SB MATOC Section 00 22 10 attachments 1 3 and 4 AM2 30Sep.docx

DOCX document 20 KB Posted

Attached to
Vertical Construction Multiple Award Task Order Contract – Total Small Business Set-Aside
Solicitation number
W9126G20R0051
Issued by

About this file

This document provides details for a solicitation to award multiple small business design-build vertical construction firm fixed price task order contracts. The Fort Worth District Corps of Engineers intends to award approximately five contracts to small businesses or joint ventures for vertical construction projects using design-build and design-bid-build processes. The maximum task order value is $30 million with a minimum of $75,000 and total program capacity of $620.1 million. Project types may include facilities such as dormitories, dining halls, classrooms, air traffic control towers, warehouses, and vehicle maintenance shops. Historically, over 50% of task orders under these contracts support sustainment, restoration and maintenance projects through the design-build method. Offerors must submit capability statements for Phase One of the two-phase evaluation process. Selected businesses will then have the opportunity to compete for vertical construction task orders from the Fort Worth District and other Southwestern Division Corps of Engineers districts.

View the file

Other files

File Type Posted
am_3.pdf PDF
FOCI Form.pdf PDF
am 2.pdf PDF
Copy of Attachment 2 Past Performance Projects Table AM2 30Sep.xlsx XLSX spreadsheet
am_2.pdf PDF
am_1 (2).pdf PDF
B3.W9126G20R0051.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PHASE 1 - TAB A

PROPOSAL DATA SHEET

SECTION 00 22 10 - ATTACHMENT 1

AM0002

Solicitation Number

Firm

Address

Phone

Fax

Email

Tax ID Number

DUNS Number

Also provide any other assigned number that identifies the member firm(s) in the <AM0002>ACASS or CCASS databases CPARS database <\AM0002>. If a separate DUNS has been created for a joint venture (J-V) it must also be submitted. Provide a DUNS number for each company identified in any proposed Contractor-subcontractor association of firms. If the firm is a joint venture or contractor-subcontractor association of firms, list the individual firms and briefly describe the nature of the association. Provide DUNS for each.

Firm 1

Nature of Association

DUNS Number

Firm 2

Nature of Association

DUNS Number

Firm 3

Nature of Association

DUNS Number

Authorized Negotiators IAW FAR 52.215-11 - The Offeror represents that the following persons are authorized to negotiate on its behalf with the Government in connection with this Request for Proposals (RFP).

Name

Title

Address

Telephone

Email

SECTION 00 22 10 - ATTACHMENT 3

(Replaces form provided in AM0001)

PAST PERFORMANCE ASSESSMENT WORKSHEET

(To be completed for each construction project submitted in Attachment 2 Past Performance Projects Table)

CONSTRUCTION OR PRIME CONTRACTOR PROJECT #_______

Offeror:

Is the Offeror part of a Joint Venture, Partnership, Teaming Arrangement, or Parent Company/subsidiary/affiliate?

If yes, identify the company who performed this project and their proposed role in the MATOC organization.

Project and Location:

Was this project performed by the division or unit of the company submitting the offer for this MATOC solicitation?

Owner:

Owner’s Point of Contact for Reference:

Telephone:

Awarded Construction Cost:
Final Construction Cost:

Explain Cost Growth, if any:

Date of Award:

Original Completion Date:
Revised Completion Date:
Percent Complete:

Explain Time Growth, if any:

General Scope of Construction and Role of the Company who performed this project:

Work Your Company Self-Performed:

Extent and Type of Work You Subcontracted Out:

Relevancy is identified in Attachment 2 Past Performance Project Table. Provide additional narrative to support relevancy assessment (in terms of scope, magnitude and complexity as compared to the scope of the RFP).

Your Performance Evaluation by Owner, if known :

SECTION 00 22 10 - ATTACHMENT 4

(Replaces form provided in AM0001)

PAST PERFORMANCE ASSESSMENT WORKSHEET

(To be completed for each design project submitted in Attachment 2 Past Performance Projects Table)

DESIGN FIRM (OR IN-HOUSE DESIGN) PROJECT #_______

Offeror (Design Firm):

Project and Location:

Was this project performed by the division or unit of the company submitting as the design firm for this MATOC solicitation?

Owner:

Owner’s Point of Contact for Reference:

Telephone:

Estimated Construction Cost:
Actual Construction Cost (if known):

Date of Award:

Original Design Completion Date:
Revised Design Completion Date:

Explain Time Growth, if any:

General Scope of Construction and Offeror’s Role in Design:

Offeror’s Role in Design (Self-Performed Work):

Extent and Type of Work You Subcontracted Out:

Relevancy is identified in Attachment 2 Past Performance Project Table. Provide additional narrative to support relevancy assessment (in terms of scope, magnitude and complexity as compared to the scope of the RFP).

Your Performance Evaluation by Owner, if known:

File details come from the government source that posted it. Updated .