AM01.pdf
PDF 1 MB Posted
- Solicitation number
- W9127820R0042
About this file
This amendment modifies a solicitation for a two-phase design-build project. The project consists of designing and constructing a consolidated emergency management facility, emergency operations center, and alternate command post at Tyndall Air Force Base in Florida. The facilities will total approximately 21,000 square feet and include reinforced concrete and masonry construction with a metal roof. The emergency operations center will provide secure office, meeting, and operations spaces. Site work will include utilities, pavements, security features, and a backup generator. The cost is estimated between $10 million and $25 million. The amendment provides clarification regarding project scope details, evaluation criteria, and proposal submission requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 20R0042 PHASE ONE SPECS.PDF | ||
| EM 385-1-1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
1 2
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE 4. REQUISITION/PURCHASE 5. PROJECT NO. (If applicable)
W9127820R0042-0001 22 SEP 2020 MEF20021
6. ISSUED BY CODE 7. ADMINISTERED BY(If other than item 6)
CODE
Corps of Engineers 109 St. Joseph St.
Mobile, AL 36602
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP code) 9A. AMENDMENT OF SOLICITATION
NO.
W9127820R0042
9B. DATED (SEE ITEM 11)
15 SEP 2020
10A. MODIFICATION OF
CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE
FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (if required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO AUTHORITY OF FAR 43.103(b)
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible) The subject solicitation for: TWO-PHASE DESIGN BUILD OF ZONE 8 EMERGENCY OPERATIONS CENTER, TYNDALL AIR FORCE BASE, FLORIDA
Is modified in the following: REFER TO THE ENCLOSED SPECIFICATION REVISIONS FOR AMENDMENT NO. 0001.
Except as provided herein, all terms and conditions of the document reference in item 9A or 10A, as Heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICE (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
BY
(Signature of contracting officer)
16C. DATE SIGNED
NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV. 10-83)
PREVIOUS EDITION UNUSABLE Prescribed by GSA
TWO-PHASE DESIGN BUILD OF ZONE 8 EMERGENCY OPERATIONS CENTER W9127820R0042
TYNDALL AIR FORCE BASE, FLORIDA MEF20021
SF 30 Page 2 Amendment No. 0001
PART I-REVISIONS MADE BY ADDED AND/OR REPLACEMENT PARAGRAPHS/PAGES/SECTIONS
The items listed below are to be replaced by the corresponding added and/or revised paragraphs/pages or sections. Added and/or revised paragraphs/pages or sections are indicated by a note in bottom right hand corner of each paragraph or page. Added sections are hereby made a part of the contract and are to be inserted in the specification in the proper numerical/alphabetical sequence.
Within the specifications, deletions from the specifications are indicated by strikethrough, e.g.: deletions are marked with strikethrough and additions to the specifications including revisions/substitutions are indicated in bold, italic and underlined, e.g.: additions are indicated thus.
Corresponding Added or Revised Paragraph SECTION Page, and/or Section
00 11 00 Revised Paragraph 5.3
00 12 00 Revised Paragraphs 1.3 and 2.3
01 00 01 Revised Paragraph 7
Encl as stated:
Revised pages of the specifications as indicated in Part I.
00 11 00 Revised by Amendment No. W9127820R0042-0001
00 11 00
5.3 Evaluation of Factor 1 – Past Performance Information of the Prime Contractor and Factor 2 – Past Performance Information of the Lead Design Firm. Factor 1 and Factor 2 will be rated individually, each with relevancy ratings and a confidence rating applied as described below.
(1) An Offeror’s “Relevant Company Effort” information will be evaluated to determine if the construction and design projects submitted are “recent”, and “relevant”. For this solicitation, the Government will give more consideration for: design-build construction project on military installations; for dollar value similar to those anticipated under this solicitation; and projects where the Offeror performed as the prime contractor, as opposed to a subcontractor. Additionally, more consideration will be given to projects that demonstrate innovative solutions to maximize budget and performance in response to performance-based requirements;
projects that demonstrate collaborative efforts involving multi-stakeholders;
and projects in which the Offeror and Lead Design Firm previously performed together. Additionally, more consideration will be given to a project portfolio that reflects successful performance of a diversity of construction and repair type projects similar to those described by this solicitation.
This project is for the design and construction of single story 21,000 square-foot facility consisting of reinforced concrete block or cast concrete walls, concrete slab on grade, steel roof structure with a standing seam metal roof system. Exterior walls are to be clad with integrally colored ground-face concrete masonry veneer for most of the exterior facade with accent bands of smooth face brick masonry and ribbed metal panels as an additional accent. The facility is comprised of three functional areas: an 11,897 11,900 square-foot consolidated facility for emergency operations center (EOC) management, a 6,900 6,878 square-foot emergency operations center and 2,269 square-foot alternate command post, and a 2,200 square-foot facility for emergency management. The facility houses the Emergency Operations Center function, which EOC function provides secure space including an operations floor, command room, conference and briefing rooms, and administrative offices. The alternate command post is the focal point for emergency action, flight following, and operational reporting functions and function will include administrative offices, briefing rooms, storage, break area, and communications center. The emergency management function provides space for planning, management, training, and operations. The function includes maintaining stores of specialized disaster response equipment. The overall scope of the project includes a backup generator, all utilities, site improvements, pavements, detection/protection features, security enhancements and other supporting work necessary to make a complete and usable facility.
