AMD 0002 25Q00969.pdf

PDF 1 MB Posted

Attached to
BB Gate Attendant Services
Solicitation number
W9126G25Q0969
Issued by

About this file

This is an Amendment (AMD 0002) to Solicitation W9126G25Q0969 for Gate Attendant Services at Benbrook Lake, South Holiday Park. The amendment revises the solicitation closing date to May 5, 2025 at 12:00 PM and includes a revised Performance Work Statement (PWS). The contract covers gate attendant services for two periods: a base year from May 11, 2025 to September 27, 2025 (72 days) and an option year from April 1, 2026 to September 27, 2026 (92 days).

The gate attendant services include collecting use fees, managing campsite reservations, conducting park inspections, assisting visitors, reporting disturbances, maintaining facilities, and performing various administrative tasks. The contractor must provide a two-person team that passes a criminal background check, maintain a professional appearance, and comply with specific security, safety, and operational requirements. The contract will be awarded as a Firm Fixed Price, with the contractor responsible for providing transportation, living quarters, and other necessary equipment and supplies not furnished by the government.

View the file

Other files

File Type Posted
W9126G25Q0969 AMD 0001.pdf PDF
W9126G25Q0969 AMD 0001.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Solicitation W9126G25Q0969 is due on May 5, 2025. Revised PWS is attached.

See Summary of Changes Block 30.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9126G25Q0969

X 9B. DATED (SEE ITEM 11)

11-Apr-2025

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

AMD 0002

5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

30-Apr-2025

CODE

US ARMY CORPS OF ENGINEERS FORT WORTH

819 TAYLOR ST, CT OFC RM 2A17

FORT WORTH TX 76102-0300

W9126G 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9126G25Q0969

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMD 0002

Solicitation W9126G25Q00969 Amend 0002 The purpose of this amendment is to:

a. Revised Solicitation with a closing date May 5, 2025, 12:00 PM.

b. Publish government responses to public request for information relative to specific project details.

All other terms and conditions remain unchanged.

Only a warranted Contracting Officer (either a Contracting Officer or an Administrative Contracting Officer (ACO)), acting within their appointed limits, has the authority to issue modifications or otherwise change the terms and conditions of this contract. If an individual other than the Contracting Officer attempts to make changes to the terms and conditions of this contract, you shall not proceed with the change and shall immediately notify the Contracting Officer. Proceeding with any work not authorized by the Contracting Officer will be at the Contractor’s own risk.

(End of Summary of Changes)

1 April 2025

FORT WORTH DISTRICT

PERFORMANCE WORK STATEMENT

GATE ATTENDANT SERVICES

1. GENERAL: This is a non-personal services contract to provide Gate Attendant Services. The Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.

1.1 DESCRIPTION OF SERVICES/INTRODUCTION: The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform Gate Attendant Services for the duration of the contract period as defined in this Performance Work Statement (PWS), except for those items specified as Government-furnished property and services within each Lake Appendix in this solicitation. The Contractor shall perform to the standards in this contract. Work to be accomplished under this contract shall be in accordance with the following:

1) Fort Worth District Performance Work Statement – Gate Attendant Services

2) Lake Appendices

3) Lake Office Gate Attendant Handbooks.

The successful Contractor must pass a criminal background check. Most Gate Attendant positions require a 2-person team, while a few locations may require only 1 person. See each Lake Appendix for specific Gate Attendant requirements for each lake.

1.1.1 Definitions:

(a) Contractor: The person awarded the contract.

(b) Contracting Officer (KO): The person with the authority to enter into, administer, and/or terminate contracts and make related determination and findings on behalf of the Government. This person will be identified on the SF 1449 (Solicitation/Contract/Order for Commercial Items).

(c) Lake Manager: The manager of the local lake. The Lake Manager may appoint an authorized representative to act on their behalf.

1.1.2 Basic Requirements: The following requirements for submitting a bid and receiving an award are now mandatory for conducting business with the DOD Government.

(a) All offerors are required to obtain a Data Universal Numbering System (DUNS) number by calling 1-800-333-0505 or by visiting www.dnb.com.

(b) All prospective Contractors must be registered in System for Award Management (SAM) database prior to any award resulting from this solicitation. If at time of award, Contractor is not registered, award will be made to the next successful “registered” offer.

Registration may be accomplished via the internet at www.sam.gov.

(c) All payments shall be made by Electronic Funds Transfer (EFT) or “direct deposit”.

(d) E-Verify Verification of Eligibility. The Contractor must use the U.S. Department of Homeland Security E-Verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award.

http://www.dnb.com/ http://www.sam.gov/ http://www.uscis.gov/e-verify

2 April 2025

1.2 SCOPE: Gate Attendant services as described in Section 1.11, WORK TO BE PERFORMED, and in each Lake Appendix.

1.3 PERIOD OF PERFORMANCE: The term of the contract and required services are defined in this solicitation in each Lake Appendix.

