Request for Proposal W9127N19R0046
The Dalles Lock and Dam Klickitat County, Washington
Packing Box and Top Plate
Project Manual
TOC-1
CODE
(Hour)
PAGE(S)
until 02:00 PM local time 06 Sep 2019
X
A
X B
C
D
EX
X
G
F 13 - 18
19 - 24
H 25 - 27 brooke.l.patterson@usace.army .mil
RATING PAGE OF PAGES
7. ISSUED BY
(Date)
IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.
Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)
Prescribed by GSA
FAR (48 CFR) 53.214(c)
1 27
(If other than Item 7)
15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO
AND
ADDRESS
SIGN OFFER (Type or print)
OF
OFFEROR
AMENDMENT NO. DATE
15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS
IS DIFFERENT FROM ABOVE - ENTER
SUCH ADDRESS IN SCHEDULE.
18. OFFER DATE
1. THIS CONTRACT IS A RATED ORDER
UNDER DPAS (15 CFR 700)
2. CONTRACT NO.
W9127N 8. ADDRESS OFFER TO
See Item 7
9. Sealed offers in original and 0 copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in
CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and w w w .fbo.gov upload conditions contained in this solicitation.
10. FOR INFORMATION
CALL:
A. NAME (NO COLLECT CALLS)
BROOKE L PATTERSON 503-808-4618
11. TABLE OF CONTENTS
SOLICITATION/ CONTRACT FORM
SUPPLIES OR SERVICES AND PRICES/ COSTS
2 - 4
X I CONTRACT CLAUSES
DESCRIPTION/ SPECS./ WORK STATEMENT
PACKAGING AND MARKING
J LIST OF ATTACHMENTS
INSPECTION AND ACCEPTANCE
DELIVERIES OR PERFORMANCE
X K
REPRESENTATIONS, CERTIFICATIONS AND
OTHER STATEMENTS OF OFFERORS
CONTRACT ADMINISTRATION DATA 7 X
SPECIAL CONTRACT REQUIREMENTS
OFFER (Must be fully completed by offeror)
X M
L INSTRS., CONDS., AND NOTICES TO OFFERORS
EVALUATION FACTORS FOR AWARD
NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.
is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.
13. DISCOUNT FOR PROMPT PAYMENT
(See Section I, Clause No. 52.232-8)
14. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments
AMENDMENT NO. DATE
to the SOLICITATION for offerors and related documents numbered and dated):
FACILITY
12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period
SOLICITATION, OFFER AND AWARD
X
(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)
PART I - THE SCHEDULE
26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE
EMAIL:TEL: (Signature of Contracting Officer)
CODE CODE
B. TELEPHONE (Include area code) C. E-MAIL ADDRESS
AWARD (To be completed by Government)
19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION
22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:
10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)
23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE
PART IV - REPRESENTATIO NS AND INSTRUCTIO NS
PART III - LIST O F DO CUMENTS, EXHIBITS AND O THER ATTACHMENTS
8 - 12
PART II - CO NTRACT CLAUSES
USACE PORTLAND DISTRICT
333 SW 1ST AVE
PORTLAND OR 97204-3440
FAX:
TEL:
FAX:
TEL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SOLICITATION
6. REQUISITION/PURCHASE NO.5. DATE ISSUED
05 Aug 2019
4. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
[ X ]
3. SOLICITATION NO.
W9127N19R0046
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job
Furnish Packing Box and Top Plate
FFP
This CLIN shall include all materials, labor, and equipment needed to fabricate, machine, and paint one packing box and top plate and deliver to The Dalles Project with all components as specified and required within the provided specifications.
FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0002 1 Job
Furnish Packing Box and Top Plate
FFP
This CLIN shall include all materials, labor, and equipment needed to fabricate, machine, and paint one packing box and top plate and deliver to The Dalles Project with all components as specified and required within the provided specifications.
FOB: Destination
NET AMT
Section B-1
0003 1 Job Furnish Packing Box and Top Plate
FFP
This CLIN shall include all materials, labor, and equipment needed to fabricate, machine, and paint one packing box and top plate and deliver to The Dalles Project with all components as specified and required within the provided specifications.
FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0004 1 Job
Furnish Packing Box and Top Plate
FFP
This CLIN shall include all materials, labor, and equipment needed to fabricate, machine, and paint one packing box and top plate and deliver to The Dalles Project with all components as specified and required within the provided specifications.
FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0005 1 Job
Furnish Packing Box and Top Plate
FFP
This CLIN shall include all materials, labor, and equipment needed to fabricate, machine, and paint one packing box and top plate and deliver to The Dalles Project with all components as specified and required within the provided specifications.
FOB: Destination
Section B-2
0006 1 Job Furnish Packing Box and Top Plate
FFP
This CLIN shall include all materials, labor, and equipment needed to fabricate, machine, and paint one packing box and top plate and deliver to The Dalles Project with all components as specified and required within the provided specifications.
