W9127824R0037_AE Services_USACE_ Mobile District_Horizontal Design Program_Amended_250124.pdf

PDF 454 KB Posted

Attached to
Notice for Architect and Engineering (A-E) Services to Support the U. S. Army Corps of Engineers (USACE) South Atlantic Division, Mobile District, Horizontal Design Program
Solicitation number
W9127824R0037
Issued by

About this file

This is a Solicitation Announcement from the U.S. Army Corps of Engineers (USACE) South Atlantic Division, Mobile District for architect-engineer (A-E) services to support their Military Design and Construction Program. The solicitation (W9127824R0037) seeks A-E services specifically for horizontal construction, with a shared capacity MATOC value of $49M and a five-year ordering period.

The procurement will be conducted using FAR Part 36.6 and Brooks Act procedures under NAICS code 541330, with no size standard restrictions. The government intends to make at least six total contract awards, with a minimum of three awards reserved for small businesses (defined as having maximum average annual receipts of $25.5M over 5 years). Required services include renovation/repair projects, new construction, master planning, design-build solicitations, feasibility studies, cost estimating, site/civil engineering for airfields and infrastructure, environmental permitting, geotechnical work, and surveying. Key personnel must include 17 specified roles such as Project Manager, Civil Engineer, Environmental Engineer, and others with specific registration requirements. Proposals using SF330 forms must be submitted via the PIEE website by February 14, 2025, with questions due by January 24, 2025 through the ProjNet system.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Select Document Type: Solicitation Announcement

Classification Code: C – Architect and Engineering Services

Subject: Notice for Architect and Engineering (A-E) Services to Support the U.S. Army Corps of Engineers (USACE) South Atlantic Division, Mobile District, Horizontal Design Program

Solicitation Number:

W9127824R0037

Set-Aside Code:

None

Response Date:

February 14 7, 2025

Place of Performance:

USACE, Mobile District

CONTRACT INFORMATION: The U.S. Army Corps of Engineers, South Atlantic Division, Mobile District requires architect-engineer (A-E) Services for its Military Design and Construction Program.

This procurement will be conducted in accordance with FAR Part 36.6 and Brooks Act selection procedures for the acquisition of A-E services. The North American Industry Classification System (NAICS) code for this action is 541330. It is open to all A-E firms regardless of size. The Government intends to award an A-E MATOC with a shared capacity of $49M with a five-year ordering period. The market research analysis supports the establishment of an unrestricted procurement with a small business reserve IAW FAR 19.503. This strategy provides a target of at least six total contract awards with at least three small business awards for the small business reserve. The small business size standard is a maximum of $25.5 million of average annual receipts for its preceding 5 fiscal years. If a minimum of 3 awards cannot be made to the small business reserve, a SB reserve will not be created, and the procurement will be operated as an unrestricted award. The SB reserve awards will be to those small business firms found most highly qualified IAW EP 715-1-7 paragraph 3-10c. Additionally, this acquisition incorporates the contract reserve process IAW FAR 19.504(c)(1)(i), Orders Under Reserves. At the task order level, the Small Business Reserve will be considered first. Should there be an insufficient number of qualified small businesses, the task order TORN will be issued to all MATOC holders.

Work under this contract will be subject to satisfactory negotiation of individual firm fixed price task orders. Rates will be negotiated for each 12-month period of the contract. All interested A-E firms are cautioned to review the restrictions of FAR Part 9.5 (Organizational and Consultant Conflicts of Interest), and all large A-E firms are reminded that in accordance with the provisions of PL 95-507, they will be expected to place subcontracts with small and disadvantaged businesses to the maximum extent practicable consistent with the efficient performance of the contract. A large business awardee must comply with FAR 52.219-9, regarding the requirement for a subcontracting plan for that part of the work to be subcontracted and will be required to submit a detailed subcontracting plan during contract negotiations. For large businesses selected for task order awards, specific subcontracting objectives will be requested and negotiated that will form the basis for task order subcontracting performance evaluation. The selected Small Business firms will be required to perform work in accordance with 52.219-14, Limitations on Subcontracting (DEVIATION 2021-O0008, Revision 1) should a task order be issued to a firm within the small business reserve.

