Amendment No. 0002 to Solicitation W9127826BA001
This is Amendment No. 0002 to Solicitation W9127826BA001 for Maintenance Dredging Operations in Mobile Harbor, Mobile, Alabama, issued by the U.S. Army Corps of Engineers Mobile District on April 22, 2026. The amendment extends the response due date from April 27, 2026 to May 4, 2026, with bid opening scheduled for May 4, 2026 at 2:45 PM CDT. The amendment revises multiple contract sections including the completion timeline, contract drawings, specifications, and bid submission procedures. Key modifications include extending the project completion period from 180 to 240 calendar days following the Notice to Proceed and updating references to electronic bid submission requirements via the Procurement Integrated Enterprise Environment (PIEE) Module.
The requirement involves trailing suction hopper dredges and/or mechanical dredges with scows for maintenance dredging operations in Mobile Harbor with an estimated contract magnitude of $10,000,000 to $25,000,000. The base bid covers dredging from Station 244+66 to 267+73 (turning basin), Station 267+73 to 600+00, and Station 1250+00 to 1370+00, with optional dredging assignments available if funding becomes available. All dredged material is to be placed into the Ocean Dredged Material Disposal Site (ODMDS) located approximately 5 miles south of Dauphin Island, Alabama. The contractor must furnish performance and payment bonds, maintain specified insurance coverage, provide transport vessels and inspector accommodations on the dredge, and comply with U.S. Army Corps of Engineers safety requirements. Liquidated damages are assessed at $4,934.00 per calendar day for failure to complete work by the deadline. Offerors must acknowledge receipt of this amendment prior to bid submission and must submit bids electronically with physical bid bonds not required unless requested by the Contracting Officer.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W9127826BA001_Bid Abstract (Signed).pdf | ||
| MRC_20260225_OPTION_1_STA_9_30___32_76.zip | ZIP file | |
| W9127826BA001_AM03.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of theoffer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.
If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBE
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
J 1 2
0002 22 APR 2026 W9127826BA001
W91278
W074 ENDIST MOBILE
KO CONTRACTING DIVISION, 100 CANAL STREET
MOBILE, AL 36602-3630
UNITED STATES
TERRI ADAMS, EMAIL: TERRI.M.ADAMS@USACE.ARMY.MIL TELEPHONE: (251) 441-
SCD: PAS:
W9127826BA001
26 MAR 2026
SEE SECTION G - CONTRACT ADMINISTRATION DATA
REFER TO THE ENCLOSED REVISED SHEETS FOR AMENDMENT NO. 0002
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
Section 00 00 00 - Procurement and Contracting Requirements
The following changes have been made:
PART I-REVISIONS MADE BY ADDED AND/OR REPLACEMENT PARAGRAPHS/PAGES/SECTIONS
The items listed below are to be replaced by the corresponding added and/or revised paragraphs/pages or sections. Added and/or revised paragraphs/pages or sections are indicated by a note in bottom right hand corner of each paragraph or page. Added sections are hereby made a part of the contract and are to be inserted in the specification in the proper numerical/alphabetical sequence.
Within the specifications, deletions from the specifications are indicated by strikethrough, e.g.: deletions are marked with strikethrough and additions to the specifications including revisions/substitutions are indicated in bold, italic and underlined, e.g.: additions are indicated thus.
SECTION Corresponding Added or Revised Paragraph
Page, and/or Section
SF1442 Revised Boxes 11 and 13a.
Section 00 73 00 Revised Commencement, Prosecution, and
Completion of Work-Construction.
Section 01 00 00 Revised Paragraph 1.1.3.
Section 01 00 01 Revised Paragraph 29.
Encl as stated
Maintenance Dredging Operations In Mobile Harbor, Mobile, Alabama W9127826BA001
SF30 Page 3 W9127826BA001-0002
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR
INFORMATION CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE
6. PROJECT NUMBER
8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
INVITATION FOR BID
NEGOTIATED (RFP)
REQUEST FOR PROPOSAL
3. DATE ISSUED PAGE OF PAGES
W9127826BA001 1 2
W9127826BA001
W074 ENDIST MOBILE
KO CONTRACTING DIVISION, 100 CANAL STREET
MOBILE, AL 36602-3630
UNITED STATES
TERRI ADAMS, EMAIL: TERRI.M.ADAMS@USACE.ARMY.MIL TELEPHONE: (251)
441-6500
W91278
TERRI ADAMS (251) 441-6500
PROJECT TITLE: MAINTENANCE DREDGING MOBILE HARBOR
PROJECT LOCATION: MOBILE, AL
MAINTENANCE DREDGING MOBILE HARBOR
*SEE SECTION 00 73 00 - COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
**FOR INFORMATION PERTAINING TO SUBMISSION OF ELECTRONIC BIDS AND VIRTUAL BID OPENING, SEE PARAGRAPH 29 IN SECTION 01 00 01
02:00 PM
27 APR 04 MAY 2026
26 March 2026
180 calendar days after receiving
Commencement, Prosecution, and Completion of Work k5ct9tma Cross-Out k5ct9tma Cross-Out
AWARD (To be completed by Government)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 12/2022) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES
CODE AT
27. PAYMENT WILL BE MADE BY
10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
SECTION 00 73 00 SUPPLEMENTARY CONDITIONS
COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK - CONSTRUCTION (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the
Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 180 240 calendar days. The time stated for completion shall include final cleanup of the premises.
