A.01.29_Finalspecs_(2).pdf

PDF 1 MB Posted

Attached to
Purchase & Delivery of Bulkheads for Bonneville Powerhouse 2, Bonneville Lock & Dam, Oregon
Solicitation number
W9127N-16-R-0031-1
Issued by

About this file

This posting simply replaces the original 'final specs' posted with this version. The only change is on the cover page where now the solicitation number is shown as opposed to the orginal where XX's were identifed.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR PROPOSAL

W9127N-16-R-0031

BONNEVILLE POWERHOUSE PROJECT

BONNEVILLE POWERHOUSE 2 DRAFT TUBE

BULKHEADS

PROJECT MANUAL

Bonneville Powerhouse 2 Draft Tube Bulkheads

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00.00 25 SUMMARY OF WORK

01 33 00 SUBMITTAL PROCEDURES

01 45 00.00 25 QUALITY CONTROL

DIVISION 05 - METALS

05 56 09.00 26 BULKHEAD SEALS

05 59 13.01 26 FABRICATION OF HYDRAULIC STEEL STRUCTURES

DIVISION 09 - FINISHES

09 97 02.13 26 PAINTING - HYDRAULIC STRUCTURES

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 11 00.00 25

SUMMARY OF WORK

PART 1 GENERAL

1.1 SUMMARY

1.2 REFERENCES

1.3 SUBMITTALS

1.4 WORK COVERED BY CONTRACT DOCUMENTS

1.4.1 Project Description

1.4.2 Location

1.5 CONTRACT END DATE

1.6 CONTRACT DRAWINGS

1.7 OCCUPANCY OF PREMISES

1.8 EXISTING WORK

1.9 ACCESS AGREEMENT

1.10 DECK ACCESS RESTRICTIONS

1.11 SECURITY PROCEDURES

1.12 CONTRACTOR'S EQUIPMENT

1.12.1 Movement of Equipment by the Contractor

1.12.2 Delivery of Bulkheads

1.13 CONTRACTOR USE OF GOVERNMENT CRANES

1.14 CONTRACTOR'S HEAVY EQUIPMENT SAFETY

1.15 CONTRACTOR'S HEAVY EQUIPMENT

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

-- End of Section Table of Contents --

01 11 00.00 25-i

SECTION 01 11 00.00 25

SUMMARY OF WORK

PART 1 GENERAL

1.1 SUMMARY

This Section provides a summary of the various Contract work elements and their relationship to each other. This summary describes work activities within interim construction completion date. This Section does not provide the technical detail for particular work activities, but describes the work as a whole, providing overall perspective to the separate tasks and their interrelationships. Use this Section in conjunction with all the Specification Sections and the Drawings to establish the total work requirements.

1.2 REFERENCES

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS

(AASHTO)

AASHTO LRFDUS (2014) AASHTO LRFD Bridge Design Specifications - Seventh Edition;

Incorporates 2015 Interim Revisions

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. The following must be submitted in accordance with Section 01 33 00, SUBMITTAL

PROCEDURES:

SD-01 Pre-work Submittals

Access and Delivery Plan; G

1.4 WORK COVERED BY CONTRACT DOCUMENTS

1.4.1 Project Description

The work includes procuring necessary materials, fabrication and painting of the draft tube bulkheads, verifying that the dimensions and tolerances shown in the plans have been met, delivery of the draft tube bulkheads to Bonneville Powerhouse 2, an onsite functionality test within the bulkhead slots and incidental related work. This effort is to include all associated works required and described within this Contract package.

01 11 00.00 25-1

1.4.2 Location

The deliveries and site work shall be located at Bonneville Powerhouse 2.

Access to the work site for personnel and for deliveries must be via Highway 14 (Washington state side) to gain access to the Bonneville Dam project . No traffic will be allowed across the Bonneville Dam project from the Oregon state side.

1.5 CONTRACT END DATE

All submittals, As-Build Drawings, and all other requirements must be submitted and approved.

1.6 CONTRACT DRAWINGS

a. The Drawings that accompany these Specifications are a part thereof.

b. One set of full size Contract drawings, maps, and Specifications will be furnished to the Contractor without charge. Reference publications will not be furnished.

c. Immediately check furnished Drawings and notify the Government of any discrepancies.

1.7 OCCUPANCY OF PREMISES

Bonneville Lock and Dam will continue with scheduled operations during the execution of this Contract. Cordination with project personnel will be required to avoid unnecessary delays or conflicts with planned operations.

1.8 EXISTING WORK

Use reasonable care to avoid damaging existing buildings, equipment, and vegetation on the Government installation.