PROJECT INFORMATION: AE services to support the Mobile District with planning and design, specifically for horizontal construction, for the Mobile District’s Engineering Design Program for the Military, Civil, and Support for Other missions, meeting the definition of AE Services as defined in 40 U.S.C. 1101 and FAR 2.101. The selected firms must have the capability using in-house staff or consultants to provide timely and cost effective responses to support the Horizontal Design Program to include but not limited to: renovation/repair projects and new construction and the development of construction plans and specifications for new horizontal construction projects; master and sub-area development planning, preparation of the technical portions of design-build solicitations; preparation of project definition and programming documents, charrettes, value engineering studies, facility condition assessments (as it relates to airfield pavements, storm drainage infrastructure, dams and levees), preliminary studies through complete Project Feasibility Report development, interviewing and investigations, cost estimating;

site/civil engineering designs and studies for airfields, roads, pavement design, grading, drainage, traffic studies, water and wastewater distribution, collection, and treatment; environmental experience with Section 404 and state wetland permits, best management practices (BMPs), modeling; power distribution and Energy Resilience Conservation Investment Program (ERCIP) projects; topographic & hydrographic surveys, subsurface utility locations/investigations and GIS application; geotechnical engineering design and studies, investigations, testing, drilling, and modeling.

Most of the work will be on military installations; however, work may also include a variety of projects under the Interagency/International Services (IIS) program. The selected firm must have the capability using in-house staff or consultants to perform surveying, mapping, geotechnical investigations, subsurface utility investigations, hazardous material testing, abatement planning, and remediation planning. Design drawings shall be produced in the AutoCAD, Autodesk Revit Building Information Modeling (BIM), Bentley BIM, or MicroStation format. The format will be specific to each project and will be specified in the AE scope of work for the specific project. If BIM is required for a specific project, all BIM models shall be delivered in their proprietary format along with exported IFC models, and 2D CAD drawings (construction documents). Technical specifications will be produced with SPECSINTACT software using Unified Facilities Guide Specifications. Responses to design review comments will be provided using the Government web-based Design Review and Checking System located at www.projnet.org. The work will be located primarily in with Mobile District Area of Responsibility (AOR) and other locations that may be assigned to the Mobile District. This includes Mobile District’s military and civil works boundaries which includes areas in the southeast United States and Central and South America.

SELECTION CRITERIA: The source selection factors for this procurement are listed below in descending order of importance. Factors 1 through 6 are primary. Factor 7 is secondary and will only be used as a tiebreaker among technically equal firms. Primary factors will be assigned a rating from “outstanding” to “unsatisfactory”, based on the risk to the Government that the Offeror will successfully perform that evaluated factor. An overall rating will also be applied to the proposal submission using the same rating scale. Proposals failing to respond or provide complete information for each factor as required by this solicitation will be determined non-compliant and will be removed from further consideration. After all ratings have been assigned, Offerors will be ranked as “Most Highly Qualified”, “Highly Qualified”, and “Not Qualified” in accordance with EP 715-1-7, Architect-Engineer Contracting In USACE.

For purposes of this solicitation, a stand-alone contract (such as a “C” or “P” type contract) or single task order under an Indefinite Delivery Contract (IDC) is considered one project. Separating activities performed under a contract or task order will not be considered multiple projects;

conversely, combining activities performed under separate contracts or task orders to produce a single project will not be evaluated or considered. A single task under an IDC is considered a project, not an IDC itself.

Factor 1. Professional Qualifications (Resumes) (SF330, Part I, Section E) (not to exceed 20 pages)

Part A – Resumes of Key Personnel (Section E, Blocks 12 – 18): Offerors must have, either in-house or through consultants or subcontractors, the disciplines listed below. To demonstrate qualifications, resumes for persons filling these disciplines are to be provided in Section E. Each resume shall be one page in length. All Key Personnel are required to have a bachelor’s or higher degree from an U.S. accredited four-year college or university with a major in the field of study (the accredited university must be listed on the resume). Where professional registration/certification required, the state of registration and license number must be included on the resume. All Professional Registrations, Licensures and/or Certifications must state certification numbers and expiration dates (as applicable). All Professional Registrations, Licensures and/or Certifications must identify the state in which obtained. Specialist disciplines shall have a degree/certification as indicated/required below and training in the area of specification. In Block 13, the role listed must use the exact same discipline nomenclature as listed below. If an individual will serve in more than one role, then all disciplines shall be clearly indicated in Block 13. If multiple resumes are provided for the same discipline, all resumes within the page limit will be evaluated and average evaluation of those resumes will be considered for that discipline. Any resumes included beyond the 20-page limit will not be evaluated, resumes included within the first 20 pages will be the only resumes evaluated. The SF330 may be modified to meet the Submission Requirements; however, the content of Section E is not to be altered and all items within Section E shall be answered completely. Additionally, all Key Personnel must be shown on the organizational chart in Section D. The following disciplines are required:

1. Project/Task Order Manager

2. Civil Engineer, professional registration required, prefer registration within Mobile

District’s AOR.

