Industry Day Presentation 20240328.pdf
PDF 8 MB Posted
- Solicitation number
- W9126G-Ind-Day-Central-City
About this file
This document is an Industry Day presentation for the Modified Central City project, a $2.4 billion flood protection initiative led by the U.S. Army Corps of Engineers (USACE) Fort Worth District and the Tarrant Regional Water District (TRWD) in Fort Worth, Texas. The presentation provides an overview of the project scope, which includes an 8,400-foot bypass channel, three flood gates, one pump station, two dams, and various valley storage mitigation sites.
Key details include upcoming contracting opportunities for construction, architecture/engineering, and ecosystem restoration work, with anticipated contract values ranging from under $1 million to over $250 million. The presentation covers the acquisition strategy, solicitation process, and small business participation requirements. It also highlights upcoming industry engagement events, such as a Sources Sought notice for the North Bypass Channel and a Request for Information to obtain feedback on proposal submission and evaluation criteria. The self-guided site visit provides potential offerors an opportunity to view the project locations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Industry Day Final Agenda.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MODIFIED CENTRAL CITY
INDUSTRY DAY
MARCH 28, 2024
OPENING REMARKS
USACE
LTC Joshua Haynes Deputy Commander
USACE, Fort Worth District
AGENDA
Time Topic 9:00 AM - 9:15 AM Introduction/Opening Remarks 9:15 AM - 9:20 AM Safety Moment 9:20 AM - 9:50 AM Tarrant Regional Water District Central City Overview & Non-Federal Sponsor Perspective Central City Small Business Program Overview, Tracking & Resources 9:50 AM - 10:20 AM City of Fort Worth Central City Opportunities Doing Work with the City of Fort Worth 10:20 AM - 11:00 AM U.S. Army Corps of Engineers Program Overview, Industry Engagement, & Opportunities Doing work with USACE 11:00 AM - 11:30 AM Wrap Up 11:30 AM - 1:00 PM Lunch 1:00 PM - 3:00 PM Central City Self-Guided Site Visit
TARRANT REGIONAL WATER DISTRICT
Kate Beck, P.E.
Program Director, Central City Flood Control Project
TRWD
CITY OF FORT WORTH
Dana Burghdoff Assistant City Manager
City of Fort Worth
SAFETY MOMENT
Samantha Smith, R.A.
Resident Engineer
SAFETY MOMENT
Safety Culture=Business Culture
Attract and Retain Top Talent
Proactive vs. Reactive Partnering between SSHO, QC Manager, and Site Superintendent
Positively Influence
TARRANT REGIONAL WATER DISTRICT (TRWD)
Central City Overview & Non-Federal Sponsor Perspective Central City Small Business Program Overview, Tracking & Resources
Matt Oliver Public Information Officer
TRWD
Crystal Alba Diverse Business Specialist
TRWD
Industry Day March 28, 2024
W A
T E
R S
U P
P L
Y
· F
L O
O D
P R
O T
E C
T
IO
N
· R
E C
R E
A T
IO
N
Diverse Business Central City At TRWD
T E
R S
U P
P L
Y
· F
L O
O D
P R
O T
E C
T
IO
N
· R
E C
R E
A T
IO
N
Certification Breakdown Report - TRWD Contracts Only Report Ending: June 30, 2023
Entity Totals Total Award DB Proposed Proposed % Total Actuals DB Actuals Actual %
TRWD/TRVA $ 66,064,697.63 $ 23,388,531.56 35% $ 57,353,285.92 $19,355,831.12 34%
Central City Contracts
