AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of the amendment is to correct the type of service in the instruction to offerors and to change the holdiay hours at Proctor Lake
1. CONTRACT ID CODE PAGE OF PAGES
J 1 36
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 22-Feb-2023
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9126G23Q0023
X 9B. DATED (SEE ITEM 11)
17-Feb-2023
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
22-Feb-2023
CODE
US ARMY CORPS OF ENGINEERS FORT WORTH
819 TAYLOR ST, CT OFC RM 2A17
FORT WORTH TX 76102-0300
W9126G 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9126G23Q0023
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
The following have been modified:
INSTRUCTIONS TO OFFERORS
INSTRUCTIONS TO OFFERORS
Request for Quotes (RFQ) Solicitation Number: W9126G23Q0023 Solicitation is issued by:
US ARMY CORPS OF ENGINEERS FORT WORTH
819 TAYLOR ST, CT OFC RM 2A17
FORT WORTH TX 76102-0300
PROJECT NAME: Three Rivers Region, Fort Worth District - Gate Attendant Services
1. This is a combined synopsis/solicitation for commercial services prepared in accordance with the format in Subpart 12.6, as supplemented with additional information included in this notice. This announcement constitutes the only solicitation; quotes are being requested and a written solicitation will not be issued.
The U.S. Army Corp of Engineers USACE), Fort Worth District intends to establish a Purchase Order Contract for non-personal serves to perform the services listed below in the description.
All proposals must fully-comply with these instructions and address all solicitation requirements to be eligible for award. As such, proposals that take exception to any term or condition of this solicitation, propose any additional term or condition, or omit any required information, may not be considered for award. Alternate proposals are not authorized and will be rejected.
Each initial offer should contain the Offeror's best terms from a price and technical standpoint. It is the Offeror’s responsibility to ensure that there are no discrepancies presented within the information contained in its offer. Potential Offerors are hereby notified that in the event there are discrepancies within the information received by the Government, or in comparison to Government information provided in the solicitation, the Government reserves the right to apply its judgment to resolve such discrepancies during the evaluation of the proposals without conducting discussions
Offerors may submit quotes for multiple positions. However, the successful offeror is only eligible to receive one award from this announcement.
Description of Services: The Contractor shall furnish, all necessary labor, transportation, equipment, materials/supplies, and supervision to perform non-personal gate attendant (AMD 0001) services in the manner, location and frequency set forth in the Performance Work Statement and schedules.
Work shall be performed in support of the USACE Three Rivers Region
Locations:
Periods of Performance is as follows:
Lofers Bend East – one (1) twelve (12) month base period Lofers Bend West – one (1) twelve (12) month base period, and one (1) twelve (12) month option period Kimball Bend – one (1) twelve (12) month base period, and one (1) twelve (12) month option period Cedron – one (1) twelve (12) month base period Plowman – one (1) twelve (12) month base period, and one (1) twelve (12) month option period.
McCown Valley – one (1) twelve (12) month base period, and one (1) twelve (12) month option period Promontory A – one (1) twelve (12) month base period, and one (1) twelve (12) month option period Promontory B – one (1) twelve (12) month base period, and one (1) twelve (12) month option period Copperas Creek – one (1) twelve (12) month base period, and one (1) twelve (12) month option period.
Sowell Creek – one (1) twelve (12) month base period, and one (1) twelve (12) month option period
The government reserves the right to limit and/or not respond to any further questions pertaining to this project received after March 1, 2023. Offerors should base their quotes on the information provided in the solicitations and all issued amendments thereto.
All answers to technical inquiries and questions are reviewed by the Contracting Officer prior to the response date.
Answers to technical inquiries may result in amendment(s) to the solicitation. If an amendment is issued, it will be posted on the Government Point of Entry website www.sam.gov.
2. This is a Request for Quote (RFQ) and incorporates FAR provisions and clauses in effect through the Federal Acquisition Circular (FAC) 220-07 (3 Aug 20). Solicitation document and incorporated provisions and clauses are those in effect through the Federal Acquisition Regulation (FAR) and Department of Defense FAR Supplement
(DFARS).
a. The provision at 52.212-1, Instructions to Offerors -- Commercial, applies to this acquisition and a statement regarding any addenda to the provision. Offerors are also required to submit a completed copy of the Request for Quotation and a completed copy of the pricing schedule.
b. Offerors include a completed copy of the provision at 52.212-3, Offeror Representations and Certifications- Commercial Items, with its offer.
c. Clause at 52.212-4, Contract Terms and Conditions-Commercial Items, applies to this acquisition and a statement regarding any addenda to the clause.
d. Clause at 52.212-5, Contract Terms and Conditions Required To Implement Statutes or Executive Orders- Commercial Items, applies to this acquisition and a statement regarding which, if any, of the additional FAR clauses cited in the clause are applicable to the acquisition
3. This acquisition is SET ASIDE 100% for Small Business.
4. PSC: R699 Support – Administrative: Other NAICS CODE: 721211, RV (Recreational Vehicle) Parks and Campgrounds SIZE STANDARD: $10 Million
5. System for Awards Management (SAM): In accordance with FAR 52.204-7(b)(1) An Offeror is required to be registered in SAM when submitting an offer or quotation and shall continue to be registered until time of award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.