1.9 ACCESS AGREEMENT

a. Submit an Access and Delivery Plan to and from the work site after the Contractor and the Contract Officer have coordinated and determined the most advantageous access to, and staging of, the Contractor's assets deployed to the work site.

b. This Access and Delivery Plan should take into account the clearance of the onsite Gantry Crane and the delivery truck. The Gantry Crane has a 12' clearnace between the top of the deck and the bottom of a stoplog in the fully raised position. The access and delivery plan should take this into account.

c. The right-of-way for the work (or delivery site) and access thereto will be furnished as stated in this paragraph subject to mutual agreement between the Contractor and the Government concerning the specific route the Contractor is to use. Such mutual agreement shall be reached prior to delivery or assembly.

d. The existing access roadway and any associated access roads on the Project, shall not be closed as a result of delivery or assembly activities associated with this Contract unless previously coordinated and approved by the Government. Traffic delays will only be permitted

01 11 00.00 25-2 in accordance with the provisions of this Section.

e. When necessary to operate on or to cross existing highways or roads, all necessary permits shall be obtained from the appropriate private or public authority.

f. In accordance with EM 385-1-1, and the accident prevention plan per EM 385-1-1 Appendix A, Minimum Basic Outline for Accident Prevention Plans, safeguards shall be provided to safely control and direct traffic when necessary for equipment to operate on or cross access roads.

g. Spillage on Project roads and state or county roads will not be permitted, and the spillage shall be immediately cleaned up at the expense of the Contractor.

h. No cleated or crawler-type equipment shall be operated on paved surfaces.

i. Damage to all roads caused by the Contractor's operations shall be repaired to preexisting conditions at the expense of the Contractor.

1.10 DECK ACCESS RESTRICTIONS

Do not block operational areas of the deck gantry crane at any time. With prior coordination and approval, the deck gantry crane may be blocked for a period no longer than four hours. One lane of traffic shall be left open at all times.

1.11 SECURITY PROCEDURES

a. All Contractor personnel, subcontractor personnel, etc. must comply with the Project's security policies. Costs associated with Contractor failure to comply with the Project security policies shall be at the expense of the Contractor.

b. The CO or designated representative will brief the Contractor on security procedures. Any such procedures will not be the basis for claims for additional money or time. The Project areas off limits to Contractor personnel will also be designated.

1.12 CONTRACTOR'S EQUIPMENT

1.12.1 Movement of Equipment by the Contractor

a. Unless otherwise noted, any vehicle crossing a project bridge is limited to AASHTO LRFDUS, HL-93 vehicle and load requirements. Submit a loading diagram for approval showing wheel loads, wheel spacing, and travel speed a minimum of 21 days prior to operating any equipment or vehicles in excess of 72,000 pounds gross vehicle weight (GVW) and axle loads of 32,000 pounds. Prior coordination and approval for such loads shall be obtained before proceeding. No exclusion trucks, multi-axle specialized hauling vehicles (SHV) or mobile cranes will be allowed on a bridge deck without prior review and approval. At a minimum, the loading diagram shall include but not be limited to the following information:

(1) A typical section and plan view of the bridge, the position of the wheel loads and wheel spacing of the truck or crane.

01 11 00.00 25-3

(2) The GVW of the vehicle and all axle weights.

1.12.2 Delivery of Bulkheads

a. Contractor to deliver the bulkhead in an upright position and ready to be picked by the site Government cranes. Adequate clearance shall be provided for the Government crane to clear the truck bed. Bottom of stoplog to deck surface is 12' when in the fully raised position.

b. Bulkheads must be delivered to a location as directed by the CO.

Location to be on the deck to be picked by Government cranes.

1.13 CONTRACTOR USE OF GOVERNMENT CRANES

The Contractor is not allowed to use Government cranes for any work or access. Use Contractor-furnished equipment to facilitate handling of items and equipment for this Contract.

1.14 CONTRACTOR'S HEAVY EQUIPMENT SAFETY

Contractor's equipment furnished for this work shall conform with all applicable OSHA requirements, and EM 385-1-1.

1.15 CONTRACTOR'S HEAVY EQUIPMENT

Coordinate with the CO and submit the planned method of transportation and operation of Contractor-furnished cranes and other heavy equipment to be used in the performance of this Contract for Government approval. Submit the proposed transportation routes and work areas to be used on the project, and placement location of the bulkheads.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