FOB: Destination
Section B-3
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government
0002 Destination Government Destination Government 0003 Destination Government Destination Government
0004 Destination Government Destination Government 0005 Destination Government Destination Government 0006 Destination Government Destination Government
CLAUSES INCORPORATED BY REFERENCE
52.246-2 Inspection Of Supplies--Fixed Price AUG 1996 52.246-16 Responsibility For Supplies APR 1984
Section E-1
Section F - Deliveries or Performance
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 180 dys. ADC 1 THE DALLES DAM
CENWP-OD-D
USACE PORTLAND DISTRICT
I-84 EXIT 88
THE DALLES LOCK AND DAM
THE DALLES OR 97058
FOB: Destination
960410
0002 360 dys. ADC 1 (SAME AS PREVIOUS LOCATION) FOB: Destination
960410
0003 540 dys. ADC 1 (SAME AS PREVIOUS LOCATION) FOB: Destination
960410
0004 720 dys. ADC 1 (SAME AS PREVIOUS LOCATION) FOB: Destination
960410
0005 900 dys. ADC 1 (SAME AS PREVIOUS LOCATION) FOB: Destination
960410
0006 1080 dys. ADC 1 (SAME AS PREVIOUS LOCATION)
FOB: Destination
960410
CLAUSES INCORPORATED BY REFERENCE
52.242-15 Stop-Work Order AUG 1989 52.242-17 Government Delay Of Work APR 1984
52.247-34 F.O.B. Destination NOV 1991
Section F-1
Section G - Contract Administration Data
CONTRACT ADMINISTRATION
Contract will be administered by:
Department of the Army, Portland District
Corps of Engineers P. O. Box 2946 Attn: CECT-NWP-S
Portland, Oregon 97208-2946
Contract Specialist:
Name: Megan Acord Telephone: 503-808-1011
Email: Megan.L.Acord@usace.army.mil
SUCCESSOR CONTRACTING OFFICER
The Contracting Officer who signed this contract is the primary Contracting Officer for the contract. Nevertheless, any Contracting Officer assigned to the Portland District and acting within his/her authority may take formal action on this contract when a contract action needs to be taken and the primary Contracting Officer is unavailable
Section G-1
Section I - Contract Clauses
CLAUSES INCORPORATED BY REFERENCE
52.202-1 Definitions NOV 2013
52.203-3 Gratuities APR 1984 52.203-5 Covenant Against Contingent Fees MAY 2014 52.203-6 Restrictions On Subcontractor Sales To The Government SEP 2006
52.203-7 Anti-Kickback Procedures MAY 2014 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or
Improper Activity
MAY 2014
52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity MAY 2014 52.203-12 Limitation On Payments To Influence Certain Federal
Transactions
OCT 2010
52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements
JAN 2017
52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper
MAY 2011
52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First-Tier
Subcontract Awards
OCT 2018
52.204-13 System for Award Management Maintenance OCT 2018 52.204-22 Alternative Line Item Proposal JAN 2017 52.204-23 Prohibition on Contracting for Hardware, Software, and
Services Developed or Provided by Kaspersky Lab and Other Covered Entities.
JUL 2018
52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment
OCT 2015
52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters
OCT 2018
52.209-10 Prohibition on Contracting With Inverted Domestic
Corporations
NOV 2015
52.211-5 Material Requirements AUG 2000
52.215-2 Audit and Records--Negotiation OCT 2010 52.215-8 Order of Precedence--Uniform Contract Format OCT 1997 52.215-14 Integrity of Unit Prices OCT 2010
52.219-6 (Dev) Notice of Total Small Business Set-Aside (DEVIATION 2019-O0003).
JAN 2019
52.219-8 Utilization of Small Business Concerns OCT 2018
52.219-14 (Dev) Limitations on Subcontracting (DEVIATION 2019-O0003). JAN 2019 52.219-28 Post-Award Small Business Program Rerepresentation JUL 2013
52.222-3 Convict Labor JUN 2003 52.222-19 Child Labor -- Cooperation with Authorities and Remedies JAN 2018 52.222-20 Contracts for Materials, Supplies, Articles, and Equipment
Exceeding $15,000
MAY 2014
52.222-21 Prohibition Of Segregated Facilities APR 2015 52.222-26 Equal Opportunity SEP 2016
52.222-37 Employment Reports on Veterans FEB 2016 52.222-40 Notification of Employee Rights Under the National Labor
Relations Act
DEC 2010
52.222-50 Combating Trafficking in Persons JAN 2019 52.222-54 Employment Eligibility Verification OCT 2015
52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011
Section I-1
52.223-18 Encouraging Contractor Policies To Ban Text Messaging
While Driving
AUG 2011
52.225-13 Restrictions on Certain Foreign Purchases JUN 2008
52.227-1 Authorization and Consent DEC 2007 52.227-2 Notice And Assistance Regarding Patent And Copyright
Infringement
DEC 2007
52.229-3 Federal, State And Local Taxes FEB 2013 52.232-1 Payments APR 1984 52.232-8 Discounts For Prompt Payment FEB 2002
52.232-17 Interest MAY 2014 52.232-23 Assignment Of Claims MAY 2014
52.232-25 Prompt Payment JAN 2017 52.232-33 Payment by Electronic Funds Transfer--System for Award
Management
OCT 2018
52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.232-40 Providing Accelerated Payments to Small Business
Subcontractors
DEC 2013
52.233-1 Disputes MAY 2014 52.233-3 Protest After Award AUG 1996
