About this file

W9126G19Q0047 Amendment#0001 Adding Cedar Ridge Park Shift A

View the file

Other files for this federal contract opportunity

Other files attached to Amendment#0001, newest first.
File Type Posted
B3_RFQ_w-Attach_11Jul2019(2).pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

W9126G19Q0047 Amendment#0001 adding Cedar Ridge Park Shift A to the gate attendant solicitation. Please see PWS Appendix for Cedar Ridge, as w ell as, the Bid Schedule. All requirements in the solicitation apply.

Quote Due Date Remains Unchanged: 19 August 2019 10:00AM EMAIL ALL QUOTES TO: CIV-OPS.Proposals@usace.army.mil

Point of Contact (POC): Daisy Ciarlariello, Contract Specialist (817) 886-1051, Daisy.Ciarlariello@usace.army.mil

1. CONTRACT ID CODE PAGE OF PAGES

J 1 10

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 23-Jul-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9126G19Q0047

X 9B. DATED (SEE ITEM 11)

10-Jul-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

23-Jul-2019

CODE

US ARMY CORPS OF ENGINEERS FORT WORTH

819 TAYLOR ST, CT OFC RM 2A17

FORT WORTH TX 76102-0300

W9126G 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9126G19Q0047

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

The following have been added by full text:

W9126G19Q0047 Amendment#0001 adding Cedar Ridge Park Shift A to the gate attendant solicitation. Please see PWS Appendix for Cedar Ridge, as well as, the Bid Schedule. All requirements in the solicitation apply.

Quote Due Date Remains Unchanged: 19 August 2019 10:00AM EMAIL ALL QUOTES TO: CIV-OPS.Proposals@usace.army.mil

Point of Contact (POC): Daisy Ciarlariello, Contract Specialist (817) 886-1051, Daisy.Ciarlariello@usace.army.mil

Amd#0001

Bid Sheet Belton Lake

Bell County, TX

Cedar Ridge Park Shift A Contract Gate Attendant Services

1 October 2019 through 30 September 2020 (Base

Year Contract Duration) 1 October 2020 through 30 September 2021 (Option

Year 1 Contract Duration) 1 October 2021 through 30 September 2022 (Option

Year 2 Contract Duration)

Cedar Ridge Park Shift A

Item # Attendant Position Price Per

Day Total Cost

Base Year Period of Performance – 184 days (1 October 2019 – 30 September 2020)

Option Year 1 Period of Performance – 184 days (1 October 2020 – 30 September 2021)

Option Year 2 Period of Performance – 184 days (1 October 2021 – 30 September 2022)

TOTAL COST

FORT WORTH DISTRICT

BELTON LAKE APPENDIX PERFORMANCE WORK STATEMENT

GATE ATTENDANT SERVICES

1. GENERAL: See below.

1.1 DESCRIPTION OF SERVICES/INTRODUCTION: Gate Attendant requirements are as follows:

Park/Shift Minimum 1 or 2 Person

Team Requirement Cedar Ridge Park A Shift 2

1.2 SCOPE: No Additional.

1.3 PERIOD OF PERFORMANCE: Estimated deliverables at Lake Belton are:

Summer & Winter Season Number

Days Surveillance

Hours Gate House

Hours Availability

Hours Cedar Ridge Park Shift A

Base Year (01 October 2019 – 30 September 2020)

184 2944 1840 1472

Cedar Ridge Park Shift A Option Year 1

(01 October 2020 – 30 September 2021) 184 2944 1840 1472

Cedar Ridge Park Shift A Option Year 2

(01 October 2021 – 30 September 2022) 184 2944 1840 1472

1.4 GENERAL INFORMATION: See below.

1.4.4 Hours of Operation: The Contractor will work a four (4) calendar day shift, four (4) calendar days on and four (4) calendar days off, and will work all holidays that fall within their four-day shift.

Twenty-four hour shifts begin at 10 pm each night and end at 10 pm the following night. Peak usage for day use parks is 2 pm to sunset on Fridays, 12 pm to sunset Saturdays and Sundays, and from open to close on holidays. Contractors will maintain adequate staffing of the gatehouse during the park operating hours. Contractor “A” will begin work on 01 October and work 4 days.