3. Geotechnical Engineer, professional registration required.

4. Environmental Engineer, professional registration required.

5. Surveyor, professional registration required, prefer registration within Mobile District’s

AOR

6. Landscape Architect, professional registration required.

7. Master planner, demonstrate experience with area development plans, installation/base development plan, overall master plans, Certified AICP or equivalent required.

8. Cost Estimator, Certified AACE, ICEC, PCEA or equivalent required.

9. Geologist, professional registration required, prefer registration within Mobile District’s

AOR.

10. Biologist

11. Archaeologist

12. Hydraulic Engineer, professional registration required.

13. Coastal Engineer, professional registration required.

14. Electrical Engineer, professional registration required.

15. Structural Engineer, professional registration required.

16. IT Systems/Network/Communications Engineer, Registered Communications Distribution

Design (RCDD) required.

17. Architect, professional registration required.

Part B – Relevant Projects (Section E, Block 19): All Key Personnel are required to have five years of project experience in their discipline demonstrated by projects with scope, magnitude, and complexity comparable to this solicitation. The definition of a project is as noted in ‘Selection Criteria’ above. Relevant projects are those that reflect experience performing the respective discipline. Relevant Project information should be brief and highlight specific roles and tasks performed by the Key Personnel, Project Type, Scope, and Costs. When completing Section E for each key person, in Block 19, include the firm with whom the person was employed when performing on the project if not the current employer. No more than five projects should be listed for each resume, and each project listed must have the design efforts completed within ten years of publication of this solicitation announcement. (Note: The projects provided for this factor may also be used to address Factor 2.)

The evaluation of Factor 1 will take into consideration the education and current registration, licensure or certification(s), or specialized training, as applicable, of each person named for each discipline and that person’s longevity with the firm named in Block 15. It will also take into consideration the person’s relevant project experience provided in Block 19. More weight will be given to experience that is like that described above in the paragraph titled Project Information and project designs that are full-design type projects, on military installations, and completed within the Mobile District AOR or the southeast United States. This factor may be assessed Strengths or Weaknesses, as appropriate. Only the Key Personnel disciplines requested in this solicitation will be evaluated.

The basis of evaluation for Factor 1 will be information submitted in Part I, Sections E and G.

Factor 2. Specialized Experience and Technical Competence (Projects) (SF330, Part I, Section F) (not to exceed 20 pages)

For Factor 2, Offeror’s are to demonstrate specialized experience and technical competence which meets the definition of A-E Services as defined in 40 U.S.C. 1101 and FAR 2.101. This factor considers specialized experience and technical competence specifically for horizontal construction with emphasis on military installations and USACE Civil Works Projects, specific to performing services like those described above in the paragraph titled Project Information.

In Section F Offerors are to submit ten projects that best illustrate the proposed team’s qualifications for award of a contract. (Note: The projects provided for Factor 1 may also be used to address this factor, however, not by reference only.) The definition of a project is as noted in “Selection Criteria” above. For each project use no more than two pages and note the contract or task order number, as applicable. The SF330 may be modified to meet the Submission Requirements; however, the content of Section F is not to be altered (removal or deletion of required blocks) and all items within Section F shall be answered completely. Five of the projects submitted shall specifically address the following areas of emphases and shall be presented in the order listed below.