T E
R S
U P
P L
Y
· F
L O
O D
P R
O T
E C
T
IO
N
· R
E C
R E
A T
IO
N
Vendor Registration www.trwd.com http://www.trwd.com/
T E
R S
U P
P L
Y
· F
L O
O D
P R
O T
E C
T
IO
N
· R
E C
R E
A T
IO
N
Vendor Registration
T E
R S
U P
P L
Y
· F
L O
O D
P R
O T
E C
T
IO
N
· R
E C
R E
A T
IO
N
Vendor Registration
CITY OF FORT WORTH
Central City Opportunities Doing Work with the City of Fort Worth
Clair Davis, P.E., CFM Senior Capital Projects Officer City of Fort Worth
Nohemi Sanchez Business Equity Manager City of Fort Worth
Central City Opportunities
Ongoing Utility Relocations The City, in partnership with TRWD and USACE, is working to clear the bypass channel in preparation for construction North Bypass Channel
Storm Drainage System: 3 ongoing relocations under construction
Sanitary Sewer and Water System: 1 ongoing relocation under construction
Franchise Utilities: coordinating Oncor relocations
South Bypass Channel Storm Drainage System: 2 ongoing relocations under construction Sanitary Sewer and Water System: 3 ongoing relocation under construction Franchise Utilities: coordinating Oncor, AT&T, and Atmos relocations
Central City and TRV TIF 9
Storm Water Projects Grand Avenue Phase 2 Part 2 Laterals North Under FWWR Storm Drain Relocations
Grand Avenue Phase 2 Part 3 Storm Drain Relocations
Cemetery (USACE) Storm Drain Relocations
New Main Street Outfall Storm Drain Relocations
8th Avenue Storm Drain Relocations
Houston Street Storm Drain Relocations – no longer neededNew Bazaar Outfall (USACE)
Greenleaf Sump Mitigation
Viola Storm Drain Relocations
Grand Avenue Part 1 Storm Drain Relocations
University Drive
Water and Sanitary Sewer Projects
Part 3 – N. Main Street Bridge Water and Sanitary Sewer Relocations
Part 4 – Channel Segment B Sanitary Sewer Relocations
Part 6 – White Settlement Bridge Water and Sanitary Sewer Relocations
Part 12 – White Settlement Bridge Sanitary Sewer Relocations
Part 1 – Henderson Street Bridge Water and Sanitary Sewer Relocations
Part 10 & 11 – Channel Segment A Water and Sanitary Sewer Relocations – 6/24
Part 14 – Bypass Channel Segment C Water and Sanitary Sewer Relocations – 12/24
Part 23 – Channel Segment D (NTP 1) Water and Sanitary Sewer Abandonments – 12/24
Part 13 – Channel Segment D (NTP 2) Water and Sanitary Sewer Relocations – 12/25
University Drive
Local Street Modifications
Part 3 - Bypass Channel Segment D
Part 4 - Bypass Channel Segment A
Part 2 - Bypass Channel Segment B
G R
EEN
LEA
F
DAKOTA
KANSAS
A R
TH
U
R
C O
M M
ER
C
IA
L
LEGEND
Proposed Street Vacate
Proposed Local Street
LEGEND
Proposed Street Vacate
Proposed Local Street
R U
PER
T
Central City Opportunities
University Drive Utility Relocations (multiple) Gateway/Oxbow Ecosystem Restoration Utility Relocation(s) Local Street Modifications Bypass Channel Segment D Water and Sanitary Sewer Relocations Clear Fork Isolation Gate Water and Sanitary Sewer Relocations Beach Street 54” water line
Panther Island Opportunities
M-248 Sanitary Sewer Rehab Panther Island Sanitary Sewer Collector Main Several water and sanitary sewer lines in conflict with the canals that will have to be relocated.
NOTE: Providing for awareness, but opportunities are not associated with the Modified Central City project.
