This document contains a prequalification of sources announcement for the construction of 11 facilities at Tyndall Air Force Base in Florida known as Zone 1 - F-35 Flightline Facilities. The facilities include maintenance hangars, squadron operations facilities, headquarters buildings, storage facilities, and more to support the beddown of F-35A aircraft. Responses to the prequalification criteria are due by November 23, 2020 and will be evaluated based on bonding capability, large construction contract past experience, and specific construction experience. Firms must meet all criteria to be considered qualified. The Army Corps of Engineers Engineering District Mobile will administer this Design-Bid-Build contract opportunity, which is designated solely for prequalified sources.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI's ‐‐ W127820R0035 PREQUALIFICATION OF SOURCES FOR TYNDALL AIR FORCE BASE

RECONSTRUCTION ZONE 1 (F‐35 FLIGHT LINE)

MOBILE DISTRICT

Questions Anwser We are an electrical contractor and are interested in this opportunity. When your prequalification process is over, would you be able to release the list to me so I can make contact with each individual GC and offer our services as part of their second-stage proposals?

The list of Prime Contractors determined to be Pre-Qualified will be posted to beta.sam.gov.

Would it be possible to obtain a list of the interested vendors for this solicitation and/or make them available in beta.SAM? I am working for a subcontractor that would like to participate but needs to know the General Contractors that are interested.

The list of Prime Contractors determined to be Pre-Qualified will be posted to beta.sam.gov."

With specific regard to the prequalification document contained on the Beta.sam website, and most specifically section 2.2a & 2.2b Large Vertical Construction Contract Past Experience, we have the following question:

So that a more comprehensive explanation of the project selected to satisfy this requirement can be communicated . . . May we include a brief/concise/comprehensive one-page data sheet for the project to convey the similarity to the stated requirement within this section?

A brief/concise/comprehensive one-page data sheet for the project may be submitted, however the project will be valideated with the project POC provided on the Pre-Qualification Form.

The questionnaire indicates that narrative attachments should be provided in Adobe PDF AND Microsoft Word. However, requested attachments (for example, a signed surety letter) cannot be provided as a Word Document. Can we provide our attachments in either Adobe PDF OR Microsoft Word? Please clarify.

The surety letter and bond capacibly may be submitted in Adobe

PDF.