6. Evaluation Information: The Government intends to award a firm fixed price (FFP) Single Award Contract resulting from this RFQ to the responsible offeror whose offer represents the best value in terms of price, past performance and technical approach and Understanding of the Work IAW 13.106-2(b)&(3).
Quote Content – The quote shall consist of the vendor information sheet. All quotation documents when printed shall fit on 8 x 11inch paper to include spreadsheets (with the appropriate page breaks). Ensure the quote is submitted in PDF format.
Quotes shall be responsive to and comply with the terms of the combined synopsis solicitation in order to be eligible to receive an award. All combined synopsis/solicitation requirements shall be addressed in sufficient written detail for the Government to determine if the offeror understands each aspect of the Government’s requirement. The offeror/quoter shall address each task separately and shall sufficient narrative and supporting data for each task.
Lack of sufficient detail shall be considered sufficient cause for the quote to be determined unacceptable. Statements that the quoter understands, can or will comply with all specifications and statements paraphrasing the specifications or parts thereof, or phrases such as “standard procedures will be used” or “well-known techniques will be used” will be considered unacceptable. The Government will reject the proposal if determined to be materially non-responsive of that does not conform to the terms of the combined synopsis/solicitation.
Quoters that fail to adhere to the submittal requirements will be determined non-responsive and will be considered ineligible for award. To be eligible to receive an award, the quote submitted in response to the combined synopsis/solicitation shall consist of the contents required in the sub-paragraphs described below:
a. Past Performance: The past performance evaluation results in an assessment of the offeror’s probability of meeting the solicitation requirement. The past performance evaluation considers each offeror’s demonstrated recent and relevant record of performance of supplying the gate attendant (AMD 0001) service that meets the contract requirements. Recent or relevant work is defined as similar work in size and scope within the past four (4) years.
NAVFAC/USACE Past Performance Questionnaire (PPQ): The quoter is required to submit one (1) PPQ with an overall rating of satisfactory or higher to be considered eligible for award. Additional PPQs submitted for assessment will be discarded and not considered for evaluation. The Contracting Officer may use additional data obtained from any available sources such as the Past Performance Information Retrieval System (PPIRS) and personal knowledge to assess the contractor’s likelihood of success in performing the solicitation’s requirements as indicated by those offerors’ record of past performance.
If for any reason, the contractor does NOT have recent or relevant past performance, the quoter is still required to submit a PPQ with a brief narrative explaining “No Recent or Relevant Past Performance”. In the case of a quoter without a record of recent or relevant past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the offeror may not be evaluated favorably or unfavorably on past performance. Therefore, the quoter shall be determined to have unknown or (“neutral”) past performance. In the context of acceptability/unacceptability, a neutral rating shall be considered “acceptable”.
Table 2. Past Performance Evaluation Ratings
Rating Description
Acceptable Based on the offeror’s performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort, or the offeror’s performance record is unknown. (See note below.)
Unacceptable Based on the offeror’s performance record, the Government has no reasonable expectation that the offeror will be able to successfully perform the required effort.
Note: A contractor’s past performance rating may be used at the Contracting Officer’s discretion to make an overall determination of the level of confidence the government has in the contractor’s capability to perform the service.
The Contracting Officer may determine that a “Substantial Confidence” or “Satisfactory Confidence” past performance rating is worth more than a “Neutral Confidence” past performance rating as stated in the evaluation
Adjectival Rating Description
Substantial Confidence Based on the offeror's recent/relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort.
Satisfactory Confidence Based on the offeror's recent/relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort
Neutral Confidence No recent/relevant performance record is available or the offeror' s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned. The offeror may not be evaluated favorably or unfavorably on the factor of past performance.
Limited Confidence Based on the offeror' s recent/relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort.
No Confidence Based on. the offeror's recent/relevant performance record, the Government has no expectation that the offeror will be able to successfully perform the required effort.
b. Price: Price proposal shall be tailored towards a Firm Fixed Price contract type. The government will evaluate all aspects of the price proposal for reasonableness. Proposals found to be unreasonable may be rejected on that basis.
The offeror agrees to hold the prices in its offer firm for 60 calendar days from the date specified for receipt of offers.
In accordance with FAR Part 29.3 – State and Local Taxes, and per Title 4 of US Code 104-07, the Government is exempt from paying state and local taxes.