52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.237-2 Protection Of Government Buildings, Equipment, And
Vegetation
APR 1984
52.242-13 Bankruptcy JUL 1995 52.243-1 Changes--Fixed Price AUG 1987 52.244-6 Subcontracts for Commercial Items JAN 2019
52.249-2 Termination For Convenience Of The Government (Fixed- Price)
APR 2012
52.249-8 Default (Fixed-Price Supply & Service) APR 1984 52.253-1 Computer Generated Forms JAN 1991 252.201-7000 Contracting Officer's Representative DEC 1991
252.203-7000 Requirements Relating to Compensation of Former DoD Officials
SEP 2011
252.203-7001 Prohibition On Persons Convicted of Fraud or Other Defense-
Contract-Related Felonies
DEC 2008
252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013
252.204-7000 Disclosure Of Information OCT 2016 252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7012 Safeguarding Covered Defense Information and Cyber
Incident Reporting
OCT 2016
252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support
MAY 2016
252.209-7004 Subcontracting With Firms That Are Owned or Controlled By The Government of a Country that is a State Sponsor of
Terrorism
OCT 2015
252.223-7006 Prohibition On Storage, Treatment, and Disposal of Toxic or Hazardous Materials
SEP 2014
252.225-7001 Buy American And Balance Of Payments Program-- Basic DEC 2017 252.226-7001 Utilization of Indian Organizations and Indian-Owned
Economic Enterprises, and Native Hawaiian Small Business
Concerns
SEP 2004
252.232-7003 Electronic Submission of Payment Requests and Receiving
Reports
DEC 2018
252.232-7010 Levies on Contract Payments DEC 2006 252.243-7001 Pricing Of Contract Modifications DEC 1991
252.243-7002 Requests for Equitable Adjustment DEC 2012
Section I-2
252.244-7000 Subcontracts for Commercial Items JUN 2013
252.247-7023 Transportation of Supplies by Sea FEB 2019
CLAUSES INCORPORATED BY FULL TEXT
52.222-35 EQUAL OPPORTUNITY FOR VETERANS (OCT 2015)
(a) Definitions. As used in this clause--
``Active duty wartime or campaign badge veteran,'' ̀ `Armed Forces service medal veteran,'' ̀ `disabled veteran,'' ``protected veteran,'' ̀ `qualified disabled veteran,'' and ̀ `recently separated veteran'' have the meanings given at FAR
22.1301.
(b) Equal opportunity clause. The Contractor shall abide by the requirements of the equal opportunity clause at 41
CFR 60-300.5(a), as of March 24, 2014. This clause prohibits discrimination against qualified protected veterans, and requires affirmative action by the Contractor to employ and advance in employment qualified protected veterans.
(c) Subcontracts. The Contractor shall insert the terms of this clause in subcontracts of $150,000 or more unless exempted by rules, regulations, or orders of the Secretary of Labor. The Contractor shall act as specified by the Director, Office of Federal Contract Compliance Programs, to enforce the terms, including action for noncompliance. Such necessary changes in language may be made as shall be appropriate to identify properly the parties and their undertakings.
(End of clause)
52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUL 2014)
(a) Equal opportunity clause. The Contractor shall abide by the requirements of the equal opportunity clause at 41
CFR 60-741.5(a), as of March 24, 2014. This clause prohibits discrimination against qualified individuals on the basis of disability, and requires affirmative action by the Contractor to employ and advance in employment qualified individuals with disabilities.
(b) Subcontracts. The Contractor shall include the terms of this clause in every subcontract or purchase order in excess of $15,000 unless exempted by rules, regulations, or orders of the Secretary, so that such provisions will be binding upon each subcontractor or vendor. The Contractor shall act as specified by the Director, Office of Federal Contract Compliance Programs of the U.S. Department of Labor, to enforce the terms, including action for noncompliance. Such necessary changes in language may be made as shall be appropriate to identify properly the parties and their undertakings.
(End of clause)
52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
Section I-3
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
FAR: https://farsite.hill.af.mil/ DFARS: http://farsite.hill.af.mil/vmdfara.htm
AFARS: http://farsite.hill.af.mil/vmafara.htm
(End of clause)
52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (APR 1984)
(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of"(DEVIATION)" after the date of the clause.
(b) The use in this solicitation of any Defense Federal Acquisition Regulation Supplement (48 CFR Chapter 2) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
(End of clause)
INCREMENTALLY-FUNDED CLAUSE
(a) Funds are not available at the inception of this contract to cover the entire contract price. The liability of the Government is limited by this clause notwithstanding any contrary provision of the "Payments to Contractor" clause, or any other clause of this contract, except the Termination for Convenience clause.