Project 1 – Military Airfield Design (Paving, Grading, Drainage, and Survey Features) Project 2 – Roadway (Bridge) Design (Paving, Grading, Drainage, and Survey Features) Project 3 – Comprehensive Stormwater Master Plan for large military installations Large

Stormwater for Site Development (Hydrology and Hydraulic analysis including 2D & 3D stormwater modeling, inventory condition assessment, flood mapping)

Project 4 – General Civil Site Design (Mass Grading and Site Development) Project 5 – Dams or Levee Systems Geotechnical including (Investigation, Slope Stability, Seepage Analysis, Structural)

Projects in which the AE Service is not 100% completed will not be evaluated. The AE service includes evaluation, design, studies, etc. it does not include construction phase assistance or construction management services. The Offeror shall state the percent complete for each project.

All projects must have been completed within ten years of publication of this solicitation announcement (see Block 22). At least six of the projects presented must show that the Offeror (the firm submitting the SF330 as the prime contractor), whether as a prime contractor or subcontractor, performed the majority (>50%) of the AE work on the project. To demonstrate such performance, Offerors shall state the percentage of work they performed. If a proposed subcontractor also worked on the project, state the percentage of work it performed. If an Offeror submits more than six projects, those projects must reflect performance of work by the Offeror, or one or more of its proposed subcontractors. For each such project state the percentage of work performed by the Offeror, and/or the percentage of work performed by each proposed subcontractor. Clearly identify the Project Number (as indicated above), Type and the Offeror’s role on the project. In Block 24, “cost” is the total value of the project, not simply the value of the work performed by the Offeror and/or any proposed subcontractor. The Government reserves the right to review any official performance evaluation system of records to inform its source selection decision. When completing Section G, in Block 26, along with the name of key personnel, include the firm with whom the person is or was associated at the time the project was performed. To demonstrate quality of past performance, for each project the Offeror must provide a Contractor Performance Assessment Report (CPAR), either interim or final. If a CPAR is not available, the Offeror must provide a NAVFAC/USACE Past Performance Questionnaire (PPQ). If a PPQ is provided and there is a CPAR, the CPAR rating will govern. CPAR and/or PPQ information for the projects shall be placed immediately following the last page of each project in Factor 2 and do not count against the page count limit. The Government reserves the right to review any official performance evaluation system of records to inform its source selection decision.

Those firms submitting as Joint Ventures (JV) must follow the same procedures as any other Offeror with the following exception. If the JV (the Offeror) cannot provide at least six projects that demonstrate performance by the JV of 50% or more of a project, as either a prime contractor or subcontractor, the JV may provide projects performed by any partner of the offering JV that reflect performance of 50% or more of a project, as either a prime contractor or subcontractor. If the Offeror does not submit any projects that demonstrate performance by the JV, then the JV Offerors are required to submit projects at least one project from each of the partners. More consideration may be given for projects that were performed as a JV.

Of the projects submitted as prescribed above, relevant projects which will be given more weight are those that reflect the specialized experience and technical competence of the Offeror and/or proposed subcontractor(s), as prime contractors or subcontractors, performing services similar to those described above in the paragraph titled Project Information. More weight will be given to experience with project designs that are full-design type projects, on military installations, and completed within the Mobile District AOR or within the southeast United States; experience with subcontracting team(s); and project design experience that are like that described above in the paragraph titled Project Information. This factor may be assessed Strengths or Weaknesses, as appropriate.

The basis of evaluation for Factor 2 will be information submitted in Part I, Sections F and G.

Factor 3. Work Management (SF330, Part I, Section H) (not to exceed 5 pages)

In Part I, Section H, the Offeror must provide a proposed work management plan demonstrating its team’s breadth of knowledge and experience with managing for horizontal design work. The narrative should describe the corporate approach, driving criteria or potential constraints, and examples of successful performance. The narrative should specifically discuss knowledge of, and experience with, work management planning to include quality management, subcontractor management, prior experience of the prime firm and any significant consultant, version control management, proactive internal and external communication protocols, and independent submittal review processes in the context of providing services under multiple task orders. More weight will be given to prior experience with subcontracting team(s) and successful management of simultaneous work that are similar to that described above in the paragraph titled Project Information. This factor may be assessed Strengths or Weaknesses, as appropriate.

Factor 4. Past Performance (SF330, Part I, Section H) (not to exceed 3 pages)

Offerors shall demonstrate in narrative (or other format) a history of customer satisfaction with the Offeror's quality of work, cost control and scheduling. Past Performance history is not to be limited to information presented in Factor 2. Past performance can be substantiated by presentation of CPARS or PPQ ratings, or customer ratings from other project evaluation systems. Customer excerpts or quotes from prior evaluations for the purposes of substantiating the narrative are not desired. The narrative should describe the corporate approach for maintaining success with customer satisfaction with the Offeror's quality of work, cost control and scheduling. This factor may be assessed Strengths or Weaknesses, as appropriate, with more weight given to successful performance ratings on Department of Defense contracts.