Doing Work with the City of Fort Worth
Doing Work for the City of Fort Worth
BUSINESS EQUITY
PROGRAM & ORDINANCE
COMPLIANCE
BUSINESS EQUITY DIVISION
TEL: 817-392-2674
FAX: 817-392-7529
EMAIL: DVIN_BEOFFICE@FORTWORTHTEXAS.GOV
BUSINESS EQUITY TEAM
NOHEMI SANCHEZ- BUSINESS EQUITY MANAGER
REMY LE- SENIOR CONTRACT COMPLIANCE SPECIALIST
ALMA IBARRA – SENIOR CONTRACT COMPLIANCE SPECIALIST
DANIELLE JACKSON – CONTRACT COMPLIANCE SPECIALIST
REQUIREMENTS
MARKETPLACE
The geographic area defined by the City’s 2020 Disparity Study 92% of City contract dollars spent in 6 counties: Dallas, Denton, Johnson, Parker, Tarrant, and Wise counties
M/WBE Goals Threshold
All projects $100,000.01 or more must be routed to the Business Equity Division to assign a Business Equity Goal, if appropriate Exceptions: Emergency Contracts and Cooperative Agreements
Minority-owned
Business Enterprise
(MBE)
A business equity firm whose owners are African American, Asian, Hispanic & Native American Indian decent ⁃ which is at least fifty-one percent (51%) owned by one or more Minority Individuals or in the case of a publicly traded business, at least fifty-one percent (51%) of all classes of the stock of which is owned by one or more Minority Individuals; and, ⁃ whose management, policies, major decisions, and daily business operations are independently managed and controlled by one or more Minority(s)
Women-owned
Business Enterprise
(WBE)
A business equity firm ⁃ which is at least fifty-one percent (51%) owned by one or more women, or in the case of a publicly traded business, at least fifty-one percent (51%) of all classes of the stock which is owned by one or more women;
and
⁃ whose management, policies, major decisions and daily business operations are independently managed and controlled by one or more such women
Certifications
• North Central Texas Regional Certification Agency (NCTRCA)
• Dallas/Fort Worth Minority Supplier Development Council (DFW/MSD)
• Women’s Business Council Southwest (WBCS)
• Texas Department of Transportation (TXDot)
REQUIREMENTS
Utilization Plan Form is a requirement for any bid with a Business Equity Goal.
Letter of Intents (LOI) are only required for M/WBE subcontractors.
Good Faith Effort (GFE) is required when the set Business Equity Goal is not going to be met.
USACE
Central City Program Overview, Industry Engagement, & Opportunities Doing Work with USACE
Kalli Egan, P.E.
Program Manager
USACE, Fort Worth District
Ali Marshall Deputy, Office of Small Business Programs
CENTRAL CITY FLOOD RISK MANAGEMENT PROJECT SUMMARY
Background:
Fort Worth floods in 1922, 1949, and 1989 basis for study Levee project of 1957 designed for 1960 population of 350,000; population is now near 900,000 and growing Growth in Tarrant, Parker and Wise Counties and impervious developments are contributing to drainage problems Project levee and floodwall designed to Standard Project Flood (SPF)+4 feet
Purpose:
To provide $2.4 billion of continued flood protection for the citizens and properties within the City and the 2,400 acres of established Fort Worth neighborhoods Restores the design level of flood protection to the existing system by realigning the river and adding closure gates
Authorization:
2005 Energy and Water Appropriations Act authorized program as described in the 2003 Trinity River Master Plan 2016 Water Infrastructure Improvements for the Nation increased project scope and cost
Non-Federal Sponsor:
Tarrant Regional Water District
Original Authorization:
2005 Energy and Water Appropriations Act
Original PPA:
Executed 5 Sep 2008 FRM (Cost Share 50/50)
Features Include:
Bypass Channel Valley Storage 2 Isolation Gates Marine Creek Dam & Channel Expansion
Reauthorization:
