UNIT ESTIMATED

PRICE AMOUNT

1 JOB SUM 1,300,000.00$

1 JOB SUM 157,000.00$

961,500 CY 2.80$ 2,692,200.00$

604,900 CY 2.03$ 1,227,947.00$

1 JOB SUM 60,000.00$

5,437,147.00$

134,200 CY 3.90$ 523,380.00$

523,380.00$

5,960,527.00$

1 JOB SUM 68,000.00$

295,400 CY 4.56$ 1,347,024.00$

115 HR 2,500.00$ 287,500.00$

30 TON 3,600.00$ 108,000.00$

1,810,524.00$ 7,771,051.00$

The apparent low bidder* Orion Marine is 9.32% below the Government's Estimate

GALVESTON EXECUTION BRANCH CHIEF

Curtis Cole, Jr.

TOTAL SCHEDULE NO. 1

OPTION NO. 2

TOTAL SCHEDULE NO. 1 AND OPTION NO. 1

0009 Standby for Docks 0010 Debris Removal, PHA Docks

TOTAL OPTION 2

TOTAL SCHEDULE NO. 1 AND OPTION NOS. 1 & 2

Pipeline Management, Port of Houston (PHA Docks)

I CERTIFY THAT I HAVE OPENED, READ, AND RECORDED ON THIS ABSTRACT ALL OFFERS RECEIVED IN

ABSTRACT OF OFFERS Page 1 Solicitation No.: W9126G18B0032 Date Issued: 17 Jul 2018 Date Opened: 24 Aug 2018 Issuing Office: USAED-Ft. Worth Project Title: Houston Ship Channel, Texas Morgan's Point to Exxon and Barbour's Cut Ship Channel in Harris County, Texas, Unrestricted Procurement Number of Amendments Issued: 4 GOVERNMENT ESTIMATE (Without Profit)

NO.

ESTIMATED

DESCRIPTION QUANTITY

ITEM

Mobilization & Demobilization

TOTAL OPTION 1

OPTION NO. 1

Pipeline Management

Site Management

Re-Dredging Barbour's Flare, Section 8

Dredging Houston Ship Channel, Sections 1 through 4

Dredging Barbour's Cut Terminal, Sections 5 through 7

0008 Dredging Port of Houston (PHA) Docks, Section

1 JOB SUM 1,500,000.00$

1 JOB SUM 400,000.00$

961,500 CY 2.50$ 2,403,750.00$

604,900 CY 2.50$ 1,512,250.00$

1 JOB SUM 40,000.00$

5,856,000.00$

134,200 CY 3.00$ 402,600.00$

402,600.00$

6,258,600.00$

1 JOB SUM 40,000.00$

295,400 CY 5.00$ 1,477,000.00$

115 HR 1,200.00$ 138,000.00$

30 TON 1,000.00$ 30,000.00$

1,685,000.00$ 7,943,600.00$

Site Management

Solicitation No.: W9126G18B0032 Date Issued: 17 Jul 2018 Date Opened: 24 Aug 2018 ABSTRACT OF OFFERS (CONT'D) Page 2

ITEM

Dredging Houston Ship Channel, Sections 1 through 4

DESCRIPTION

Business Size: Small Business Woman-Owned Offeror: #1 RLB Contracting, Inc., Port Lavaca, Texas Issuing Office: USAED-Ft. Worth

ESTIMATED

NO. QUANTITY

Dredging Barbour's Cut Terminal, Sections 5

TOTAL SCHEDULE NO. 1

0006 Re-Dredging Barbour's Flare, Section 8

TOTAL OPTION 1

TOTAL SCHEDULE NO. 1 AND OPTION NOS. 1 & 2

TOTAL SCHEDULE NO. 1 AND OPTION NO. 1

OPTION NO. 2

Pipeline Management, Port of Houston (PHA Docks)

