W9127826RA075_Industry Day Presentation.pdf
PDF 12 MB Posted
- Solicitation number
- Not on record
About this file
This document is an Industry Day presentation agenda and facility overview for the U.S. Army Corps of Engineers' Cape Canaveral Space Force Station modernization program. The presentation occurred on July 30, 2026, and covered two contracting scenarios for infrastructure improvements.
The U.S. Space Force's Range of the Future 2028 Strategic Intent requires increased launch posture over the next decade, necessitating infrastructure improvements to support daily launches, multiple launches per day, elimination of critical day restrictions, infrastructure redundancy and resiliency, and reduced personnel impacts. The FY27 program includes six projects totaling approximately $384 million: Launch Support Facility ($84M), Command Facility ($85M), Security Forces Operations Facility ($48M), LRS Vehicle Maintenance Facility ($75M), Base Support Warehouse ($51M), and Communications Plant Warehouse ($41M). The FY28 program includes five projects totaling approximately $381.8 million: Redundant Power Along ICBM Road ($22.3M), Widen ICBM Road ($55M), Base Support Complex ($46.5M), Consolidated Munitions Storage ($212M), and Communications Duct Bank ($46M). Scenario #1 proposes a traditional Design-Bid-Build approach with two separate solicitations: Solicitation #1 covering the four mission support district facilities, and Solicitation #2 covering the two warehouse district facilities. Scenario #2 presents an innovative contracting approach using a single solicitation with either Progressive Design-Build (PDB), Construction Manager at Risk (CM at Risk), or Design-Build-Build (DB2B) delivery methods. Phase 1 deliverables would include topographic and utility surveys, geotechnical boring logs, HAZMAT surveys, 95% design documents, planning charrette reports, design analysis, environmental analysis, and Installation Facility Standards.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AGENDA
0700-0800 ARRIVE AND SET UP
0800-1100 PRESENTATION
CAPE OVERVIEW
PROJECTS OVERVIEW
SCENARIO #1 FULL DESIGN
SCENARIO #2 INNOVATIVE CONTRACTING APPROACH
1100-1200 NETWORKING
INDUSTRY DAY
JULY 30, 2026
▪ The U.S. Space Force’s Range of the Future 2028 Strategic Intent identified the requirement to increase launch posture over the next 10 years. Infrastructure must be improved to meet this new requirement.
▪ Primary Goals:
▪ Range must be able to support launching EVERY day.
▪ Range must be able to support multiple launches per day.
▪ Range must eliminate all critical day restrictions.
▪ Establish infrastructure redundancy and resiliency.
▪ Reduce personnel impacts associated with launch and landing activities.
PROGRAM SCOPE & DELIVERABLES
RELOCATING NON-LAUNCH MISSIONS
LAUNCH
OPERATIO
NS
SLD45/DoW
OPERATIO
NS
AND LAUNCH SUPPORT
SUPPORT FUNCTIONS BEING RELOCATED
SUPPORT FUNCTIONS
BEING RELOCATED
MISSION SUPPORT
CAMPUS
WAREHOUSE
DISTRICT
FY27 PROGRAM
Project Number Title Prg Amt
DBEH033000 Launch Support Facility $84,000,000
DBEH033001 Command Facility $85,000,000
DBEH227755 Security Forces Operations Facility $48,000,000
DBEH227784 LRS Vehicle Maintenance Facility $75,000,000
DBEH227756 Base Support Warehouse $51,000,000
DBEH227786 Communications Plant Warehouse $41,000,000
FY28 PROGRAM
Project Number Title Prg Amt
DBEH227761 Redundant Power Along ICBM Road $22,300,000
DBEH227764 Widen ICBM Road $55,000,000
DBEH227773 Base Support Complex $46,500,000
DBEH227778 Consolidated Munitions Storage $212,000,000
DBEH251705 Communications Duct Bank $46,000,000
MISSION SUPPORT DISTRICT (CAMPUS)
LAUNCH
SUPPORT
FACILITY
COMMAND
FACILITY
SECURITY
FORCES
OPERATIONS
FACILITY
LRS VEHICLE
MAINTENANCE
FACILITY
WAREHOUSE DISTRICT
COMMUNICATIONS
PLANT
WAREHOUSE
BASE
SUPPORT
SONIC BOOM
OVERPRESSURE
CONCERNS
MISSION SUPPORT
DISTRICT (CAMPUS)
LAUNCH SUPPORT AND
COMMAND FACILITIES
OVERALL SITE PLAN
LAUNCH
SUPPORT
FACILITY
COMMAND
OVERALL VIEW FROM NORTH PROMENADE
OVERALL VIEW FROM SOUTH COMMONS
LAUNCH SUPPORT MAIN ENTRANCE
LAUNCH SUPPORT FROM NORTHWEST
LAUNCH SUPPORT FROM SOUTHWEST
LAUNCH SUPPORT 1ST FLOOR
LAUNCH SUPPORT 2ND FLOOR
LAUNCH SUPPORT 3RD FLOOR
COMMAND BUILDING MAIN ENTRANCE
COMMAND BUILDING FROM NORTHEAST
COMMAND BUILDING FROM SOUTHEAST
COMMAND 1ST FLOOR
COMMAND 2ND FLOOR
COMMAND 3RD FLOOR
INFRASTRUCTURE IMPROVEMENTS
NEW
ELECTRICAL
LINE TIE IN TO
EXISTING
SUBSTATION
NEW SANITARY
FORCEMAIN TIE
INTO EXISTING
LIFT STATION
SECURITY FORCES OPERATIONS AND
LRS VEHICLE MAINTENANCE FACILITIES
SECURITY
FORCES
OPERATIONS
FACILITY
LRS VEHICLE
MAINTENANCE
SECURITY FORCES MAIN ENTRANCE
SECURITY FORCES FROM SOUTHEAST
SECURITY FORCES SITE PLAN
SECURITY FORCES FLOOR PLAN
LRS VEHICLE MAINTENANCE MAIN ENTRANCE
LRS VEHICLE MAINTENANCE FROM SOUTHEAST
LRS VEHICLE MAINTENANCE SITE PLAN
LRS VEHICLE MAINTENANCE FLOOR PLAN
WAREHOUSE DISTRICT
PROJECT
LOCATION
➢Total Area
➢Warehouse 1
➢Warehouse 2
➢Contractor Laydown
➢Comms Duct Bank
EXISTING SITE/
DEMOLITION
➢Building 85110–
Landscape Facility
➢4,000 SF Building
➢137K SF Pavement
➢HAZMAT Report:
Asbestos, Lead Based
Paint, etc.