(b) Pursuant to the authority of 33 U.S.C. § 621 and 16 U.S.C. § 839d-1, this contract is incrementally funded on a fiscal year basis by the Bonneville Power Administration (BPA). Funds are not available at the inception of this contract to cover the entire contract price. The sum of $153,000.00 has been reserved under this contract by the Corps and is available for payment to the contractor during the current fiscal year. In accordance with the
Memorandum of Agreement (MOA) between BPA and the Department of the Army (Contract No. DE MS79- 94BP94655), the Sub-agreement 13GS-75438 between the Corps and BPA sets the total funding requirements for project construction and the annual funding requirements. The Corps has agreed to perform the work specified within the estimated annual funding requirements and shall coordinate with BPA in updating funding requirements.
The liability of the Corps for payments beyond the funds currently reserved under this contract is contingent on the availability of additional funds from BPA under the MOA and Sub-agreement.
(c) Failure to make payments in excess of the amount currently reserved, or that may be reserved from time to time, shall not be considered a breach of this contract, and shall not entit le the contractor to a price adjustment under the terms of this contract.
(d) Contingent upon additional funds being provided by BPA to the Corps, the contracting officer may at any time reserve additional funds for payments under this contract by issuing an administrative change to the contract.
(e) If earnings will be such that funds reserved for this contract will be exhausted before the end of the fiscal year, the contractor shall give written notice to the contracting officer of the estimated date of exhaustion and the amount of additional funds which will be needed to meet payments due or to become due under this contract during that fiscal year. The contractor shall give the notice not less than 45 or more than 60 days prior to the estimated date of exhaustion.
(f) Upon receipt of the contractor’s notice under paragraph (e), the contracting officer shall promptly provide written notice to the contractor that the Corps is -
Section I-4
(1) Increasing the Corps’ reservation of funds under this contract in a specified amount; or
(2) Reducing the scope of work or terminating the contract; or
(3) Unable to reserve additional funds until the following fiscal year.
(g) No payments will be made after exhaustion of funds except to the extent that additional funds are reserved for the contract. Any suspension, delay, or interruption of work arising from exhaustion or anticipated exhaustion of funds shall not constitute a breach of this contract and shall not entitle the contractor to any price adjustment under a “Suspension of Work” or similar clause or in any other manner under this contract.
(h) An equitable adjustment in performance time shall be made for any increase in the time required for performance of any part of the work arising from exhaustion of funds or the reasonable anticipation of the exhaustion of funds.
(i) If, upon the expiration of sixty (60) days after the beginning of the fiscal year following an exhaustion of funds, the Corps has failed to reserve sufficient additional funds to cover payments otherwise due, the contractor, by written notice delivered to the contracting officer at any time before such additional funds are reserved, may elect to treat his right to proceed with the work as having been terminated. Such a termination shall be at no cost to the
Corps, except that, to the extent that additional funds to make payment therefore are allocated to this contract, it may be treated as a termination for the convenience of the Government.
(j) If at any time it becomes apparent that the funds reserved for any fiscal year are in excess of the funds required to meet all payments due or to become due the contractor because of work performed and to be performed under this contract during the fiscal year, the Corps reserves the right, by modification to the contract, to reduce said reservation by the amount of such excess.
(k) The term “Reservation” means funds that have been set aside and made available for payment under this contract by the Corps.
(End of clause)
Section I-5
The Dalles Packing Box and Top Plate
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 22 00.00 25 MEASUREMENT AND PAYMENT
01 33 00 SUBMITTAL PROCEDURES
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.15 25 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 78 39.00 25 PROJECT RECORD DOCUMENTS
DIVISION 05 - METALS
05 50 03.00 26 METALWORK FABRICATION, MACHINE WORK, MISCELLANEOUS
PROVISIONS
DIVISION 09 - FINISHES
09 97 02.00 26 PAINTING: HYDRAULIC STRUCTURES
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION J-1
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00.00 25
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 GENERAL INFORMATION
1.2 UNIT PRICE PAYMENT ITEMS
1.3 JOB PAYMENT ITEMS
1.4 MEASURE AND PAYMENT
1.4.1 Furnish Packing Box and Top Plate, CLIN 0001
1.4.2 Furnish Packing Box and Top Plate, CLIN 0002
1.4.3 Furnish Packing Box and Top Plate, CLIN 0003
1.4.4 Furnish Packing Box and Top Plate, CLIN 0004
1.4.5 Furnish Packing Box and Top Plate, CLIN 0005
1.4.6 Furnish Packing Box and Top Plate, CLIN 0006
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
-- End of Section Table of Contents --
SECTION 01 22 00.00 25 Page 1
SECTION J-2
SECTION 01 22 00.00 25
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 GENERAL INFORMATION
In each instance, the Contract price for an item will constitute full compensation as herein specified, as shown, or as otherwise approved. The Contract price and payment will also constitute full compensation for all work incidental to completion of the item, unless such work is otherwise specifically mentioned for separate payment under another line item. In the event any work is required by the specifications Sections or by the Drawings and not specifically mentioned in the measurement and payment paragraphs, separate or direct payment will not be made and all costs thereof are incidental to the work and included in the Contract prices and payments for all Contract Line Item Numbers (CLIN) listed in the price schedule.