-- End of Section --

01 11 00.00 25-4

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 GENERAL

1.1 GENERAL INFORMATION

1.2 SUBMITTALS

1.3 DEFINITIONS

1.3.1 Submittal Descriptions (SD)

1.3.2 Approving Authority

1.3.3 Work

1.4 SUBMITTAL DESIGNATION

1.5 SUBMITTAL REGISTER

1.5.1 Maintain Submittal Register

1.5.2 Use of Submittal Register

1.5.3 Government Approval Submittals

1.5.3.1 Quantity of Submittals

1.5.3.2 Processing of "G" Submittals.

1.5.4 Information Only Submittals

1.5.4.1 General

1.5.4.2 Processing of Information Only Submittals

1.6 SUBMITTAL COORDINATION

1.6.1 Submittal Coordination Meeting

1.6.2 Submittal Register ENG Form 4288-R

1.6.3 Submittal Register Updates

1.7 SCHEDULING

1.8 TRANSMITTAL FORM (ENG FORM 4025-R)

1.9 CROSS-REFERENCE (ENG FORM 4288-R/ENG FORM 4025-R)

1.10 SUBMITTAL PROCEDURES

1.10.1 e-Submittals

1.10.2 Approval of Submittals by the Contractor

1.10.3 Drawings

1.10.3.1 Shop Drawing Reproducibles

1.10.3.2 Printed Material

1.11 SAMPLES REQUIRING LABORATORY ANALYSIS

1.12 PURCHASE ORDERS

1.13 CERTIFICATES OF COMPLIANCE

1.14 DISAPPROVED SUBMITTALS

1.15 APPROVED SUBMITTALS

1.16 APPROVED SAMPLES

1.17 CONTRACTOR'S FILES

1.18 PAYMENT

1.19 WITHHOLDING OF PAYMENT

1.20 CONTRACTOR APPROVAL STAMP

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

01 33 00-i

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 GENERAL

1.1 GENERAL INFORMATION

a. Make submittals as required by the Specifications. The Contracting Officer (CO) may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective Sections.

b. Use the same units of weights and measures on all submittals as those used in the Contract Drawings.

c. Each submittal must be complete and in sufficient detail to allow ready determination of compliance with Contract requirements.

d. The Contractor's Quality Control (CQC) System Manager shall check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the Contract requirements must be clearly identified. Submittals must include items such as: Contractor's, manufacturer's, or fabricator's drawings;

descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders;

samples; O&M manuals (including parts list); certifications;

warranties; and other such required submittals.

e. Submittals requiring Government approval must be scheduled and approved prior to the acquisition of the material or equipment covered thereby.

f. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Safety Data Sheets (SDS) and in compliance with existing laws and regulations.

g. Submittals requiring professional licensure, signature, and stamp must comply with all State professional licensing and registration requirements.

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. Submit the following in accordance with this Section:

SD-01 Pre-work Submittals

Submittal Register; G

SD-07 Certificates

Authorized Shop Drawing Approvers

01 33 00-1

1.3 DEFINITIONS

1.3.1 Submittal Descriptions (SD)

Submittal requirements are specified in the technical Sections and in the preliminary submittal register (ENG Form 4288-R, Attachment A1).

Submittals are identified by Submittal Description (SD) numbers and titles as follows:

SD-01 Pre-work Submittals

Submittals required prior to start of construction work. Includes, but not limited to: schedules, tabular list of data, or tabular list including location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work.

Certificates of insurance.

Surety bonds.

List of proposed subcontractors.

List of proposed products.

Construction Progress Schedule.

Submittal register.

Schedule of prices.

Health and safety plans.

Work plan.

Contractor Quality Control (CQC) plan.

Environmental protection plan.

SD-02 Shop Drawings

Drawings, diagrams, and schedules specifically prepared to illustrate some portion of the work.

Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.

Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.

SD-03 Product Data

Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance, and other characteristics of materials, systems, or equipment for some portion of the work.

Warranty language when the Contract requires extended product warranties.

01 33 00-2

SD-04 Samples

Fabricated or unfabricated physical examples of materials, equipment, or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.

Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.

Field samples and mock-ups constructed on the project site establish standards by which the ensuing work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.

SD-06 Test Reports

Report signed by authorized official of testing laboratory that a material, product, or system identical to the material, product, or system to be provided has been tested in accordance with specified requirements. (Testing must have been within three years of date of Contract award for the project.)

Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.

Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.

Investigation reports.

Daily logs and checklists.

Final acceptance test and operational test procedure.

Any reports required by the CO or designated representative to assure successful completion of tasks during the life of the Contract.

SD-07 Certificates

Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system, or material attesting that product, system, or material meets specification requirements. Must be dated after award of project Contract and clearly name the project.

Document required of Contractor, or of a manufacturer, supplier, installer, or subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.

Confined space entry permits.

Text of posted operating instructions.

01 33 00-3

1.3.2 Approving Authority

Office or designated person authorized to approve submittal.

1.3.3 Work

As used in this Section, on- and off-site construction required by Contract documents, including labor necessary to produce submittals (except those SD-01 Pre-Construction Submittals noted above) construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.

1.4 SUBMITTAL DESIGNATION

Submittals are classified as follows:

a. Government Approved (G).

b. Information Only. Submittals not requiring Government approval will be for information only.

1.5 SUBMITTAL REGISTER

1.5.1 Maintain Submittal Register

a. Prepare and maintain Submittal Register, ENG Form 4288-R, , as the work progresses. Do not change data which is output in columns (c), (d), (e), and (f) as delivered by Government; retain data which is output in columns (a), (g), (h), and (i) as approved. This list may not be all inclusive and additional submittals may be required.

b. The Government will provide the preliminary submittal register in electronic format with the following fields completed, to the extent that will be required by the Government during subsequent usage.

(1) Column (c): Lists Specification Section in which submittal is required.

(2) Column (d): Lists each submittal description (SD No. and type, e.g. SD-02 Shop Drawings) required in each Specification Section.

(3) Column (e): Lists one principal paragraph in Specification Section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting project requirements.

1.5.2 Use of Submittal Register

Submit submittal register with project schedule and QC plan. Verify that all submittals required for work are listed and add missing submittals.

Coordinate, update, and complete the fields on the submitted register with the project schedule.