2016 Water Infrastructure Improvements for the Nation Amended PPA:
Executed 19 Jan 2021 FRM (Cost Share 65/35) ER (Cost Share 65/35) REC (Cost Share 50/50) Features Include:
Bypass Channel Valley Storage 3 Isolation Gates Marine Creek Dam & Channel Expansion Samuels Avenue Dam Pump Station Pedestrian/Maintenance Bridges Ecosystem Restoration Interior Water Feature (Recreation Only)
PPA = Project Partnership Agreement FRM = Flood Risk Management ER = Ecosystem Restoration REC = Recreation
PROJECT AUTHORIZATION
HISTORY
MODIFIED CENTRAL CITY PROJECT PHASING
Bypass Channel North Channel South Channel Trinity Point, Clear Fork, and Tarrant
Regional Water District (TRWD) Isolation Gates
TRWD Pump Station Valley Storage (5,250 acre-ft) 6 primary sites completed (Samuels, Riverside Park, Ham Branch, Site A, Site C, and Site H)
4 primary sites remaining 3 contingency sites identified (not shown) Dams Samuels Ave Lock and Dam Marine Creek Dam and Channel
Expansion Aquatic Habitat Mitigation Sycamore Creek (Site A) Ham Branch Ecosystem Restoration Rockwood Park Ecosystem
Restoration Gateway Oxbow Ecosystem
Restoration (not shown) Pedestrian Bridges North and South Bypass Pedestrian
Bridges (not shown) West Fork Pedestrian Bridge
Samuels Avenue/Marine Creek Dams & Marine Creek Expansion
Samuels Avenue Valley Storage
Riverside Park Valley Storage
Ham Branch Valley Storage
Site A Valley Storage
Site C Valley Storage Site E Valley
Storage
Site H Valley Storage
Site K Valley Storage
Rockwood Park Valley Storage
Rockwood Park Ecosystem Restoration
University Drive Valley Storage
South Bypass Channel
Clear Fork Gate
Trinity Point Gate
North Bypass Channel
TRWD Gate & Pump Station
West Fork Maintenance/ Pedestrian Bridge
FLOOD RISK MANAGEMENT
COMPLETED VALLEY STORAGE SITES
Samuels Avenue Valley Storage
Riverside Park Valley Storage
Ham Branch Valley Storage
Site A Valley Storage
Site C Valley Storage
Site H Valley Storage
MITIGATION: HAM BRANCH & SYCAMORE CREEK
AQUATIC HABITAT
Design Funded? Yes
Construction Funded? Yes
Status Reviewing Phase 1 Proposals
Next Major Milestone Complete Phase 2 RFP
Ham Branch Aquatic Habitat Mitigation
Implementation Funded? Yes
Status
Plantings underway by Lewisville Aquatic Ecosystem Restoration Facility (LAERF)
Sycamore Creek Aquatic Habitat Mitigation
Ham Branch Aquatic Habitat Mitigation
Sycamore Creek (Site A) Aquatic Habitat Mitigation
NORTH BYPASS CHANNEL – PHASE 1
Design Funded? Yes
Construction Funded? Yes
Status 60% Design Reviewed
Next Major Milestone 90% Design Submittal
Temporary Levee
Temporary Levee
Partial Tie-In A
Hard Edge
Soft Edge
NORTH BYPASS CHANNEL – PHASE 1 OPTION
Construction option required to allow additional time for site preparation
Partial Tie-In A
SOUTH BYPASS CHANNEL – PHASE 1
Design Funded? Yes
Construction Funded? Yes
Status 30% Design Reviewed
Next Major Milestone 60% Design Submittal
SOUTH BYPASS CHANNEL – PHASE 2
Design Funded? Yes
Construction Funded? No
Status 30% Design Reviewed Awaiting FY25 Workplan
Next Major Milestone 60% Design Submittal
Hard
UPSTREAM VALLEY STORAGE – PHASE 1
Design Funded? Yes
Construction Funded? Yes
Status Concept Design Reviewed
Next Major Milestone 30% Design Submittal
Rockwood Park Valley Storage
University Drive Valley Storage
Tie-In B
UPSTREAM VALLEY STORAGE – PHASE 2
Design Funded? No
Construction Funded? No
Status Awaiting FY24 Workplan
Next Major Milestone Design Start
West Fork Maintenance/ Pedestrian Bridge
DOWNSTREAM VALLEY STORAGE – PHASE 1
Design Funded? No
Construction Funded? No
Status Awaiting TRWD Site Preparation
Next Major Milestone 90% Design Submittal
Site E Valley
DOWNSTREAM VALLEY STORAGE – PHASE 2
Design Funded? No
Construction Funded? No
Status Awaiting FY24 Workplan
Next Major Milestone Design Start