1.2 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this Contract on which the Contract unit price payments will be made are listed in Section 00 10 00, PRICE SCHEDULE, and described below. The unit price and payment made for each item listed will constitute full compensation for furnishing all plant, labor, materials, and equipment; performing all associated Contractor quality control, environmental protection, commissioning, preparation of working as-built drawing redlines, O&M manuals, tests and reports, meeting safety requirements; and for performing all work required for each of the unit price items.
1.3 JOB PAYMENT ITEMS
Payment items for the work of this Contract for which Contract job payments will be made are listed in Section 00 10 00, PRICE SCHEDULE, and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job item, must be included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed will constitute full compensation for furnishing all plant, labor, materials, and equipment;
performing all associated Contractor quality control, environmental protection, commissioning, preparation of working as-built drawing redlines, O&M manuals, tests and reports, meeting safety requirements; and for performing all work required for which separate payment is not otherwise provided. Provide a schedule of values for job items prior to the first pay request. Update with each subsequent payment request.
1.4 MEASURE AND PAYMENT
1.4.1 Furnish Packing Box and Top Plate, CLIN 0001
Payment will be made on a per job basis under CLIN 0001. Payment shall include all materials, labor, and equipment needed to fabricate, machine, and paint one packing box and top plate assembly and deliver to The Dalles Project with all components as specified and required.
SECTION 01 22 00.00 25 Page 2
SECTION J-3
1.4.2 Furnish Packing Box and Top Plate, CLIN 0002
Payment will be made on a per job basis under CLIN 0002. Payment shall include all materials, labor, and equipment needed to fabricate, machine, and paint one packing box and top plate and deliver to The Dalles Project with all components as specified and required.
1.4.3 Furnish Packing Box and Top Plate, CLIN 0003
Payment will be made on a per job basis under CLIN 0003. Payment shall include all materials, labor, and equipment needed to fabricate, machine, and paint one packing box and top plate and deliver to The Dalles Project with all components as specified and required.
1.4.4 Furnish Packing Box and Top Plate, CLIN 0004
Payment will be made on a per job basis under CLIN 0004. Payment shall include all materials, labor, and equipment needed to fabricate, machine, and paint one packing box and top plate and deliver to The Dalles Project with all components as specified and required.
1.4.5 Furnish Packing Box and Top Plate, CLIN 0005
Payment will be made on a per job basis under CLIN 0005. Payment shall include all materials, labor, and equipment needed to fabricate, machine, and paint one packing box and top plate and deliver to The Dalles Project with all components as specified and required.
1.4.6 Furnish Packing Box and Top Plate, CLIN 0006
Payment will be made on a per job basis under CLIN 0006. Payment shall include all materials, labor, and equipment needed to fabricate, machine, and paint one packing box and top plate and deliver to The Dalles Project with all components as specified and required.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
-- End of Section --
SECTION 01 22 00.00 25 Page 3
SECTION J-4
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 GENERAL INFORMATION
1.2 SUBMITTALS
1.3 DEFINITIONS
1.3.1 Submittal Descriptions (SD)
1.3.2 Approving Authority
1.3.3 Work
1.4 SUBMITTAL DESIGNATION
1.5 SUBMITTAL REGISTER
1.5.1 Maintain Submittal Register
1.5.2 Use of Submittal Register
1.5.3 Government Approved Submittals
1.5.3.1 Quantity of Submittals
1.5.3.2 Processing of "G" Submittals.
1.5.4 Information Only Submittals
1.5.4.1 General
1.5.4.2 Processing of Information Only Submittals
1.6 SUBMITTAL COORDINATION
1.6.1 Submittal Coordination Meeting
1.6.2 Submittal Register ENG Form 4288-R
1.7 SCHEDULING
1.8 TRANSMITTAL FORM (ENG FORM 4025-R)
1.9 CROSS-REFERENCE (ENG FORM 4288-R/ENG FORM 4025-R)
1.10 SUBMITTAL PROCEDURES
1.10.1 Approval of Submittals by the Contractor
1.10.2 Drawings
1.10.2.1 Printed Material
1.11 PURCHASE ORDERS
1.12 CERTIFICATES OF COMPLIANCE
1.13 DISAPPROVED SUBMITTALS
1.14 APPROVED SUBMITTALS
1.15 APPROVED SAMPLES
1.16 CONTRACTOR'S FILES
1.17 PAYMENT
1.18 WITHHOLDING OF PAYMENT
1.19 CONTRACTOR APPROVAL STAMP
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
-- End of Section Table of Contents --
SECTION 01 33 00 Page 1
SECTION J-5
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 GENERAL INFORMATION
a. Make submittals as required by the Specifications. The Contracting Officer (CO) may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective Sections.
b. Use the same units of weights and measures on all submittals as those used in the Contract Drawings.
c. Each submittal must be complete and in sufficient detail to allow ready determination of compliance with Contract requirements.