Quotes for this solicitation are due March 09, 2023, by 10:00 AM CST.
Electronic copies of each volume shall be submitted through the Solicitation Module of the Procurement Integrated Enterprise Environment (PIEE) suite at https://piee.eb.mil/. Quotes submitted by mail or hand carried will not be evaluated. Proposals sent through proprietary or third-party File Transfer Protocol (FTP) sites or DoD SAFE will not be retrieved. It is the responsibility of the Offeror to confirm receipt of proposals. All proposals received after the exact time specified for receipt shall be treated as late submissions and will not be considered except under facts and circumstances allowed by the Federal Acquisition Regulation (FAR).
There are 10 general steps a vendor must follow in order to use PIEE application modules. A complete list can be viewed at the following site:
https://piee.eb.mil/xhtml/unauth/web/homepage/vendorGettingStartedHelp.xhtml#step5
For instructions on how to post an offer, please refer to the Posting Offer demo:
https://pieetraining.eb.mil/wbt/sol/Posting_Offer.pdf.
It is the Offeror’s responsibility to obtain written confirmation of receipt of all electronic files of the full proposal by the Fort Worth District Contracting office. The Offeror must obtain prior approval from the Contracting Officer (Jamauh D. Winston) or the Contract Specialist (Ms. Patricia Dickson) patricia.l.dickson@usace.army.mil to use the alternate submission method. Offerors are responsible for ensuring electronic copies are virus-free and shall run an anti-virus scan before submission.
Electronic copies of each volume shall be compatible with the following software products: Adobe Acrobat Reader 11 and Microsoft Office Suite 2016. Narrative portions of the proposal shall be in Adobe Acrobat portable document file (pdf) searchable text format. The Offeror shall not embed sound or video (e.g., MPEG) files into the proposal files. Electronic files shall be clearly identified for each volume, section, and item.
7. Submittals: Offerors must submit representation and certifications in accordance with the provisions at FAR 52.212-3 Offeror Representation and Certifications – Commercial Item (Accessible at https://www.acquisition.gov) or the vendor may verify their Online Representation and Certification Application (ORCA) is updated in SAM by checking “Yes” on the Vendor information sheet. The contract specialist will verify the quoters FAR & DFAR Reports are updated in SAM.GOV prior to determining the quoter responsive.
Submit the following PDF files in the response to the RFQ:
a. Attach the Vendor Information Sheet and Priced Schedules. Compile the vendor information sheet and schedules and submit as one conformed document. Label Submittal: Company Name, Quote.
b. Technical Approach and Understanding of Work (See Clause 52.212-2 Evaluation – Commercial Items)
c. Past Performance NAVFAC/USACE Past Performance Questionnaire (See Clause 52.212-2 Evaluation – Commercial Items). Recent or relevant work is defined as similar work in size and scope within the past four (4) years. The Contracting Officer shall deem an offeror non-responsive if the offeror fails to submit a PPQ IAW 52.212-1(b)(10). If for any reason the contractor does NOT have recent or relevant past performance, the offeror is still required to submit a PPQ with a brief narrative explaining, "No Recent or Relevant Past Performance in block 6 of the PPQ Contractor Information Sheet. An Offeror that submits a PPQ that is deemed neither recent nor relevant will be treated as “NEUTRAL”. PPQ Submittals shall consist of the Contractor Information Sheet and the Completed Adjectival Rating Sheets. Compile the two (2) PPQs and submit them as one conformed document (2).
d. Pre-Priced Bid Schedule & Task Order Schedule. Incomplete bid schedules will be rejected and the quoter will be deemed non-responsive.
e. Complete and return the provisions at 52.204-24, and 52.204-26. Compile the Provisions and submit as one conformed document. Label Submittal: Company Name, Provisions.
f. If applicable, acknowledge and return any amendments with your submittals. Compile the amendments and submit as one conformed document. Label Submittal: Company Name.
g. Contractors that failure to adhere to the submittal requirements will be determined non-responsive and will be considered ineligible for award.
h. Please NOTE this solicitation requires offerors to enter a National Institute of Standards and Technology (NIST) score in the Supplier Performance Risk System (SPRS) prior to responding to this solicitation. The NIST score is a responsiveness item. Bids/offers from contractors with a NIST score in SPRS will be considered qualified and eligible for award. * If the apparent awardee does not correct the omission by refusing to enter its NIST score within 14 days after the allotted time then it can be safely deemed “not responsive” and ineligible to receive the award.
Reference: 252.204-2019 - Notice of NIST SP 800-171 DoD Assessment Requirements
Reference: 252.204-2020 - NIST SP 800-171 DoD Assessment Requirements
See the Attached Quick Entry Guide to assists with entering NIST Assessment.