01 33 00-4

1.5.3 Government Approval Submittals

1.5.3.1 Quantity of Submittals

SD-01, SD-02, SD-03, and SD-05 through SD-11 submittals: Upload submittals with corresponding ENG 4025-R transmittal forms (Attachment A2) as outlined in paragraph entitled e-Submittals. SD-04 submittals: Submit two samples of "G" submittals with two corresponding ENG 4025-R transmittal forms, unless otherwise specified. Upon completion of review, "G" submittal copies will be marked with an action code, dated, electronically signed, and electronically returned to the Contractor as specified below:

1.5.3.2 Processing of "G" Submittals.

a. Submittals will be reviewed and processed as follows:

(1) Approved as Submitted (Action Code "A"): Submittals which can be approved without correction will be stamped "Approved" and returned electronically to the Contractor.

(2) Approved, Except as Noted on Drawings (Action Code "B"):

Submittals which have only minor discrepancies will be annotated in red to indicate necessary corrections. Marked material will be stamped "Approved Except as Noted" and returned electronically to the Contractor for correction.

(3) Approved, Except as Noted on Drawings, Resubmission Required (Action Code "C"): Submittals which are incomplete or require more than minor corrections will be annotated in red to indicate necessary corrections. Marked material will be stamped "Approved Except as Noted - Resubmission Required" and returned electronically to the Contractor for correction. Resubmittal of only those items needing correction required.

(4) Will be Returned by Separate Correspondence (Action Code "D"): Submittals will be addressed by Serial Letter and the Contractor must respond according to instructions in the letter.

(5) Disapproved (Action Code "E"): Submittals which are fundamentally in error, cover wrong equipment or construction, or require extensive corrections, will be returned to the Contractor stamped "Disapproved." Submittal will be returned electronically to the Contractor and an explanation will be furnished on the submitted material or on ENG Form 4025-R indicating reason for disapproval. Complete resubmittal required.

(6) Receipt Acknowledged (Action Code "F"): Submittals stamped "Receipt Acknowledged" are complete and returned electronically to the Contractor.

(7) Other (Specify) (Action Code "G"): Submittals requiring other specific action will be stamped "Other (Specify)" and returned with a description in the Remarks section. Submittal will be returned electronically to the Contractor. Resubmittal of only those items needing correction required.

(8) Receipt Acknowledged, Does Not Comply (Action Code "X"):

Submittals which have been received but do not comply with Contract requirements. Submittal will be returned electronically

01 33 00-5 to the Contractor stamped "Receipt Acknowledged, Does Not Comply" and an explanation will be furnished. Corrective action and resubmittal required.

b. Resubmittal will not be required for approved submittals unless subsequent changes are made by Contractor or by Contract modification.

For submittals required to be resubmitted, make corrections required, note any changes by dating the revisions to correspond with the change request date, and promptly resubmit the corrected material.

Resubmittals must be associated with the "parent" by use of sequential numbers (for example, resubmittal of transmittal 8 will be 8.1, 8.2, etc). Government costs incurred after the first resubmittal may be charged to the Contractor.

1.5.4 Information Only Submittals

1.5.4.1 General

Upload submittal with corresponding ENG 4025 forms as outlined in paragraph entitled e-Submittals. Normally information only submittals will not be returned. Government approval is not required on information only submittals. These submittals will be used for information purposes. The Government reserves the right to require the Contractor to resubmit any item found not to comply with the Contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the CO from requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.

1.5.4.2 Processing of Information Only Submittals

Submit information only submittals electronically prior to delivery of the material or equipment to the job site. ENG Form 4025-R must be marked with the words "Contractor approved - information copy only" in the REMARKS block of the form. Submittals will be monitored and spot checks made.

When such checks indicate noncompliance, the Contractor will be notified by the same method used for Government Approval submittals. Resubmittal of nonconforming information only submittals must be reclassified Government Approval ("G") and re-submitted electronically for approval.

1.6 SUBMITTAL COORDINATION

1.6.1 Submittal Coordination Meeting

Meet with the CO, after the pre-work conference and before any submittals are sent to the CO, to further develop the preliminary submittal register (ENG Form 4288-R). During the meeting identify and group all required items into the categories as shown in paragraph entitled SUBMITTAL

DESIGNATION.

1.6.2 Submittal Register ENG Form 4288-R

Coordinate the submittal register with the progress schedule and submit within 30 days of Notice to Proceed. In preparing the final document, allow a minimum of 21 days for review and approval, and possible resubmittal of each item on the register.

01 33 00-6

1.6.3 Submittal Register Updates

The CQC System Manager must review the listing at least every 30 days and take appropriate action to maintain an effective system. Submit copies of updated or corrected listings to the CO at least every 30 days in the quantity specified.

1.7 SCHEDULING

Schedule and submit concurrently submittals covering component items forming a system or items that are interrelated. Adequate time (a minimum of 30 calendar days) must be allowed and shown on the register for Government review and approval. No delay damages or time extensions will be allowed for time lost in late submittals.

a. Coordinate scheduling, sequencing, preparing, and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential resubmittal of requirements.

b. Submittals called for by the Contract documents must be listed on the register. Approval by the CO does not relieve the Contractor of supplying submittals required by the Contract documents but which have been omitted from the register.

c. Re-submit register and annotate monthly with actual submission and approval dates. When all items on the register have been fully approved, no further re-submittal is required.

d. Carefully control procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Submittal Register."