d. Proposed deviations from the Contract requirements must be clearly identified. Submittals must include items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.
e. Submittals requiring Government approval must be scheduled and approved prior to the acquisition of the material or equipment covered thereby.
f. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Safety Data Sheets (SDS) and in compliance with existing laws and regulations.
g. Submittals requiring professional licensure, signature, and stamp must comply with all State professional licensing and registration requirements.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. Submit the following in accordance with this Section:
SD-01 Prefabrication Submittals
Submittal Register; G
SD-07 Certificates
Authorized Shop Drawing Approvers
SECTION 01 33 00 Page 2
SECTION J-6
1.3 DEFINITIONS
1.3.1 Submittal Descriptions (SD)
Submittal requirements are specified in the technical Sections and in the preliminary submittal register (ENG Form 4288-R, Attachment A1).
Submittals are identified by Submittal Description (SD) numbers and titles as follows:
SD-02 Shop Drawings
Drawings, diagrams, and schedules specifically prepared to illustrate some portion of the work.
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.
Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance, and other characteristics of materials, systems, or equipment for some portion of the work.
Warranty language when the Contract requires extended product warranties.
SD-04 Samples
Fabricated or unfabricated physical examples of materials, equipment, or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.
Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.
Field samples and mock-ups constructed on the project site establish standards by which the ensuing work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product, or system identical to the material, product, or system to be provided has been tested in accordance with specified requirements. (Testing must have been within three years of date of Contract award for the project.)
Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.
SECTION 01 33 00 Page 3
SECTION J-7
Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports.
Daily logs and checklists.
Final acceptance test and operational test procedure.
Any reports required by the CO or designated representative to assure successful completion of tasks during the life of the Contract.
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system, or material attesting that product, system, or material meets specification requirements. Must be dated after award of project Contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, installer, or subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.
Confined space entry permits.
Text of posted operating instructions.
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
Special requirements necessary to properly close out a Contract. For example, Record Drawings and as-built drawings.
1.3.2 Approving Authority
Office or designated person authorized to approve submittal.
1.3.3 Work
As used in this Section, on- and off-site fabrication required by Contract documents, including labor necessary to produce submittals (except those SD-01 Prefabrication Submittals noted above) fabrication, materials, products, equipment, and systems incorporated or to be incorporated in such fabrication.
1.4 SUBMITTAL DESIGNATION
Submittals are classified as follows:
a. Government Approved (G). They are considered to be "shop drawings."
b. Information Only. Submittals not requiring Government approval will be for information only. These submittals are not considered to
SECTION 01 33 00 Page 4
SECTION J-8
be "shop drawings."
1.5 SUBMITTAL REGISTER
1.5.1 Maintain Submittal Register
a. Prepare and maintain Submittal Register, ENG Form 4288-R, , as the work progresses. Do not change data which is output in columns (c), (d), (e), and (f) as delivered by Government; retain data which is output in columns (a), (g), (h), and (i) as approved. This list may not be all inclusive and additional submittals may be required.
b. The Government will provide the preliminary submittal register in electronic format with the following fields completed, to the extent that will be required by the Government during subsequent usage.
Column (c): Lists Specification Section in which submittal is required.
Column (d): Lists each submittal description (SD No. and type, e.g. SD-02 Shop Drawings) required in each Specification Section.
Column (e): Lists one principal paragraph in Specification Section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting project requirements.
c. Thereafter, track all submittals by maintaining a complete list, including completion of all data columns, including dates on which submittals are received and returned by the Government.
1.5.2 Use of Submittal Register
Submit submittal register with project schedule. Verify that all submittals required for work are listed and add missing submittals.
Coordinate, update, and complete the fields on the submitted register in RMS CM with the project schedule and QC plan.
1.5.3 Government Approved Submittals
1.5.3.1 Quantity of Submittals
SD-01, SD-02, SD-03, and SD-05 through SD-11 submittals: ENG 4025-R transmittal forms (Attachment A2). SD-04 submittals: Submit two samples of "G" submittals with two corresponding ENG 4025-R transmittal forms, unless otherwise specified. Upon completion of review, "G" submittal copies will be marked with an action code, dated, and returned to the Contractor as specified below:
1.5.3.2 Processing of "G" Submittals.
a. Submittals will be reviewed and processed as follows:
(1) Approved as Submitted (Action Code "A"): Submittals which can be approved without correction will be stamped "Approved" and to the Contractor.
(2) Approved, Except as Noted on Drawings (Action Code "B"):
Submittals which have only minor discrepancies will be annotated
SECTION 01 33 00 Page 5
SECTION J-9
in red to indicate necessary corrections. Marked material will be stamped "Approved Except as Noted" and to the Contractor for correction.
(3) Approved, Except as Noted on Drawings, Resubmission Required (Action Code "C"): Submittals which are incomplete or require more than minor corrections will be annotated in red to indicate necessary corrections. Marked material will be stamped "Approved Except as Noted - Resubmission Required" and to the Contractor for correction. Resubmittal of only those items needing correction required.
