Text version

Bid Schedule

OVERHEAD CRANE MAINTENANCE
BID SCHEDULE

**NOTE: Estimated quantities are for pricing purposes only. Does not reflect actual amount of work.**

Base Year
10 May 2018 - 9 May 2019
EST
CLINDescription:QTYU/MU/PTotal

0001 Preventative Maintenance 275 Each ______ ______

0002 Daytime Service Calls 150 Each ______ ______

0003 After Hour Service Calls 25 Each ______ ______

0004Repair Work
Hourly Rate Daytime Hours: $___________2,000Hours1
Hourly Rate After Hours: $___________1,000Hours1

0005 Parts $320,000.00 Lump Sum 1 $320,000.00

0006 Load Test 275 Each ______ ______

0007 Crane Operation Training 12 Each ______ ______

0008 Contractor Manpower Reporting 12 Each ______ ______

Base Year Total

1st Option Period
10 May 2019 - 9 May 2020
EST
CLINDescription:QTYU/MU/PTotal

1001 Preventative Maintenance 275 Each ______ ______

1002 Daytime Service Calls 150 Each ______ ______

1003 After Hour Service Calls 25 Each ______ ______

1004Repair Work
Hourly Rate Daytime Hours: $___________2,000Hours1
Hourly Rate After Hours: $___________1,000Hours1

1005 Parts $320,000.00 Lump Sum 1 $320,000.00

1006 Load Test 275 Each ______ ______

1007 Crane Operation Training 12 Each ______ ______

1008 Contractor Manpower Reporting 12 Each ______ ______

1st Option Period Total ______

2nd Option Period
10 May 2020 - 9 May 2021
EST
CLINDescription:QTYU/MU/PTotal

2001 Preventative Maintenance 275 Each ______ ______

2002 Daytime Service Calls 150 Each ______ ______

2003 After Hour Service Calls 25 Each ______ ______

2004Repair Work
Hourly Rate Daytime Hours: $___________2,000Hours1
Hourly Rate After Hours: $___________1,000Hours1

2005 Parts $320,000.00 Lump Sum 1 $320,000.00

2006 Load Test 275 Each ______ ______

2007 Crane Operation Training 12 Each ______ ______

2008 Contractor Manpower Reporting 12 Each ______ ______

2nd Option Period Total ______

3rd Option Period
10 May 2021 - 9 May 2022
EST
CLINDescription:QTYU/MU/PTotal

3001 Preventative Maintenance 275 Each ______ ______

3002 Daytime Service Calls 150 Each ______ ______

3003 After Hour Service Calls 25 Each ______ ______

3004Repair Work
Hourly Rate Daytime Hours: $___________2,000Hours1
Hourly Rate After Hours: $___________1,000Hours1

3005 Parts $320,000.00 Lump Sum 1 $320,000.00

3006 Load Test 275 Each ______ ______

3007 Crane Operation Training 12 Each ______ ______

3008 Contractor Manpower Reporting 12 Each ______ ______

3rd Option Period Total ______

4th Option Period
10 May 2022 - 9 May 2023
EST
CLINDescription:QTYU/MU/PTotal

4001 Preventative Maintenance 275 Each ______ ______

4002 Daytime Service Calls 150 Each ______ ______

4003 After Hour Service Calls 25 Each ______ ______

4004Repair Work
Hourly Rate Daytime Hours: $___________2,000Hours1
Hourly Rate After Hours: $___________1,000Hours1

4005 Parts $320,000.00 Lump Sum 1 $320,000.00

4006 Load Test 275 Each ______ ______

4007 Crane Operation Training 12 Each ______ ______

4008 Contractor Manpower Reporting 12 Each ______ ______

4th Option Period Total ______

Contract Total ______

**NOTE: Estimated quantities are for pricing purposes only. Does not reflect actual amount of work.**