1.8 TRANSMITTAL FORM (ENG FORM 4025-R)

Use the sample transmittal form (ENG Form 4025-R, Attachment A2) for submitting both Government Approval and Information Only submittals in accordance with the instructions on the reverse side of the form. These forms will be furnished to the Contractor. Fill forms in completely prior to submittal. Exercise special care to ensure proper listing of the specification paragraph number(s) and Contract Drawing sheet number(s) pertinent to the data submitted for each item. List each submittal item separately on the form, naming subcontractor, supplier, or manufacturer;

applicable specification paragraph number(s); drawing/sheet number; pay item number; and any other information needed to identify the item, define its use, and locate it in the work. One or more ENG 4025-R forms may be used per Specification Section, however, DO NOT include more than one Specification Section per transmittal.

1.9 CROSS-REFERENCE (ENG FORM 4288-R/ENG FORM 4025-R)

To provide a cross-reference between the approved submittal register and transmittal forms, the Contractor must record the "transmittal numbers" assigned when submitting items in column "Transmittal No." of the ENG Form 4288-R. The numbers in column "Transmittal No." of the submittal register must correspond to the column "Item No." on ENG Form 4025-R.

1.10 SUBMITTAL PROCEDURES

Upload submittals in accordance with subparagraphs entitled Government

01 33 00-7

Approved Submittals and Information Only Submittals, unless indicated otherwise in the technical specifications. Submit a complete collated "reviewers copy" with one ENG 4025-R form and attachments (not originals).

Submit hard copy and electronic copies of Record (as-built) Drawings and O&M Manuals in accordance with the applicable Specification Sections.

1.10.1 e-Submittals

The intent of electronic submittals is to expedite the construction process by reducing paperwork, improving information flow, and decreasing turnaround time. Transmit all submittals, including either an electronically signed or signed scanned copy of form ENG 4025, to the Government electronic (PFD) format via email. At completion of Contract closeout, provide a minimum of two archival discs (DVD-R) that include all documents and tracking logs. Color samples, color charts, or physical material samples shall not be transmitted electronically. e-Submittals will not relieve the Contractor from following all applicable requirements within this and other Specifications Sections.

1.10.2 Approval of Submittals by the Contractor

a. Submit names and titles of Contractor Authorized Shop Drawing Approvers to the CO with the ENG Form 4288-R. Supplier or subcontractors certifications are not acceptable as meeting this requirement.

b. Before submittal to the CO, the Contractor's Authorized Shop Drawing Approvers must review and correct shop drawings prepared by subcontractors, suppliers, and itself, for completeness and compliance with Drawings and Specifications. Do not use red markings for correcting material to be submitted. Red markings are reserved for CO's use.

c. Submittals for Government Approval must first be Contractor-approved and stamped, see paragraph entitled CONTRACTOR APPROVAL STAMP.

d. Submittals not conforming to the requirements of this Section will be returned to the Contractor for correction and resubmittal.

1.10.3 Drawings

Each drawing must be not larger than D size (22 inches high by 34 inches wide), include a title block in lower right hand corner, and a 3- by 4-inch clear area adjacent. The title block must contain vendor's name, Contract number, description of item(s), Contract line item number, and a revision block. Separate drawings are required for each Contract line item. Where drawings are submitted for assemblies of more than one piece of equipment or systems, of components dependent on each other for compatible characteristics, complete information must be submitted on all such related components at the same time. The information must be complete and the sequence of drawing submittal must be such that all information is available for reviewing each drawing. Drawings for all items and equipment, of special manufacture or fabrication, must consist of complete assembly and detail drawings. All revisions after initial submittal must be shown by number, date, and subject in revision block. Any drawing or electronic drawing file submitted, that is not of satisfactory quality, will be returned and must be corrected and re-submitted.

01 33 00-8

1.10.3.1 Shop Drawing Reproducibles

Upon completion of the work under this Contract, provide a complete set of:

a. Show all changes and revisions, including any field changes, made up to the time that the work is accepted. Include all pertinent data files to reproduce the complete set. Record files on CD-ROM, CD-R discs only, or other digital media noted otherwise in this Contract.

b. Full-size reproducible hard-copy sets of drawings identical to the electronic drawing files. Show all changes and revisions, including field changes, made up to the time that the work is accepted.

1.10.3.2 Printed Material

All requirements for shop drawings must apply to catalog cuts, illustrations, printed specifications, or other data submitted, except that the 3- by 4-inch clear area adjacent to the title block is not mandatory.

Mark out inapplicable portions of the documents. Applicable items such as model numbers, sizes, and accessories must be indicated by arrow or highlighted.

1.11 SAMPLES REQUIRING LABORATORY ANALYSIS

See Section 01 45 00.00 25, QUALITY CONTROL, for procedures and address for samples requiring Government testing.