(4) Will be Returned by Separate Correspondence (Action Code "D"): Submittals will be addressed by Serial Letter and the Contractor must respond according to instructions in the letter.
(5) Disapproved (Action Code "E"): Submittals which are fundamentally in error, cover wrong equipment or fabrication, or require extensive corrections, will be returned to the Contractor stamped "Disapproved." to the Contractor and an explanation will be furnished on the submitted material or on ENG Form 4025-R indicating reason for disapproval. Complete resubmittal required.
(6) Receipt Acknowledged (Action Code "F"): Submittals stamped "Receipt Acknowledged" are complete and to the Contractor.
(7) Other (Specify) (Action Code "G"): Submittals requiring other specific action will be stamped "Other (Specify)" and returned with a description in the Remarks section. to the Contractor.
Resubmittal of only those items needing correction required.
(8) Receipt Acknowledged, Does Not Comply (Action Code "X"):
Submittals which have been received but do not comply with Contract requirements. to the Contractor stamped "Receipt Acknowledged, Does Not Comply" and an explanation will be furnished. Corrective action and resubmittal required.
b. Resubmittal will not be required for approved submittals unless subsequent changes are made by Contractor or by Contract modification. For submittals required to be resubmitted, make corrections required, note any changes by dating the revisions to correspond with the change request date, and promptly resubmit the corrected material. Resubmittals must be associated with the "parent" by use of sequential . Government costs incurred after the first resubmittal may be charged to the Contractor.
1.5.4 Information Only Submittals
1.5.4.1 General
Normally information only submittals will not be returned. Government approval is not required on information only submittals. These submittals will be used for information purposes. The Government reserves the right to require the Contractor to resubmit any item found not to comply with the Contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the CO from requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish samples for testing by the Government
SECTION 01 33 00 Page 6
SECTION J-10
laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.
1.5.4.2 Processing of Information Only Submittals
Submit information only submittals prior to delivery of the material or equipment to the job site. ENG Form 4025-R must be marked with the words "Contractor approved - information copy only" in the REMARKS block of the form. Submittals will be monitored and spot checks made. When such checks indicate noncompliance, the Contractor will be notified by the same method used for Government Approval submittals. Resubmittal of nonconforming information only submittals must be reclassified Government Approval ("G") and re-submitted for approval.
1.6 SUBMITTAL COORDINATION
1.6.1 Submittal Coordination Meeting
Meet with the CO, after the prefabrication conference and before any submittals are sent to the CO, to further develop the preliminary submittal register (ENG Form 4288-R). During the meeting identify and group all required items into the categories as shown in paragraph entitled SUBMITTAL DESIGNATION.
1.6.2 Submittal Register ENG Form 4288-R
Coordinate the submittal register with the progress schedule and submit within 30 days of Notice to Proceed. In preparing the final document, allow a minimum of 30 days for review and approval, and possible resubmittal of each item on the register.
1.7 SCHEDULING
Schedule and submit concurrently submittals covering component items forming a system or items that are interrelated. Adequate time (a minimum of 30 calendar days) must be allowed and shown on the register for Government review and approval. No delay damages or time extensions will be allowed for time lost in late submittals.
a. Coordinate scheduling, sequencing, preparing, and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential resubmittal of requirements.
b. Submittals called for by the Contract documents must be listed on the register. Approval by the CO does not relieve the Contractor of supplying submittals required by the Contract documents but which have been omitted from the register.
c. Re-submit register and annotate monthly with actual submission and approval dates. When all items on the register have been fully approved, no further re-submittal is required.
d. Carefully control procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Submittal Register."
SECTION 01 33 00 Page 7
SECTION J-11
1.8 TRANSMITTAL FORM (ENG FORM 4025-R)
Use the sample transmittal form (ENG Form 4025-R, Attachment A2) for submitting both Government Approval and Information Only submittals in accordance with the instructions on the reverse side of the form. These forms are included in the RMS CM software that the Contractor is required to use for this Contract, per Section 01 45 00.15 25, RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM). Fill forms in completely prior to submittal. Exercise special care to ensure proper listing of the specification paragraph number(s) and Contract Drawing sheet number(s) pertinent to the data submitted for each item. List each submittal item separately on the form, naming subcontractor, supplier, or manufacturer;
applicable specification paragraph number(s); drawing/sheet number; pay item number; and any other information needed to identify the item, define its use, and locate it in the work. One or more ENG 4025-R forms may be used per Specification Section, however, DO NOT include more than one Specification Section per transmittal.
1.9 CROSS-REFERENCE (ENG FORM 4288-R/ENG FORM 4025-R)
To provide a cross-reference between the approved submittal register and transmittal forms, the Contractor must record the "transmittal numbers" assigned when submitting items in column "Transmittal No." of the ENG Form 4288-R. The numbers in column "Transmittal No." of the submittal register must correspond to the column "Item No." on ENG Form 4025-R.