Contact Help Desk at (866)618-5988 for additional assistance
VENDOR INFORMATION SHEET
W9126G20Q0023 Three Rivers Gate Attendant Services
COMPANY NAME
POC
(Last, First Middle)
ADDRESS
(Number & Street) (City, State and Zip)
PHONE NUMBER MOBILE
(Area code and number) (Area code and number)
EMAIL ADDRESS___________________________________________
Unique Identity NUMBER CAGE CODE NUMBER_______________
Vendor’s Online Representation and Certification Application (ORCA) are updated in SAM Yes No
Signature Date
ATTACHMENT 1
NAVFAC/USACE PAST PERFORMANCE QUESTIONAIRE (Form PPQ-0)
CONTRACT INFORMATION (Contractor to complete Blocks 1-4)
1. Contractor Information Firm name: CAGE Code:
Address: DUNS Number:
Phone Number:
Email Address:
Point of Contact: Contact Phone Number:
2. Work Performed as: Prime Contractor Sub Contractor Joint Venture Other (Explain) Percent of Project work performed:
If subcontractor, who was the prime (Name/Phone #):
3. Contract Information Contract Number:
Delivery/Task Order Number (if applicable):
Contract type: Firm Fixed Price Cost Reimbursement Other (please specify):
Contract Title:
Contract Location:
Award Date (mm/dd/yy):
Contract Completion Date (mm/dd/yy):
Actual Completion Date (mm/dd/yy) Explain Differences:
Original Contract Price (Award Amount):
Final contract Price (to include all modifications, if applicable):
Explain Differences:
4. Project Description:
Complexity of Work High Med Routine How is this project relevant to project of submission? (Please provide details such as similar equipment, requirements, conditions, etc.)
CLIENT INFORMATION (Client to complete Blocks 5-8)
5. Client Information Name:
Title:
Phone Number:
Email Address:
6. Describe the client’s role in the project:
7. Date Questionnaire was completed (mm/dd/yy):
8. Client’s Signature:
NOTE: NAVFAC/USACE REQUESTS THAT THE CLIENT COMPLETES THIS QUESTIONNARIE AND
SUBMITS DIRECTLY BACK TO THE OFFEROR. THE OFFEROR WILL SUBMIT THE COMPLETED
QUESTIONNARIE TO USACE WITH THEIR PROPOSAL, AND MAY DUPLICATE THIS
QUESTIONNAIRE FOR FUTURE SUBMISSION ON USACE SOLICITATION. CLIENTS ARE HIGHLY
ENCOURAGED TO SUBMIT QUESTIONNAIRES DIRECTLY TO THE OFFEROR. HOWEVER,
QUESTIONNAIRES MAY BE SUBMITTED DIRECTLY TO USACE. PLEASE CONTACT THE
OFFEROR FOR USACE POC INFORMATION. THE GOVERNMENT RESERVES THE RIGHT TO
VERIFY ANY AND ALL INFORMATION ON THIS FORM.
AFTER COMPLETION, PLEASE EMAIL TO: CIV-OPS.Proposals@usace.army.mil Ensure the former employer references the solicitation number in the email subject line.
ADJECTIVE RATINGS AND DEFINITIONS TO BE USED TO BEST REFLECT
YOUR EVALUATIONOF THE CONTRACTOR’S PERFORMANCE
RATING DEFINITION NOTE
(E) Exceptional Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor was highly effective.
An Exceptional rating is appropriate when the Contractor successfully performed multiple significant events that were of benefit to the Government/Owner. A singular benefit, however, could be of such magnitude that it alone constitutes an Exceptional rating. Also, there should have been NO significant weaknesses identified.
(VG) Very Good Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.
A Very Good rating is appropriate when the Contractor successfully performed a significant event that was a benefit to the Government/Owner. There should have been no significant weaknesses identified.
(S) Satisfactory Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.
A Satisfactory rating is appropriate when there were only minor problems, or major problems that the contractor recovered from without impact to the contract. There should have been NO significant weaknesses identified. Per DOD policy, a fundamental principle of assigning ratings is that contractors will not be assessed a rating lower than Satisfactory solely for not performing beyond the requirements of the contract.
(M) Marginal Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor’s proposed actions appear only marginally effective or were not fully implemented.
A Marginal is appropriate when a significant event occurred that the contractor had trouble overcoming which impacted the Government/Owner.
(U) Unsatisfactory Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains serious problem(s) for which the contractor’s corrective actions appear or were ineffective.
An Unsatisfactory rating is appropriate when multiple significant events occurred that the contractor had trouble overcoming and which impacted the Government/Owner. A singular problem, however, could be of such serious magnitude that it alone constitutes an unsatisfactory rating.
(N) Not Applicable No information or did not apply to your contract
Rating will be neither positive or negative.
TO BE COMPLETED BY CLIENT
PLEASE CIRCLE THE ADJECTIVE RATING WHICH BEST REFLECTS
YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE.
