B.08 W9126G23R0082 POCA Solicitation.pdf
PDF 2 MB Posted
- Solicitation number
- W9126G23R0082
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B08 W9126G23R0082 Amendment 0002.pdf | ||
| B.08 W9126G23R0082 POCA Solicitation.pdf | ||
| ATTACHMENTS 1 and 2 PPQ.pdf | ||
| B.08 W9126G23R0082 Amendment 0001.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Army Corps of Engineers Fort Worth District
Indefinite Delivery Indefinite Quantity (IDIQ) 8(a) Performance Oriented Construction
Activity (POCA) Contract Capital Region (CRO) Fort Worth District, Texas
W9126G23R0082 Amendment 0001 January 9, 2023
FY23 Performance Oriented Construction Activity (POCA) for US Army Corps of Engineers, Fort Worth District, Capital Region, Texas.
Contractor w ill provide a timely response to the maintenance, repair, or rehabilitaiton needs at Government installation and facilities w ithin the Capital Region footprint. Typical efforts include, but are not limited to these areas: maintenace, repair, rehabilitation, energy conservation, environmental, logistical, and operation. The contractor w ill be required to perform all facets of the w ork such as surveying the problem, recommending a solution, and correction of the problem in a timely manner. The contractor shall maintain the capability to provide a quick response for this w ork. Task orders issues under this contract shall be issued for w ork assigned to USACE - Fort Worth District, Capital Region, Texas.
NIKISHA W COOK 817-915-5257
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
04-Jan-2023
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________ calendar days after receiving aw ard, X notice to proceed. This performance period is mandatory, negotiable. (See _________________________Task Order
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
YES X NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________03 Feb 2023 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.
B. An offer guarantee is, X is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
US ARMY CORPS OF ENGINEERS FORT WORTH
819 TAYLOR ST, CT OFC RM 2A17
FORT WORTH TX 76102-0300
W9126G
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
11:00 AM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
(817) 886-6403FAX:TEL: TEL: FAX:
W9126G23R0082 214
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
Section SF 30 - Block 14 Continuation Page (SF 30)
AMENDMENT 1
A. CONTRACT CHANGES: 00 21 00 – Instructions to Offerors Section: Last day to submit Projnet questions corrected. Attachments 1 and 2 are added. Wage Determination revised, Jan 05, 2023.
B. TECHNICAL SPECIFICATION CHANGES: There are no technical specification changes with this amendment
C. CONTRACT DRAWINGS: NA
Section 00 10 00 - Solicitation
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job
BASE YEAR: POCA - CAPITAL REGION
FFP
Provide timely response to the maintenance, repair, or rehabilitation needs at Government installations and facilities. Typical efforts include, but are not limited to these areas: maintenance, repair, rehabilitation, energy conservation, environmental, logistical, and operation. The contractor will be required to perform all facets of the work such as surveying the problem, recommending a solution, and correction of the problem in a timely manner. The contractor shall maintain the capability to provide quick response for this work. Task orders issued under this POCA contract shall be issued for work assigned to USACE - Fort Worth District, Capital Region, TX
FOB: Destination
PSC CD: Y1PZ
NET AMT
1001 1 Job
OPTION OPTION YEAR 1: POCA - CAPITAL REGION
FFP
Provide timely response to the maintenance, repair, or rehabilitation needs at Government installations and facilities. Typical efforts include, but are not limited to these areas: maintenance, repair, rehabilitation, energy conservation, environmental, logistical, and operation. The contractor will be required to perform all facets of the work such as surveying the problem, recommending a solution, and correction of the problem in a timely manner. The contractor shall maintain the capability to provide quick response for this work. Task orders issued under this POCA contract shall be issued for work assigned to USACE - Fort Worth District, Capital Region, TX
2001 1 Job
OPTION OPTION YEAR 2: POCA - CAPITAL REGION
FFP
Provide timely response to the maintenance, repair, or rehabilitation needs at Government installations and facilities. Typical efforts include, but are not limited to these areas: maintenance, repair, rehabilitation, energy conservation, environmental, logistical, and operation. The contractor will be required to perform all facets of the work such as surveying the problem, recommending a solution, and correction of the problem in a timely manner. The contractor shall maintain the capability to provide quick response for this work. Task orders issued under this POCA contract shall be issued for work assigned to USACE - Fort Worth District, Capital Region, TX