Factor 5. Capacity to Accomplish the Work (SF330, Part I, Section H) (not to exceed 2 pages)

Firms are to clearly demonstrate the capacity to accomplish at least four $500,000 individual task orders simultaneously as the Prime. This factor may be assessed Strengths or Weaknesses, as appropriate.

Factor 6. Knowledge of Locality (SF330, Part I, Section H) (not to exceed 2 pages)

Offers are to clearly demonstrate their knowledge of the locality of the Mobile District’s AOR specifically in support of the Horizontal Program. This includes Mobile District’s military and civil works boundaries which includes areas in the southeast United States and Central and South America. The narrative should describe any known geological features, climatic conditions, local construction methods, regulatory agency coordination and permitting requirements, and/or other features that are unusual or unique to Mobile District’s AOR and the southeast United States. This factor may be assessed Strength or Weakness, as appropriate.

Factor 7. SB and SDB Participation (SF330, Part I, Section H) (not to exceed 3 pages including the Small Business Participation Plan Form)

Small Business Participation Plan (LB and SB Offerors). All Offerors shall identify the extent to which Small Businesses (SBs), Veteran-Owned Small Businesses (VOSBs), Service-Disabled Veteran-Owned Small Businesses (SDVOSBs), HUBZone Small Businesses, Small Disadvantaged Businesses (SDBs) Woman-Owned Small Businesses (WOSBs), would be utilized in the performance of this proposed contract. The expected minimum participation goals are listed in the evaluation criteria below.

Evaluation Criteria: All Offerors (both large and small businesses) will be evaluated on the level of small business commitment that they demonstrate for the proposed acquisition. A small business Offeror also receives credit for their small business participation as a Prime Contractor and can apply their dollar value and calculate percentages in all the applicable small business categories.

The Government will evaluate the proposals to determine which offeror(s) propose the best value in terms of meeting all the Small Business Participation goals using the following criteria:

a. The extent of participation of small business in terms of the percentage of the value of the total acquisition. Expected minimum percentages are:

1. Small Business: 6.0% of total contract value (aggregate of all small businesses participation including the small business socioeconomic contracting programs (i.e., 8(a), HUBZone, SDVOSB, or WOSB programs).

2. Small Disadvantaged Business (SDB): 1.5% of total contract dollars.

3. Women-Owned Small Business (WOSB): 2.0% of total contract dollars.

4. Veteran-Owned Small Business (VOSB): 2.0% of total contract dollars.

5. Service-Disabled Veteran-Owned Small Business (SDVOSB): 1.0% of total contract dollars.

b. The extent to which such firms, as defined in FAR Part 19, are specifically identified in proposals, and linked to specific work. This should include a diagram or narrative showing generally when socio-economic expenditures will occur throughout the period of performance. This data will assist in quantifying expectations of subcontracting percentage achievement when evaluating subcontracting performance on Individual Subcontracting Reports. Provide the names of Small Business, VOSB, SDVOSB, HUBZONE SB, SDB, or WOSB who would participate in the proposed contract, identifying specific components to be produced or services to be performed by them, and the estimated total dollars of such work;

c. The extent of commitment to use such firms (existing written and enforceable commitments as opposed to business relationships that are simply planned or theoretical);

d. The identification of the complexity and variety of work that will be performed by the specific small businesses. The extent to which the Offeror provides detailed explanations/documentation supporting the proposed participation percentages, or lack thereof. This can include market research showing availability of relevant companies certified in the socio-economic categories corresponding to proposed participation percentages.

NOTE: All Offerors (both large and small businesses) are required to complete the following Small Business Participation Plan Form and submit with their proposal. This form will be the primary source of data used to evaluate the Small Business Participation factor. Offerors market research and small business participation analysis in accordance with the evaluation criteria listed in the previous paragraphs should be reflected on this form. Provide the names of the small business firms that would participate in the proposed contract, identifying specific components to be produced or services to be performed by them in addition to the information required above. The Small business Participation Plan Form shall be included with the SF330, Part I, Section H. If applicable, The Joint Venture (JV) Agreements, signed Teaming Agreements, and/or Letters of Commitment are to be submitted with SF330, Part II.