Position Number Days

Surveillance Hours

Gate House Hours

Availability Hours

South Holiday A Summer Season Base

(May 11, 2025-September 27, 2025)

72 1152 720 1152

South Holiday A Summer Season Option 1

(April 1, 2026-September 27, 2026)

92 1472 1104 1104

CALENDAR DAYS WORKED (base year and option period)

SHIFT A – SOUTH HOLIDAY

Base Year 2025-2026

May: 11-14, 19-22, 27-30 Total: 16 days June: 4-7, 12-15, 20-23, 28-30 Total: 15 days July: 1, 6-9, 14-17, 22-25, 30, 31 Total: 15 days August: 1, 2, 7-10, 15-18, 23-26, 31 Total: 15 days September: 1-3, 8-11, 16-19, 24-27 Total: 15 days

Total: 72 days

SHIFT A- SOUTH HOLIDAY

Option Year 2026-2027

April: 1-4, 9-12, 17-20, 25-28 Total: 16 days May: 3-6, 11-14, 19-22, 27-30 Total: 16 days June: 4-7, 12-15, 20-23, 28-30 Total: 15 days July: 1, 6-9, 14-17, 22-25, 30, 31 Total: 15 days August: 1, 2, 7-10, 15-18, 23-26, 31 Total: 15 days September: 1-3, 8-11, 16-19, 24-27 Total: 15 days

Total: 92 days

1.4 GENERAL INFORMATION:

1.4.1 Quality Control: Not Applicable.

1.4.2 Quality Assurance: The Government shall evaluate the Contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan. This plan is primarily focused on what the Government must do to ensure that the Contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the minimum acceptable defect rate(s).

1.4.2.1 Inspection and Contract Performance: The service performed by the Contractor under the provisions of this contract shall be subject to inspections by the Contracting

3 April 2025

Officer, Lake Manager, or the designated Quality Assurance (QA) representative to ensure strict compliance with the terms of the contract.

(a) Notification of Deficiencies: The Contractor shall be notified in writing of any serious or recurring deficiency in service observed by the Contracting Officer or Lake Manager.

(b) Documentation of Deficiencies: Written notifications and memoranda for the record shall be prepared for the Contracting Officer. The original will be part of the contract file at the U.S. Army Corps of Engineers, Fort Worth District Office and a copy will be issued to the Contractor.

(c) Correction of Contract Deficiencies: Upon receipt of notification of deficiency in service, Contractors will immediately correct deficiencies and /or take steps to prevent recurrence of the deficiency.

(d) Deficiencies of Service: This contract may be terminated by the Contracting Officer.

(e) Evaluation of Performance: All Contractors will have their performance evaluated no less than mid-term and at the conclusion of their contract. Audits are performed per EC 1130-2-550 on a quarterly basis and recorded on ENG Form 6065, which will be placed into the contract file.

1.4.3 Government Holidays: The Contractor will work the holidays that fall on their shift.

New Year’s Day Labor Day Martin Luther King Jr.’s Birthday Columbus Day President’s Day Veteran’s Day Memorial Day Thanksgiving Day

Juneteenth Christmas Day Independence Day

1.4.4 Hours of Operation: The hours of park operation are as specified in each Lake Appendix.

The Contractor will provide staffing during all posted hours of park operation.

1.4.5 Place of Performance: The work to be performed under this contract will be performed as described in each Lake Appendix.

1.4.6 Type of Contract: The Government will award a Firm Fixed Price contract.

1.4.7 Security Requirements:

1.4.7.1 General Security Requirements and Guidance: The security requirements described below apply to all contract personnel (including employees of the prime Contractor (“Contractor”) and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (e.g., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, 4 April 2025 the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as “RAMs”), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures—this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this contract, should the FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures..

1.4.7.2 Antiterrorism (AT) Level I Training: All contract personnel requiring routine access to Army installations, facilities, and controlled access areas, or requiring network access shall complete initial and annual refresher AT Level I awareness training. Online AT Level I awareness training is available at https://jko.jten.mil/ (website subject to change).

1.4.7.3 Physical Security and Access Control Requirements: All contract personnel requiring physical access to a federal installation or facility shall comply with the access control procedures of that location. Contract personnel requiring unescorted access to meet contract performance requirements on a DoD installation in the US shall be vetted by the installation/facility Provost Marshal/Directorate of Emergency Services/Security Office using the National Crime Information Center-Interstate Identification Index (commonly referred to as “NCIC-III”) and Terrorist Screening Database (commonly referred to as “TSDB”). Contract personnel shall comply with all personal identity verification requirements specified in installation/facility policies and procedures.

Contract personnel who do not meet requirements for unescorted access to USACE facilities shall coordinate escorted access with the Government representative, as needed.

Contract personnel who receive keys, access cards, or lock combinations that provide access to government-owned property shall comply with key and lock control procedures of the RA.

1.4.7.4 Suspicious Activity Reporting training (e.g. iWATCH, CorpsWatch, or See Something, Say Something): All contract personnel shall receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.

1.4.7.5 Pre-screen candidates using E-Verify Program: Contractors shall comply with the requirements set forth in FAR clause 52.222-54 Employment Eligibility Verification and FAR Subpart 22.18 in using the E-Verify Program at (https://www.e-verify.gov/) (website subject to change) to meet the contract employment eligibility requirements.

Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws in accordance with FAR 22.102-1(i). An initial list of verified/eligible candidates shall be provided to the COR no later than three business days after the initial contract award. When contracts are with individuals, the individuals will be required to

5 April 2025 complete a Form I-9, Employment Eligibility Verification, and submit it to the Contracting Officer to become part of the official contract file.

1.4.8 Special Qualifications: Not Applicable.

1.4.9 Pre-work Conference: The Contractor will be required to attend a pre-work conference at no additional cost to the Government to review the policies outlined in the PWS. This conference will be conducted by the Lake Manager or their representative, at each local lake office or other agreed upon location. See each Lake Appendix for additional details and requirements.

1.4.9.1 Training. The Contractor will be provided I-Watch and CorpsWatch Training and Southwestern Division Authorized Collectors Training. The training will be conducted at the pre-work conference and will be documented as complete in the contract files.

1.4.10 Contracting Officer Representative (COR): Not applicable.

1.4.11 Contractor Key Personnel: Gate Attendant.

1.4.12 Identification of Contractor Employees: Government-furnished Contractor identification badges or tags will be worn by the Contractor during on-duty hours at all locations

1.4.13 Contractor Travel: Not Applicable.

1.4.14 Data Rights: The Government has unlimited rights to all documents/material produced under this contract. All documents and materials, to include the source codes of any software, produced under this contract shall be Government owned and are the property of the Government with all rights and privileges of ownership/copyright belonging exclusively to the Government. These documents and materials may not be used or sold by the Contractor without written permission from the Contracting Officer. All materials supplied to the Government shall be the sole property of the Government and may not be used for any other purpose. This right does not abrogate any other Government rights.

1.4.15 Organizational Conflict of Interest: Not Applicable.

1.5 GOVERNMENT-FURNISHED ITEMS AND SERVICES:

1.5.1 Facilities: The Government will provide a gate house in the park in which the Contractor will work.

1.5.2 Equipment: The Government will provide a non-networked computer for non-sensitive data entry, computer monitors, printers, telephone and radio communication equipment.

1.5.3 Materials: The Government will provide gate house supplies, including forms, maps, brochures, handouts, computer paper, staplers, staples, china markers, water hose and sprinklers.

The Government will provide other items as specified in each Lake Appendix.

1.5.4 Trailer Site: Unless otherwise indicated in the lake-specific appendices, the Government will furnish a site for self-contained travel trailer or motor home with 110- volt electricity, water, and sewer hook-ups and/or dump station nearby. If the Contractor’s travel trailer is not configured or adaptable to the sewage, water or electric hookups available at the site, the Government will not be responsible for providing attachments, etc. No reimbursement will be made whenever utilities are not available and must be secured elsewhere. The use of the facilities is at the Contractor’s own risk and damage to personal equipment will be the sole responsibility of the Contractor. Site shall be restored to original condition after period of performance is completed.

1.6 CONTRACTOR-FURNISHED ITEMS AND RESPONSIBILITIES:

6 April 2025

1.6.1 General: Any additional supplies, equipment, facilities, and services the Contractor desires to perform work under this contract that are not listed under Section 1.5, Government-Furnished Items and Responsibilities, of this PWS shall be furnished by the Contractor.

1.6.2 Equipment: The Contractor will provide a transportation vehicle, which can be operated independently of the RV free of leaks and in good mechanical condition for use in performing the requirements of the contract. Proof of liability insurance will be submitted during the pre-work conference and prior to the work start date. All motor vehicles and operators will comply with state laws such as licensed operators, vehicle safety equipment, etc. The Contractor may be required to display the vehicle identification provided by the Government on the vehicle while on duty. The Contractor’s vehicle will not display Emergency Red and/or Blue Lights, use a siren, or otherwise represent an appearance of an emergency vehicle while on duty. The Contractor will supply the gas for operation of the vehicle while on duty.