1.10 SUBMITTAL PROCEDURES
Upload submittals in accordance with subparagraphs entitled Government Approved Submittals and Information Only Submittals, unless indicated otherwise in the technical specifications. Submit a complete collated "reviewers copy" with one ENG 4025-R form and attachments (not originals). Submit hard copy and electronic copies of Record (as-built) Drawings and O&M Manuals in accordance with the applicable Specification Sections.
1.10.1 Approval of Submittals by the Contractor
a. Submit names and titles of Contractor Authorized Shop Drawing Approvers to the CO with the ENG Form 4288-R. Supplier or subcontractors certifications are not acceptable as meeting this requirement.
b. Before submittal to the CO, the Contractor's Authorized Shop Drawing Approvers must review and correct shop drawings prepared by subcontractors, suppliers, and itself, for completeness and compliance with Drawings and Specifications. Do not use red markings for correcting material to be submitted. Red markings are reserved for CO's use.
c. Submittals for Government Approval must first be Contractor-approved and stamped, see paragraph entitled CONTRACTOR
APPROVAL STAMP.
d. Submittals not conforming to the requirements of this Section will be returned to the Contractor for correction and resubmittal.
SECTION 01 33 00 Page 8
SECTION J-12
1.10.2 Drawings
Each drawing must be not larger than D size (22 inches high by 34 inches wide), include a title block in lower right hand corner, and a 3- by 4-inch clear area adjacent. The title block must contain vendor's name, Contract number, description of item(s), Contract line item number, and a revision block. Separate drawings are required for each Contract line item. Where drawings are submitted for assemblies of more than one piece of equipment or systems, of components dependent on each other for compatible characteristics, complete information must be submitted on all such related components at the same time. The information must be complete and the sequence of drawing submittal must be such that all information is available for reviewing each drawing. Drawings for all items and equipment, of special manufacture or fabrication, must consist of complete assembly and detail drawings. All revisions after initial submittal must be shown by number, date, and subject in revision block.
Any drawing submitted, that is not of satisfactory quality, will be returned and must be corrected and re-submitted.
1.10.2.1 Printed Material
All requirements for shop drawings apply to catalog cuts, illustrations, printed specifications, or other data submitted, except the 3- by 4-inch clear area adjacent to the title block is not mandatory. Mark out inapplicable portions of the documents. Applicable items such as model numbers, sizes, and accessories must be indicated by arrow or highlighted.
1.11 PURCHASE ORDERS
a. Each purchase order issued by the Contractor for materials and equipment to be incorporated into the work must:
(1) Clearly identify the applicable Contract number
(2) Carry an identifying number
(3) Be in sufficient detail to identify the material being purchased
(4) Indicate a definite delivery date.
b. Furnish copies of purchase orders to the CO when the Contractor requests assistance for expediting deliveries of equipment or materials, or when requested by the CO for the purpose of quality assurance review.
1.12 CERTIFICATES OF COMPLIANCE
Submit of certificates required for demonstrating proof of compliance of materials with specification requirements. Each certificate must be signed by an official authorized to certify on behalf of the manufacturing company, contain the name and address of the Contractor, the project name and location, and the quantity and date or dates of shipment or delivery to which the certificates apply. Copies of laboratory test reports submitted with certificates must contain the name and address of the testing laboratory and the date or dates of the tests to which the report applies. Certification shall not be construed as relieving the Contractor from furnishing satisfactory material if, after tests are performed on selected samples, the material is found not to meet the specific
SECTION 01 33 00 Page 9
SECTION J-13
requirements.
1.13 DISAPPROVED SUBMITTALS
a. Make all corrections required by the CO and promptly furnish a corrected submittal in the form specified for the initial submittal.
If the Contractor considers any correction or notation on the returned submittals to constitute a change to the Contract drawings or Specifications; notice as required under Contract Clause 52.243-4, CHANGES, is to be given to the CO. The Contractor must be responsible for the dimensions and design of connection details and fabrication of work. Failure to point out deviations may result in the Government requiring rejection and removal of such work at the Contractor's expense.
b. If changes are necessary to submittals, make such revisions and re-submit the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.
1.14 APPROVED SUBMITTALS
a. The CO's approval or acceptance of submittals shall not be construed as a complete check, and indicates only that .
b. Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor must be responsible for dimensions, the design of adequate connections and details, and the satisfactory fabrication of all work.
c. After submittals have been approved by the CO, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.
1.15 APPROVED SAMPLES
a. Approval of a sample is only for the characteristics or use named in such approval and must not be construed to change or modify any Contract requirements. Before submitting samples, ensure that the materials or equipment will be available in quantities required. No change or substitution will be permitted after a sample has been approved.
b. If requested, approved and/or disapproved samples, including those which may be damaged in testing, will be returned at the expense of the Contractor upon completion of the Contract.
c. Failure of any materials to pass the specified tests will be sufficient cause for refusal to consider, under this Contract, any further samples of the same brand or make of that material.
Government reserves the right to disapprove any material or equipment which previously has proved unsatisfactory in service.
d. Samples of various materials or equipment delivered on the site or in place may be taken by the CO for testing.
This is the start of the file's text. The full file is on GovTribe.