0008 Dredging Port of Houston (PHA) Docks, Section

0001 Mobilization & Demobilization

0009 Standby for Docks 0010 Debris Removal, PHA Docks

TOTAL OPTION 2

OPTION NO. 1

Pipeline Management

1 JOB SUM 3,450,000.00$

1 JOB SUM 800,000.00$

961,500 CY 7.20$ 6,922,800.00$

604,900 CY 5.30$ 3,205,970.00$

1 JOB SUM 250,000.00$

14,628,770.00$

134,200 CY 4.20$ 563,640.00$

563,640.00$

15,192,410.00$

1 JOB SUM 300,000.00$

295,400 CY 5.10$ 1,506,540.00$

115 HR 5,500.00$ 632,500.00$

30 TON 3,000.00$ 90,000.00$

2,529,040.00$ 17,721,450.00$

TOTAL OPTION 2

TOTAL OPTION 1

TOTAL SCHEDULE NO. 1 AND OPTION NO. 1

OPTION NO. 2

Pipeline Management, Port of Houston (PHA Docks) Dredging Port of Houston (PHA) Docks, Section

Offeror: #2 Manson Construction Co.

Business Size: Other Than Small Business

ABSTRACT OF OFFERS (CONT'D) Page 3 Solicitation No.: W9126G18B0032 Date Issued: 17 Jul 2018 Date Opened: 24 Aug 2018

ESTIMATEDITEM

Issuing Office: USAED-Ft. Worth

NO. QUANTITY

0001 Mobilization & Demobilization 0002 Pipeline Management

Dredging Houston Ship Channel, Sections 1 through 4

0004 Dredging Barbour's Cut Terminal, Sections 5

DESCRIPTION

Debris Removal, PHA Docks

Re-Dredging Barbour's Flare, Section 8

Standby for Docks

TOTAL SCHEDULE NO. 1

0005 Site Management

1 JOB SUM 1,000,000.00$

1 JOB SUM 200,000.00$

961,500 CY 4.64$ 4,461,360.00$

604,900 CY 4.02$ 2,431,698.00$

1 JOB SUM 100,000.00$

8,193,058.00$

134,200 CY 3.50$ 469,700.00$

469,700.00$

8,662,758.00$

1 JOB SUM 25,000.00$

295,400 CY 3.21$ 948,234.00$

115 HR 2,500.00$ 287,500.00$

30 TON 2,500.00$ 75,000.00$

1,335,734.00$ 9,998,492.00$

TOTAL SCHEDULE NO. 1

0001 Mobilization & Demobilization 0002 Pipeline Management

Dredging Houston Ship Channel, Sections 1 through 4

0004 Dredging Barbour's Cut Terminal, Sections 5

QUANTITY

0006 Re-Dredging Barbour's Flare, Section 8

OPTION NO. 1

Debris Removal, PHA Docks

TOTAL OPTION 2

Solicitation No.: W9126G18B0032 Date Issued: 17 Jul 2018 Date Opened: 24 Aug 2018 Issuing Office: USAED-Ft. Worth Offeror: #3 Crosby Dredging, LLC, Galliano, Louisiana Business Size: Other Than Small Business

ITEM ESTIMATED

ABSTRACT OF OFFERS (CONT'D) Page 4

NO. DESCRIPTION

Site Management

OPTION NO. 2

Pipeline Management, Port of Houston (PHA

Standby for Docks

1 JOB SUM 1,100,000.00$

1 JOB SUM 350,000.00$

961,500 CY 2.75$ 2,644,125.00$

604,900 CY 2.50$ 1,512,250.00$

1 JOB SUM 80,000.00$

5,686,375.00$

134,200 CY 2.65$ 355,630.00$

355,630.00$

6,042,005.00$

1 JOB SUM 50,000.00$

295,400 CY 2.30$ 679,420.00$

115 HR 2,000.00$ 230,000.00$

30 TON 1,500.00$ 45,000.00$

1,004,420.00$ 7,046,425.00$

TOTAL SCHEDULE NO. 1

OPTION NO. 1

ITEM

0002 Pipeline Management

Dredging Houston Ship Channel, Sections 1 through 4

0004 Dredging Barbour's Cut Terminal, Sections 5

QUANTITY

ABSTRACT OF OFFERS (CONT'D) Page 5 Solicitation No.: W9126G18B0032 Date Issued: 17 Jul 2018 Date Opened: 24 Aug 2018 Issuing Office: USAED-Ft. Worth Offeror: * #4 Orion Marine Group Business Size: Other Than Small Business