Contractor “B” will start work on 05 October and work 4 days. This pattern continues throughout the term of the contract.

Contractor Mon Tues Wed Thurs Fri Sat Sun

1 Year Surveillance Hours Gate House Hours Availability Hours

6:00am-10:00pm 10:00am-8:00pm 8:00pm-6:00am

1.4.5 Place of Performance The work to be performed under this contract will be performed at parks on Belton and Stillhouse Hollow Lakes. The Belton/Stillhouse Lake Office is located 1 mile south of US 190 on FM 1670 in Belton, Texas.

1.4.5.1. Cedar Ridge Park: Facilities include 68 campsites with water and electric hook-ups, eight screen shelters, a group camp area and two day use group picnic shelters, restrooms with hot showers, camper activity center with a meeting area and coin operated washers & dryers, two boat ramps, fishing dock, swimming beach, playground, basketball court, dump station and a privately owned marina. Free wireless Internet access is available at the park. A storage building is available for the attendants use.

1.4.6 Type of Contract: No Additional.

1.4.7 Security Requirements: See below.

1.4.7.1 Physical Security: Only Contract Gate Attendants, Volunteers, Law Enforcement, and other USACE authorized personnel are allowed in the gatehouse. Doors must remain closed and locked at all times. No campers or visitors are allowed in the gatehouse without prior approval of Gate Attendant Coordinator or Lake Manager.

1.4.8 Special Qualifications: Not Applicable.

1.4.9 Pre-work Conference: Orientation for Belton and Stillhouse Hollow Lakes is held the first day of the contract from 1:00 PM – 4:30 PM at the Belton Lake Office Conference Room, unless the 1st falls on a weekend then the date shall be the following Monday. Contractors will bring proof of appropriate bonding and insurance to the pre-work conference. All contractors are required to attend at no additional cost to the government. Contract requirements and training on all facets of the Gate Attendant Program shall be covered during this meeting. Successful Contractor who are new to the Recreation One Stop (R1S) are encouraged to work with the current contractor at the park to learn the system. Successful contractor will receive web based on-the-job training for R1S, and shall become proficient within three duty shifts.

1.4.10 Contracting Officer Representative (COR): Not applicable.

1.4.11 Contractor Key Personnel: Gate Attendant.

1.4.12 Identification of Contractor Employees: No Additional.

1.4.13 Contractor Travel: Not Applicable.

1.4.14 Data Rights: No Additional.

1.4.15 Organizational Conflict of Interest: Not Applicable.

1.5 GOVERNMENT-FURNISHED ITEMS AND SERVICES: See below.

1.5.1 Facilities: No Additional.

1.5.2 Equipment: No Additional.

1.5.3 Materials: The Government will provide in the gate house forms, maps, brochures, handouts, light bulbs, air conditioning filters, computer paper, staplers, staples, markers, notepads, pens, pencils, tape, water hose and sprinklers. The Government will also supply the Fort Worth District Use Fee Program SOP.

1.5.4 Trailer Site: The Government shall provide a 20/30/50 amp electrical pedestal, water and sewage hook-up at each Contract Gate Attendant site at no cost to the Contractor. Any other utility or service shall be obtained by to the Contractor. We DO NOT allow mail to be delivered to the office or to the parks. Contractor must rent a post office box.

1.6 CONTRACTOR-FURNISHED ITEMS AND RESPONSIBILITIES: See below. .

1.6.1 General: No Additional.

1.6.2 Equipment: No Additional.

1.6.3 Materials: No Additional.

1.6.3.1 Sustainability: No Additional.

1.6.4 Temporary Living Quarters: The Contractor shall furnish a fully operable “self-contained” recreational vehicle (RV) of the travel trailer or motor home type to serve as temporary living quarters for the duration of the contract. Maximum size of the trailer is determined by physical limitations of the site furnished. It will be located near the entrance to the park at a location to be designated by the Lake Manager. Pickup (shell-type) campers, pop-up tent trailer, tents, mini-travel trailers, mobile homes, buses, or any other types of recreation vehicles which do not meet general size requirements or the self-contained classification as determined by inspection of the Contracting Officer or his/her authorized representative will not be acceptable. The Contractor will be the sole occupants of the site.