1. QUALITY
a) Quality of technical data/report preparation efforts E VG S M U N
b) Ability to meet quality standards for technical performance E VG S M U N
c) Timeliness/effectiveness of contract problem resolution without extensive customer guidance.
E VG S M U N
d) Adequacy/effectiveness of quality control program and adherence to contract quality assurance requirements (without adverse effect on performance)
E VG S M U N
2. SCHEDULE/TIMELINESS OF PERFORMANCE:
a) Compliance with contract delivery/completion schedules including any significant intermediate milestones. (If liquidated damages were assessed or the schedule was not met, please address below)
b) Rate the contractor’s use of available resources to accomplish tasks identified in the contract
E VG S M U N
3. CUSTOMER SATISFACTION:
a) To what extent were the end users satisfied with the project? E VG S M U N
b) Contractor was reasonable and cooperative in dealing with your staff (including the ability to successfully resolve disagreements/disputes; responsiveness to administrative reports, businesslike and communication)
c) To what extent was the contractor cooperative, businesslike, and concerned with the interests of the customer?
E VG S M U N
d) Overall customer satisfaction E VG S M U N
4. MANAGEMENT/PERSONNEL/LABOR
a) Effectiveness of on-site management, including management of subcontractors, suppliers, materials, and /or labor force?
E VG S M U N
b) Ability to hire, apply, and retain qualified workforce to this effort
E VG S M U N
c) Government Property Control E VG S M U N
d) Knowledge/expertise demonstrated by contractor personnel E VG S M U N
e) Utilization of Small Business concerns E VG S M U N
f) Ability to simultaneously manage multiple projects with multiple disciplines E VG S M U N
g) Ability to assimilate and incorporate changes in requirement and/or priority, including planning, execution and response to Government changes
h) Effectiveness of overall management (including ability to effectively lead, manage and control the program)
E VG S M U N
5. COST/FINANCIAL MANAGEMENT
a) Ability to meet the terms and conditions within the contractually agree price(s)?
E VG S M U N
b) Contractor Proposed innovative alternative methods/processes that reduced cost, improved maintainability or other factors that benefited the client
c) If this is/was a Government cost type contract, please rate the Contractor’s timeliness and accuracy in submitting monthly invoices with appropriate back-up documentation, monthly status reports. Budget variance reports, compliance with established budgets and avoidance of significant and/or unexplained variances (under runs or overruns)
d) In the Contractor’s accounting system adequate for management and tracking of costs? If no, please explain in Remarks section.
YES NO
e) If this is/was a Government contract, has/was this contract been partially or completely terminated for default or convenience or are there any pending terminations? Indicate if show cause or cure notices were issued, or any default action in comment section below.
YES NO
f) Have there been any indication that the contractor has had any financial problems? If yes, please explain below.
YES NO
6. SAFETY/SECURITY
a) To What extent was the contractor able to maintain an environment of safety, adhere to its approved safety plan, and respond to safety issues? (Includes: following the users rules, regulations, and requirements, regarding housekeeping, safety, correction of noted deficiencies, etc.)
b) Contractor complied with all security requirements for the project and personnel security requirements. E VG S M U N
7. GENERAL
a) Ability to successfully respond to emergency and/or surge situations (including notifying COR, PM or Contracting Officer in a timely manner regarding urgent contractual issues)
b) Compliance with contractual terms/provisions (explain if specific issues)
E VG S M U N
c) Would you hire or work with this firm again? (If no, please explain below)
YES NO
d) In Summary, provide an overall rating for the work performed by this contractor.
E VG S M U N
Please provide responses to the questions above (if applicable) and/or additional remarks. Furthermore, please provide a brief narrative addressing specific strengths, weaknesses, deficiencies, or other comments which may assist our office in evaluating performance risk (Please attach additional pages in necessary
PWS APPENDIX
APPENDIX PERFORMANCE WORK STATEMENT (PWS)
GATE ATTENDANT SERVICES
PROCTOR LAKE
1. GENERAL: No additional items.
1.1 DESCRIPTION OF SERVICES/INTRODUCTION: No additional items.
1.2. SCOPE: Gate Attendant services as described in the PROCTOR LAKE Appendix PWS, Section 1.11, Work to be Performed, and the Fort Worth District Gate Attendant Services PWS.
1.3 PERIOD OF PERFORMANCE: Estimated deliverables are shown in table below:
Position: Copperas Creek Quantity Base Period:
01 April 2023 through 31 March 2024
Option Period 1:
01 April 2024 through 31 March 2025
TOTAL AMOUNT:
Position: Promontory A Quantity
01 April 2023 through 30 September 2023
01 April 2024 through 30 September 2024
TOTAL AMOUNT:
Position: Promontory B: Quantity
01 April 2024 through 30 September 2024
TOTAL AMOUNT:
Position: Sowell Creek Quantity
01 April 2023 through 31 March 2024
01 April 2024 through 31 March 2025
1.4 GENERAL INFORMATION:
1.4.1 Quality Control: No additional items.
1.4.2 Quality Assurance: No additional items.
1.4.3 Government Holidays: Gatehouse hours will be 09:00 to 19:00 hrs (AMD 0001). during holidays that fall within the contractor’s shift. Government holidays are Martin Luther King Day, Presidents Day, Memorial Day, Juneteenth, July 4th, Labor Day, Columbus Day, and Veterans Day (eight (8) total holidays per year).
1.4.4 Hours of Operation:
SOWELL and COPPERAS CREEK - Contractors will work four (4) days per week, days worked are Friday, Saturday, Sunday, Monday. Contractor “A” shift will start on 1 April 2023. Summer Hours will start 1 April through 30 September. Winter hours are from 1 October through 31 March.
PROMONTORY - Contractors will work a four (4) day on / four (4) day off shifts. Contractor “A” shift will start on 1 April 2023. Summer Hours will start 1 April through 30 September. Park closed October 1-March 31.
SOWELL and COPPERAS CREEK
Contractor Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Summer Hours Surveillance Hours Gate House Hours Availability Hours
0600-1900 0900-1900 1900-
OFF
1900-0600
1900-
Winter Hours Surveillance Hours
0600-1800 0900-1800 1800-
1800-0600
PROMONTORY
Summer Hours Surveillance Hours
1.4.5 Place of Performance: The work to be performed under this contract will be performed at Proctor Lake.
1.4.5.1 Copperas Creek Park: Located approximately 8 miles northeast of Comanche, Texas. From Comanche, Texas, take Highway 67/377 northeast then turn left on FM 2861. Follow road for 2 miles to the park entrance. Facilities include 67 campsites with water and electric hook-ups, 3 restrooms with hot showers, 2 group shelters, 1 day use areas, and three boat ramps.
1.4.5.2 Sowell Creek Park: Located approximately 14 miles northeast of Comanche, Texas following U.S. Highway 377/67 and FM 1476. Facilities include 61 campsites with water and electric hook-ups, 3 restrooms with hot showers, 1 group shelter, 3 day use areas, and two boat ramps.
1.4.5.3 Promontory Park: 7217 FM 2318, Comanche, TX 76442
TOTAL AMOUNT:
Located approximately 10 miles northeast of Comanche, Texas following U.S. Highway 16 and FM 2318. Facilities include 77 campsites – primitive sites, water and electric hook-up sites, 3 restrooms with hot showers, 4 pit style restrooms, 4 group shelters, 5 screen shelters, 1 day use area, and 2 boat ramps.
1.4.6 Type of Contract: No additional items.
1.4.7 Security Requirements:
1.4.7.1 Physical Security: The Contractor shall be responsible for safeguarding all Government equipment, information and property provided for Contractor use. At the close of each work period, Government facilities, equipment, and materials shall be secured.
1.4.7.2 Key Control: Government keys provided to the Contractor will be issued and controlled in accordance with IAW AR 190-51 and the U.S. Army Corps of Engineers, Recreation Operations and Maintenance Guidance and Procedures, EC 1130-2-550, Chapter 9 and the USACE Recreation Use Fee Standard Operating Procedure. The Contractor shall establish and implement methods of making sure all keys/key cards issued to the Contractor by the Government are not lost or misplaced and are not used by unauthorized persons. NOTE: All references to keys include key cards. No keys issued to the Contractor by the Government shall be duplicated. The Contractor shall immediately report any occurrences of lost or duplicate keys/key cards to the Contracting Officer. The Contractor shall prohibit the use of Government issued keys/key cards by any persons other than the Contractor and team member. The Contractor shall prohibit the opening of locked areas by persons other than the Contractor and team member.
1.4.7.3 Lock Combinations: The Contractor shall establish and implement methods of ensuring that all lock combinations are not revealed to unauthorized persons. The Contractor shall ensure that lock combinations are changed when personnel having access to the combinations no longer have a need to know such combinations.
1.4.7.4 General security requirements and guidance: The security requirements described below apply to all contract personnel (including employees of the prime Contractor (“Contractor”) and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (e.g., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as “RAMs”), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures—this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this contract, should the FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.
1.4.7.5 Suspicious Activity Reporting Training (e.g. iWATCH, CorpsWatch, or See Something, Say Something):
All contract personnel shall receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.
1.4.7.5 Pre-screen candidates using E-Verify Program: Contractors shall comply with the requirements set forth in FAR clause 52.222-54 Employment Eligibility Verification and FAR Subpart 22.18 in using the E-Verify Program at (https://www.e-verify.gov/) (website subject to change) to meet the contract employment eligibility requirements.
Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws in accordance with FAR 22.102-1(i). An initial list of verified/eligible candidates shall be provided to the COR no later than three business days after the initial contract award. When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, and submit it to the Contracting Officer to become part of the official contract file.
1.4.8 Special Qualifications: No additional items.
1.4.9 Pre-Work Conference: Successful bidders will be required to attend a pre-work conference to be held at a date and time specified by the Lake Manager. It is the successful bidder’s responsibility to contact the lake office for pre-work conference time and date prior to the start of the contract. Training session will be held as scheduled with the gate attendant coordinator. Gate Attendants will not receive any separate payment for attending the pre-work conference. During this time successful bidder will bring an original copy of a current security bond to be left at the Lake Office. Gate Attendants shall attend additional training sessions as required by the Lake Manager during the contract on a regularly scheduled workday.
1.4.10 Contracting Officer Representative (COR): Not required per DFARS PGI 201.602-2(d)(v)(A).
1.4.11 Contractor Key Personnel: No additional items.
1.4.12 Identification of Contractor Employees: No additional items.
1.4.13 Contractor Travel: No additional items.
1.4.14 Data Rights: No additional items.
1.4.15 Organizational Conflict of Interest: Any real or potential conflicts of interest, such as the contractor/ subcontractor having business or family association with a USACE employees should be immediately reported to the Contracting Officer for disposition. Potential OCI may be mitigated or could result in contract termination or subcontractor removal
1.5. GOVERNMENT-FURNISHED ITEMS AND SERVICES:
1.5.1 Facilities: No additional items.
1.5.2 Equipment: The Government will provide computer, computer monitors, printers, telephone and radio communication equipment.
1.5.3 Materials: The Government will provide in the gate house forms, maps, brochures, handouts, light bulbs, air condition filters, computer paper, staplers, staples, china markers, and water hose. The Government will also supply the Fort Worth District Use Fee Program SOP, and the Proctor Lake Gate Attendant Handbook.
1.5.4 Trailer Site: A storage building is available for the Contractor’s use.
1.6 CONTRACTOR-FURNISHED ITEMS AND RESPONSIBILITIES:
1.6.1 General: The Contractor shall furnish all supplies, equipment, facilities and services required to perform work under this contract that are not listed under Section 1.5 of this PWS.
1.6.2 Equipment: The Contractor shall provide a transportation vehicle, which can be operated independently of the RV free of leaks and in good mechanical condition for use in performing the requirements of the contract.
Minimum state required liability insurance must be carried. Proof of liability insurance will be submitted to the Lake Manager prior to work start date.
1.6.3. Materials: The Contractor shall furnish all materials, excluding those furnished by government as specified above and needed to operate the gatehouse. This list includes, but is not limited to, hi-liters, color markers, notepads, pens, pencils, tape, trash bags, cleaning supplies, restroom supplies and any other items that may be necessary to operate the gatehouse.
1.6.3.1 In the performance of this contract, the Contractor shall make maximum use of products containing recovered materials that are EPA-designated items unless the product cannot be acquired;
(1) Competitively within a timeframe providing for compliance with the contract performance schedule;
(2) Meeting contract performance requirements; or
(3) At a reasonable price.
Information about this requirement is available at EPA’s Comprehensive Procurement Guidelines web site, https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program . The list of EPA-designated items is also available at https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program#products, items may include, but are not limited to the following products used on-site in execution of this contract.
• Two ply toilet tissue
• Paper hand towels
• Trash can liners
• Bio based content cleaners, solvents, detergents and disinfectants.
1.6.3.2 As required by the Resource Conservation and Recovery Act of 1976 (42 U.S.C. 6962(c)(3)(A)(i)), the offeror certifies, by signing this offer, that the percentage of recovered materials content for EPA-designated items to be delivered or used in the performance of the contract will be at least the amount required by the applicable contract specifications or other contractual requirements.
1.6.3.3 References
• FAR Provision 52.223-1 – Biobased Product Certification
• FAR Clause 52.223-2 – Affirmative Procurement of Biobased Products Under Service and Construction Contracts
• FAR Provision 52.223-4 – Recovered Material Certification
• FAR Clause 52.223-9 – Estimate of Percentage of Recovered Material Content for EPA-Designated Items
• FAR Clause 52.223-17 – Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts
1.6.4. Personnel: Minimum of two (2) person team over 21 years of age shall remain in the park during the entire work shift as specified by the Lake Manager.
1.7 CONTRACTOR MANAGEMENT REPORTING (CMR): No additional items.
1.8 APPLICABLE PUBLICATIONS (CURRENT EDITIONS): The Contractor must abide by all applicable State, Federal and Local Laws and regulations, publications, manuals, and local policies and procedures, including the Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, the Fort Worth District Use Fee Program SOP, and the Proctor Lake Office Gate Attendant Handbook.
1.9 ATTACHMENT/TECHNICAL EXHIBIT LIST:
1.9.1 Attachment 1/Technical Exhibit 1 – Performance Requirements Summary: See Attachments at end of document.
1.9.2 Attachment 2/Technical Exhibit 2 – Deliverables Schedule: See Attachments at end of document.
1.10 SAFETY: No additional items.
1.11 WORK TO BE PERFORMED: Additional items as described below.
TASK 1. User Fees: No additional items.
(a) User Fee Collection: The contractor will collect all user fees in accordance with the Fort Worth District Use Fee Program SOP. User fees will be collected through the operation of a computer and the National Recreation Reservation System (NRRS), Recreation One Stop (Recreation.gov), Outdoor Recreation Management System (ORMS), cash register or User Fee Permit Books. Monies, fee books, annual day use fee passes, credit vouchers, credit card receipts, America the Beautiful Senior Pass, America the Beautiful Access Pass and other America the Beautiful passes, and user fee permits will be stored in a permanently installed vault or safe provided by the Government, or as directed by the Lake Manager. The Contractor is then required to purchase a money order for the amount of the User Fees collected. The Gate Attendants are required to turn in the money order and the user fee documents to a Park Ranger at the Lake Office.
(b) Audits and Fee Security: No additional items.
(c) Cash on Hand: Contractors will be required to start the day with one hundred dollars to be used for change.
TASK 2. Campsite Reservations: No additional items.
TASK 3. Group Shelters: If group/screen shelters in the park are rented, Gate Attendants will unlock electric panels and entrance gates for the renter. Upon departure of a renter, Gate Attendant will conduct an inspection of the group/screen shelter, barbecue pit and associated items. Gate Attendant will advise renter if additional cleaning is required. Park Ranger will be notified if renter fails to properly clean group/screen shelter, barbecue pit, or associated items. Gate Attendant will complete required inspection reports and turn in the reports to the Lake Manager or designated representative a minimum of once per week.
TASK 4. Camping Status: The Contractor’s camping status will match the reservation arrival reports. The Contractor will make sure that the campers who are listed on the reservation arrival reports are current and are in agreement with NRRS, ORMS (Outdoor Recreation Management System) or the ORMS reservation reports. Contractor shall perform the duty of changing campsite status markers in accordance with established policies of the Lake Manager. In the event all electrical and/or non-electrical campsites are occupied, Contractor will maintain a waiting list and notify those individuals, in order of placement on the waiting lists, whenever a campsite becomes vacant.
TASK 5. Park Inspection: Gate attendants will make a minimum of four (4) park inspections each workday.
Additional inspections may be required to check on visitor complaints, deliver messages, and check park status.
The Contractor shall inform park visitors and campers of any violation of rules, regulations, and policies in a friendly, informative manner and ask for compliance.
TASK 6. Visitor Assistance: No additional items.
TASK 7. Disturbances: No additional items.
TASK 8. Complaints: No additional items.
TASK 9. Lost and Found: The Contractor will maintain a lost and found department in the gatehouse. Any items not picked up after two (2) weeks will be turned in to a Park Ranger. The Contractor will prepare a lost and found report on all lost and found property. The Contractor will ensure that proper identification is obtained from individuals before release of any lost and found property.
TASK 10. Image, Personal Appearance and Dress: Contractors may be required to dress to a standard that will be determined by the Lake Manager. If required to dress to a standard, uniform attire will be provided by the Lake Office.
TASK 11. Cooperation with Others: No additional items.
TASK 12. Living Area and Gatehouse Maintenance:
(a) Trailer Area Maintenance: Gate attendant campsite shall be kept clean and maintained by the contract gate attendant to a perimeter of 30 feet surrounding the campsite.
(b) Pets: No additional items.
(c) Excessive Personal Items: No additional items.
(d) Smoking: No additional items.
(e) Gatehouse Maintenance: The Contractor will maintain the gatehouse, both inside and outside, in a clean, orderly and sanitary condition at all times. The gatehouse will be thoroughly cleaned at the end of each shift to the Lake Manager or designated representative’s satisfaction to include the following: toilet facilities, carpet (vacuumed), hard floors (swept and mopped), windows, entire interior building surfaces (dusted and cleaned if necessary) and litter free outside building and walking surfaces for seventy-five (75) feet perimeter of gatehouse. Gate Attendants will provide all equipment, tools, supplies, and materials necessary to clean the gatehouse. Gate Attendant shall water the lawn, flowers, trees, and shrubs in the immediate area of the gatehouse and/or trailer site as instructed by lake personnel.
The Government will provide hose and sprinklers.
(f) Trash Removal: No additional items.
(g) Living Quarters Security: No additional items.
TASK 13. No Soliciting: No additional…