➢ Included with Warehouse
1 (Current Design)
ENVIRONMENTAL
CONCERNS
➢ Protected Species
➢Site Lighting
➢Cultural Resource Area
➢HAZMAT
➢Status of survey, permits, registration, etc.
BASE SUPPORT WAREHOUSE
EXTERIOR RENDERING
SITE PLAN
FLOOR PLAN
(ADMIN AREA)
COMMUNICATIONS PLANT WAREHOUSE
EXTERIOR RENDERING
SITE PLAN
FLOOR PLAN ROTATED
(ADMIN AREA)
COMMUNICATIONS DUCT BANK
DESIGN – BID - BUILD
SCENARIO #1
SOLICITATION #1
SCENARIO #1
SOLICITATION #2
• LAUNCH SUPPORT FACILITY
• COMMAND FACILITY
• SECURITY FORCES
OPERATION FACILITY
• LRS VEHICLE MAINTENANCE
FACILITY
• BASE SUPPORT WAREHOUSE
• COMMUNICATIONS PLANT
INNOVATIVE CONTRACTING APPROACH
(PDB, CM at RISK, DB2B)
SCENARIO #2
ONE SOLICITATION
SCENARIO #2
• LAUNCH SUPPORT FACILITY
• COMMAND FACILITY
• SECURITY FORCES
OPERATION FACILITY
• LRS VEHICLE MAINTENANCE
FACILITY
• BASE SUPPORT WAREHOUSE
• COMMUNICATIONS PLANT
TENTATIVE ITEMS TO BE PROVIDED TO BE
PROVIDED WITH PHASE 1 PACKAGE
• TOPOGRAPHIC AND UTILITY SURVEYS
• GEOTECHNICAL BORINGS LOGS
• HAZMAT SURVEY
• 95% DESIGN DOCUMENTS (FIO)
• PLANNING CHARRETTE REPORTS
• DESIGN ANALYSIS
• ENVIRONMENTAL ANALYSIS
• INSTALLATION FACILITY STANDARDS (IFS)
67PROGRESSIVE DESIGN-BUILD (PDB)
WITH OT
68PROGRESSIVE DESIGN-BUILD (PDB)
69PROGRESSIVE DESIGN-BUILD (PDB)
| Slide 1 |
| Slide 2: INDUSTRY DAY |
| Slide 3: Program Scope & Deliverables |
| Slide 4: Relocating Non-Launch Missions |
| Slide 5: Fy27 Program |
| Slide 6: Fy28 Program |
| Slide 7 |
| Slide 8 |
| Slide 9 |
| Slide 10 |
| Slide 11 |
| Slide 12 |
| Slide 13 |
| Slide 14 |
| Slide 15 |
| Slide 16 |
| Slide 17 |
| Slide 18 |
| Slide 19 |
| Slide 20 |
| Slide 21 |
| Slide 22 |
| Slide 23 |
| Slide 24 |
| Slide 25 |
| Slide 26 |
| Slide 27 |
| Slide 28 |
| Slide 29 |
| Slide 30 |
| Slide 31 |
| Slide 32 |
| Slide 33 |
| Slide 34 |
| Slide 35 |
| Slide 36 |
| Slide 37 |
| Slide 38 |
| Slide 39 |
| Slide 40 |
| Slide 41 |
| Slide 42 |
| Slide 43 |
| Slide 44 |
| Slide 45: Project Location |
| Slide 46 |
| Slide 47 |
| Slide 48 |
| Slide 49: Existing Site/ Demolition |
| Slide 50: Environmental Concerns |
| Slide 51 |
| Slide 52 |
| Slide 53: Site Plan |
| Slide 54: FLOOR Plan |
| Slide 55: FLOOR Plan (ADMIN AREA) |
| Slide 56 |
| Slide 57 |
| Slide 58: Site Plan |
| Slide 59: FLOOR Plan |
| Slide 60: FLOOR Plan rotated (ADMIN AREA) |
| Slide 61 |
| Slide 62 |
| Slide 63 |
| Slide 64 |
| Slide 65 |
| Slide 66 |
| Slide 67 |
| Slide 68 |
| Slide 69 |
File details come from the government source that posted it. Updated .