1.6.5 Personnel: Minimum of two (2) person team over 21 years of age. Gate Attendants will work a four (4) day on and four (4) day off shift. A minimum of one of the two person team will man the gatehouse during duty hours.

1.7 CONTRACTOR MANAGEMENT REPORTING (CMR): Not Applicable.

1.8 APPLICABLE PUBLICATIONS (CURRENT EDITIONS): No Additional.

1.9 ATTACHMENT/TECHNICAL EXHIBIT LIST: See below.

1.9.1 Attachment 1/Technical Exhibit 1 – Performance Requirements Summary: See attached.

1.9.2 Attachment 2/Technical Exhibit 2 – Deliverables Schedule: See attached.

1.10 SAFETY: No Additional.

1.11 WORK TO BE PERFORMED (AND OTHER RESPONSIBILITIES): See below.

TASK 1. Use Fees:

(a) Use Fee Collection: The contractor will be trained according to current fee training requirements prior to collecting fees. User fees will be collected through the operation of a computer and the R1S, cash register or User Fee Permit Books. User fees and user fee documents will be delivered to the project office by the gate attendant and turned in to an authorized fee collector or placed in provided collection location as designated by the lake manager. All cash money will be converted to a cashier’s check as directed prior to being turned into the project office. A schedule for fee money turn in will be established at the pre-work conference. In the event fees do not balance, the contractor will be responsible for any shortages and any excess collections will be added to a deposit for collection.

(b) Audits and Fee Security: No Additional

(c) Cash on Hand: No Additional

(d) Remittance Procedures and Inspection of Use Fees: No Additional

TASK 2. Campsite Reservations: No Additional

TASK 3. Group Shelters: No Additional

TASK 4. Camping Status: The Contractors camping status will match the reservation arrival reports. The Contractor will make sure that the individuals that are on the reservation arrival reports are current and in agreement with R1S. Contractor shall perform the duty of changing campsite status markers in accordance with established policies of the Lake Manager.

TASK 5. Park Inspection: The Contractor shall inspect entire park a minimum of four (4) times daily in. The Contractor shall inform park visitors and campers of any violation of rules, regulations, and policies in a friendly, informative manner and ask for compliance. In addition to these patrols the areas shall be inspected prior to start of gate house duties and all vehicles in the park without passes should be tagged for payment and a log kept of each vehicle. The Contractor shall keep an inspection report in a neat and timely manner. The Contractor shall check all restroom lights and guard lights at least once during the hours of darkness each day to insure that they are working properly. The Lake Office will be notified of any guard lights that are inoperative during the first scheduled workday after discovering them inoperative. During cold weather, the Contractor will monitor drinking fountains, water hydrants and park facilities to prevent freezing. Water hydrants and water cutoffs will be turned on and off as required by the Lake Manager.

TASK 6. Complaints: No Additional

Visitor Assistance: No Additional

Disturbances: Contact information for this lake office is: (254) 939-2461.

Lost and Found: The Contractor will maintain a lost and found department in the gatehouse. All items will be turned into the project office when fees are submitted. The Contractor will prepare a lost and found report on all lost and found property. The Contractor will insure that proper identification is obtained from individuals before release of any lost and found property.

Image, Personal Appearance and Dress: No additional

Cooperation with Others: No Additional

Living Area and Gatehouse Maintenance: No additional

No Soliciting: No Additional.

Weapons: No Additional.

Alcohol: No Additional.

Government Property: No Additional.

Absenteeism: No Additional.

Visitors of the Contractor/Gate Attendant: No Additional.

Security Bonding (Bonding for Fee Collection): No Additional.

Physical Security and Key Control: No Additional.

Gate Operations: All gate closings and openings shall be performed as indicated in the table below. The attendant is solely responsible for the opening and closing of park gates at the assigned times. The attendant will place a combination lock on the exit gate and place a card with the combination number on any vehicle left unattended in the park. At no time will a vehicle be locked behind a gate with no means of exit.