1.12 PURCHASE ORDERS

a. Each purchase order issued by the Contractor for materials and equipment to be incorporated into the work must:

(1) Clearly identify the applicable Contract number

(2) Carry an identifying number

(3) Be in sufficient detail to identify the material being purchased

(4) Indicate a definite delivery date.

b. Furnish copies of purchase orders to the CO when the Contractor requests assistance for expediting deliveries of equipment or materials, or when requested by the CO for the purpose of quality assurance review.

1.13 CERTIFICATES OF COMPLIANCE

Submit an electronic copy of certificates required for demonstrating proof of compliance of materials with specification requirements. Each certificate must be signed by an official authorized to certify on behalf of the manufacturing company, contain the name and address of the Contractor, the project name and location, and the quantity and date or dates of shipment or delivery to which the certificates apply. Copies of laboratory test reports submitted with certificates must contain the name and address of the testing laboratory and the date or dates of the tests to which the report applies. Certification shall not be construed as relieving the Contractor from furnishing satisfactory material if, after tests are performed on selected samples, the material is found not to meet

01 33 00-9 the specific requirements.

1.14 DISAPPROVED SUBMITTALS

a. Make all corrections required by the CO and promptly furnish a corrected submittal in the form specified for the initial submittal.

If the Contractor considers any correction or notation on the returned submittals to constitute a change Specifications, is to be given to the CO. The Contractor must be responsible for the dimensions and design of connection details and construction of work. Failure to point out deviations may result in the Government requiring rejection and removal of such work at the Contractor's expense.

b. If changes are necessary to submittals, make such revisions and re-submit the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.

1.15 APPROVED SUBMITTALS

a. The CO's approval or acceptance of submittals shall not be construed as a complete check, and indicates only that .

b. Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the Contactor Quality Control (CQC) requirements of this Contract must be responsible for dimensions, the design of adequate connections and details, and the satisfactory construction of all work.

c. After submittals have been approved by the CO, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.

1.16 APPROVED SAMPLES

a. Approval of a sample is only for the characteristics or use named in such approval and must not be construed to change or modify any Contract requirements. Before submitting samples, ensure that the materials or equipment will be available in quantities required. No change or substitution will be permitted after a sample has been approved.

b. If requested, approved and/or disapproved samples, including those which may be damaged in testing, will be returned at the expense of the Contractor upon completion of the Contract.

c. Failure of any materials to pass the specified tests will be sufficient cause for refusal to consider, under this Contract, any further samples of the same brand or make of that material. Government reserves the right to disapprove any material or equipment which previously has proved unsatisfactory in service.

d. Samples of various materials or equipment delivered on the site or in place may be taken by the CO for testing. Samples failing to meet Contract requirements will automatically void previous approvals.

Contractor must replace such materials or equipment to meet Contract requirements.

e. Approval of the Contractor's samples by the CO does not relieve the Contractor of his responsibilities under the Contract.

01 33 00-10

1.17 CONTRACTOR'S FILES

Maintain "Approved as Accepted" and "Approved, Except as Noted on Drawings" (Action Codes "A" and "B") shop drawing files in fabrication shops and at field sites for Government use.

1.18 PAYMENT

Separate payment will not be made for submittals, and all costs associated therein must be included in the applicable unit prices or job prices contained in the Price Schedule. Payment will not be made for any material or equipment which does not comply with Contract requirements.

1.19 WITHHOLDING OF PAYMENT

No payment will be made for any materials incorporated into the work for Information Only submittals found to contain errors.

01 33 00-11

1.20 CONTRACTOR APPROVAL STAMP

Stamps used by the Contractor on the submittal data to certify that the submittal meets Contract requirements must be similar to the following:

| CONTRACTOR |

| (Firm Name) | | _____ Approved | | _____ Approved with corrections as noted on submittal data and/or | | attached sheets(s). |

| SIGNATURE: __________________________________________________________ |

| TITLE: ______________________________________________________________ |

| DATE: _______________________________________________________________ |

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

01 33 00-12

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 45 00.00 25

QUALITY CONTROL

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 LABORATORY VALIDATION

1.4 PAYMENT

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

3.1.1 Quality Control System

3.1.2 Project Superintendent

3.2 CONTRACTOR QUALITY CONTROL PLAN

3.2.1 Content of the CQC Plan

3.2.2 Acceptance of CQC Plan

3.2.3 Notification of Changes

3.3 COORDINATION MEETING

3.4 QUALITY CONTROL ORGANIZATION

3.4.1 Personnel Requirements

3.4.2 CQC System Manager Qualifications

3.4.3 CQC Specialized Personnel

3.4.4 Fabrication Quality Management for Contractors

3.4.5 Organizational Changes

3.5 SUBMITTALS AND DELIVERABLES

3.6 QUALITY CONTROL

3.6.1 Preparatory Phase

3.6.2 Initial Phase

3.6.3 Follow-up Phase

3.6.4 Additional Preparatory and Initial Phases

3.7 TESTS

3.7.1 Testing Procedure

3.7.2 Testing Laboratories

3.7.3 Onsite Laboratory

3.7.4 Furnishing or Transportation of Samples for Testing

3.8 COMPLETION INSPECTION

3.8.1 Punch-Out Inspection

3.8.2 Pre-Final Inspection

3.8.3 Final Acceptance Inspection

3.9 DOCUMENTATION

3.10 NOTIFICATION OF NONCOMPLIANCE

01 45 00.00 25-i

SECTION 01 45 00.00 25

QUALITY CONTROL

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM E329 (2014a) Standard Specification for Agencies Engaged in the Testing and/or Inspection of Materials Used in Construction