(End of condition)
VARIATION IN ESTIMATED QUANTITY (APR 1984)
If the quantity of a unit-priced item in this contract is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity. If the quantity variation is such as to cause an increase in the time necessary for completion, the
Contractor may request, in writing, an extension of time, to be received by the Contracting Officer within 10 days from the beginning of the delay, or within such further period as may be granted by the Contracting Officer before the date of final settlement of the contract. Upon the receipt of a written request for an extension, the Contracting
Officer shall ascertain the facts and make an adjustment for extending the completion date as, in the judgement of the Contracting Officer, is justified.
(End of condition)
SITE VISIT (CONSTRUCTION) (FEB 1995)
(a) The conditions, Differing Site Conditions, and Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) Site visits may be arranged during normal duty hours by contacting:
Name: Jacob Lambert
Address: 100 Canal St., Mobile, AL 36602
Telephone: 251-690-3487
(End of Condition)
Maintenance Dredging Operations In Mobile Harbor, Mobile, Alabama
Solicitation No.
W9127826BA001
Section 00 73 00
Maintenance Dredging Operations in Solicitation No.
SECTION 01 00 00
SECTION 01 00 00
ADDITIONAL SPECIAL CONTRACT REQUIREMENTS
PART 1 GENERAL
1.1 STATEMENT OF WORK
1.1.1 Dredging: The scope of work of the contract is to perform maintenance dredging in Mobile Harbor including disposal of dredged material into the Ocean Dredged Material Disposal Site (ODMDS). The base bid for maintenance dredging will be from Station 244+66 to 267+73 (turning basin), Station 267+73 to 600+00, and Station 1250+00 to 1370+00. A 100ft buffer will be applied to the red-side channel toe of the turning basin (Station 244+66 to 267+73). The buffer area will not be included in the required dredging prism; however, if material is removed/dredged from the 100ft buffer area it will be paid at the contract unit price for dredging.
Optional dredging assignments from Station 9+30 to 32+76, Station 105+00 to 150+00, and Station 164+00 to 212+00 may be included in the contract if funding becomes available and approved by the Contracting Officer (KO).
Should additional areas within Mobile Harbor require maintenance dredging during the contract period, such work may be included under this contract at the discretion of the Contracting Officer. The contractor is to perform such additional dredging in accordance with the same terms, conditions and specifications set forth in this contract.
The scope also includes supplying dredge-related supplies and equipment such as tugs, barges, cranes, attendant plants, and other marine equipment associated with channels and coastal restoration projects.
1.1.2 Dredge Material Disposal: All dredged material will be placed into the Ocean Dredged Material Disposal Site (ODMDS) located approximately 5-miles south of Dauphin Island, Alabama as shown in the contract drawings.
1.1.3 Project Duration and Completion: The work under this contract shall commence upon issuance of the Notice to Proceed and shall be completed within 180 240 calendar days following the Notice to Proceed (NTP).
1.2 SUBMITTALS
See the technical sections for approval and detail requirements for submittals. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES and the required technical section:
SD-11 Closeout Submittals
Contractor Prepared As-Built Drawings; G, OP
1.3 CONTRACT DRAWINGS, MAPS, AND SPECIFICATIONS
(a) The Contractor will be furnished with a digital copy of the advertised solicitation, including all contract clauses, drawings, and specifications. Paper copies of the specifications and drawings will be the responsibility of the Contractor. The work shall conform to the
SECTION 01 00 00
technical provisions outlined in the specifications and the contract drawings.
(b) Omissions from the drawings or specifications or the misdescription of details of work which are manifestly necessary to carry out the intent of the drawings and specifications, or which are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work, but they shall be performed as if fully and correctly set forth and described in the drawings and specifications.
(c) The Contractor shall check all drawings furnished them immediately upon their receipt and shall promptly notify the Contracting Officer of any discrepancies. Figures marked on drawings shall in general be followed in preference to scale measurements. Large scale drawings shall in general govern small scale drawings. The Contractor shall compare all drawings and verify the figures before laying out the work and will be responsible for any errors which might have been avoided thereby.