Park Hours of Operation, Belton & Stillhouse Hollow Lakes

Location Open AM Close PM Mileage* Responsible Attendant

Cedar Ridge Park 6:00 10:00 N/A Cedar Ridge Park

1.12 GENERAL LIABILITY AND OTHER INSURANCE: No Additional.

1.13 DAMAGE RESPONSIBLITY: No Additional.

1.14 LIABILITY: No Additional.

1.15 PERMITS/COMPLIANCE: No Additional.

1.16 COMMUNICATIONS EQUIPMENT: A telephone shall be provided at each gatehouse for official business use. Any charges determined to be personal or long distance other than official business are not allowed and shall be the responsibility of the Contractor. The gatehouse telephone shall be answered by the Contractor on duty. Additional phone lines and/or any change, alteration or tampering with phone or data lines in the gatehouse is prohibited. The phone number will not be given out to the public or as your personal phone number.

1.17 PAYMENT FOR SERVICES: No Additional.

1.18 TERMINATION: No Additional.

1.18.1 Grounds for Termination: No Additional.

1.19 DUTY OF CONTRACTOR TO FINISH CONTRACT: No Additional.

1.20 OTHER REQUIREMENTS: Contractors will complete reports as required by the Lake Manager. The reports include; but are not limited to: Daily Activity Reports, Inspection Reports, Incident Reports and Lost and Found Reports.

TECHNICAL EXHIBIT 1

PERFORMANCE REQUIREMENTS SUMMARY

The Contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.

Performance Objective (The Service required)

Standard

PERFORMANCE

THRESHOLD

Method of

Surveillance

Task # 1 The Contractor shall collect User Fees, SWF PWS 1.11 Task 1

The Contractor Completed Financial Statements and Deposit Statements for User Fees must agree.

Zero (0) deviation from standard

100% inspection

Task # 2 The Contractor shall pick up/print/review reservation data reports, maintain status reports to ensure campsite status is current, show competency in R1S SWF 1.11 Task 2

Contractor completed status reports monitoring dates of arrivals, departures, no shows, cancellations, and showed competency in R1S

Zero (0) deviation from standard.

100% Inspection.

Task #3 The Contractor shall check in reservations for Group Shelters upon park arrival SWF PWS 1.11 Task 3

Contractor completed status reports monitoring dates of arrivals, departures, no shows, cancellations

Zero (0) deviation from standard

100% Inspection

Task #4 The Contractor shall maintain record of current status for each campsite occupied SWF PWS 1.11 Task 4

Contractor completed status reports monitoring dates of arrivals, departures, no shows, cancellations

Zero (0) deviation from standard

100% Inspection

Task # 5 The Contractor shall inspect parks.

Park Inspections SWF PWS 1.11 Task 5

The Contractor completed daily inspections during contract specified times.

Allowable deviation 1 incomplete daily inspection per quarter.

100% Inspection

Task #6 The Contractor shall maintain written record of Park Facilities complaints SWF PWS 1.11 Task 6

Contractor completed log of Park Facility’s complaints by date

Zero (0) deviation from standard

100% Inspection

TECHNICAL EXHIBIT 2

DELIVERABLES SCHEDULE

DELIVERABLE FREQUENCY # OF COPIES MEDIUM/FORMAT SUBMIT TO

Financial Statements

SWF PWS 1.11

Task 1

Within one day of completing shifts

Original and two (2) copies

Hard Copy Lake Office

Completed Status Reports SWF PWS

1.11 Task 2

Within one day of completing shifts

1 original Hard Copy Lake Office

Completed Status report of Check in

Group Shelter Reservations SWF PWS 1.11 Task 3

Within one day of completing shifts

1 original Hard Copy Lake Office

Completed Status report of Campsite Occupancy SWF PWS 1.11 Task 4

Within one day of completing shift

1 original Hard Copy Lake Office

Completed Daily Inspection Report

SWF PWS 1.11

Task 5

Within one day of completing shift

1 original Hard Copy Lake Office

Completed log of Park Facility’s

Complaints SWF PWS 1.11 Task 6

Within one day of completing shifts

1 original Hard Copy Lake Office