Tailshaft Cladding Facility. Facility shall be certified by ABS to perform welding repairs, bearing sleeve replacement and fiberglass work on shipboard propulsion tailshafts.
Perform nondestructive testing (NDT) on all blade bolts IAW original equipment manufacturer (OEM) requirements. Inspection services shall be performed by ABS Certified Personnel.
Demonstrate ability to pitch full ahead / astern pitch prior to undocking. All testing and final adjustments shall be coordinated with the COR, Technical Representative.
07. Inspection / Documentation
Provide product data on blade bolts and foot seals. Provide proof that they are compatible and certified for use with the OEM. Provide ABS Certificate of Inspection and Class Approval.
Within 2 weeks of the work task’s completion, provide a service report from the factory authorized Hundested Propeller A/S Technical Representative.
Inspections shall be witnessed by the COR.
08. CONTRACT ADMINISTRATOR
Contract will be administered by:
Department of the Army, Portland District Corps of Engineers Attn: CENWP-CT-P, Brandon Laisch P. O. Box 2946 Portland, Oregon 97208-2946 Name: Brandon Laisch Telephone: 503-808-4608 E-mail: brandon.m.lasich@usace.army.mil
INVOICE SUBMITTAL:
Submit Original Invoice to:
U.S. Army, COE, Finance Center Attn: CEFC-AO-P 5722 Integrity Drive Millington, TN 38054-5005 One Invoice Copy to Sam Repman, Trista Stark, and Brandon Laisch:
samuel.j.repman@usace.army.mil trista.m.stark@usace.army.mil brandon.m.lasich@usace.army.mil
File details come from the government source that posted it. Updated .