(d) The list of drawings and maps provided in the Index Sheet of the Plans for this solicitation are hereby incorporated by reference into these specifications.
NOTE: Refer to the folio of drawings for the index of drawings in this solicitation.
1.4 PHYSICAL DATA
Data and information furnished or referred to below is for the Contractor's information. The Government will not be responsible for any interpretation or conclusion drawn from the data or information by the Contractor.
1.4.1 General: The indications of physical conditions on the drawings and in the specifications are the result of site investigations and surveys.
1.4.2 Location: The work to be done under these specifications is located within the limits of Mobile Harbor federal navigation channel. Work assignments include Station 244+66 to 267+73, Station 267+73 to 600+00 and Station 1250+00 to 1370+00. The Ocean Dredged Material Disposal Site (ODMDS) is located approximately 5-miles south of Dauphin Island, Alabama. Optional dredging assignments are located in the Mobile River at Station 9+30 to 32+76, Station 105+00 to 150+00, and Station 164+00 to 212+00.
1.4.3 Contractor’s Investigation Responsibility: The Contractor should investigate submerged, surface, and overhead structures in the work areas and other locations which may be necessary to traverse. The exact location, depths, and height of submarine cables, pipes, highlines, etc. (as applicable), are not known and it will be necessary for the Contractor to ascertain interference problems and notify the respective owners in advance of dredging operations. The Contractor shall make all arrangements with the respective owners of the structure to assure satisfactory completion of dredging in the vicinity with a minimum interruption of service and shall perform operations in such a manner as will avoid damage to these facilities.
1.4.4 Weather Conditions: The sites of the work are exposed to local disturbances in the Mobile Harbor, which may cause suspension of the work for short unknown periods of time. During tropical hurricanes which may occur from June to November, inclusive, the project channels do not afford a safe refuge for floating plant. There are no unusual currents except during floods, when velocities of 2 to 4 miles per hour may be expected; however, the Contractor should investigate all sites of work and determine for themself the requirements of the work. Under ordinary conditions, the Mean Tidal Range is 1.2 feet. The working season extends over the entire year. Tides in Mobile Harbor are affected by extended periods of strong north or south winds.
1.4.5 Transportation Facilities: The work areas are accessible by water via the Gulf Intracoastal Waterway and the Gulf of America. The Contractor shall investigate any limitations imposed by bridges or other structures on water access to the project site. Highway access (Federal, state, and local) is available to the near vicinity of all work areas. Rail and highway transportation is available to Mobile, Alabama. Water transportation is available to the site of the work. The Contractor shall make their own investigation of available roads for transportation, load limits for bridges and roads, and other road conditions affecting the transportation of materials and equipment to the work sites.
1.4.6 Channel Traffic: The traffic using the Mobile, Alabama Shipping Channel is considered to be a combination of heavy and large commercial vessels, and various sized recreational craft, respectively. The type of traffic consists of general container ships, bulk carriers, fuel tankers, tow boats, Navy ships, charter fishing boats, passenger boats, and pleasure craft.
CAUTION: When navigation conditions become hazardous due to inclement weather (fog, storm, etc.) or other circumstances, the Contractor shall maintain appropriate communication with project traffic. The Contractor shall particularly comply with all U.S. Coast Guard regulations pertaining to proper activation of fog (and any other) signaling devices (sound, light, etc.).
1.4.7 Obstruction of Navigation Channels: The Government will not undertake to keep the work areas and navigation channels free from vessels or other obstructions, except to the extent of such regulations, if any, as may be prescribed by the Secretary of the Army, in accordance with the provisions of Section 7 of the Rivers and Harbors Act approved 8 August 1917. The Contractor will be required to conduct the work in such manner as to obstruct navigation as little as possible, and in case the Contractor's plant so obstructs any navigation channel as to make difficult or endanger the passage of vessels, said plant shall be promptly moved on the approach of any vessel to such an extent as may be necessary to afford a practicable passage. Upon the completion of the work the Contractor shall promptly remove their plant, including ranges, buoys, piles, and other marks placed by them under the contract in navigable waters or on shore.
1.5 TIME EXTENSIONS
Notwithstanding any other provisions of this contract, it is mutually understood that the time extensions for changes in the work will depend upon the extent, if any, by which the changes cause delay in the completion of the various elements of construction. The change order granting the time extension may provide that the contract completion date will be extended only for those specific elements so delayed and that the remaining contract completion dates for all other portions of the work will not be altered and may further provide for an equitable readjustment of liquidated damages under the new completion schedule. Change orders involving time extensions must be obtained in writing from the Government's Representative.