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following must be submitted in accordance with Section 01 33 00, SUBMITTAL PROCEDURES:

SD-01 Pre-work Submittals

Contractor Quality Control Plan; G

Fabrication Quality Management for Contractors

Furnish documentation that the Contractor Quality Control System Manager has completed the Corps of Engineers course titled "Construction Quality Management for Contractors."

SD-06 Test Reports

Weekly CQC Report

1.3 LABORATORY VALIDATION

For tests performed under this Contract, use a testing laboratory validated by the Corps of Engineers Material Testing Center (MTC). See paragraph entitled TESTS.

1.4 PAYMENT

Separate payment will not be made for providing and maintaining an effective Quality Control system, and all associated costs will be included in the applicable unit prices or lump-sum prices contained in the Price Schedule.

01 45 00.00 25-1

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

3.1.1 Quality Control System

Establish and maintain an effective quality control (QC) system. The quality control system must consist of plans, procedures, and organization necessary to produce an end product which complies with the Contract requirements. The QC system must cover all work operations, both onsite and offsite, and be keyed to the proposed fabrication sequence.

3.1.2 Project Superintendent

Identify an individual, within the organization, as Project Superintendent. The Project Superintendent must be a Journeyman with a minimum of five years experience in a verifiable Project Superintendent role on jobs similar to this Contracts. The designated Project Superintendent must be acceptable to the CO. The Project Superintendent must be held responsible for the quality of work on the job and is subject to removal by the Contracting Officer (CO) for non-compliance with the quality requirements specified in the Contract. In this context the highest level manager responsible for the overall fabrication activities, including quality and production is the Project Superintendent. The Project Superintendent must maintain a physical presence at the site at all times, except as otherwise acceptable to the CO, and must be responsible for all fabrication related activities at the site. Identify an alternate for the Project Superintendent to serve in the event of the Project Superintendent's absence and/or to cover work performed on additional shift. The requirements for the alternate are the same as the designated Project Superintendent.

3.2 CONTRACTOR QUALITY CONTROL PLAN

Submit no later than 21 days after receipt of Notice to Award, the Contractor Quality Control (CQC) Plan proposed to implement the requirements of Contract. The Government will consider an interim plan for the first 10 days of operation. Fabrication will be permitted to begin only after acceptance of the CQC Plan or acceptance of an interim plan applicable to the particular feature of work to be started. Work outside of the features of work included in an accepted interim plan will not be permitted to begin until acceptance of a CQC Plan or another interim plan containing the additional features of work.

3.2.1 Content of the CQC Plan

Include, as a minimum, the following to cover all fabricaton operations, both onsite and offsite, including work by subcontractors, fabricators, suppliers, purchasing agents:

a. A description of the quality control organization, including a chart showing lines of authority and acknowledgment that the CQC staff must implement the three phase control system for all aspects of the work specified. Include in the staff a CQC System Manager.

b. The name, qualifications (in resume format), duties, responsibilities, and authorities of each person assigned a CQC

01 45 00.00 25-2 function; see paragraph entitled QUALITY CONTROL ORGANIZATION.

c. A copy of the letter to the CQC System Manager signed by an authorized official of the firm which describes the responsibilities and delegates sufficient authorities to adequately perform the functions of the CQC System Manager, including authority to stop work which is not in compliance with the Contract. Letters of direction to all other various quality control representatives outlining duties, authorities, and responsibilities must be issued by the CQC System Manager. Copies of these letters must be furnished to the Government.

d. Procedures for scheduling, reviewing, certifying, and managing submittals, including those of subcontractors, offsite fabricators, suppliers, and purchasing agents. These procedures must be in accordance with Section 01 33 00, SUBMITTAL PROCEDURES.

e. Control, verification, and acceptance testing procedures for each specific test to include the test name, specification paragraph requiring test, feature of work to be tested, test frequency, and person responsible for each test. (Use laboratory facilities approved by the CO.)

f. Procedures for tracking preparatory, initial, and follow-up control phases and control, verification, and acceptance tests including documentation.

g. Procedures for tracking fabricaton deficiencies from identification through acceptable corrective action. Establish verification procedures that identified deficiencies have been corrected.

h. Reporting procedures, including proposed reporting formats.

i. A list of the definable features of work. A definable feature of work is a task which is separate and distinct from other tasks, has separate control requirements, and may be identified by different trades or disciplines, or it may be work by the same trade in a different environment. Although each Section of the specifications may generally be considered as a definable feature of work, there are frequently more than one definable features under a particular section. This list will be agreed upon during the coordination meeting.