(Note: The remainder of Paragraph 5.3 is unchanged by this amendment.)
(Note: The remainder of the section is unchanged by this amendment.)
This page was intentionally left blank for duplex printing.
00 12 00
00 12 00
1.3 This project is for the design and construction of single story 21,000 square-foot facility consisting of reinforced concrete block or cast concrete walls, concrete slab on grade, steel roof structure with a standing seam metal roof system. Exterior walls are to be clad with integrally colored ground-face concrete masonry veneer for most of the exterior facade with accent bands of smooth face brick masonry and ribbed metal panels as an additional accent. The facility is comprised of three functional areas: an 11,897 11,900 square-foot consolidated facility for emergency operations center (EOC) management, a 6,900 6,878 square-foot emergency operations center and 2,269 square-foot alternate command post, and a 2,200 square-foot facility for emergency management. The facility houses the Emergency Operations Center function, which EOC function provides secure space including an operations floor, command room, conference and briefing rooms, and administrative offices. The alternate command post is the focal point for emergency action, flight following, and operational reporting functions and function will include administrative offices, briefing rooms, storage, break area, and communications center. The emergency management function provides space for planning, management, training, and operations. The function includes maintaining stores of specialized disaster response equipment. The overall scope of the project includes a backup generator, all utilities, site improvements, pavements, detection/protection features, security enhancements and other supporting work necessary to make a complete and usable facility.
Specific and detailed scope information of the project is as indicated in this solicitation.
2.0 PHASE TWO - PROPOSAL SUBMISSION REQUIREMENTS.
2.1 Only those firms selected during Phase One for participation in Phase Two may submit a proposal.
2.2 Submit the electronic proposal package to the U.S. Army Corps of Engineers via DoD SAFE (https://safe.apps.mil/) as indicated on the Standard Form 1442 (SF 1442) in this solicitation. The Government must receive your proposal no later than the time and date specified in Block 13 of SF 1442.
The DoD SAFE system notification must show it was dropped off prior to the specified time. Any and all amendments to the solicitation shall be acknowledged by signing on each amendment (SF30) and by completing Block 19 of the SF 1442. To confirm proposal receipt, you may call the Point of Contact listed on the SF1442.
2.3 Submit your proposal as follows:
Submit one (1) electronic copy of Volume III in Portable Document File
(PDF) format. Label the pdf “Volume III”.
Submit one (1) electronic copy of the entire proposal (“Volume III and
IV”) in Portable Document File (PDF) format. Label the pdf “Volumes III and IV”.
Hard copies of Volumes I and II are not required to be submitted, and will not be accepted or evaluated. However, when formatting the PDF
00 12 00 files the page size should be 8-1/2” x 11” for all pages except schedules and organizational charts, as applicable, which should be 11” x 17” (counts as one sheet toward page limitation).
01 00 01
01 00 01
7. DESCRIPTION OF WORK
In general, the work shall consist of the following: the facility is comprised of three functional areas: Emergency Operations Center function (EOC), alternate Command Post and emergency management. Project consists of the design and construction of a consolidated facility for emergency management (2,200 sf), emergency operations center (11,900 sf) and alternate command post (6,900 sf). Construction consists of a single story 21,000 sf facility consisting of reinforced concrete block or cast concrete walls, concrete slab on grade, steel roof structure with a standing seam metal roof system.
Exterior walls are to be clad with integrally colored ground-face concrete masonry veneer for most of the exterior facade with accent bands of smooth face brick masonry and ribbed metal panels as an additional accent. This project includes a backup generator, all utilities, site improvements, pavements, detection/protection features, security enhancements and other supporting work necessary to make a complete and usable facility. The facility will also house the Emergency Operations Center function. The EOC will provide secure space including an operations floor, command room, conference and briefing rooms, and administrative offices. The alternate command post will include administrative offices, briefing rooms, storage, break area, and communications center. The emergency management function provides space for planning, management, training, and operations. The function includes maintaining stores of specialized disaster response equipment. The North American Industry Classification System (NAICS) code for this project is 236220.
NOTE: The above general outline of features of the work does not in any way limit the responsibility of the Contractor to perform all work and furnish all plant, labor, equipment and materials required by the specifications and the drawings referred to therein. The cost of this work is estimated to be between $10,000,000 and $25,000,000.00.
End of Paragraph
This page was intentionally left blank for duplex printing.