1.6 CONTRACTOR PREPARED AS-BUILT DRAWINGS
1.6.1 General: In accordance with SPECIAL CONTRACT REQUIREMENT paragraph: CONTRACT DRAWINGS, MAPS AND SPECIFICATIONS, the Government will furnish the Contractor one electronic set of solicitation drawing files and any amendments for use in preparation of as-built drawings by the Contractor. Copies of the drawings will be the responsibility of the
Contractor. The as-built drawings shall be a record of the construction as completed by the Contractor. They shall include all the information shown on the contract set of drawings and a record of all deviations, modifications, or changes from those drawings, however minor, which were incorporated in the work, all additional work not appearing on the contract drawings, and all changes which are made after final inspection of the contract work. In the event the Contractor accomplishes additional work which changes the as-built conditions after submission of the as-built drawings, the Contractor shall furnish revised and/or additional drawings as required to depict as-built conditions. The requirements for these additional drawings will be the same as for the as-built drawings included in the original submittal.
1.6.2 Red line as-built drawings: The Contractor shall have on their staff personnel to mark up a set of paper copy construction drawings to show the as-built conditions. These as-built marked copies shall be kept current and available on the job site at all times. All changes from the contract plans which are made in the work or additional information which might be uncovered during construction shall be accurately and neatly recorded, as the events occur, by means of details and notes. The Contractor shall call attention to entries by red lining areas affected. The red line as-built drawings will be jointly inspected for accuracy and completeness by the Contracting Officer's Representative and a responsible representative of the Contractor prior to submittal of each request for payment. The Contracting Officer Representative's approval of the current status of the as-built drawings shall be a prerequisite for the approval of request for progress payment and request for final payment under the contract. The drawings shall show the following information, but not be limited thereto:
1.6.2.1 The location and description of any utility lines or other installations of any kind or description known to exist within the construction area that are not already shown on the contract drawings.
The location includes dimensions to permanent features.
1.6.2.2 The location and dimensions of any changes within the construction area.
1.6.2.3 All changes or modifications which result from the final inspection.
1.6.3 Submittal of as-built drawings for review and approval: The
Contractor shall participate in monthly review meetings with the Contracting Officer's Representative to show the progress made the preceding month and make all required changes. At time of final construction inspection, the Contractor shall submit one copy of the red lined as-built drawings to the Contracting Officer's Representative for his review and approval. The as-built drawings shall be certified as to their correctness by the signature of an authorized representative of the Contractor. Upon Government approval of the Contractor's red lined copy of the as-built drawings, the Contractor shall prepare and provide an electronic set of as-built drawings by incorporating the red line marked up notations on the construction drawings into the electronic set of solicitation drawings and amendments. Submittals are to be to the Contracting Officer's Representative not later than ten
(10) calendar days after project completion date.
1.6.4 Final Drawing Format:
1.6.4.1 The solicitation drawing files and any amendments thereto will be furnished to the Contractor in electronic format. The solicitation drawing files have been prepared using .dwg or .dxf format. The
Contractor shall utilize this file format to revise/redraft each solicitation drawing and/or amendment drawing to reflect all changes made during construction as indicated by the red line marked up notations on the construction drawings. Revisions/redrafting shall match the font styles, sizes, and formats; line weights/thicknesses and styles/types; and all other drafting elements used on the solicitation drawing/amendments. All elements must be incorporated into each as-built drawing file; the use of reference files shall not be permitted.
1.6.4.2 All revisions made to the solicitation drawings and/or amendment drawings to reflect changes made during construction shall be flagged and shall have the revision block completed as follows. The entry in the description column of the revision block shall read "AS-BUILT". The date of the revision and one approving initial from a responsible person within the Contractor's Firm shall also be included in the revision block.
Above the drawing title block the drawing will be labeled in bold letters "AS-BUILT". The flagged changes and revision block format shall be in accordance with the examples shown in the Mobile District Design Manual located on the Internet athttp://www.sam.usace.army.mil/Missions/MilitaryMissions/Engine ering/ Engineering-Design-Manual/
The Contractor shall also furnish a revised index of drawings to match the actual design drawings. The drawing title blocks shall be in a uniform format to match the requirements as specified in the Design Manual.
1.6.4.3 The electronic set of as-built drawing files shall be submitted in .dwg or .dxf file format.
1.6.5 Payment: No separate payment will be made for preparation of the as-built drawings required under this contract. All costs will be considered a subsidiary obligation of the contract.
