W9127825R0010_Consolidation DF Redacted.pdf
PDF 7 MB Posted
- Attached to
- CENTAM MATOC - Construction & Repair Projects Federal contract opportunity
- Solicitation number
- W9127825R0010
About this file
This is a Determination & Findings (D&F) document discussing the consolidation of construction and repair projects for the U.S. Army Corps of Engineers Mobile District. The document outlines both quantitative and qualitative benefits of consolidating multiple requirements under a single contract vehicle, though it notes the quantitative benefits threshold was not met. The requirements involve construction projects to be performed at multiple locations, funded through annual appropriations.
The document indicates contractor engagement sessions were held with positive participation, and contractors were instructed to register in SAM.gov and PIEE systems for access to current and future solicitations. The projects are described as being typically identified late in the fiscal year prior to construction award, creating time constraints for design and RFP development. The consolidation appears to be structured as a Multiple Award Task Order Contract (MATOC) under solicitation number W9127825R0010, with an anticipated award date of January 29, 2026.
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
-- (i) Two or more requirements of the Federal agency for supplies or services that have been provided to or performed for the Federal agency under two or more separate contracts, each of which was lower in cost than the total cost of the contract for which offers are solicited; or (ii) Requirements of the Federal agency for construction projects to be performed at two or more discrete sites.
consolidated acquisition. Although the quantitative benefits are not met, the qualitative benefits of the consolidated approach are critical to the success of the Mobile District.
(1)
(2)
(3)
(4)
There was good engagement from the contractors in all sessions. Contractors were requested to begin registering in SAM.gov and PIEE to ensure they could access current and future solicitations.
are typically funded by annual appropriations that expire at the end of the FY.
These projects are typically identified, defined, and provided to the District late in the FY preceding the year of construction award, allowing limited time for design or Design Build RFP development in the fiscal year of construction award essential projects leaves little time for contract execution once the RFP is completed, and therefore
File details come from the government source that posted it. Updated .