This solicitation is for the rewind of two hydroelectric generating units at Hartwell Powerhouse in Hartwell, Georgia. The contractor will be responsible for pre-disassembly testing, disassembly, electromagnetic analysis of the proposed winding design, inspection of stator frames, design and testing of prototype coils, manufacture and testing of production coils, removal and installation of stator components, cleaning and testing of rotors, and reassembly, start-up, and post-installation testing. The work must be performed in accordance with specifications and drawings. The government intends to award a firm fixed price C-type construction contract for work with an estimated cost between $10-25 million.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
1 2
3. EFFECTIVE 4. REQUISITION/PURCHASE 5. PROJECT NO. (If applicable)2. AMENDMENT/MODIFICATION
NO. W9127820R0018-0002 4 MAR 2020
6. ISSUED BY CODE 7. ADMINISTERED BY(If other than item 6)
CODE
Corps of Engineers 109 St. Joseph St.
Mobile, AL 36602
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP code) 9A. AMENDMENT OF SOLICITATION
NO.
W9127820R0018
9B. DATED (SEE ITEM 11)
31 JAN 2020
10A. MODIFICATION OF
CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (if required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority)
THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO AUTHORITY OF FAR 43.103(b)
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible)
The subject solicitation for: Hartwell Powerhouse Rewind of Units 3&4, Hartwell, GA
Is modified in the following: REFER TO THE ENCLOSED ADDITIONAL SPECIFICATIONS FOR AMENDMENT NO. 0002
Except as provided herein, all terms and conditions of the document reference in item 9A or 10A, as Heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICE (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
BY
(Signature of contracting officer)
16C. DATE SIGNED
NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV. 10-83)
PREVIOUS EDITION UNUSABLE Prescribed by GSA
Unit 3 and 4 Generator Rewind at Hartwell Powerhouse in Hartwell, GA
W9127820R0018
SF 30 Page 2 W9127820R0018-0002
REVISIONS MADE BY ADDED AND/OR REPLACEMENT PARAGRAPHS/PAGES/SECTIONS
The items listed below is added to the solicitation. Added sections are hereby made a part of the contract and are to be inserted in the proper numerical/alphabetical sequence.
ADDED SECTIONS
48 70 01.00 26 NERC COMPLIANCE FOR HYDROGENERATORS
SECTION 48 70 01.00 26
NERC COMPLIANCE FOR HYDROGENERATORS
PART 1 GENERAL
1.1 GENERAL
This section covers additional testing, model validation and reporting requirements that are required to document the Hartwell Units 3 and 4 hydrogenerators compliance with the current North American Electrical Reliability Corporation (NERC) Bulk Power System (BPS) Electric Reliability Compliance Standards and Requirements with applicability to a Generator Owner. The testing and model validation shall be performed using one and/or more of the standard models listed within the most current version of the NERC "Acceptable Models List." This document contains the acceptable list of models and software simulation programs and can be found at NERC.com.
Perform testing and model validation of the following hydrogenerator systems using the applicable standard models and software simulation programs from the NERC Acceptable Models List; GE PSLF, Siemens PSS-E, or PowerWorld Simulator:
a. Generator
b. Excitation System
c. Power System Stabilizer
d. Turbine/Governor
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE 421.5 (1992, R2005) IEEE Recommended Practices for Excitation System Models for Power System Stability Studies
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals having an "I" are for information only. Designation following the "G" or "I" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with
SECTION 01 33 00 SUBMITTAL PROCEDURES:
SD-05 Design Data
Within 120 calendar days after date of receipt of written notice of award:
Model Validation Test Procedures; G, HDC
Personnel Qualifications for Model Validation Testing; G, HDC
SD-06 Test Reports
Test reports for all tests shall be submitted for approval within 60 calendar days of completing the testing.
Model Validation Test Report; G, HDC Electronic copies shall be Portable Document Format (PDF) with bookmarks matching the index. Include all information necessary for submission to NERC and the Regional Entity with enough detail to answer basic questions of methods and tests performed. Where applicable, submit separate appendices of fill-in compliance forms.
Raw Test Data; G, HDC Provide on a CD or DVD. Comma Separated Value (CSV) with column headings and necessary scaling factors applied or provided in a separate document to determine actual quantities.
Dynamic Data File; G, HDC Provide the text file necessary for incorporation into the simulation program used.
1.4 Unit Information
a. Generator:
Westinghouse 73,333 kVA
0.90 power factor 100 rpm
13.8 kV 60 Hz
b. Governor:
Voith Siemens Allen Bradley PLC Control
c. Turbine:
Newport News Shipbuilding and Drydock Company 91,500 horsepower at a net head of 170 feet
d. Excitation System:
Eaton-Cutler Hammer Static Exciter 560 volts AC
1061 ADC
e. Power System Stabilizer:
Eaton-Cutler Hammer
1.5 Applicable NERC Standards
1.5.1 MOD-025-1
Verification of Generator Gross and Net Reactive Power Capability: Test for and report information necessary to document Generator Owner compliance with this NERC standard.
1.5.2 MOD-026-1
Verification of Models and Data for Generator Excitation Control System or Plant Volt/VAR Control Functions: Test for and report information necessary to document Generator Owner compliance with this NERC standard.