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 POP 01-FEB-2023 TO
31-JAN-2024
N/A BELTON LAKE OFFICE
JEFFREY PHILLIPS
3110 FM 2271
BELTON TX 76513-9717
254-742-3061
9674CD
1001 POP 01-FEB-2024 TO
31-JAN-2025
N/A (SAME AS PREVIOUS LOCATION)
2001 POP 01-FEB-2025 TO
31-JAN-2026
N/A (SAME AS PREVIOUS LOCATION)
CLIN SCHEDULE
CLIN Schedule
PERFORMANCE ORIENTED CONSTRUCTION
ACTIVITY CONTRACT (POCA)
CAPITAL REGION LAKES
CLIN# Description Coefficient Factor
0001 Pre-Priced Items
0002 Non-Pre-priced Items
0003 Asbestos and Lead-Based Paint
1001 Pre-Priced Items
1002 Non-Pre-priced Items
1003 Asbestos and Lead-Based Paint
2001 Pre-Priced Items
2002 Non-Pre-priced Items
2003 Asbestos and Lead-Based Paint
1. The offeror's Construction price coefficient factor(s) SHALL include all prime and sub-contractor profit, home office overhead, jobsite overhead, and other costs not included in the bare labor, material, and equipment costs from the unit price book or in the non- pre-priced items. These costs include, but are not limited to, the following:
(a) Corporate, Regional, and Site offices (i.e. Office buildings, office spaces, office trailers, office management, office equipment and supplies, etc)
(b) Profit
(c) Performance and Payment Bonds (per Army Federal Regulation Supplement (AFARS) 17.9004 2(h))
(d) Insurance
(e) Compliance with environmental laws, protection and safety
(f) Tax Laws
(g) Protection for moving of Government property
(h) Submittals (i.e. preparation and distribution of Work Plans, Risk Analyses and weekly reports, as-builts, CQC Plans, Safety Plans, Accident Prevention Plans, Hazard Analyses, Test Procedures, Tests, Test Reports, Status Reports, Catalog Cut Sheets, Technical Data Sheets, Shop Drawings, Schedules, O&M Manuals, etc.)
(i) Price quotations
(j) Contractor adjustments to Government Unit Prices
(k) All cleaning, to include final cleaning, shall be applicable per each task order.
(l) All waste and excess materials
(m) Permits, licenses and fees
(n) Mobilization and close-out for total contract, close-out for each task order. Mobilization shall be negotiated with each task order.
(o) Bulletin Board and Project and Safety Signs “If required/Applicable”
(p) Principles, project management, supervision and construction supervision
(q) Technical support staff (i.e. estimator, draftsman/CADD operator, etc.) (r) Administrative support staff (i.e. clerks, secretaries, assistants, etc.)
(s) Quality Control and Quality Control Staff
(t) Travel (includes all associated costs for all personnel)
(u) Marketing and Training (i.e. videos, user guides, brochures, promotions, associated travel, etc.)
(v) Collaboration/face-to-face meetings with all Program/Project stakeholders (i.e.
progress reviews, negotiations, etc.)
(w) Interest associated with funding of equipment and payroll
(x) Employee payroll taxes, insurance and fringe benefits
(y) Risk of lower than expected contract dollar volume
(z) Risk of high inflation costs for option periods
(aa) Risk of poor subcontractor performance and re-performance
(bb) Other risks of doing business
(cc) Business taxes, contributions, memberships, corporate headquarters support (legal, financial, etc.)
(dd) Cost of using electronic payroll software.
(ee) Toilet Facilities
(ff) DD1354
(gg) Utility Locations
(hh) Warranty Tag
(ii) O&M Training
(jj) O&M Manual
2. UNIT PRICE BOOK: The unit price book shall consist of the RSMeans Facilities Construction Cost Data and CCI’s in effect at the time of task order award. All costs shall be bare costs.
The following Subdivisions/Major Classifications, as contained in any of the RSMeans bound or electronic databases shall not be used as line items in pricing task orders issued under this contract. These costs shall be covered in the contractor’s coefficients:
Subdivision 01-31 – Project Management and Coordination, excluded in its entirety.
Subdivision 01-32 – Construction Progress Documentation, excluded in its entirety.
Subdivision 01-41 – Regulatory Requirements, excluded in its entirety.
Subdivision 01-52 – Construction Facilities, excluded in its entirety.
01 11 31 20 - Construction Management Fees, excluded in its entirety.
01 11 31 50 - Models, excluded in its entirety.
01 11 31 75 - Renderings, excluded in its entirety.
01 21 16 - Contingencies, excluded in its entirety.
01 21 53 - Factors Allowance, excluded in its entirety.
01 21 55 - 01 21 63 - Job Conditions/Overtime/Cost Indexes/Taxes - excluded in their entirety.
01 54 09.50 - Personnel Protective Equipment, excluded in its entirety.
01 93 08 50. Equipment, excluded in its entirety.
No informational portion of RSMeans books (introduction, chapter tips, etc.) shall be construed as permitting cost changes or deviations from the RSMeans line items used for the UPB.