1.7 ATTENDANT PLANT
1.7.1 Attendant plant shall be composed of such barges, fuel, water, pipe derrick, anchor, etc., floating, submerged, and slip joint discharge pipe, and other attendant or auxiliary plant as may be required for operations under these specifications whether or not these items are specifically mentioned. The auxiliary and attendant plant shall be in good condition and of sufficient size and capability to efficiently serve the dredge.
1.7.1.1 A Marine VHF Radio, FCC type accepted with the following channels: Channel 16, (156.8 MHZ), Channel 13, (156.65 MHZ), Channel 12, (156.6 MHZ), Channel 14, (156.7 MHZ), and Channels 26 and 28 for public correspondence. A separate receiver must be provided on Channel 13, (156.6 MHZ) in compliance with Public Law 92-63.
1.7.1.2 In addition to the above-mentioned radios, the Contractor shall provide additional space in the inspector’s office as specified in the paragraph entitled “Inspector's Office” for placement of one VHF marine radio. The radio shall be able to receive all VHF marine channels and scan two channels continuously. The radio will be furnished at the expense of the Contractor.
http://www.sam.usace.army.mil/Missions/MilitaryMissions/Engineering/ http://www.sam.usace.army.mil/Missions/MilitaryMissions/Engineering/
1.7.2 Transport Vessel: The Contractor shall provide one transport vessel, with twin propellers, not less than 40 feet in overall length, with enclosed space for three passengers, to adequately operate in all areas included in the scope of work. This vessel must have an operator on site at all times; be capable of traveling at a speed of 20 knots (23 MPH) or greater in good weather and capable of traveling safely at night and in intense fog; (such vessel shall meet or exceed US Coast Guard regulations for vessels 65 feet or less in length); and the vessel shall have a Certificate of Inspection by the US Coast Guard, or at least from a Marine Surveyor. This vessel shall be for the primary use of the Government Inspector. The use of this vessel for Contractor's crew changes, or any other use of this vessel by the Contractor shall be secondary to the Government Inspector shift changes. This vessel shall be equipped with the following at a minimum: built-in fuel tanks with correctly operating fuel gauges;
marine and company radios; windshield wipers; running and spotlights;
and all required survey equipment. The Contractor shall secure satisfactory landing location for this vessel.
1.7.3 Inspector’s Office: The Contractor shall provide the Government inspector office space on board the dredge. The office shall include air conditioning, desk, chair, file cabinet, etc. The office shall be equipped with a dredge electronic tracking system capable of continuously displaying real time positioning of the dredge, by track plot or CRT screen, in relation to both the before-dredge surveyed shoals and at the disposal area. This system should be identical to the matrix screen found in the lever room.
1.8 PRECONSTRUCTION CONFERENCE
1.8.1 A preconstruction conference will be arranged by the
Government's representative after award of contract and before commencement of work. The Government's representative will notify the Contractor of the time and date set for the meeting. At this conference, the Contractor shall be oriented with respect to Government procedures and line of authority, contractual, administrative, and construction matters. Additionally, a schedule of required submittals will be discussed.
1.8.2 The Contractor shall bring to this conference the
submittals listed in Section 01 33 00 Paragraph entitled Preconstruction Submittals in either completed or draft form.
1.9 PROJECT SIGN
The Contractor shall furnish and install a project sign and a safety performance sign at all public boat marinas within 10 miles of dredging operations or moored equipment \within 60 calendar days after notice to proceed. The signs shall be constructed as indicated on the figures bound herein. Size, lettering, color, and paint shall conform to the details shown in Figure 5B "Construction Sign," Figure 5C "Fabrication and Mounting Guidelines," and Figure 5D "Safety Performance Sign," bound herein. All parts of frames and signs shall be given a primer coat of oil paint and a minimum of two finish coats of white semi-gloss paint. The Contractor shall maintain the sign in a "like new" condition throughout the life of the project, repainting and replacing members as necessary to accomplish this requirement. A map showing the location of all project signs shall be submitted to the Government. Final Payment will be withheld until all signs are removed. No direct payment will be made for the signs or maintenance of the signs.
1.10 LIQIDATED DAMAGES
If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $4,934.00 for each calendar day of delay until the work is completed and accepted.
If the Government terminates the Contractor’s right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
1.11 DATUM AND BENCHMARKS
The plane of reference of Mean Lower Low Water (MLLW) as used in these specifications is that determined by the benchmark and tide gage data as on file at the U.S Army, Corps of Engineers, Mobile District Office and the Irvington Site Office. The Contractor can obtain such data from the Project Engineer, Irvington Site Office, telephone (251)957-6019.
1.12 FINAL EXAMINATION AND ACCEPTANCE
As soon as practicable (within 14 calendar days or less if agreed to by the Contracting Officer) after completion of the entire work or any designated section thereof (if the work is divided into sections), as in the opinion of the Contracting Officer, the work in this section will not be subject to damage by further operations under the contract, such work will be thoroughly examined at the cost and expense of the Government by sounding or by sweeping, or both, as determined by the Contracting Officer, for determination of ACCEPTABILITY of PERFORMANCE by the Contractor. In order to ensure a feasible “face” of material for efficient dredging operations, work sections will be considered accepted if 90% of the material from the required dredging prism is removed;
however, the Contractor should make an attempt to dredge uniformly to not leave shoals and/or lumps. Should any shoals, lumps, or other lack of contract required dredging prism depth, width, or slope beyond the 90% acceptance criteria be disclosed by the Government’s examination, the Contractor will be required to remove said shoals by dragging or dredging the affected surface until the acceptable condition is corrected. Payment will be based on before-dredging (BD) and after-dredging(AD) quantity computations. Payment quantities and acceptance will be based on high frequency survey data run on 100-ft intervals including points of intersection. The contract drawings include typical sections showing the existing channel dimensions, the advanced maintenance, and the allowable overdepth. If the unacceptable shoal (work) area(s) of the channel bottom/slope is soft and the shoal (work) area(s) is small and forms no material obstruction to navigation, the removal of such shoal(s) may be waived at the discretion of the Contracting Officer. If re-dredging is required to correct the unacceptable work, the dredging will be paid at the current unit price for dredging, however, the maximum payment quantity (original and re-dredgings) will be the original computed pay quantity in the required dredging prism (plus any applicable allowable overdepth quantity, as applicable) based on the original before-dredging surveys. The Contractor or their authorized representative will be notified when soundings and/or sweepings are to be made and will be permitted to accompany the survey party. When the original or unacceptable area(s) is found to be in satisfactory condition, it will be accepted finally. Should more than two sounding or sweeping operations by the Government over an area be necessary by reason of work for the removal of unacceptable shoals disclosed at a prior sounding or sweeping, the cost of such third and any subsequent sounding or sweeping operations will be charged against the Contractor at the rate of $2,500.00 per day for each day in which the Government (or Government A-E Contractor) plant is engaged in sounding or sweeping and/or is enroute to or from the site or held at or near the said site for such operations.
For the purpose of acceptance, the work to be done will be divided into approximate 2,000-foot sections as defined below:
Dredging Reach No. From Station To Station 1 (partial) 244+66 260+00
2-18 260+00 600+00
19-24 1250+00 1370+00
Optional dredging assignments will be divided into approximate 2,000-foot sections as defined below:
Dredging Reach No. From Station To Station
Option 1:
1 (partial) 9+30 22+00
2 (partial) 22+00 32+76
Option 2:
1 (partial) 105+00 110+00
2-3 110+00 150+00
Option 3:
1 (partial) 164+00 172+00
2-3 172+00 212+00
1.12.1 Final acceptance of the whole or part of the work and the deductions or corrections of deductions made thereon will not be reopened after having once been made, except on evidence of collusion, fraud, or obvious error, and the acceptance of a completed section shall not change the time of payment of the retained percentages of the whole or any part of the work.
1.12.2 After acceptance by the Government, of the whole or part of the work, but before the Contractor has effected demobilization, should any shoals, lumps, or other lack of required contract depth be disclosed by an examination made by the Government, the Contractor may be requested to remove any such shoal by using the on-site dredging plant and process, to be paid at the original contract rate for dredging in this location.
This additional dredging is subject to a supplemental agreement under the contract and is only activated by the Contracting Officer (and if funds are available).
1.12.3 Shoaling in the dredging prism, which occurs in the whole or part of the work not yet offered by the Contractor as candidate for acceptance examination by the Government, is the responsibility of the Contractor (notwithstanding other clauses or provisions of this contract).
The Contractor should order the accomplishment of all the work of this contract in such a manner that causes the least exposure to such in-process shoaling.
1.13 PERFORMANCE EVALUATION OF CONTRACTOR
As a minimum, the Contractor's performance will be evaluated upon final acceptance of the work. However, interim evaluation may be prepared at any time during the contract performance when determined to be in the best interest of the Government.
The evaluation will be completed in the Contractor Performance Assessment Reporting System (CPARS), and the Contractor will be rated either exceptional, very good, satisfactory, marginal, or unsatisfactory in the areas of Quality, Schedule, Cost Control, Management, Small Business, Regulatory, and Other Areas. The Contractor will be advised of any unsatisfactory rating, either in an individual element or in the overall rating, prior to completing the evaluation, and all Contractor comments will be made a part of the official records. Performance Evaluation Reports will be available to all DOD Contracting offices for their future use in determining Contractor responsibility, in compliance with DFARS 36.201(c)(1).