SMALL BUSINESS PARTICIPATION PLAN FORM

(a) Check the applicable size and categories for the PRIME offeror only -- Check all applicable boxes:{ } Large Prime{ } Historically Black Colleges or Universities and Minority Institutions (HBCU/MI)or{ } Small Business Prime; also categorized as a{ } Small Disadvantaged Business (SDB){ } Woman-Owned Small Business (WOSB){ } Historically Underutilized Zone (HUB Zone) Small Business{ } Veteran-Owned Small Business (VOSB){ } Service-Disabled Veteran- Owned Small Business (SDVOSB)

(b) Submit the total combined percentage of work to be performed by both large and small businesses (include the percentage of work to be performed both by Prime and Subcontractors):

Example: If Prime proposes a price of $1,000,000 (including all options), and small business(es) will provide $250,000 in services/supplies as a Prime or subcontractor, the % planned for small businesses is 25%; and 75% for large business equaling 100%.Total Percentage planned for Large Business(es): _______%Total Percentage planned for Small Business(es): _______% Total:

_______% (Total Must =100%)

(c) Please indicate the total percentage and/or total dollars of participation to be performed by each type of subcategory of small business. The percentage of work performed by Small Businesses that qualify in multiple small business categories may be counted in each category:

Example: Victory Prop Mgt (WOSB and SDVOSB) performing 2%; and Williams Group (SDB, HUBZone Small Business and WOSB) performing 3%. Results equate to: SDB 3%; HUBZone 3%;

WOSB 5%; SDVOSB 2%; VOSB 2%;).

SDVOSBs are also VOSBs automatically; however, VOSBs are not automatically SDVOSBs.

Small Disadvantaged Business _______% HUB Zone Small Business _______% Woman-Owned Small Business _______% Service-Disabled Veteran-Owned SB _______% Veteran Owned Small Business _______%

(d) List principal supplies/services to be performed by Small Businesses:

Example: If a Small Business qualifies also as a WOSB and a SDVOSB, and you can add them to each category below for which they qualify.

Name of Company Type of Service/Supply:

Small Business SB):__________________________________________________________

Small Disadvantaged Business (SDB):____________________________________________

Women-Owned Small Business (WOSB):_________________________________________

Veteran-Owned Small Business (VOSB):__________________________________________ Service-Disabled Veteran-Owned Small Business (SDVO):___________________________

Historically Black Colleges and Universities and Minority Institutions (HBCU/MI):

(e) Describe the extent of commitment to use small businesses (for example, what types of commitments if any, are in place for this specific acquisition either ? small business prime, written contract, verbal, enforceable, non-enforceable, joint venturing, mentor-protege, etc.)____________________________________________________________________________

**end of Small Business Participation Plan Form***

Additional Important Note for Other Than U.S. Small Businesses ONLY.IAW FAR 52.219-9, if a large business is selected as one of the most highly qualified firms to enter into negotiations for a contract, it must submit an acceptable Small Business Subcontracting Plan to be eligible for award.

Subcontracting Plans shall not be submitted at the time of SF330 submission. A Small Business Subcontracting Plan is separate from the Small Business Participation plan and must meet the requirements of FAR 52.219-9 and DFARS 252.219-7003 (or DFARS 252.219-7004 if the offeror has a comprehensive subcontracting plan). SMALL BUSINESS SUBCONTRACTING PLANS

SHALL REFLECT AND BE CONSISTENT WITH THE TOTAL CONTRACT DOLLAR

COMMITMENTS OFFERED IN THE SMALL BUSINESS PARTICIPATION PLAN

Interviews. As required by acquisition regulations, interviews for the purpose of discussing prospective contractor qualifications will be conducted by the A-E Evaluation Board (Selection Board). Interviews will be held with those offerors deemed by the Board to be qualified for award.

Interviews will be conducted by telephone and will most likely occur 30 working days after the Selection Board convenes. Phone calls and personal visits for the purpose of discussing this solicitation are not allowed.