1.6.3 Materials: The Contractor shall furnish all materials, excluding those furnished by Government as specified above in Section 1.5, needed to operate the gatehouse. This list includes, but is not limited to highlighters, color markers, notepads, pens, pencils, tape, trash bags, cleaning supplies, restroom supplies and any other items that may be necessary to operate the gatehouse.

1.6.4 Temporary Living Quarters: The Contractor shall furnish a fully operable “self-contained” recreational vehicle (RV) of the travel trailer or motor home type to serve as temporary living quarters for the duration of the contract. Maximum size of the trailer is determined by physical limitations of the site furnished. It will be located near the entrance to the park at a location to be designated by the Lake Manager. Pickup (shell-type) campers, pop-up tent trailer, tents, mini-travel trailers, mobile homes, buses, or any other types of recreation vehicles which do not meet general size requirements or the self-contained classification as determined by inspection of the Contracting Officer or his/her authorized representative will not be acceptable. The Contractor will be the sole occupants of the site.

1.6.5 Personnel: See each Lake Appendix.

1.7 CONTRACTOR MANAGEMENT REPORTING (CMR): Not Applicable.

1.8 APPLICABLE PUBLICATIONS (CURRENT EDITIONS): The Contractor must abide by all applicable regulations, publications, manuals, and local policies and procedures. These include latest Title 36 CFR Part 327, EC 1130-2-550, the USACE Recreation Use Fee SOP, Lake Appendix, Lake Office Gate Attendant Handbook and United States Army Corps of Engineers EM 385-1-1, Safety and Health Requirements Manual.

1.9 ATTACHMENT/TECHNICAL EXHIBIT LIST:

1.9.1 Attachment 1/Technical Exhibit 1 – Performance Requirements Summary: See each Lake Appendix.

1.9.2 Attachment 2/Technical Exhibit 2 – Deliverables Schedule: See each Lake Appendix.

1.10 SAFETY:

1.10.1 Safety Manual Requirements: The Contractor(s) shall comply with all pertinent sections of the U.S. Army Corps of Engineers' Safety and Health Requirements Manual, EM 385-1-1, current at the time of award, and any subsequent revisions. This manual can be found on-line at:

www.usace.army.mil/usace-docs/eng-manuals/em385-1-1/toc.htm.

1.11 WORK TO BE PERFORMED:

http://www.usace.army.mil/usace-docs/eng-manuals/em385-1-1/toc.htm

7 April 2025

TASK 1. Use Fees: The Contractor will follow fee collection, credit voucher, refund, campsite reservation and remittance procedures established by the U.S. Army Corps of Engineers, Recreation Operations and Maintenance Guidance and Procedures, Chapter 9- Recreation Use Fees (EC 1130- 2-550, Chapter 9) and the Corps Recreation Use Fee Program SOP. These regulations can be accessed on the web at http://corpslakes.usace.army.mil.

(a) Use Fee Collection: The Contractor is required to collect Use Fees daily, to ensure visitors have paid applicable use fees, utilizing the U.S. Army Corps of Engineers Use Permit (ENG Form 4457), Recreation One Stop (R1S), Outdoor Recreation Management Suite (ORMS) Field Manager Program, an automated cash register, and/or collection from an honor vault. This includes going through the park to collect and safeguard fees when necessary. The Contractor is required to collect use fees for specialized recreation sites, facilities and services provided by the Corps of Engineers. This may include, but is not limited to, camping, group facility use, day use, special facility use, and multiple site rental use. The Contractor is required to accept cash, personal check, traveler’s checks, money orders or credit card payments as methods of use fee payment.

(b) Audits and Fee Security: The Contractor will be responsible for Use Fee Permits (ENG Form 4457), cash register receipts and journal, computer generated receipts, signed credit card receipts, and all collected forms of use fee payments until turned over to an authorized fee collector/cashier. The Contractor may be audited at any time, with or without prior notice, and is required to place all forms of collected use fee payments/monies in the gatehouse cash drawer or fee safe provided immediately upon receipt. The cash drawer or fee safe will remain closed immediately after every transaction and the automatic lock shall not be defeated at any time.

(c) Remittance Procedures and Inspection of Use Fees: All lakes require use fee remittance a minimum of once a week. See “Use Fee Collections” in each Lake Appendix, for which process is used at the location(s) on which you are bidding. Inspections will be performed during the contract period as deemed necessary by the Lake Manager.

TASK 2. Campsite Reservations: The Contractor will comply with the Fort Worth District Camping and Reservation Policy Manual and the Lake Gate Attendant Handbook, both of which are available at the lake office. The Contractor will adhere to guidelines and procedures established under the Recreation One Stop (R1S), using Outdoor Recreation Management Suite (ORMS) Field Manager program in the campground. The Contractor may also be required to take advance campsite reservations, which would consist of receiving and booking reservations requests, collecting and processing camping fees, and handling cancellation and refund requests. The Contractor will be required to perform some or all the following duties daily:

(a) Pick up reservation data reports, i.e. bookings, arrival reports, cancellation reports, etc., from the local lake office or accept the reports delivered in person, and /or transmitted by telephone, electronic mail received through a computer, facsimile machine, etc.