3.2.2 Acceptance of CQC Plan

Acceptance of the plan is required prior to the start of fabrication.

Acceptance is conditional and will be predicated on satisfactory performance during the fabrication. The Government reserves the right to require the Contractor to make changes in the CQC Plan and operations including removal of personnel, as necessary, to obtain the quality specified.

3.2.3 Notification of Changes

After acceptance of the CQC Plan, notify the CO in writing of any proposed change. Proposed changes are subject to acceptance by the CO.

3.3 COORDINATION MEETING

After the and prior to acceptance by the Government of the Plan, the

01 45 00.00 25-3

Contractor shall meet with the CO and discuss the Contractor's quality control system. Submit the Plan for review a minimum of 5 calendar days prior to the Coordination Meeting. During the meeting, a mutual understanding of the system details shall be developed, including the forms for recording the CQC operations, control activities, testing, administration of the system for both onsite and offsite work, and the interrelationship of Contractor's Management, and control with the Government's Quality Assurance. Minutes of the meeting will be prepared by the Government and signed by both the Contractor and the CO and will become a part of the Contract file. There may be occasions when subsequent conferences will be called by either party to reconfirm mutual understandings and/or address deficiencies in the system or procedures which may require corrective action by the Contractor.

3.4 QUALITY CONTROL ORGANIZATION

3.4.1 Personnel Requirements

The requirements for the CQC organization are a CQC System Manager and sufficient number of additional qualified personnel to ensure Contract compliance. The Safety and Health Manager must receive direction and authority from the CQC System Manager and serve as a member of the CQC staff. Personnel identified in the technical provisions as requiring specialized skills to assure the required work is being performed properly must be included as part of the CQC organization. The Contractor's CQC staff must maintain a presence at the site at all times during progress of the work and have complete authority and responsibility to take any action necessary to ensure Contract compliance. All CQC staff members must be subject to acceptance by the CO. Promptly complete and furnish all letters, material submittals, shop drawing submittals, schedules, and all other project documentation to the CQC organization. The CQC organization must maintain these documents and records at the site at all times, except as otherwise acceptable to the CO.

3.4.2 CQC System Manager Qualifications

Identify an individual, within the onsite work organization, as CQC System Manager who shall be responsible for writing and executing a complete CQC plan, overall management of CQC, and have the authority to act in all CQC matters for the Contractor. The CQC System Manager must be a Journeyman with a minimum of five years experience in a verifiable CQC role on jobs similar to this Contract. This CQC System Manager must be on the site at all times during fabrication and be employed by the prime Contractor. The CQC System Manager can be the SSHO on this project. Identify in the plan an alternate for the CQC System Manager to serve in the event of the CQC System Manager's absence and/or to cover work performed on additional shifts. The requirements for the alternate are the same as the designated CQC System Manager.

3.4.3 CQC Specialized Personnel

In addition to CQC personnel specified elsewhere in the Contract, provide as part of the CQC organization specialized personnel to assist the CQC System Manager for the following areas: mechanical, civil, if the CQC manager is not qualified to cover these areas. These individuals may be employees of the prime or subcontractor; must be responsible to the CQC System Manager; be physically present during work on their areas of responsibility; and meet the same experience/education qualifications in their own discipline as for the CQC Manager. These individuals may perform

01 45 00.00 25-4 other duties but must be allowed sufficient time to perform their assigned quality control duties as described in the Quality Control Plan. A single person may cover more than one area provided that they are qualified to perform QC activities in each designated and that workload allows.

3.4.4 Fabrication Quality Management for Contractors

In addition to the above experience and/or education requirements, the CQC System Manager and Alternate CQC System Manager must have successfully completed the course entitled "Construction Quality Management For Contractors." This course is periodically offered by the Associated Builders and Constructors, Inc., or Associated General Contractor, Inc. and must be retaken every five years. The course has been coordinated with the Navy and certificates from the Navy will be accepted. For further information regarding courses in the Portland area contact: Associated General Contractors, Oregon-Columbia Chapter at (503) 682-3363 or http://www.agc-oregon.org/education-and-training/army-corps-of-engineers/.

3.4.5 Organizational Changes

Maintain the CQC staff at full strength at all times. When it is necessary to make changes to the CQC staff, revise the CQC Plan to reflect the changes and submit the changes to the CO for acceptance.

3.5 SUBMITTALS AND DELIVERABLES

Submittals, if needed, must comply with the requirements in Section 01 33 00, SUBMITTAL PROCEDURES. The CQC organization must be responsible for certifying that all submittals and deliverables are in compliance with Contract requirements.

3.6 QUALITY CONTROL

Contractor Quality Control is the means by which the Contractor ensures that the fabrication to include that of subcontractors and suppliers, complies with the requirements of the Contract. At least three phases (Preparatory, Initial, and Follow-up) of control must be conducted by the CQC System Manager for each definable feature of the fabrication work as follows:

3.6.1 Preparatory Phase

This phase must be performed prior to beginning work on each definable feature of work, after all required plans/documents/materials are approved/accepted, and after copies are at the work site. This phase includes:

a.…