1.5.3 MOD-027-1
Verification of Models and Data for Turbine/Governor and Load Control or Active Power/Frequency Control Functions: Test for and report information necessary to document Generator Owner compliance with this NERC standard.
1.5.4 MOD-032-1
Data for Power System Modeling and analysis: Test for and report information necessary to document Generator Owner compliance with this NERC draft standard. Until approved by FERC, it is acceptable to consider this requirement as compliance with MOD-010-0, MOD-011-0, MOD-012-0, MOD-013-1, MOD-014-0, and MOD-015-0.1 per the intended consolidation of MOD-032-1.
1.6 Applicable Regional Entity standards
With reference to the NERC standard listed in paragraph 1.5, the Contractor is responsible for researching all specific or additional applicable Generator Owner testing and reporting required by SERC.
PART 2 PRODUCTS
NOT USED
PART 3 EXECUTION
3.1 Model Validation Procedures and Personnel Qualifications
Submit Model Validation Test Procedures. The Contractor shall prepare for approval detailed field test procedures for model validation testing of the identified hydrogenerator systems. Provide a detailed step-by-step procedure of all required connections, test equipment, test sequence, operations, measurements and adjustments, and a list of the proposed dynamic simulation models. Testing and reporting shall be completed to satisfy the specific requirements of in addition to the NERC requirements noted in "Applicable NERC Standards." Approval of the test procedure does not release the contractor from the responsibility of testing and preparing a report that is acceptable to the Generator Owner's Transmission Planner and/or Planning Coordinator. The contractor is responsible for researching all Generator Owner testing and model validation requirements.
3.2 Personnel Qualifications
Submit Personnel Qualifications for Model Validation Testing. Test personnel shall have experience with the contractor's test equipment and test procedures and with the operating functionality and configuration of the type of governor and exciter (both manufacturer and model) to be tested. The test personnel must have experience performing model validation testing of similar hydrogenerator systems, at a minimum of five (5) different generating plants in the past two (2) years. Contractor shall submit for approval a resume and experience list of the individual(s) who will perform hydrogenerator systems (i.e., generator, exciter, turbine-governor, PSS, etc.) the testing and the individual(s) who will be the knowledgeable technician or engineer. One qualified individual may perform one or more of the identified roles.
3.3 Model Validation Field Testing
a. Field Testing. Test the identified hydrogenerator systems in accordance with the listed NERC Standards and Requirements as necessary to demonstrate compliance.
b. Contractor Supplied Items. The contractor shall supply the following:
(1) All equipment, materials, personnel, and any and all services as required in connection with generator, governor, and excitation system model validation testing (this includes, but is not limited to, test equipment, laptops, and software);
(2) A knowledgeable exciter technician or engineer to provide onsite support during the described testing;
(3) knowledgeable turbine-governor technician or engineer to provide onsite support during the described testing;
(4) All software as necessary for the knowledgeable exciter technician or engineer to program and operate the exciter during testing;
(5) All software as necessary for the knowledgeable turbine-governor technician or engineer to program and operate the turbine-governor during testing;
(6) Provide wiring termination strip to Government for connection to Government owned equipment and control systems, as described in the test procedure;
c. Government Support During Testing. The Government will provide the following support for testing:
(1) Powerhouse operators to operate government owned equipment and control systems as described in the approved written test procedures;
(2) Electricians to perform modifications to unit controls if needed for the tests as well as perform all wiring connections to Government owned equipment;
(3) Access to AC power outlets and/or extension cords in the area where the data recording equipment will be used;
(4) Previously prepared validation and modeling reports, if available;
(5) Equipment schematics or elementary drawings as requested by Contractor (if available).
(6) Equipment operation and maintenance manual as requested by Contractor (if available).
3.4 Model Validation Reporting
a. Computer Simulations. Perform computer simulations to ensure that the generator, turbine-governor, exciter, and PSS models, with parameters corresponding to as-left equipment settings, represent equipment dynamic performance with sufficient accuracy for power system stability studies. Models and computer simulations program shall be one or more on the standard models listed within the most current version of the NERC "Acceptable Models List.". Models shall be selected to appropriately model the equipment. Custom models shall not be accepted.
b. Model Validation Test Report. The Contractor shall submit a test report that includes a subjective evaluation of equipment performance as well as the models and the correct model parameters presented in a format suitable for transmittal to the Generator Owner's Transmission Planner and/or Planning Coordinator. The report shall include a generator capability curve verified through testing. The Contractor shall be available to respond in writing to inquiries from the Generator Owner's Transmission Planner and/or Planning Coordinator regarding test procedures and results. All deliverable products and working papers shall be the property of the U.S. Government.
Procedures and reports shall be provided as Microsoft Word files.
c. Raw Test Data. Provide the raw test data in comma separated values (CSV) format on either a compact disc or digital video disc. Create the file names for the CSV files such that it is apparent which facility, unit, and test is being completed. Provide either as a header to columns or as a separate key file the contents and scaling factors for all columns.
d. Dynamic Data File. Provide the dynamic data file (.dyd) for the modeled data on either a compact disc or digital video disc. The file can be provided on the same disc with the raw test data in paragraph
3.3 (c).
-- End of Section --