(b) Maintain and update necessary status reports utilizing charts, status boards, note pads, card systems, computer/cash register systems, ORMS, Field Manager, R1S, etc., to ensure that campsite status is kept current at all times.

(c) Keep records and monitor date of arrivals, departures, no-shows, cancellations, etc.

(d) Fill out refund and credit voucher forms according to policy.

(e) Post or identify reserved and vacant campsites by positing provided signs or markers.

The Contractor will also maintain records as necessary for the administration of the campsite reservation program as directed by the Lake Manager. The Contractor will accept

8 April 2025 the campsite reservation permit/confirmation letter as both proof and payment of the reservation.

TASK 3. Group Shelters: The Contractor will keep records and ensure compliance of group shelter use as required by the Lake Manager including the use of the R1S system, where applicable. The Contractor may be required to take advance reservations for these facilities, and also check in the reservations once they arrive in the park. The Contractor may also be required to turn on utilities at these sites in preparation for arrival of these visitors.

TASK 4. Camping Status: The Contractor will record the campsite occupied and maintain record of the current status for each campsite occupied. The Contractor will keep written records of each camper’s length of stay to ensure compliance with the Fort Worth District camping policy. The Contractor will register park users, issue appropriate passes and deliver messages to visitors. The Contractor will keep a written record of campers who are turned away due to lack of campsites or campsites with desired hook-ups. The Contractor shall also participate as required in all Recreation Use Surveys that may be conducted.

TASK 5. Park Inspection: The Contractor will inspect the park area and facilities a minimum number of times each day as required by each Lake Appendix. Inspections will be made in a vehicle provided and maintained by the Contractor. During all inspections, if the Contractor observes park users violating Corps of Engineers rules and regulations (Title 36 CFR, Part 327), the Contractor shall advise the visitor of the violation. The Contractor is not to pursue enforcement. If violations persist, the Contractor shall contact a Park Ranger. If a Park Ranger is not available, the Contractor will record any violations of USACE rules or regulations and forward them immediately to the Lake Manager.

TASK 6. Visitor Assistance: The contractors are not required to be in the gatehouse for the duration of the surveillance hours but must be made available to assist UACE personnel and park patrons.

One contractor must always man the gate house from 8:00 am to 8:00 pm. The gatehouse will be occupied by the Contractor during the above time, during which time they will assist the park visitors by providing information concerning the visitor’s stay. This may include providing free copies of informational pamphlets, rules and regulations and/or maps. The Contractor will conduct themselves in a professional and courteous manner at all times. The Contractor will advise campers and park visitors: (1) to utilize only developed facilities or designated overflow areas and, (2) to operate and park all vehicles and campers only on paved surfaces or designated parking areas. The Contractor will advise campers of quiet hours (10:00 P.M. until 6:00 A.M.) as they enter the park.

TASK 7. Disturbances: The Contractor will promptly report all accidents, violations of law, disturbances and situations that could affect health and safety of visitors to the Park Ranger or Lake Manager. In the event the Contractor is unable to communicate with the Park Ranger and the situation dictates, the Contractor will contact the local law enforcement officers as soon as practical.

All communications with local law enforcement officers will be reported to the Park Ranger or Lake Manager, on the next workday. The Contractor will not attempt to apprehend any violators or enforce rules, regulations, or laws. Attendants will inform park visitors of rules, regulations and laws and refer violations to the Park Ranger. NOTE: Serious incidents such as a fatality in the park or situations of significant public interest will be reported immediately to the local law enforcement agency and to the Lake Manager. Contact information will be available at each applicable lake office.

TASK 8. Complaints: The Contractor will keep a written record of all complaints and criticisms of park facilities. These records will be given to the Lake Manager at regular intervals or upon request.

TASK 9. Lost and Found: The Contractor will keep lost and found articles in the gatehouse or trailer and turn over all found articles with as much information as possible to a Park Ranger in accordance to each lake policy.

9 April 2025

TASK 10. Image, Personal Appearance and Dress: The Contractor shall, at all times when on duty and when dealing with the public, be required to maintain a fully-clothed and neat, well-groomed appearance. Contractor-furnished shirts, hats and/or vests identifying the Contractor as the attendant are encouraged and may be required as noted in the lake appendices. In no way shall these clothing items create an appearance that the Contractor or their employee is an employee of the Government.

