W9127N-16-R-0028

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

PROJECT TITLE: BONNEVILLE LOCK AND DAM, WASHINGTON SHORE FISH LADDER, LAMPREY PASSAGE STRUCTURES

SEE CONTINUATION PAGES

1. CONTRACT ID CODE PAGE OF PAGES

J 1 6

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 01-Jul-2016

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9127N-16-R-0028

X 9B. DATED (SEE ITEM 11)

22-Jun-2016

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

01-Jul-2016

CODE

US ARMY CORPS OF ENGINEERS

333 SW 1ST AVE

PORTLAND OR 97204-3440

W9127N 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00010 - SOLICITATION CONTRACT FORM

The Issued By organization below has been added:

US ARMY CORPS OF ENGINEERS

333 SW 1ST AVE

PORTLAND OR 97204-3440

SECTION 00100 - BIDDING SCHEDULE / INSTRUCTIONS TO BIDDERS

The following have been added by full text:

AMENDMENT NO. 0001

The purpose of this amendment is to incorporate the following changes to Solicitation No. W9127N-16-R-0028:

1) Update Bidder Inquiries instructions to move inquiries to Projnet.

2) Update FAR Clause 52.236-27 Alt 1, to revise the last paragraph of the bidder inquiry instructions.

3) Delete Clause 52.300-4001, Evidence of Authority from Section 00100 and insert the Evidence of

Authority in Section 00600.

All other terms and conditions remain unchanged.

The following have been modified:

INQUIRIES

BIDDER INQUIRIES

(All inquiries regarding this solicitation are to be submitted via ProjNet-Bid. Telephone and email inquiries will not be accepted. ProjNet-Bid is a web-based program that allows offerors to post questions regarding the solicitation, and to view all questions by other offerors, and answers by the U.S. Army Corps of Engineers.)

ProjNet-Bid can be accessed through the ProjNet website: https://www.projnet.org/projnet/.

To access the ProjNet-Bid website the first time:

1) Register.

2) Click Quick Add Key. (The Agency is USACE.)

3) Enter the following information for access:

The Bidder Inquiry Key: V6CIIK-GVB54S

Valid business contact information (e.g. Company name, contact person, business address, phone number and email address). (required on first project only)

Establish secret question and answer which will be used as a password (required on first project

4) For subsequent access use your email address, the Bid Inquiry Key and response to the secret question to access the ProjNet-Bid Module 00100.

5) Submit questions or review questions and answers. (A bidder who submits a question will receive an automated email notification that their question has been received. When an answer is posted to a question, the question and answer is then available for all other bidders to review.

6) For a specific step-by-step for POSTING YOUR INQUIRIES, is available in the Reference link on the Contract Viewer.

7) For questions about the ProjNet-Bid, please contact the Call Center help desk. The contact information is listed on the ProjNet website.

No response will be posted to inquiries after the Close of Business on the third business day preceding the solicitation due date. All bidders will be held to have reviewed the questions and responses in ProjNet-Bid prior to bid submission. Nothing in the solicitation is changed unless an amendment is sent out.

(End of Summary of Changes)

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for 13 Jul 2016. In order to participate in the site visit you must contact Matthew Chase, James Schroeder, and Daniel Ellis to provide the following information:

1. Names of people who will be attending the site visit.

2. The Company they work for.

3. Date and place of birth of each person to be on site, and

4. Any other information he may need for security purposes.

To request participation, provide the names of attendees to Matthew Chase at Matthew.T.Chase@usace.army.mil;

James Schroeder at James.W.Schroeder@usace.army.mil; and Daniel Ellis at Daniel.J.Ellis@usace.army.mil no later than 24 hours before the scheduled visit. US citizenship is required. Please verify that attendees are US citizens.

Anyone not on the approved list prior to the start time of the site visit will not be allowed through the security gate.

Date: July 13, 2016 Time: 9:00AM Location: Bonneville Lock and Dam Security Office POC: Mr. Matthew Chase

(c) Additional Requirements:

All prospective bidders must be United States Nationals.

All sites require long pants and closed toe shoes.

All sites will require hard hats, if you do not have a hard hat, the Corps shall supply hard hats at each location.

All attendees must bring a valid form of identification. State Identification, Drivers License, Passport, Common Access Card, are all acceptable.

No large bags or backpacks will be allowed in the powerhouses.

No photography will be allowed.

Those who do not arrive in time for the safety briefing will not be allowed to tour the facility.

All inquiries regarding this solicitation are to be submitted via ProjNet-Bid. Telephone and email inquiries will not be accepted. ProjNet-Bid is a web-based program that allows offerors to post questions regarding the solicitation, and to view all questions by other offerors, and answers by the U.S. Army Corps of Engineers.

(End of provision)

The following have been deleted:

52.300-4001 Evidence of Authority (MAY 1995) FEB 2001

SECTION 00600 - REPRESENTATIONS & CERTIFICATIONS

The following have been added by full text:

EVIDENCE OF AUTHORITY

A. CORPORATE CERTIFICATE/AUTHORITY TO BIND PARTNERSHIP

If the proposal is submitted by a corporation, the Corporate Certificate below must be submitted. If the proposal is submitted by a partnership, the Authority to Bind Partnership below must be completed and a copy of the partnership agreement included with the proposal. If the proposal is submitted by a Joint Venture, the Corporate Certificate below must be completed by each member of the Joint Venture and a copy of the Joint Venture Agreement showing the percentage of ownership of each firm included with the proposal.

CORPORATE CERTIFICATE

I, , certify that I am the (Title) of the corporation named as Proposer/Contractor herein; that , who signed this proposal/contract on behalf of the Proposer/Contractor was then (Title) of said corporation; that said proposal/contract was duly signed for and on behalf of said corporation by authority of its governing body and within the scope of its corporate powers.

(Corporate Seal) (Signature)

AUTHORITY

TO BIND

PARTNERSHIP

This is to certify that the names and signatures of all partners are listed below and that the person signing the proposal had authority to actually bind the partnership pursuant to its partnership agreement. Each of the partners individually has full authority to enter into and execute contractual instruments on behalf of said partnership, with the United States of America except as follows: (State "none" or describe limitations, if any). This authority shall remain in full force and effect until such time as the revocation of authority by any cause whatsoever has been furnished in writing to and acknowledged by the Contracting Officer.

Names and signatures of all partners:

(End of Certification)

(End of Summary of Changes)