SUBMISSION REQUIREMENTS: Interested AE firms or joint ventures (JVs) with the capabilities to perform this work are invited to submit one complete PDF of their SF330 (Architect- Engineer Qualifications) proposal. Offerors must submit the electronic proposal package to the USACE via the Procurement Integrated Enterprise Environment (PIEE) website (https://piee.eb.mil). Emailed submissions of proposals are not permitted and will not be accepted under any circumstances. The Government must receive your proposal no later than the time and date as specified in this solicitation. The PIEE website must show the proposal was prior to the specified time. Offerors may confirm proposal receipt by emailing the following Points of Contact:

Ms. Linda Bookout at Linda.L.Bookout@usace.army.mil. The current edition of the SF330 (Revision 07/2021) must be used and may be obtained from the Government Printing Office or from the following web site:

http://www.gsa.gov/portal/forms/download/116486. PDFs shall be compatible with Adobe Acrobat XI or an earlier version. Proposals submitted in a format other than as described above will not be accepted. All Offerors responding to this solicitation shall identify on the front cover of the SF330 their company name, solicitation number, and socioeconomic category in regard to NAICS 541330 (LARGE BUSINESS, SMALL BUSINESS, WOMAN OWNED SMALL BUSINESS, etc). All Offerors, to include JVs, submitting proposals shall obtain a Unique Entity Identifier (UEI). Include the UEI in Part I, Section B, Block 5 next to the name of the firm. Additionally, all Offerors, to include JVs, must be registered in the System for Award Management (SAM). For instructions on registering with the SAM, go to https://www.sam.gov/SAM. JVs are to include a fully executed JV Agreement with their proposal at Part II. JVs submitting as 8(a) are to include a JV Agreement that has been reviewed by their respective SBA District. All fonts in Part I shall be at least 11 or larger in Arial (not Arial Narrow) to include text, tables, and figures. Fonts in Part II shall be at least 7 or larger in Arial (not Arial Narrow). Pages shall be 8-1/2 inches by 11 inches. The Organizational Chart required in Part I, Section D and the Matrix required by Part I, Section G may be presented on a sheet up to 11 inches by 17 inches. If 11 inches by 17 inches pages are used for sections D and G, each page will count as one page respectively. Do not use multi-column formatting. The SF330 is to be organized as indicated below.

Part I of the SF330 shall not exceed 68 pages, including cover sheets, cover letters, separators (tabs or divider pages), acronym list, and blank sheets, and shall be organized as follows:

SF330, Part I, Sections A, B, C and D.

SF330, Part I, Section E.

SF330, Part I, Section F.

SF330, Part I, Section G.

SF330, Part I, Sections H and I.

Part II of the SF330 is required for each branch office of the Offeror and any subcontractor that will perform a key role under the contract. Part II shall be organized as follows:

SF330, Part II General

SF330, Part II, Joint Venture Agreement, Teaming Agreements, and/or Letters of Commitment (as applicable).

OFFERS MUST BE RECEIVED BY THE METHODS INDICATED ABOVE NO LATER

THAN THE TIME AND DATE SHOWN ON PIEE WEBSITE, OR WILL BE

CONSIDERED LATE. To verify your submittal has been delivered, you may email Ms. Linda Bookout at: Linda.L.Bookout@usace.army.mil.

ALL QUESTIONS SHALL BE SUBMITTED VIA THE BIDDER INQUIRY PORTAL IN

PROJNET at http://www.projnet.org/projnet. No other means of communication (e-mail, fax, or telephone) will be accepted. Questions should be submitted no later than 31 24 January 2025, 2:00 PM Central Time to allow time for a response. On this date and time, the portal will be closed. To submit and review inquiries, firms will need to be current registered users of the ProjNet system. To register, go to the link above, click the BID tab, select BIDDER INQUIRY, select USACE, enter the Bidder Inquiry Key for this solicitation as listed below, and your e-mail address, and then click login. Complete all required information and then click CREATE USER.

Verify that information on the next screen is correct and click CONTINUE. From this page you can view all bidder inquiries for this solicitation or add an inquiry. Offerors or Bidders will receive an acknowledgement of their question via e-mail, followed by a response to their question after it has been processed by our team. The Solicitation Number is: W9127824R0037. The Bidder Inquiry Key is: FPRUKC-2UEHZZ. Firms are requested to review the Bidder Inquiry Portal for previous questions and responses, prior to submission of a new inquiry on the Portal. CAUTION: