W9127824B0001 Abstract - Mobile Harbor Phase 6.pdf

PDF 389 KB Posted

Attached to
Abstract for W9127824B0001 - Mobile Harbor Deepening and Widening, Phase 6, Mobile, Alabama (CHC22012)
Solicitation number
Not on record
Issued by

About this file

This document is an Abstract of Offers for the federal contract opportunity W9127824B0001 - Mobile Harbor Deepening and Widening, Phase 6, Mobile, Alabama.

The solicitation is for dredging and construction services, including mobilization/demobilization, dredging of the Mobile Upper Bay Channel and Turning Basin, placement of dredged material at Deer River and Dauphin Island Causeway Beneficial Use Sites, and construction of a sand berm at the Dauphin Island Causeway Beneficial Use Site. The abstract provides a detailed bid tabulation showing the five bidders' estimated quantities, unit prices, and total bid amounts for each contract line item. The government estimate (IGE) is also provided for comparison. The lowest total bid of $75,357,737 was submitted by Cashman Dredging.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Item No.

Description Unit Estimated Quantity

Unit Price

Estimated Amount

Estimated Quantity

Unit Price Estimated Amount

Estimated Quantity

Unit Price

Estimated Amount

Estimated Quantity

Unit Price

Estimated Amount

Estimated Quantity

Unit Price

Estimated Amount

Mobilization and Demobilization

JOB 1 XXX $12,070,275.00 1 XXX $38,920,000.00 1 XXX $11,000,000.00 1 XXX $35,839,000.00 1 XXX $16,750,000.00

Dredging of Mobile Upper Bay Channel and Turning Basin

CY 1,122,000 $19.05 $21,374,100.00 1,122,000 $26.65 $29,901,300.00 1,122,000 $17.50 $19,635,000.00 1,122,000 $40.40 $45,328,800.00 1,122,000 $38.50 $43,197,000.00

Placement at Deer

River Beneficial Use Site Marsh Fill Area

SY 82,360 $23.04 $1,897,574.40 82,360 $104.00 $8,565,440.00 82,360 $24.00 $1,976,640.00 82,360 $5.40 $444,744.00 82,360 $10.00 $823,600.00

Construction of Sand Berm at the Dauphin

Island Causeway Beneficial Use Site

LF 9,310 $389.45 $3,625,779.50 9,310 $1,015.00 $9,449,650.00 9,310 $300.00 $2,793,000.00 9,310 $181.10 $1,686,041.00 9,310 $100.00 $931,000.00

Placement at Dauphin Island Causeway

Beneficial Use Site Marsh Fill Area

SY 345,870 $8.93 $3,088,619.10 345,870 $47.00 $16,255,890.00 345,870 $12.00 $4,150,440.00 345,870 $5.40 $1,867,698.00 345,870 $10.00 $3,458,700.00

Dredging and

Placement in the Relic Shell Placement Site

CY 2,169,858 $21.94 $47,606,684.52 2,169,858 $25.00 $54,246,450.00 2,169,858 $16.50 $35,802,657.00 2,169,858 $16.00 $34,717,728.00 2,169,858 $20.00 $43,397,160.00

$89,663,032.52 $157,338,730.00 $75,357,737.00 $119,884,011.00 $108,557,460.00TOTAL IGE TOTAL BID TOTAL BID TOTAL BID

ABSTRACT

SOLICITATION W9127824B0001

Mobile Harbor, Alabama, Deepening and Widening - Phase 6

GREAT LAKES (LB)

Mobile, Alabama

DUTRA (LB)IGE CASHMAN (LB) WEEKS MARINE (LB)

TOTAL BID

File details come from the government source that posted it. Updated .