Section 00 21 00 - Instructions
INSTRUCTIONS 00 21 00
Section 00 21 00 - Instructions, Conditions and Notices to Offerors INSTRUCTION TO OFFERORS
A. INQUIRIES
OFFEROR'S QUESTIONS AND COMMENTS
Questions and/or comments relative to these documents should be submitted via e-mail or mailed to:
Contract Specialist Primary POC U.S. Army Corps of Engineers, Fort Worth District ATTN: Nikisha Cook Contracting Specialist U.S. Army Corps of Engineers 819 Taylor Street Fort Worth, TX 76102
Phone: 817-915-5257 Email:
nikisha.w.cook@usace.army.mi l Bidder Inquiry Technical inquiries and questions relating to proposal procedures or bonds are to be submitted via: Bidder Inquiry in ProjNet at http://www.projnet.org/projnet To submit and review bid inquiry items, bidders will need to be a current registered user or self-register into system. To self-register go to web page, click BID tab select Bidder Inquiry, select agency USACE, enter Project Id for this solicitation listed below, and your e-mail address, click login. Fill in all required information and click create user. Verify that information on next screen is correct and click continue.
From this page you may view all bidder inquiries or add inquiry.
Bidders will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.
The Solicitation Number is: W9126G23R0082 The Bidder Inquiry Key is: J4DDYB-B9934F
Last day to submit ProjNet questions is ten (10) calendar days prior to proposal due date in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary. If the system is not closed in a timely manner, any inquiry posted within seven ten calendar days of the receipt of proposals will still be regarded as untimely and will not be afforded a substantive response.
Offerors are requested to review the specification in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.
The call center operates weekdays from 8AM to 5PM U.S. Central Standard Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.
Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals
Oral explanations or instructions are not binding. Any information given to an Offeror which impacts the solicitation and/or offer will be given in the form of a written amendment to the solicitation. As this is a competitive negotiation acquisition, there is no public bid opening and no information will be given out as to the number of Offerors or the results of the competition until all awards are made.
B. DIRECTIONS FOR SUBMITTING PROPOSALS
Electronic copies of each volume shall be submitted through the Solicitation Module of the Procurement Integrated Enterprise Environment (PIEE) suite at https://piee.eb.mil/. Proposals submitted by mail or hand carried will not be evaluated. Proposals sent through proprietary or third-party File Transfer Protocol (FTP) sites or DoD SAFE will not be retrieved. It is the responsibility of the Offeror to confirm receipt of proposals. All proposals received after the exact time specified for receipt shall be treated as late submissions and will not be considered except under facts and circumstances allowed by the Federal Acquisition Regulation (FAR).
There are 10 general steps a vendor must follow in order to use PIEE application modules. A complete list can be viewed at the following site:
https://piee.eb.mil/xhtml/unauth/web/homepage/vendorGettingStartedHelp.xhtml#step5
For instructions on how to post an offer, please refer to the Posting Offer demo:
https://pieetraining.eb.mil/wbt/sol/Posting_Offer.pdf.
It is the Offeror’s responsibility to obtain written confirmation of receipt of all electronic files of the full proposal by the Fort Worth District Contracting office. In the event that the Solicitation Module is down, the alternate method for proposal submission is via email to:
nikisha.w.cook@usace.army.mil and paige.e.stone@usace.army.mil ONLY.
Offerors are responsible for ensuring electronic copies are virus-free and shall run an anti-virus scan before submission.
Electronic copies of each volume shall be compatible with the following software products:
Adobe Acrobat Reader 11 and Microsoft Office Suite 2016. Narrative portions of the proposal shall be in Adobe Acrobat portable document file (pdf) searchable text format. The Offeror shall not embed sound or video (e.g., MPEG) files into the proposal files. Electronic files shall be clearly identified for each volume, section, and item.
Contracting Officer: Paige E. Stone, paige.e.stone@usace.army.mil , 817-886-1124
Contract Specialist: Nikisha Cook, nikisha.w.cook@usace.army.mil ,817-915-5257
1. DELIVERY of hard copies and/or CD-ROMs of offers, modifications thereto, or cancellations of offers will not be accepted.
2. OFFERS BY TELEGRAPH. Offers received by telegraph, modifications thereto, or cancellations of offers will or will not be accepted.
3. FACSIMILE OFFERS. Facsimile offers, modifications thereto, or cancellations of offers will or will not be accepted.
4. EMAIL. Offers received by email, modifications thereto, or cancellations of offers will or will not be accepted.
C. PREPROPOSAL CONFERENCE / SITE VISIT
SITE VISIT. A site visit is not necessary to award the base contract. Site visits for individual task orders will be performed with the successful offeror as needed after contract award.
IMPORTANT NOTES. (1) Remarks and explanations addressed during the conference shall not qualify or alter the terms and conditions of the solicitation.
(2) The terms and conditions of the solicitation remain unchanged unless the solicitation is formally amended in writing.