-- End of Section --
Section 01 00 01
SECTION 01 00 01
GENERAL CONTRACT REQUIREMENTS
1. BOARD OF CONTRACT APPEALS
2. REQUESTS FOR INFORMATION
3. DESCRIPTION OF WORK
4. PREAWARD INFORMATION
5. CONTRACT PRICES - BIDDING SCHEDULE
6. REQUIRED INSURANCE
7. EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE
8. U.S. ARMY CORPS OF ENGINEERS SAFETY AND HEALTH REQUIREMENTS MANUAL,
EM 385- 1-1
9. AFFILIATED BIDDERS
10. MANUALS AND PUBLICATIONS
11. BULLETIN BOARD
12. LABOR REPORTS
13. PROTECTION OF MATERIAL AND WORK
14. ENGLISH-SPEAKING REPRESENTATIVE
15. PROHIBITION AGAINST CONTRACTING WITH INDIVIDUALS OR ENTITIES
DESIGNATED AS SIGNIFICANT NARCOTICS TRAFFICKERS
16. CONTRACTOR PAYMENT REQUEST
17. PARTNERING
18. POTABLE WATER
19. PRESERVATION OF HISTORICAL, ARCHEOLOGICAL, AND CULTURAL RESOURCES . 9
20. WORK IN QUARANTINED AREA
21. KEY PERSONNEL, SUBCONTRACTORS AND OUTSIDE ASSOCIATES OR CONSULTANTS
22. ACCOMMODATIONS AND MEALS FOR INSPECTORS
23. SEAGOING BARGE ACT
24. DELIVERY, PROSECUTION AND TERMINATION
25. SUNDAYS, HOLIDAYS AND NIGHTS
26. RETAINAGE--SMALL BUSINESS SUBCONTRACTING REPORTING
27. JOINT VENTURE BID REQUIREMENTS
28. SMALL BUSINESS SUBCONTRACTING PLAN
29. PROCEDURES FOR SUBMISSION OF BIDS AND BID OPENING
Maintenance Dredging Operations In Mobile Harbor, Mobile, Alabama
Solicitation No.
W9127826BA001
1. BOARD OF CONTRACT APPEALS
The agency board of contract appeals having jurisdiction over all appeals from final decisions of the Contracting Officer under the Contract Disputes Act of 1978 is the Armed Services Board of Contract Appeals, Skyline Six, 5109 Leesburg Pike, 7TH Floor, Falls Church, Virginia 22041.
End of Paragraph
2. REQUESTS FOR INFORMATION
Any questions about this solicitation, including technical questions about plans and specifications, shall be submitted via the Bidder Inquiry Portal in ProjNet at https://www.projnet.org. To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below the key for access. A prospective vendor who submits a comment /question will receive an acknowledgement of their comment/question via email, followed by an answer to the comment/question after it has been processed by our technical team. All timely questions and approved answers will be made available through ProjNet.
Questions shall be submitted no later than 17 April 2026 at 2:00 PM Central Time (CT) to allow time for a response, and amendment to the solicitation if necessary. On this date and time, the portal will be closed.
For technical questions, no other means of communication, e-mail, fax, or telephone will be accepted. Oral exchanges between Offerors or Bidders and the government prior to award of the contract will not be binding. In addition to information available to Offerors or Bidders on the Bidder Inquiry Portal, any information concerning this solicitation will be furnished to all Offerors or Bidders as an amendment to the solicitation if the information is necessary to the submittal of offers or bids.
The Solicitation Number is: W9127826BA001 The Bidder Inquiry Key is: BKW6YE-UVRJUF
Specific Instructions for ProjNet Bid Inquiry Access:
1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.
2. Identify the Agency. This should be marked as USACE.
3. Key. Enter the Bidder Inquiry Key listed above.
4. Email. Enter the email address you would like to use for communication.
5. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.
6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret
Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.
7. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.
Specific Instructions for Future ProjNet Bid Inquiry Access:
1. For future access to ProjNet, you will not be emailed any type of password. You will utilize your Secret Question and Secret Answer to log in.
Maintenance Dredging Operations In Mobile Harbor, Mobile, Alabama
2. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.
3. Identify the Agency. This should be marked as USACE.
4. Key. Enter the Bidder Inquiry Key listed above.
5. Email. Enter the email address you used to register previously in ProjNet.
6. Click Continue. A page will then open asking you to enter the answer to your Secret Question.
7. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.
Note: Questions/comments should be entered in the system one at a time. Lists of questions uploaded into ProjNet, regardless of the format, will not be answered.