Site K Valley
TRINITY POINT GATE & TIE-IN
Trinity Point Gate
Tie-In C
Design Funded? Yes
Construction Funded? No
Status Design Charrette Held
Next Major Milestone Concept Design Submittal Construction Sequence Analysis
CLEAR FORK GATE & TIE-IN
Design Funded? Yes
Construction Funded? No
Status Design Charrette Held
Next Major Milestone Concept Design Submittal Construction Sequence Analysis
Clear Fork Gate
Tie-In D
TRWD GATE & PUMP STATION
Design Funded? Yes
Construction Funded? No
Status Design Charrette Held
Next Major Milestone Concept Design Submittal Construction Sequence Analysis
TRWD Gate & Pump Station
DAMS
Design Funded? No
Construction Funded? No
Status Awaiting FY24 Workplan
Next Major Milestone Design Start
Samuels Avenue/Marine Creek Dams & Marine Creek Expansion
ECOSYSTEM RESTORATION
GATEWAY/OXBOW
Design Funded? No
Construction Funded? No
Status Awaiting FY24 Workplan
Next Major Milestone Design Start
Gateway/Oxbow Ecosystem Restoration
ECOSYSTEM RESTORATION
ROCKWOOD PARK
Rockwood Park Ecosystem Restoration
Design Funded? No
Construction Funded? No
Status Awaiting FY24 Workplan
Next Major Milestone Design Start
FINAL TIE-IN
Design Funded? Yes
Construction Funded? No
Status 60% Design Reviewed
Next Major Milestone 90% Design Submittal
Final Tie- In A
CENTRAL CITY PROJECT SCHEDULE
CENTRAL CITY PROJECT SCHEDULE
INDUSTRY ENGAGEMENT
EXCHANGES WITH INDUSTRY
REQUEST FOR INFORMATION – NORTH BYPASS CHANNEL
Link:
https://sam.gov/opp/bddaac5565ac480d8 7fd1eda2967aa5d/view#general Two purposes:
1) To meet 1-on-1 with a target of the first ten (10) PRIME contractors
2) To obtain written feedback on draft proposal submission and evaluation criteria
Future amendment:
1) Any additional information disclosed by the Government (not anticipated)
2) White Paper summarizing considerations on proposal submission and evaluation criteria feedback received
Be on the lookout for other Requests for Information (Special Notices)… https://sam.gov/opp/bddaac5565ac480d87fd1eda2967aa5d/view#general https://sam.gov/opp/bddaac5565ac480d87fd1eda2967aa5d/view#general
CONTRACT OPPORTUNITIES
Project Name Location Category Release Qtr Cost Range Acquisition Strategy Solicitation Type Feature*
Active
Central City, UTRB, CON CENTRAL CITY, FORT WORTH, UPPER TRINITY RIVER BASIN CONSTRUCTION FY24Q2 (Actual) $10M - $20M NONE / No set aside used RFP2 / RFP - Two Step Ham Branch Aquatic Mitigation
Central City, UTRB, CON CENTRAL CITY, FORT WORTH, UPPER TRINITY RIVER BASIN CONSTRUCTION FY25Q1 $100M - $250M TBD RFP1 / RFP – One Step Bypass Channel North –
Phase 1
Central City, UTRB, CON CENTRAL CITY, FORT WORTH, UPPER TRINITY RIVER BASIN CONSTRUCTION FY25Q3 $50M - $100M TBD TBD Bypass Channel South –
Phase 1
Central City, UTRB, CON CENTRAL CITY, FORT WORTH, UPPER TRINITY RIVER BASIN CONSTRUCTION TBD $50M - $100M TBD TBD
Upstream Valley Storage
– Phase 1 (includes Rockwood Park VS, University Drive VS, and Bypass Channel North – Phase 2)
Capability Expressed for FY24 (Subject to FY24 Workplan)
Central City, UTRB, CON CENTRAL CITY, FORT WORTH, UPPER TRINITY RIVER BASIN AE TBD $5M - $10M NONE / No set aside used IDC / Competitive DO/TO against existing contract
Samuels Avenue/Marine Creek Dams
Central City, UTRB, CON CENTRAL CITY, FORT WORTH, UPPER TRINITY RIVER BASIN AE TBD < $1M SB / Small Business IDC / Competitive DO/TO against existing contract West Fork Ped/Maint Bridge
Central City, UTRB, CON CENTRAL CITY, FORT WORTH, UPPER TRINITY RIVER BASIN AE TBD $1M - $5M SB / Small Business IDC / Competitive DO/TO against existing contract Gateway/Oxbow ER
Central City, UTRB, CON CENTRAL CITY, FORT WORTH, UPPER TRINITY RIVER BASIN AE TBD < $1M SB / Small Business IDC / Competitive DO/TO against existing contract Rockwood Park ER