Government-furnished Contractor identification badges or tags will be worn by the Contractor during on-duty hours at all locations. Cut-offs are not allowed, and shorts must be knee-length or longer. Shoes shall be worn at all times; flip flops or similar footwear will not be permitted.

TASK 11. Cooperation with Others: The Contractor will maintain good communications and relations with the public, other Contractors, volunteers, Corps of Engineers employees and others who work with the Corps of Engineers for the construction of new facilities, repair of existing facilities, sanitation services, trash pick-up services, and grass mowing, etc. The Contractor will allow Corps of Engineers employees to utilize communication facilities furnished by the Government. Cooperation will include, but not be limited to summoning assistance and reporting all instances of vandalism, harassment, public intoxication, speeding, etc., to proper authorities. The Contractor will diligently attempt to provide for the needs of our visiting public as public relations representatives for the Corps of Engineers.

TASK 12. Living Area and Gatehouse Maintenance:

(a) Trailer Area Maintenance: The Contractor will maintain the area where the trailer is parked (Gate Attendant Site) in a clean and sanitary condition at all time. No dog pens, horse corrals, poultry cages or similar facilities for pets or the raising of animals will be allowed.

(b) Pets: All pets will be confined in the Contractor’s trailer or on a leash of 6-foot or less in length and must not disturb park visitors. The Contractor’s site will remain clean of animal waste at all times. Pets will have all vaccinations as required by the state laws and will wear a collar that displays the vaccination tags at all times. No pets are allowed inside the gatehouse.

(c) Excessive Personal Items: No washers, dryers, deep freezers, or excessive personal items will be permitted around trailer pad areas or inside the gatehouse.

(d) Smoking: Smoking is not allowed in or within 30 feet of the gatehouse.

(e) Gatehouse Maintenance: The Contractor will maintain the gatehouse in a clean, orderly and sanitary condition at all times. The Contractor will provide all equipment, tools, and supplies necessary to clean the gatehouse. Only authorized personnel are to enter the gatehouse at any time.

(f) Trash Removal: Solid waste and refuse shall be deposited in a nearby trash receptacle (dumpster) furnished by the Government.

(g) Living Quarters Security: Security of the Contractor’s living quarters and all personal property shall remain the Contractor’s responsibility throughout the duration of the contract. The Government accepts no responsibility for, nor will it be liable for, damage or theft occurring to the Contractor’s property.

TASK 13. No Soliciting: Contractor will not solicit, advertise, sell or offer to sell any unauthorized goods or services to campers or visitors on public property (CFR Title 26, Section 327.18).

10 April 2025

TASK 14. Weapons: Firearms or any type of object that could be considered a weapon will not be carried or kept in the park (e.g. pepper spray, clubs). This includes, but not limited to the gatehouse or trailer occupied by the Contractor.

TASK 15. Alcohol: The Contractor will not consume or be under the influence of alcoholic beverages, illicit drugs and/or medication unless administered under a doctor’s prescription while on duty or while in view of the public. This includes, but is not limited to, the park entrance area, attendant site, gatehouse, park restrooms, campsites, etc.

TASK 16. Government Property: The Contractor will be required to return Government property on the last day of the contract. The Contractor will be held liable for any missing or damaged Government equipment or materials. Computers, printers, radios, and telephone equipment provided by the Government are for official use only. Contractor shall not use gate house computers for personal business or install any personally owned software. Any damages incurred as result of personally-owned software being installed on the Government computers will be considered damages to Government property and Contractor will be held responsible for reimbursement to the Government any cost associated with repairs or replacement of the equipment.

Final payment will not be paid until all Government property is returned and all fee monies have been turned in.

TASK 17. Absenteeism: The Lake Manager should be contacted and given as much advance notice as possible about anticipated absences. The Lake Manager must approve all absences in advance.

An absence by any one or both of the two-person contract team, without prior approval by the Lake Manager, is grounds for dismissal of the Contractor and termination of the contract. If arrangements will be made for someone to cover the shift, these persons must be approved in advance by the Lake Manager and must meet the required bonding and insurance requirements. Payment for time not performed will be subtracted from the lump sum amount at the daily rate. The daily rate is calculated by dividing the lump sum by the total number of days.

TASK 18. Visitors of the Contractor/Gate Attendant: Adult family members and friends will not live with the Contractor. “Living with the Contractor” is defined as a person staying with the Contractor for more than 14 days in a 30-day period. Visitors of the Contractor will be required to lodge in the Contractor’s trailer, or, if they have their own equipment, visitors will be required to camp at a campsite in the park and pay the regular camping fee. Visitors will not be allowed to connect to the Contractor’s utilities at any time. All non-authorized personnel are to remain outside the gate house at all times.