FOR OFFICIAL USE ONLY SOURCE SELECTIONINFORMATION FAR 3.104
PART II - PROPOSAL INSTRUCTIONS
A. PROPOSAL SUBMISSION REQUIREMENTS AND INSTRUCTIONS
1. REQUIREMENT FOR SEPARATE PRICE AND TECHNICAL PROPOSALS.
a. Each Offeror must submit both a Price Proposal (Pricing Schedule) and a Technical Proposal. The Price Proposal and the Technical Proposal must be submitted as separate volumes. Ensure that the outside of each separate volume is clearly marked to indicate its contents and the identity of the Offeror.
b. Both the Price Proposal and the Technical Proposal must be received by the closing date and time set for receipt of proposals.
c. No coefficients and/or dollar amounts from the Price Proposal are to be included in the Technical Proposal.
d. All information intended to be evaluated as part of the Technical Proposal must be submitted as part of the Technical Proposal. Do not merely cross-reference similar material in the Price Proposal, or vice versa.
Also, do not include links to websites in lieu of incorporating information into your proposal.
e. Do not include exceptions to the terms and conditions of the solicitation in either the technical or price proposal. Should the offer include any standard company terms and conditions that conflict with the terms and conditions of the solicitation, the offer may be determined "unacceptable" and thus ineligible for award.
Should the Offeror have any questions related to specific terms and conditions, these should be resolved prior to submission of the offer.
2. PROPOSAL FORMAT & GENERAL INSTRUCTIONS
a. Submit only the electronic files specifically authorized and/or required elsewhere in this section. Do not submit excess information, to include audio-visual materials, electronic media, etc. All pages shall be numbered. A single side of a sheet of paper equals one page.
b. Although hard copies are not accepted, each file shall be clearly indexed, and logically assembled. Font size shall be 10 or larger. An unusual font style, such as script or condensed print, shall not be used for any submission. All page margins shall be at least one (1) inch wide, but may include headers and footers of the solicitation, project title, and company. Pages shall be formatted to print on 8 ½ by 11 inch paper, unless another paper size is specifically authorized elsewhere in this section for a particular submission. Spreadsheets must fit to 11x14 or 11x17 paper size unless specifically authorized in this section for a particular submission.
Offerors shall prepare proposals in the English language. Proposals shall be in a narrative format, organized and titled so that each section of the proposal follows the order and format of the factors. Information presented should be organized so as to pertain to only the evaluation factor in the section that the information is presented. Information pertaining to more than one evaluation factor should be repeated in each section for each applicable factor. Electronic files shall be Microsoft Windows compatible. Files shall be submitted in their native format (i.e. doc, xls, ppt, etc.), or if in pdf format, shall be in searchable text. If the electronic files are of a size at which they must be compressed (zipped), they shall be compressed into one zipped folder.
c. Electronic copies of each volume shall be submitted through the Solicitation Module of the Procurement Integrated Enterprise Environment (PIEE) suite at https://piee.eb.mil/ as stated above.
d. "Confidential" projects cannot be submitted to demonstrate capability unless all of the information required for evaluation as specified herein can be provided to the Government as part of the Offeror's technical proposal. Offerors that include in their proposals information that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, must be clearly marked in accordance with the instructions at FAR 52.215-1, Instructions to Offerors-Competitive Acquisition", paragraph (e), "Restriction on disclosure and use of data".
e. In the case of an Offeror that is part of a large, multi-segmented business concern, provide information directly pertaining to the specific segment of the business concern (i.e., the division, group, unit, etc.) that will perform work under the prospective contract.
f. Proposal revisions shall be submitted as page replacements with revised text readily identifiable, e.g., bold face print or underlining. The source of the revision or amendment, e.g., Error, Omission or Clarification shall be included and be annotated for each revision. Proposal replacement pages shall be numbered and clearly marked "REVISED", with the date of revision. Revised page will be submitted in a different color than the original pages being replaced.
g. Please NOTE this solicitation requires offerors to enter a National Institute of Standards and Technology (NIST) score in the Supplier Performance Risk System (SPRS). The NIST score must be submitted with proposals and a required for award. Reference: 252.204-7019 - Notice of NIST SP 800-171 DoD Assessment Requirements Reference: 252.204-7020 - NIST SP 800-171 DoD Assessment Requirements See the Attached Quick Entry Guide to assist with entering NIST Assessment. Contact Help Desk at (866)618-5988 for additional assistance.
3. VENTURE PROPOSAL REQUIREMENTS. When proposing as a joint venture, all members of the joint venture shall sign the bid bond unless a written agreement by the joint venture is furnished with the proposal designating one firm with the authority to bind the other member(s) of the joint venture. In addition, a copy of the joint venture agreement shall be submitted with the proposal. Failure to comply with the foregoing requirements may eliminate the proposal from further consideration. For 8(a) or 8(a) joint venture, the Offeror shall ensure that it complies with the applicable requirements of 13 CFR Part 124 respectively.
4. BID GUARANTEE. A Bid Guarantee will be required with this proposal. The penal sum of the bond is as stated in provision 52.228-1, Bid Guarantee.
5. DISCUSSIONS. The Government intends to evaluate proposals and award a contract without discussions with Offerors, in accordance with FAR 52.215-1, Instructions to Offerors-Competitive Acquisitions. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary.
A "Competitive Range" is a subjective determination of the most highly rated proposals in the event that discussions with Offerors are required. In such an event, the SSA will approve a competitive range of all the most highly rated proposals.
If discussions are held, the Government may engage in a broad give and take with each Offeror in the competitive range, in accordance with FAR 15.306 (d). The Government will provide the Offeror an advance agenda for the discussions. During discussions, the Government may ask the Offeror to further explain its proposal and to answer questions about it.
Upon conclusion of discussions, those Offerors still considered the most highly rated, will be afforded an opportunity to submit their proposal revisions for final evaluation and selection.
In addition to the other proposal information, the Contracting Officer shall use this information in making an affirmative responsibility determination for award to the Successful Offerors, in accordance with FAR Part 9.
Failure to achieve an affirmative responsibility determination will make the Offeror ineligible for award.
6. COST OR PRICING DATA. Offerors are not required to submit Cost or Pricing Data with their offers.
SUPPLEMENTAL INSTRUCTIONS
A. OVERVIEW
The Government will evaluate the proposals in accordance with the evaluation criteria described herein, using the evaluation rating systems outlined for selection procedures. Price information will be evaluated for fairness, reasonableness, and for material unbalancing, as described herein.
Evaluation will be conducted in accordance with FAR Part 15.
B. BASIS OF AWARD
The Contracting Officer will award a firm fixed-price contract to that responsible Offeror whose proposal conforms to the RFP, is fair and reasonable, and offers the best overall value to the Government, considering the non-price factors described herein, and price (coefficient) as determined by the Source Selection Authority.
All evaluation factors, other than price (coefficient), when combined, are considered significantly more important than the price (coefficient). The intent of this RFP is to obtain the best value proposal. After the Government individually evaluates each proposal, the Contracting Officer/Source Selection Authority will compare proposals to determine which proposal represents the best value. The Government reserves the right to accept other than the lowest priced (coefficient) offer or to reject all offers. The Government will not award a contract to an Offeror whose proposal contains a deficiency, as defined in FAR 15.001. If there is a lower priced (coefficient), conforming offer(s), the Contracting Officer/Source Selection Authority must determine that the added value of a more expensive proposal would justify award to that Offeror.
C. PROPOSAL CONTENTS AND RELATED EVALUATION FACTORS
D. VOLUME 1 - SPECIFIC INSTRUCTIONS FOR VOLUME 1 - TECHNICAL PROPOSAL
Submit the Technical proposal in a searchable, unsecured PDF file titled:
"W9126G23R0082_Firmname_Volume l_Technical.pdf"
*Enter your firm's name for Firmname.
Factor
Location
Description
Relative Importance
FACTOR 1 Vol. 1 Management Approach Most important Factor
FACTOR 2 Vol. 1 Quality Control Program 2nd Most Important Factor, less important than Factor 1, more important than Factor 3, Factor 4, and Factor 5.
FACTOR 3
Vol. 1
Safety Program
3rd Most Important Factor. Less important than Factor 1 and Factor 2, more important than Factor 4 and Factor 5.
FACTOR 4
Past Performance
4th Most Important Factor. Less important than Factor 1, Factor 2, and Factor 3 more important than Factor 5
FACTOR 5
Sample Problem
5th Most Important Factor. Less important than Factor 1, Factor 2, Factor 3, and Factor 4.
FOR OFFICIAL USE ONLY SOURCE SELECTION INFORMATION FAR 3.104
1. VOLUME 1, FACTOR 1 - MANAGEMENT APPROACH
GENERAL: Offerors shall describe their Plan and Resources for execution of a Performance Oriented Construction Activity contract (POCA). Offerors shall possess an overall management capability to manage and execute POCA task orders. Describe management of work scope systematically and efficiently in order to maximize operational and financial performance, to minimize project risk.
a. Submission Requirements:
PLAN: Describe your plan and capabilities to respond to the Government's notification of a proposed Task Order requirement. Include your plan and capabilities to estimate, prepare, submit, and negotiate Task Order proposals within the range anticipated under the awarded contract; your plan to interface with the Government for informational, collaborative, and historical purposes regarding a wide variety of construction, maintenance and repair projects constructed simultaneously; your plan for task order management under the awarded contract, including your plan for conducting meetings and tracking the high volume of task order projects simultaneously. Limit the Plan description to two (2) pages.
RESOURCES: Provide an organization chart depicting work responsibilities, reporting relationships, lines of communication, and authority to approve new work / changes to current work. Describe your corporate systems and capabilities to maintain the execution and completion of a POCA contract. Demonstrate your corporate reach- back capabilities for successful POCA task order execution, i.e.: plan of action for providing corporate support in a timely manner by providing resources from other parts of the corporation for unusual needs such as increased workload in a compressed timeframe, and how the Government will benefit. Demonstrate the ability to manage/construct (i.e. as many as 25 or more) small to medium-scale construction, maintenance and repair projects (typically in the range of $20,000 - $250,000 each), in different locations, simultaneously within the Capital Region Lakes. Also, demonstrate the ability to respond to multiple concurrent requests for proposal by Government as this will be a common occurrence. Limit the Resources description to two (2) pages.
b. Evaluation Criteria:
PLAN - The Government will review the clarity, adequacy, capabilities and strengths of the Offerors described plan to respond to the Government's notification of a proposed task order requirement. The plan will be evaluated to determine the Offeror's understanding to estimate, prepare, submit and negotiate task order proposals within the range anticipated under the awarded contract, the Offeror' s plan to interface with the Government for informational, collaborative, and historical purposes regarding a wide variety of construction, maintenance, and/or repair projects simultaneously; the Offeror's plan for task order management under the awarded contract, including their plan for conducting meetings and tracking a high volume of task order projects simultaneously. Offerors who describe a clear understanding of the POCA process plan may receive a higher rating for this factor.
RESOURCES - The Government will evaluate the Offerors proposed corporate systems and capabilities to maintain the execution and completion of a POCA contract. An Offeror must clearly demonstrate their existing corporate resources and plan to procure new resources in a timely manner for unusual needs such as increased workload in a compressed timeframe. Offerors will be evaluated on their ability to manage/construct as many as 25 or more small to medium-scale construction and repair projects in different locations, simultaneously within the Capital Region Lakes. The Government will evaluate strengths and weaknesses of the Offeror's description of their corporate systems and proposed personnel dedicated to the POCA team as well as the Offeror's plan to manage and staff the POCA team during both low, and high, volume proposal construction periods.
2. VOLUME 1, FACTOR 2 - QUALITY CONTROL PROGRAM
1. Do not submit a quality control plan. Offeror shall describe their plan for producing technical specifications using SpectsIntact Editor and describe quality control inspections and acceptance of work. Address how QC plans will be made project specific and provide pertinent information regarding inspection of work, correction of nonconforming work, and acceptance and close-out procedures for task order projects.
2. Offeror shall describe their plan to communicate and enforce task order requirements, adherence to technical specifications, and workmanship to work force (i.e. in house and subcontractors)..
3. Offeror shall describe their plan for submittals and conformance to a Performance Oriented Construction Activity contract and its individual task order specifications.
4. Offeror shall provide information on how it will process internal and external requests for information, shop drawings, progress meetings, site visits, contract completion, closeout, as-built and completion documentation.
5. Offeror shall describe their plan for providing technical specifications, testing, quality control reporting, shop drawing support, proposed plan for quality control staffing levels and quality control responsibilities.
6. Offeror shall explain the development of the technical specifications, describing resources and capabilities using SpecsIntact Editor to produce site specific Unified Facility Guide Specifications (UFGS) for individual task order.
7. The page limitation for Factor 2 is limited to ten (10) pages. Offers exceeding the page limitation for this factor will not be reviewed past the ten pages.
1. The Offeror will be evaluated on the following items and how they relate to POCA. Evaluations will be based on their narrative plan for creating technical specifications, inspection and acceptance of work, how the QC plans will be made project specific and provide pertinent information regarding inspection of work, correction of nonconforming work, and acceptance and close-out procedures for task order projects.
2. Offeror will be evaluated on their plan to communicate and enforce task order requirements, adherence to technical specifications, and workmanship to work force (i.e. in house and subcontractors).
3. Offeror will be evaluated on the description of their plan for submittals and conformance to a POCA Contract and its individual task order specifications.
4. Offeror will be evaluated on provided information on how they will handle internal and external requests for information, shop drawings, progress meetings, site visits, contract completion, closeout, as-built and completion documentation.
5. Offeror shall describe their plan for providing, testing, quality control reporting, shop drawing support, proposed plan for quality control staffing levels and quality control responsibilities.
6. Offeror will be evaluated on their explanation of the process to develop technical specifications, describing resources and capabilities using SpecsIntact Editor to produce site specific Unified Facility Guide Specifications (UFGS) for individual task orders.
3. VOLUME 1, FACTOR 3- SAFETY PROGRAM
1. Do not submit a Site-Specific Safety Plan. Offeror shall describe their plan for developing a site-specific safety plan.
Address how Safety plans will be made project specific and provide pertinent information regarding inspection of work, correction of nonconforming practices, and resources available for task order projects.
2. Offeror shall describe their plan to communicate and enforce safety standards to work force (i.e. in house and subcontractors).
3. Offeror shall describe their plan for safety conformance to a Performance Oriented Construction Activity contract and its individual task order specifications.
4. Offeror shall describe their plan for providing safety reporting, proposed plan for safety staffing levels and safety responsibilities.
5. Offeror shall explain the development of the POCA contract safety plans as a living document and how Activity Hazard
Analysis, fall protection plan, confined space plan, lift plan, scaffolding plan, excavation/trenching plan, and any other site-specific plans for individual task orders will be implemented into the safety plan.
6. The page limitation for Factor 3 is limited to ten (10) pages. Offers exceeding the page limitation for this factor will not be reviewed past the tenth page.
b. Evaluation Criteria:
1. The Offeror will be evaluated on the following items and how they relate to POCA. Evaluations will be based on their narrative plan for inspection and acceptance of practices, how the Safety plans will be made project specific and provide pertinent information regarding inspection of work, correction of nonconforming practices, and resources available for task order projects.
2. Offeror will be evaluated on their plan to communicate and enforce safety standards to work force (i.e. in house and subcontractors).
3. Offeror will be evaluated on their plan for safety conformance to a Performance Oriented Construction Activity contract and its individual task order specifications.
4. Offeror will be evaluated on their plan for providing safety reporting, proposed plan for safety staffing levels and safety responsibilities.
5. Offeror will be evaluated on their explanation for the development of the POCA contract safety plan as a living document and how Activity Hazard Analysis, fall protection plan, confined space plan, lift plan, scaffolding plan, excavation/trenching plan, and any other site-specific plans for individual task orders will be implemented into the safety plan
4. VOLUME 1, FACTOR 4- PAST PERFORMANCE
1. The Offeror shall demonstrate past performance through the submission of similar projects, using the Past Performance Assessment Worksheet- (Attachment 1). If the Offeror is a joint venture, provide past performance information for construction projects relevant to each of the proposed roles on this project. If any firm has multiple functions or divisions, limit the project examples to those performed by the division or unit submitting the offer.
Offeror shall submit a minimum of one (1) and no more than five (5) projects completed or substantially completed within four (4) years from the date of this solicitation that best represents their experience similar to the scope of work for this solicitation. At least one (1) project submitted must be 100% completed. Any additional projects submitted (not to exceed four (4)) must be at least 50% completed. If Offeror is proposing as a Joint Venture (N) and past performance cannot be provided as a N, individual partners may submit his/her past performance information, not to exceed the maximum of five (5) projects total.
2. The Past Performance Questionnaire (PPQ) included in the solicitation (Attachment 2) is provided for the Offeror to submit to the client for each project the Offeror included in its proposal for Factor 4, Past Performance that does not have a final CPARS evaluation or is a non-Federal Government project. Ensure correct phone numbers and email addresses are provided for the client point of contact. Completed PPQ should be submitted with your proposal. If the Offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the Offeror should complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s). Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If any negative past performance information is received to which the Offeror has not previously had an opportunity to respond, the contractor will be given an opportunity to provide rebuttal. If the client requests, questionnaires may be submitted directly to the Government's point of contact, Nikisha Cook, via nikisha.w.cook@usace.army.mil prior to proposal closing date. Offerors shall not incorporate by reference into their proposals PPQ's previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation.
3. Do not request a PPQ on project(s) that have final evaluations. If a final CPARS evaluation exists and a PPQ is provided for the same project, the CPARS evaluation will be reviewed as the official past performance record for the project, and the PPQ will not be considered by the Source Selection Evaluation Board or the Source Selection Authority.
4. For USACE or other DoD projects which are underway but do not yet have an interim CPARS evaluation, one PPQ per contract may be submitted; to be considered, the PPQ shall be signed by the Administrative Contracting Officer (ACO) or Contracting Officer’s Representative (COR) for the contract.
5. Offerors may submit performance recognition documents received within the last four (4) years, such as awards, award fee determinations, customer letters of commendation, and any other forms of performance recognition relevant to the submitted projects to demonstrate the Offeror's performance capabilities and customer satisfaction.
6. Offerors may submit information on past performance issues and corrective actions taken to prevent these issues from reoccurring. Discuss whether these corrective actions have been implemented on contracts awarded subsequent to the performance issues, the effectiveness of the corrective actions, and POC information for the subsequent contracts.
7. In addition to the above, the Government may review any other sources of information for evaluation of past performance. Other sources may include, but are not limited to, past performance information retrieved through the Past Performance Information Retrieval System (PPIRS), including Contractor Performance Assessment Reporting System (CPARS), using all CAGE/ Unique Entity Identifier/DUNS number(s) of team members (Partnership, Joint Venture, Teaming Arrangement, or parent company/subsidiary/affiliate) identified in the offeror's proposal, inquiries of owner representative(s), Federal Awardees Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the offeror. While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with the Offeror.
8. Projects will be considered relevant to this procurement if they are similar in complexity, in type, scope, or magnitude. Relevancy is defined as:
a) The highest project relevancy will be considered if Offeror is the Prime contractor of base
SATOC/POCA contract. Provide list of SATOC or POCA task orders awarded under the contract to include contract values in Attachment 1 - Past Performance Assessment Worksheet.
b) The next highest project relevance will be considered if Offeror demonstrated management of contracts that contain multiple and concurrent renovation projects valued from $20,000 to $250,000.
9. The Offeror may provide a supplemental narrative (not project lists), not to exceed two (2) pages, explaining how any corporate past performance that is not directly related to the specific projects above is applicable to this project and how the Government will benefit.
b. RELEVANCY DETERMINATION:
1. The Government will evaluate the Offerors past performance to determine how relevant the past performance is to the project under consideration. Past performance on the projects identified in the project forms will receive more consideration than past performance provided in the supplemental narrative. The Government will place greater value on projects performed as a prime contractor than as a subcontractor, depending upon overall role and relevancy considerations. Federal Government project past performance will not be rated inherently more important than non-Federal Government project past performance.
2. More relevant past performance will typically be a stronger predictor of future success and have more influence on the past performance confidence assessment than past performance of lesser relevance.
3. Contracts with lower degrees of relevance will not be as strong of predictors of likely future contract performance success and will typically have less influence on the final past performance confidence rating.
4. Contracts that have little or no relevance typically do not influence the performance confidence rating;
however, any contracts with adverse past performance could reflect larger company-wide concerns and may impact upon the past performance confidence rating.
5. Based on the relevancy of the projects submitted, an overall relevancy determination will be assessed as an interim step prior to establishing a confidence rating. For an overall relevancy determination of "relevant" or higher, the Offeror must demonstrate past performance that meets any defined aspects of relevancy on this project.
c. CONFIDENCE EVALUATION CRITERIA:
1. The SSEB will review the past performance information available, to include CPARS and other past performance information deemed relevant, to determine the quality and usefulness as it applies to performance confidence assessment. If any firm has multiple functions or divisions, the Government will only evaluate past performance of the division or unit submitting the offer. If the Government cannot establish the Offeror' s relevant past performance, it reserves the right to utilize the Past Performance Questionnaire to conduct telephone interviews on any source it deems relevant to the evaluation. Owners/references may be asked to comment on items such as quality of construction, timeliness, management of the work, subcontractor management, including timely payment to subs or suppliers, safety, relations between owner and contractor, level of support for such things as as-built documentation, O&M manuals, training, correcting construction errors, warranty work, etc. The Government will not release the information gathered to the Offeror at any time, in order for the Government to solicit candid, unbiased interview comments. The Government's evaluation is not limited to past performance information on the cited example projects.
2. In determining the performance confidence rating for Past Performance, the degree of relevancy/recency of all of the considered efforts; the overall performance record of the offeror on each contract assessed; number and severity of problems, the demonstrated effectiveness of corrective actions taken (not just planned or promised);
and trend data will be considered. Contracts with higher degrees of relevance will typically have a greater influence on the final performance confidence rating. Contracts with lower degrees of relevance will typically have less influence on the final performance confidence rating however, any contracts with adverse past performance could reflect larger company-wide concerns and may impact upon the past performance confidence rating. Contracts which are comparatively more recent may be better predictors of likely future success than older contracts. The resulting relevant/recent assessment conclusions will then be combined, along with the assessed quality of performance on prior contracts, to arrive at a single performance confidence rating for the Past Performance Factor.
3. The confidence rating will be established based on the past performance of the firms or that of its predecessor, if applicable. An entity may not establish past performance based on the past performance of its key personnel apart from that of the entity. If the Government does not obtain past performance information and cannot establish a past performance record for the Offeror through other sources, a rating of Unknown (Neutral) confidence will be assigned. If negative information is received, the Offeror will be given an opportunity to provide input as required by FAR 15. CPARs that are part of the official record will be utilized as if the Offeror has already had an opportunity to respond.
5. VOLUME 1, FACTOR 5- SAMPLE PROBLEM
1. Offerors shall complete the sample POCA Problem below and provide a cost proposal utilizing the given information below. Use only the sample coefficients and CCI provided. Do not use your coefficients provided under Volume 2 - Price/Cost proposal.
SAMPLE PROBLEM – A recommended work item identified in an Annual Inspection of a Capital Region Lake has initiated a task order to remove and replace damaged interior office walls and flooring.