Offerors are requested to review the solicitation and amendments in their entirety, as well as to review the Bidder Inquiry Portal for previous questions and responses, prior to submission of a new inquiry on the Portal.
CAUTION: ANY INQUIRY SUBMITTED AND ANSWERED WITHIN THIS SYSTEM, WILL BE
ACCESSIBLE TO VIEW BY ALL INTERESTED OFFERORS OR BIDDERS ON THIS SOLICITATION.
The call center for the ProjNet operates weekdays from 8 AM to 5 PM U.S. Central Time Zone. The telephone number is 1-800-428-HELP.
End of Paragraph
3. DESCRIPTION OF WORK
In general, the requirement will be for trailing suction hopper dredges and/or mechanical dredges with scows for maintenance dredging of Mobile Harbor, Mobile, Alabama.
NOTE: The above general outline of features of the work does not in any way limit the responsibility of the Contractor to perform all work and furnish all plant, labor, equipment and materials required by the specifications and the drawings referred to therein.
Disclosure of Magnitude: $10,000,000 - $25,000,000
4. PREAWARD INFORMATION
Each bidder shall furnish either with his bid or within 3 days after a request is made for submittal of preaward data a statement of whether he is now or ever has been engaged in any work similar to that covered by the specifications herein, the dollar value thereof, the year in which such work was performed, and the manner of its execution, and giving such other information as will tend to show the bidder's ability to prosecute the required work. The "such other information" referred to above shall include but is not limited to the following:
a. The name and address of the office or firm under which such similar work was performed. Include names and telephone numbers of personnel within each organization who are familiar with the prospective contractor's performance.
Maintenance Dredging Operations In Mobile Harbor, Mobile, Alabama
b. A list of key personnel available for the instant project and their qualifications.
c. A copy of bidder's latest financial statement, including the names of banks or other financial institutions with which the bidder conducts business. If the financial statement is more than 60 days old, a certificate should be attached stating that the financial condition is substantially the same, or if not the same, the changes that have taken place. Such statements will be treated as confidential.
d. A list of present commitments, including the dollar value thereof, and name of office under which the work is being performed. Include names and telephone numbers of personnel within each organization who are familiar with the prospective contractor's performance.
e. If the bid exceeds $1,000,000 and the prospective contractor is a large business concern, he must submit a subcontracting plan in compliance with the Contract Clause entitled SMALL BUSINESS
SUBCONTRACTING PLAN.
5. CONTRACT PRICES - BIDDING SCHEDULE
Payment for the various items listed in the Bidding Schedule shall constitute full compensation for furnishing all plant, labor, equipment, appliances, materials and bonds (performance and payment), and for performing all operations required to complete the work in conformity with the drawings and specifications.
All costs for work not specifically mentioned in the Bidding Schedule shall be included in the contract prices for the items listed.
6. REQUIRED INSURANCE
The Contractor shall procure and maintain during the entire period of his performance under this contract, the following minimum insurance in accordance with the Contract Clause entitled "Insurance-Work on a Government Installation." Workmen's Compensation and Employers' liability Insurance:
Workmen's Compensation and Occupational Disease Coverage in accordance with statutory limits.
Employers' Liability Coverage with a minimum limit of $100,000.
Comprehensive Automobile Liability Insurance:
Bodily injury coverage with minimum limits of $200,000 per person and $500,000 per occurrence. Property Damage Coverage with a minimum limit of $20,000 per occurrence.
Comprehensive General Liability Insurance:
Bodily injury coverage with minimum limits of $500,000 per occurrence.
Maintenance Dredging Operations In Mobile Harbor, Mobile, Alabama
7. EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE
(a) This clause does not apply to terminations.
(b) Allowable cost for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a contractor or subcontractor at any tier shall be based on actual cost data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the contractor's accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series equipment from the contractor's accounting records, costs for that equipment shall be based upon the applicable provisions of EP 1110-1-8, "Construction Equipment Ownership and Operating Expense Schedule," Region III. Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the contracting officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retrospective pricing, the schedule in effect at the time the work was performed shall apply.
(c) Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-36.
Rates for equipment rented from an organization under common control, lease-purchase arrangements, and sale-leaseback arrangements will be determined using the schedule, except that actual rates will be used for equipment leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees.
(d) When actual equipment costs are proposed and the total amount of the pricing action exceeds the small purchase threshold, the contracting officer shall request the contractor to submit either certified cost or pricing data, or partial/limited data, as appropriate. The data shall be submitted on Standard Form 1411, "Contract Pricing Proposal Cover Sheet."
8. U.S. ARMY CORPS OF ENGINEERS SAFETY AND OCCUPATIONAL HEALTH
REQUIREMENTS MANUAL, EM 385- 1-1
This…