TASK 19. Security Bonding (Bonding for Fee Collection): The Contractor must be fully bonded or insured to cover collected funds not received by the designated Government agent or Recreation One Stop by furnishing the Contracting Officer proof of such bond or security in the minimum amount of $5,000.00 payable to the U.S. Army Corps of Engineers. Condition of the bond obligation covers the loss of Government Funds/Use Fees that are stolen or embezzled by the contract Gate Attendant. The bond must name all persons that will be working under this contract and handle Government Funds/Use Fees. The bonds should note that the contract Gate Attendant collectors are not a direct employee of the Government. Term of the bond is for a minimum 60 days past the Contractor’s effective date of termination. A condition in the bond will require the bonding company to notify the Corps of Engineers before the bond is modified, terminated or cancelled, prior to the original termination date. The Contractor must provide a copy of the bond at the Pre-work Conference. The Contractor shall not start work without proof of bonding. The Contractor can choose one of the following options to fulfill this requirement:

(a) Obtain a Business Services, Volunteer in Parks (VIP), Fidelity, or Dishonesty bond from an insurance agent meeting the criteria stated in Task 19, above. The cost of the bond varies by type, individual and the issuing company.

11 April 2025

(b) Furnish an irrevocable, unconditional letter of credit from a financial institution in the specified amount.

TASK 20. Physical Security and Key Control: See Sections 1.4.7.1 and 1.4.7.2 above.

1.12 GENERAL LIABILITY AND OTHER INSURANCE: In addition to automobile insurance required in 1.6.2 Equipment, the Contractor is responsible for obtaining and paying for any other insurance desired, including but not limited to, medical, general liability, and comprehensive property. The Contractor may be responsible for damage to private or Government property if in the opinion of the Contracting Officer or his designated representative the damage is a result of Contractor negligence.

1.13 DAMAGE RESPONSIBLITY: The Contractor shall be responsible for restoring any Government facilities, structures, or trees damaged as a result of his/her operation. The Contractor shall also be responsible for any damage to private property, and will notify the Lake Manager immediately of damage to Government property and/or private property, and injury to any person resulting from his/her operation. The Contractor will notify the Lake Manager immediately of damage to Government facilities due to vandalism or other causes on the day such damage is first noticed.

1.14 LIABILITY: During the period of this contract, the Contractor shall be responsible for all injuries or damages of any nature caused or contributed to by the Contractor, his/her agents, and/or employees while engaged in work under this contract.

1.15 PERMITS/COMPLIANCE: The Contractor shall, without additional expense to the Government, be responsible for complying with and obtaining any necessary licenses and/or permits. The Contractor will comply with all Federal, State, County, and Municipal laws, codes and regulations in connection with the performance of the work.

1.16 COMMUNICATIONS EQUIPMENT: The Contractor may be required to operate and use radio equipment for communication with the Park Rangers and lake office. The Government will furnish radio equipment when required, and the Contractor will be trained on its use.

1.17 PAYMENT FOR SERVICES: Payment will be made monthly by Electronic Funds Transfer (EFT) in accordance with FAR 52.212.4. Payment will be made upon receipt and acceptance of proper invoice in accordance with 5 CFR 1315.5 (within approximately 10 days).

1.18 TERMINATION: Failure of the Contractor to provide items in full and to provide complete services listed in the contract specifications and applicable specific park sheets may be grounds for termination.

Breach of contract and/or voluntary termination of contract without sufficient cause may jeopardize the Contractor’s standing for future contract with the U.S. Army Corps of Engineers. Contractors may be terminated if the Government determines Gate Attendant services are no longer needed due to unforeseen closures of the park or major facilities (e.g., beaches, boat ramps, restrooms, campgrounds). Unforeseen closures would include those resulting from droughts, flood, storm damage, infrastructure failure and previously unknown safety hazards.

1.18.1 Grounds for Termination: Inappropriate conduct or unacceptable actions of a Contractor may be grounds for termination of the contract. Examples of actions meriting termination include, but are not limited to:

(a) Theft, misappropriation, personal use, and/or improper security and accountability of use fees or Government services, property, equipment, facilities and/ or supplies. Any of these acts may also result in criminal prosecution.

(b) Consumption of alcoholic beverages and/or intoxication while on duty, and possession or use of illicit drugs at any time.

12 April 2025

(c) Discrimination, harassment, profanity, or other inappropriate behavior perpetrated against customers, Corps of Engineers personnel, or other Contractors.

(d) Recurring written and/or verbal complaints from visitors and/or Lake Office personnel on Attendant’s attitude, lack of cooperation and/or resistance to implementation of policies and program as directed by the Lake Manager or his/her authorized representative.

(e) Failure to follow security procedures, including the allowance of unauthorized personnel inside the gatehouse or the Contractor (non-public) work area of the gatehouse/entrance stations.