Re-Dredging Barbour's Flare, Section 8

TOTAL OPTION 2

Standby for Docks

0010 Debris Removal, PHA Docks

OPTION NO. 2

Pipeline Management, Port of Houston (PHA

Site Management

0001 Mobilization & Demobilization

ESTIMATED

NO. DESCRIPTION

1 JOB SUM 1,250,000.00$

1 JOB SUM 775,000.00$

961,500 CY 6.75$ 6,490,125.00$

604,900 CY 7.00$ 4,234,300.00$

1 JOB SUM 75,000.00$

12,824,425.00$

134,200 CY 8.00$ 1,073,600.00$

1,073,600.00$

13,898,025.00$

1 JOB SUM 75,000.00$

295,400 CY 7.00$ 2,067,800.00$

115 HR 2,700.00$ 310,500.00$

30 TON 7,500.00$ 225,000.00$

2,678,300.00$

16,576,325.00$

ABSTRACT OF OFFERS (CONT'D) Page 6

Dredging Port of Houston (PHA) Docks, Section

NO. DESCRIPTION QUANTITY

0001 Mobilization & Demobilization

Solicitation No.: W9126G18B0032 Date Issued: 17 Jul 2018 Date Opened: 24 Aug 2018 Issuing Office: USAED-Ft. Worth Offeror: #5 Mike Hooks, Inc.

Business Size: Other Than Small Business

ITEM ESTIMATED

Site Management

TOTAL SCHEDULE NO. 1

TOTAL SCHEDULE NO. 1 AND OPTION NO. 1

OPTION NO. 2

Pipeline Management, Port of Houston (PHA

0009 Standby for Docks

0010 Debris Removal, PHA Docks

TOTAL OPTION 2

OPTION NO. 1

0006 Re-Dredging Barbour's Flare, Section 8

0002 Pipeline Management

Dredging Houston Ship Channel, Sections 1 through 4

0004 Dredging Barbour's Cut Terminal, Sections 5

1 JOB SUM 2,250,000.00$

1 JOB SUM 250,000.00$

961,500 CY 6.50$ 6,249,750.00$

604,900 CY 6.50$ 3,931,850.00$

1 JOB SUM 50,000.00$

12,731,600.00$

134,200 CY 4.25$ 570,350.00$

570,350.00$

13,301,950.00$

1 JOB SUM 50,000.00$

295,400 CY 4.25$ 1,255,450.00$

115 HR 4,000.00$ 460,000.00$

30 TON 4,000.00$ 120,000.00$

1,885,450.00$

15,187,400.00$

TOTAL SCHEDULE NO. 1 AND OPTION NO. 1

0009 Standby for Docks

0010 Debris Removal, PHA Docks

TOTAL OPTION 2

0005 Site Management

TOTAL SCHEDULE NO. 1

0006 Re-Dredging Barbour's Flare, Section 8

ABSTRACT OF OFFERS (CONT'D) Page 7 Solicitation No.: W9126G18B0032 Date Issued: 17 Jul 2018 Date Opened: 24 Aug 2018 Issuing Office: USAED-Ft. Worth Offeror: #6 Weeks Marine

OPTION NO. 2

Pipeline Management, Port of Houston (PHA Docks) Dredging Port of Houston (PHA) Docks, Section

Business Size: Other Than Small Business

ITEM ESTIMATED

NO. DESCRIPTION QUANTITY

0001 Mobilization & Demobilization

0002 Pipeline Management

Dredging Houston Ship Channel, Sections 1 through 4

0004 Dredging Barbour's Cut Terminal, Sections 5

2018-08-24T15:09:23-0500
COLE.CURTIS.JR.1231025746

File details come from the government source that posted it.