Capability Expressed for FY25 (Subject to FY25 Workplan)
Central City, UTRB, CON CENTRAL CITY, FORT WORTH, UPPER TRINITY RIVER BASIN CONSTRUCTION FY25Q3 $100M - $250M TBD
TBD - Package with Bypass Channel South – Phase 1
Bypass Channel South – Phase 2
CONTRACT OPPORTUNITIES
*Not included are ~10 unfunded construction opportunities
MARKET RESEARCH – NORTH BYPASS CHANNEL
Sources Sought Link:
https://sam.gov/opp/87fe9ac583434ef99 70b4ec1b195d89e/view
Purpose: Gain knowledge of interest, capabilities and qualifications of various members of industry, to include the Large and Small Business Community: Small Business, Section 8(a), Historically Underutilized Business Zones (HUB-Zone), Service-Disabled Veteran-Owned Small Business (SDVOSB), and Women-Owned Small Business (WOSB)
Deadline: April 1, 2024, 5:00 Central Time https://sam.gov/opp/87fe9ac583434ef9970b4ec1b195d89e/view https://sam.gov/opp/87fe9ac583434ef9970b4ec1b195d89e/view
Presentation for:
Central City Industry Day 28 March 2024
Small Business Programs
Ali Marshall Deputy, Office of Small Business Programs (OSBP) Fort Worth District (SWF) U.S. Army Corps of Engineers (USACE) Alisa.Marshall@usace.army.mil mailto:Alisa.Marshall@usace.army.mil
AGENDA
Small Business Advocate Provides
Acquisition Strategy / Source Selection Process
Solicitation Process
Sub-Contracting Opportunities
Central City Projects
Small Business Advocate Provides Advocate Assure SB are given fair opportunity and consideration in procurements
Inform Forecast Opportunities, Acquisition Process, Outreach Events
Counsel Capability Statement Improvements Include Updated Experience, Performance Rating, General Description, and $
Amount DSBS Profile Improvements Include Keywords, Performance Area, Bonding Increases, Updated Experience
Assist Encourage Sources Sought Response, Participation, Networking, Subcontracting District Staff with Acquisition Strategy Include (Research & Recommend SB)
Review SB Coordination Records, SB Participation Proposals, SB Subcontracting Plans
Acquisition Strategy / Source Selection Process
Small Business Set-asides or Full and Open (Unrestricted) Competitive acquisitions:
• Invitation for Bid (IFB)
• Best Value Trade Office (BVTO)
Small Business or Socio-Economic Small Business Set-asides may use 8(a) Program:
Competitive 8(a) Sole Source 8(a)
Did you know?
Full and Open Competition means all may submit proposal (regardless of size)
Solicitation Process Solicitations may be found: (Registration required) https://sam.gov https://piee.be.mil
View solicitations in sam.gov, search by DoDAAC or by Name (view only capability):
W9126G or US Army Engineer District Ft Worth
Submit proposal in PIEE:
Follow specific solicitation requirements
Did you know?
Assuring fair proportion of Government contracts is with Small Business (FAR19) https://sam.gov/ https://piee.be.mil/
+Attachments
PIEE Website: https://piee.eb.mil/
PIEE SOLICITATION PROCESS
+Amendments Solicitation
PIEE
Solicitation
Module
Posts
Transfers Proposal View Only
Proposal Manager
Search / View
PIEE
Vendor Roles
Contractor Offer
Download
Log in
Proposal Manager
Posts / Withdraws
PIEE
Solicitation
Module
Log in
PIEE Web Based Training
+Attachments +Amendments
Solicitation
Vendor Proposal Submission
Contractors
Transfers to SAM.gov https://piee.eb.mil/
What this means to Contractors:
• Search Fort Worth District specific opportunities in PIEE, search Contracting Office DODAAC to see all RFPs, RFQs and IFBs (View, Download, & Submit Proposal)
• Search Fort Worth District specific opportunities in SAM.gov, search under DODAAC to see all RFPs, RFQs and IFBs. (View Only)
• Consider updating subscriptions or registries to include Fort Worth’s DODAAC.
PIEE Search Page
PIEE SEARCH
What is a DODAAC Department of Defense Activity Address Code
• Fort Worth (SWF) W9126G
FORT WORTH DISTRICT
SWF postings https://sam.gov/content/home
Subcontracting Opportunities
Army Federal Acquisition Regulation (AFAR) Encourages:
Small Business Participation
AFAR Requires:
Small Business Sub-contracting Plan
Small Business Programs strives to provide networking for sub-contracting opportunities Other recourses:
1. SBA: https://www.sba.gov/district/dallas-fort-worth
2. APEX Accelerator (DFW): https://www.uta.edu/research/centers/cross-timbers
Did you know?
Contracts awarded to Large Business must include SB Subcontracting Plan
(FAR 52.219-9)
https://www.sba.gov/district/dallas-fort-worth https://www.uta.edu/research/centers/cross-timbers
UPCOMING EVENTS
SWF Office of Small Business
Programs
Contractor Opportunities!
Corpus Christy Army Depot Industry Day, 4 April 2024 Registration Link: Morning Session https://delmarptac.ecenterdirect.com/events/16875 Afternoon Session https://delmarptac.ecenterdirect.com/events/16876
El Paso APEX Accelerator Small Business Industry Day, 14 May 2024 Registration Link: https://www.elpasococ-events.org
Dyess Air Force Base Industry Day (B-21 Program), 3 June 2024 Registration Link: TBD
Email Capability Statement to Alisa.Marshall@usace.army.mil https://delmarptac.ecenterdirect.com/events/16875 https://delmarptac.ecenterdirect.com/events/16876 https://www.elpasococ-events.org/ mailto:Alisa.Marshall@usace.army.mil
INTRODUCTION TO SBA
Fort Worth District is supported by a local SBA Representative
Procurement Center Representative (PCR) Small Business Administration (SBA)
Derek Gadberry Procurement Center Representative, North Texas
Area V, SBA Office of Government Contracting derek.gadberry@sba.gov Cell: 202-765-9446 mailto:derek.gadberry@sba.gov
PROCUREMENT CENTER REPRESENTATIVE
Inform Informs agencies on updates to SB regulations and changes in SBA certification programs
Assist Assists agencies in meeting their SB goals through training, counseling and technical assistance; participates in outreach events
Review Review Subcontracting Plans for compliance prior to award
Audit and Advocate Assures SBs are given fair consideration and opportunity in federal procurements; review Agency’s SB coordination records
Counsel Receives copies of Cure/Show Cause notices of SB firms headquartered in the PCRs territory; contacts firm to offer assistance if needed
QUESTIONS
Thank You
Go forth and be successful
WRAP UP
Questions Lunch Options
Self-Guided Site Visit
QUESTIONS
WHAT’S FOR LUNCH?
There are numerous options within walking distance of Fort Worth Central Station
Branch & Bird 640 Taylor St.
Potbelly 540 Throckmorton St.
Salsa Limon 550 Throckmorton St.
Picchi Pacchi 411 W 7th St.
Bailey’s BBQ 826 Taylor Street Salata 520 Commerce St.
Corner Bakery 615 Main Street Mi Cocina 509 Main Street Subway 1001 Jones St.
SELF-GUIDED SITE VISIT
Two Locations Transportation is on your own USACE & TRWD Staff will be onsite from
1:00 PM – 3:00 PM
Ham Branch Aquatic Habitat Mitigation Parking Location: Harmon Field Park Address: 672 N South Freeway Instructions: Park in the large parking lot. First viewing area is at the Pedestrian Bridge.
North Bypass Channel Location: TRWD Admin Office Address: 800 E Northside Drive Instructions: Come in the main TRWD drive off Northside Drive.
Park in a non- designated parking spot. Viewing area is directly to the south of Building 800.
VIRTUAL TOUR
Link: https://experience.arcgis.com/experience/0f3b5566801d4e96b7ca886b28d97ad5/ **Use of this virtual tour is part of the beta testing to leverage technology for industry engagement** https://experience.arcgis.com/experience/0f3b5566801d4e96b7ca886b28d97ad5/
CLOSING
BE ON THE LOOKOUT FOR A SURVEY IN THE COMING WEEKS…
THANK YOU… AND BE SAFE!!!
| Modified Central City�Industry Day��March 28, 2024� |
| Opening Remarks�USACE |
| Agenda |
| Opening Remarks�Tarrant Regional Water District |
| Opening Remarks�City of Fort Worth |
| Safety Moment |
| Safety Moment |
| Tarrant Regional Water District (TRWD) |
| Slide Number 9 |
| Slide Number 10 |
| Slide Number 11 |
| Slide Number 12 |
| Slide Number 13 |
| Slide Number 14 |
| Slide Number 15 |
| Slide Number 16 |
| Slide Number 17 |
| Slide Number 19 |
| Slide Number 20 |
| Slide Number 21 |
| Slide Number 22 |
| Slide Number 23 |
| Slide Number 24 |
| Slide Number 25 |
| Slide Number 26 |
| Slide Number 27 |
| Slide Number 28 |
| City of Fort Worth |
| Slide Number 31 |
| Ongoing Utility Relocations |
| Central City and TRV TIF 9 |
| Slide Number 34 |
| Slide Number 35 |
| Slide Number 36 |
| Central City Opportunities |
| Panther Island Opportunities |
| Slide Number 39 |
| Doing Work for the City of Fort Worth |
| Slide Number 41 |
| Slide Number 42 |
| REQUIREMENTS |
| REQUIREMENTS |
| Slide Number 46 |
| Slide Number 47 |
| Slide Number 48 |
| Slide Number 49 |
| USACE |
| Central City Flood Risk Management Project Summary |
| Project Authorization�History |
| Modified Central City Project Phasing |
| Flood Risk Management�Completed Valley Storage Sites |
| MITIGATION: Ham Branch & Sycamore Creek �Aquatic Habitat |
| Flood Risk Management�North Bypass Channel – Phase 1 |
| Flood Risk Management �North Bypass Channel – Phase 1 Option |
| Flood Risk Management �South Bypass Channel – Phase 1 |
| Flood Risk Management�South Bypass Channel – Phase 2 |
| Flood Risk Management�Upstream valley storage – Phase 1 |
| Flood Risk Management�Upstream valley storage – Phase 2 |
| Flood Risk Management�Downstream valley storage – Phase 1 |
| Flood Risk Management�Downstream valley storage – Phase 2 |
| Flood Risk Management�Trinity Point Gate & Tie-In |
| Flood Risk Management�Clear ForK Gate & Tie-In |
| Flood Risk Management�TRWD Gate & Pump Station |
| Flood Risk Management�Dams |
| Ecosystem Restoration�Gateway/Oxbow |
| Ecosystem Restoration�RockwooD Park |
| Flood Risk Management�Final Tie-In |
| Central City Project Schedule |
| Central City Project Schedule |
| Industry Engagement |
| Exchanges with Industry |
| Request for Information – North Bypass Channel |
| Contract Opportunities |
| contract opportunities |
| Market Research – North Bypass Channel |
| Slide Number 79 |
| Agenda |
| Slide Number 81 |
| Slide Number 82 |
| Slide Number 83 |
| PIEE solicitation process |
| Piee search |
| Fort Worth District |
| Slide Number 87 |
| Upcoming events |
| Introduction to SBA |
| Slide Number 90 |
| Procurement Center Representative |
| Questions |
| WRAP Up |
| Questions |
| What’s for lunch? |
| Self-Guided Site Visit |
| Virtual Tour |
| Closing |
File details come from the government source that posted it. Updated .