(f) Inability to perform duties and job responsibilities in accordance with the General Specifications, Specific Park Sheet(s) and Lake Office Gate Attendant Handbook.

(g) Violations of public health and safety, including smoking in the gatehouse.

(h) Failure to maintain a neat, clean, well-groomed personal appearance.

(i) Failure to abide by Title 36 CFR, Chapter III, Section 327.

1.19 DUTY OF CONTRACTOR TO FINISH CONTRACT: The Contractor may not terminate the contract. If the Contractor fails to complete the contract through the specified term including option periods (if applicable), the Contractor is subject to re-procurement cost.

1.20 OTHER REQUIREMENTS: See each Lake Appendix included in this solicitation for further requirements.

***SPECIAL NOTICE***

All persons handling Government monies or accessing the Government computer system under this contract shall be subject to a background investigation to establish their reliability, trustworthiness, conduct and character. By execution of the contract, the Contractor certifies that all persons providing such services under the contract are so qualified, including but not limited to, not having been convicted of a felony. Any person so found not to have the necessary reliability, trustworthiness, conduct and character shall be dismissed. If the Contractor fails to meet this requirement, the contract will be terminated for default. By providing a bid on this contract, you are providing authorization for U.S. Army Corps of Engineers, its agents or representatives to investigate your background, as deemed necessary by such agent or representative, to establish your trustworthiness, reliability and character. In the course of performance of this contract, the Contractor/Contractor Personnel may come into contact with or possession of information covered by the Privacy Act (e.g. Social Security numbers) and/or sensitive personal information of Corps of Engineers employees/members of the public/patrons/customers (e.g., personal checks with account numbers, credit card numbers). The Contractor/Contractor Personnel shall not memorize copy or record this information in any way, nor shall they use their access to this information for any personal reason or financial gain, or provide this information to any third person or party. Failure to comply with these restrictions will result in the immediate termination of the Contractor employee, and may subject the employee to civil suit for money damages and/or criminal prosecution to the fullest extent under the law. Repeated violation of this provision may serve as a basis for termination of the contract.

The Contractor will secure an acknowledgement from every employee that they have read, understand and will comply with this paragraph.

1 April 2025

FORT WORTH DISTRICT

PERFORMANCE WORK STATEMENT

GATE ATTENDANT SERVICES

1. GENERAL: This is a non-personal services contract to provide Gate Attendant Services. The Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.

1.1 DESCRIPTION OF SERVICES/INTRODUCTION: The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform Gate Attendant Services for the duration of the contract period as defined in this Performance Work Statement (PWS), except for those items specified as Government-furnished property and services within each Lake Appendix in this solicitation. The Contractor shall perform to the standards in this contract. Work to be accomplished under this contract shall be in accordance with the following:

1) Fort Worth District Performance Work Statement – Gate Attendant Services

2) Lake Appendices

3) Lake Office Gate Attendant Handbooks.

The successful Contractor must pass a criminal background check. Most Gate Attendant positions require a 2-person team, while a few locations may require only 1 person. See each Lake Appendix for specific Gate Attendant requirements for each lake.

1.1.1 Definitions:

(a) Contractor: The person awarded the contract.

(b) Contracting Officer (KO): The person with the authority to enter into, administer, and/or terminate contracts and make related determination and findings on behalf of the Government. This person will be identified on the SF 1449 (Solicitation/Contract/Order for Commercial Items).

(c) Lake Manager: The manager of the local lake. The Lake Manager may appoint an authorized representative to act on their behalf.

1.1.2 Basic Requirements: The following requirements for submitting a bid and receiving an award are now mandatory for conducting business with the DOD Government.

(a) All offerors are required to obtain a Data Universal Numbering System (DUNS) number by calling 1-800-333-0505 or by visiting www.dnb.com.

(b) All prospective Contractors must be registered in System for Award Management (SAM) database prior to any award resulting from this solicitation. If at time of award, Contractor is not registered, award will be made to the next successful “registered” offer.

Registration may be accomplished via the internet at www.sam.gov.

(c) All payments shall be made by Electronic Funds Transfer (EFT) or “direct deposit”.

(d) E-Verify Verification of Eligibility. The Contractor must use the U.S. Department of Homeland Security E-Verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award.

http://www.dnb.com/ http://www.sam.gov/ http://www.uscis.gov/e-verify

2 April 2025

1.2 SCOPE: Gate Attendant services as described in Section 1.11, WORK TO BE PERFORMED, and in each Lake Appendix.

1.3 PERIOD OF PERFORMANCE: The term of the contract and required services are defined in this solicitation in each Lake Appendix.

Position Number

Surveillance Hours

Gate House Hours

Availability Hours

South Holiday A Summer Season Base

(May 11,…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .