AMEND-0001_W9126G18B0015.pdf
PDF 8 MB Posted
- Solicitation number
- W9126G18B0015
About this file
Amendment No. 0001
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Abstract-W9126G18B0015.pdf | ||
| Preliminary-Abstract-W9126G18B0015.pdf | ||
| W9126G18B0015-Specs.pdf | ||
| W9126G18B0015-Plans.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W45VAK80362713 010810
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Unrestricted Procurement for Matagorda Ship Channel, Texas, Peninsula to Point Comfort in Matagorda and Calhoun Counties, Texas, Pipeline Dredging is hereby amended as follows:
Continued on Page 2.
1. CONTRACT ID CODE PAGE OF PAGES
J 1
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9126G18B0015
X 9B. DATED (SEE ITEM 11)
03-Aug-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
29-Aug-2018
CODE
US ARMY CORPS OF ENGINEERS FORT WORTH
2000 FORT POINT ROAD
GALVESTON TX 77550-1229
W9126G 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
M3ODXMAN
Typewritten Text
W9126G18B0015
A0001-2
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
1. The specifications for Solicitation No. W9126G18B0015, Matagorda Ship Channel, Texas, Matagorda Peninsula to Point Comfort in Matagorda and Calhoun Counties, Texas, Pipeline Dredging, are hereby amended as follows:
THE PROPOSAL DUE DATE IS HEREBY RESCHEDULED FOR 11 SEPTEMBER 2018 AT 2:00
P.M. CDT.
a) Specifications.
(1) SECTION 00 11 00.00 45, BID SCHEDULE – The enclosed SECTION 00 11 00.00 45, entitled BID SCHEDULE, supersedes that issued with this Solicitation.
(2) SECTION 00 73 00.01 45, SPECIAL CONTRACT REQUIREMENTS, STANDARD – The enclosed SECTION 00 73 00.01 45, entitled SPECIAL CONTRACT REQUIREMENTS, STANDARD, supersedes that issued with this Solicitation.
(3) SECTION 01 22 00.10, MEASUREMENT AND PAYMENT – The enclosed SECTION 01 22 00.10, entitled MEASUREMENT AND PAYMENT, supersedes that issued with this Solicitation.
(4) SECTION 01 35 26.01 45, GOVERNMENT SAFETY REQUIREMENTS – The enclosed SECTION 01 35 26.012 45, entitled GOVERNMENT SAFETY REQUIREMENTS, supersedes that issued with this Solicitation.
(5) SECTION 01 45 01.00, QUALITY CONTROL – The enclosed SECTION 01 45 01.00, entitled QUALITY CONTROL, supersedes that issued with this Solicitation.
(6) SECTION 01 57 20.00 45, ENVIRONMENTAL PROTECTION – The enclosed SECTION 01 57 20.00 45, entitled ENVIRONMENTAL PROTECTION, supersedes that issued with this Solicitation.
(7) SECTION 35 20 23.16 45, PIPELINE DREDGING, APPENDIX 1 – QUANTITY
SUMMARY TABLE – The enclosed SECTION 35 20 23.16 45, entitled PIPELINE DREDGING, APPENDIX 1 – QUANTITY SUMMARY TABLE, supersedes that issued with this Solicitation.
b) Drawings
(1) DRAWINGS NO. G-002, G-003, C-101, AND C-103 THROUGH C-106 - The enclosed drawings no. C-101, and C-103 through C-106 supersedes that issued with this Solicitation.
(2) DRAWINGS NO. C-110, C-111, AND C-324 THROUGH C330 - The enclosed drawings no.
C-110, C-111, and C-324 through C326, are in addition to that issued with this Solicitation.
2. This amendment shall be attached to and become a part of the solicitation.
9 Encls:
1. SECTION 00 11 00.00 45, BID SCHEDULE
2. SECTION 00 73 00.01 45, SPECIAL CONTRACT REQUIREMENTS, STANDARD
3. SECTION 01 22 00.10, MEASUREMENT AND PAYMENT
4. SECTION 01 35 26.012 45, GOVERNMENT SAFETY REQUIREMENTS
5. SECTION 01 45 01.00, QUALITY CONTROL
6. SECTION 01 57 20.00 45, ENVIRONMENTAL PROTECTION
W9126G18B0015
A0001-3
7. SECTION 35 20 23.16 45, PIPELINE DREDGING, APPENDIX-1- QUANTITY SUMMARY
TABLE
8. DRAWINGS NO. C-101, AND C-103 THROUGH C-106
9. DRAWINGS NO. C-110, C-111, AND C-324 THROUGH C330
SWG FILE NO.:GUAD 705-240 SOLICITATION NO.:W9126G18B0015
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 11 00.00 45
BID SCHEDULE
PART 1 GENERAL
1.1 BID SCHEDULE
1.1.1 Schedule No. 1
1.1.2 Option No. 1
1.1.3 Option No. 2
1.2 EVALUATION OF OPTIONS (July 1990) (FAR 52.217-5)
-- End of Section Table of Contents --
DOCUMENT 00 11 00.00 45 Page 1
(TO ACCOMPANY AMENDMENT NO. 0001 TO SOLICITATION NO. W9126G18B0015)
SECTION 00 11 00.00 45
BID SCHEDULE
AMENDMENT NO. 0001
PART 1 GENERAL
1.1 BID SCHEDULE
(TO BE ATTACHED TO STANDARD FORM 1442)
1.1.1 Schedule No. 1
Item No.
Description Estimated Quantity
Unit Unit Price Estimated Amount
SCHEDULE NO. 1
0001 Mobilization and Demobilization
1 JOB SUM $___________
0002 Pipeline Management 1 JOB SUM $___________
0003 Dredging Station 12+000 to 65+000
2,091,667 CY $_________ $___________
TOTAL SCHEDULE NO. 1 $___________
NOTE: Completion time stated in SECTION 00 73 00.01 45 SPECIAL CONTRACT REQUIREMENTS, STANDARD is for Schedule No. 1 work.
DOCUMENT 00 11 00.00 45 Page 2
BID SCHEDULE (CONT'D)
(TO BE ATTACHED TO STANDARD FORM 1442)
1.1.2 Option No. 1
Item No.
Description Estimated Quantity
Unit Unit Price Estimated Amount
OPTION NO. 1
0004 Pipeline Management 1 JOB SUM $___________
0005 Dredging - Station 65+000 to 115+000
2,090,130 CY $_________ $___________
TOTAL OPTION NO. 1 $___________
TOTAL SCHEDULE NO. 1 AND OPTION NO. 1 $___________
NOTE FOR OPTION NO. 1: The Government may exercise this Option by written notice to the Contractor prior to completion of all authorized work. An additional time of 104 calendar days will be added to this Contract for completion of this Option.
DOCUMENT 00 11 00.00 45 Page 3
(TO BE ATTACHED TO STANDARD FORM 1442)
1.1.3 Option No. 2
Item No.
Description Estimated Quantity
Unit Unit Price Estimated Amount
OPTION NO. 2
0006 Dredging - Calhoun Port Authority Docks
1 JOB SUM $___________
TOTAL OPTION NO. 2 $___________
TOTAL SCHEDULE NO. 1, OPTIONS NO. 1 AND 2 $___________
NOTE FOR OPTION NO. 2: The Government may exercise this Option by written notice to the Contractor prior to completion of all authorized work. An additional time of 30 calendar days will be added to this Contract for completion of this Option.
DOCUMENT 00 11 00.00 45 Page 4
(TO BE ATTACHED TO STANDARD FORM 1442)
1.2 EVALUATION OF OPTIONS (July 1990) (FAR 52.217-5)
Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
-- End of Document --
DOCUMENT 00 11 00.00 45 Page 5
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 73 00.01 45
SPECIAL CONTRACT REQUIREMENTS, STANDARD
PART 1 GENERAL
1.1 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) (FAR
52.211-10)
1.2 LIQUIDATED DAMAGES - CONSTRUCTION (SEPT 2000) (FAR 52.211-12)
1.3 PHYSICAL DATA (APR 1984) (FAR 52.236-4)
1.4 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE(MAR 1995)
1.5 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984) (52.236-1)
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
-- End of Section Table of Contents --
DOCUMENT 00 73 00.01 45 Page 1
SECTION 00 73 00.01 45
SPECIAL CONTRACT REQUIREMENTS, STANDARD
AMENDMENT NO. 0001
PART 1 GENERAL
1.1 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) (FAR
52.211-10)
The Contractor shall be required to:
(a) Commence work under this contract within 10 calendar days after the date the Contractor receives the Notice to Proceed;
(b) Prosecute the work diligently, and
(c) Complete the entire work ready for use not later than 105 (AM#1)114 calendar days after the date the Contractor receives the Notice to Proceed. The time stated for completion shall include final cleanup of the premises.
1.2 LIQUIDATED DAMAGES - CONSTRUCTION (SEPT 2000) (FAR 52.211-12)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $3,643.00 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
1.3 PHYSICAL DATA (APR 1984) (FAR 52.236-4)
Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
(a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by condition surveys.
(b) Weather Conditions. Under normal conditions Under ordinary conditions, the mean tidal range is about 1.5 feet. The height of tide is largely dependent on the force, direction, and duration of the wind. Strong northerly winds may depress the water surface as much as, and in some instances more than 2 feet below Mean Lower Low Water (MLLW), while southerly winds may raise the water surface as much as, and in some instances more than 3 feet above MLLW.
(c) Transportation Facilities. The immediate vicinity is served by railroad, highway, and deep and shallow draft channels. The proposed site is accessible bywater from Port Lavaca, Port O'Connor Texas and
DOCUMENT 00 73 00.01 45 Page 2 other coastal ports.Rail highway connections are available at the City of Port Lavaca, andPoint Comfort, Texas.
(d) Other Information. Channel traffic consists of (deep draft ships, small boats of various sizes, fishing vessels, ferries, tugs, tows consisting of a tug and one or more barges). Traffic will interfere with dredging operations to some extent.
1.4 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE(MAR 1995)
(a) This special contract requirement does not apply to terminations. See 52.249-5000, Basis for Settlement of Proposals, and FAR Part 49.
(b) Allowable cost for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a contractor or subcontractor at any tier shall be based on actual cost data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the con-tractor's accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series equipment from the contractor's accounting records, costs for that equipment shall be based upon the applicable provisions of EP 1110-1-8, Construction Equipment Ownership and Operating Expense Schedule, Region VI. Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the contracting officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retroactive pricing, the schedule in effect at the time the work was performed shall apply.
(c) Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-36, Rental Costs. Rates for equipment rented from an organization under common control, lease-purchase arrangements, and sale-leaseback arrangements, will be determined using the schedule, except that actual rates will be used for equipment leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees.
(d) When actual equipment costs are proposed and the total amount of the pricing action exceeds the SAT, the contracting officer shall request the contractor to submit either certified cost or pricing data, or partial/limited data, as appropriate. The data shall be submitted on Standard Form 1411, Contract Pricing Proposal Cover Sheet.
NOTE: A copy of EP 1110-1-8, "CONSTRUCTION EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE," is available at the following website:
http://www.publications.usace.army.mil/USACEPublications/EngineerPamphlets.aspx.
1.5 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984) (52.236-1)
The Contractor shall perform on the site, and with its own organization, work equivalent to at least forty (40%) percent of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction and the Contracting Officer determines that the reduction would be to the advantage of the Government.
DOCUMENT 00 73 00.01 45 Page 3
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
-- End of Document --
DOCUMENT 00 73 00.01 45 Page 4
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00.10
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 SUBMITTALS
1.2 LUMP SUM PAYMENT ITEMS
1.2.1 Mobilization and Demobilization
1.2.1.1 Payment
1.2.1.2 Unit of Measure
1.2.2 Pipeline Management
1.2.2.1 Payment
1.2.2.2 Unit of Measure
1.2.3 (AM#1)Dredging Calhoun Port Authority Docks
1.2.3.1 Payment
1.2.3.2 Unit of Measure
1.3 UNIT PRICE PAYMENT ITEMS
1.3.1 Dredging
1.3.1.1 Payment
1.3.1.2 Dredging Partial Payment
1.3.1.3 Measurement
1.3.1.4 Government Surveys
1.3.1.5 Surveys During Progress of Work
1.3.1.6 Unit of Measurement
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
-- End of Section Table of Contents --
SECTION 01 22 00.10 Page 1
SECTION 01 22 00.10
MEASUREMENT AND PAYMENT
AMENDMENT NO. 0001
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Surveys; G
1.2 LUMP SUM PAYMENT ITEMS
Payment items for the work of this Contract for which Contract lump sum payments will be made are listed in the BID SCHEDULE and specified below.
All costs for items of work, which are not specifically mentioned to be included in a particular lump sum or unit price payment item, will be included in the listed lump sum item most closely associated with the work involved. The lump sum price and payment made for each item listed will constitute full compensation for furnishing plant, labor, materials, and equipment, and performing any associated Contractor Quality Control, administrative requirements, environmental protection, meeting safety requirements, tests and reports, and for performing the work required for which separate payment is not otherwise provided.
1.2.1 Mobilization and Demobilization
1.2.1.1 Payment
The Contract price for "Mobilization and Demobilization" will include the costs in connection with mobilization and demobilization of the plant necessary to perform work under the various bid items. The Contract price shall include transportation and other costs incidental to delivery of the plant and other equipment to the general work area in condition ready for operation and, after the completion of the work, for removal of the plant and equipment from the work site(s). Payment for mobilization and demobilization will be pursuant to the conditions as defined in the SECTION
00 72 00 CONTRACT CLAUSES.
1.2.1.2 Unit of Measure
Unit of measure: Job.
SECTION 01 22 00.10 Page 2
1.2.2 Pipeline Management
1.2.2.1 Payment
Payment for "Pipeline Management", in Schedule No. 1, and "Pipeline Management", in Option No. 1, will be made for costs associated with laying, handling of dredge pipelines, from the dredge to the Placement Area, procurement of materials, and for construction of ramps or installation of culvert pipes that may be necessary in connection with placing and removal of pipeline and final clean up of pipeline route.
Monthly partial payments will be based on the estimates of dredging completed during the period up to 80 percent of the Contract price and the remaining 20 percent will be paid in the first monthly partial payment after removal of the pipeline and the final clean-up of the pipeline route.
1.2.2.2 Unit of Measure
Unit of measure: Job.
1.2.3 (AM#1)Dredging Calhoun Port Authority Docks
1.2.3.1 Payment
Payment for "Dredging - Calhoun Port Authority Docks", in Option No. 2, will be made for all costs associated with Mobilization and Demobilization, Pipeline Management, and Dredging of Calhoun Port Authority Docks. The Contract price will include cost associated with the removal of dredged material, transportation, placement at the Placement Area, laying and handling of dredge pipelines, procurement of materials, and for construction of ramps or installation of culvert pipes that may be necessary in connection with placing and removal of pipeline, removal of the plant and equipment from the worksite, and final cleanup of pipeline route.
1.2.3.2 Unit of Measure
Unit of measure: Job.
1.3 UNIT PRICE PAYMENT ITEMS
Payment items for the work in this Contract on which the Contract unit price payments will be made are listed in the BID SCHEDULE and specified below. The unit price and payment made for each item listed will constitute full compensation for furnishing plant, labor, materials, and equipment, and performing any associated Contractor Quality Control, administrative requirements, environmental protection, meeting safety requirements, tests and reports, and for performing the work required for each of the unit price items.
1.3.1 Dredging
1.3.1.1 Payment
Payment for "Dredging Station 12+000 to 65+000", in Schedule No. 1, and "Dredging" in Option No. 1, (AM#1)and "Dredging - Station 65+000 to 115+000", in Option No. 1, will be made for costs associated with the removal of dredged material, transportation, and placement at the Placement Area.
SECTION 01 22 00.10 Page 3
1.3.1.2 Dredging Partial Payment
Partial payment will be based on approximate quantities determined by fathometer soundings or sweepings taken behind the dredge. The Contractor shall submit hydrographic surveys, raw survey data, and volume calcutions to support partial payments of dredging sections for pay requests. Partial pay requests without supporting data will not be paid. Final pay quantities will be based on Government Before-Dredging and After-Dredging surveys.
1.3.1.3 Measurement
The material removed will be measured by cubic yard in place, by means of soundings taken before and after dredging. The total quantity of dredged material will be the theoretical quantity between the bottom surface shown by fathometer soundings of the last survey made "before-dredging" and the bottom surface shown by the fathometer soundings of a survey made "after-dredging", within the limits of the overdepth and side and end slopes, less deductions that may be required for misplaced material.
1.3.1.4 Government Surveys
The Government will use the tide staffs shown on the drawings for vertical control. Real Time Kinematic (RTK) or Virtual Reference Station (VRS) will not be used. Differential Global Positioning System (DGPS) will be used for horizontal control.
Processing survey data will be performed with HYPACK software using the Kingfisher Method (updated 5/6/2016). Volumes will be computed by average end area using cross sectional survey lines. Before and After Dredge cross sections will be run on 200-foot stations and at changes in the template.
If the Contractor elects to use HYPACK software, the Government will provide the survey line files for the Contractor's use.
1.3.1.5 Surveys During Progress of Work
Contract depth will be determined by surveys taken behind the dredge as work progresses. The Contractor shall take progress soundings or sweepings and submit drawings and data of the surveys.
1.3.1.6 Unit of Measurement
Unit of measure: cubic yard.
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
-- End of Section --
SECTION 01 22 00.10 Page 4
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 35 26.01 45
GOVERNMENTAL SAFETY REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
1.2 DEFINITIONS
1.2.1 Competent Person (CP)
1.2.2 Competent Person, Confined Space
1.2.3 Competent Person, Cranes and Rigging
1.2.4 Competent Person, Excavation/Trenching
1.2.5 Competent Person, Fall Protection
1.2.6 Competent Person, Scaffolding
1.2.7 Competent Person (CP) Trainer
1.2.8 High Risk Activities
1.2.9 High Visibility Accident
1.2.10 Load Handling Equipment (LHE)
1.2.11 Medical Treatment
1.2.12 Near Miss
1.2.13 Operating Envelope
1.2.14 Qualified Person (QP)
1.2.15 Qualified Person, Fall Protection (QP for FP)
1.2.16 Recordable Injuries or Illnesses
1.2.17 USACE Property and Equipment
1.2.18 Load Handling Equipment (LHE) Accident or Load Handling
Equipment Mishap
1.3 SUBMITTALS
1.4 MONTHLY EXPOSURE REPORTS
1.5 REGULATORY REQUIREMENTS
1.6 SITE QUALIFICATIONS, DUTIES, AND MEETINGS
1.6.1 Personnel Qualifications
1.6.1.1 Site Safety and Health Officer (SSHO)
1.6.1.2 Contractor Quality Control (QC) Manager:
1.6.1.3 Competent Person Qualifications
1.6.1.3.1 Competent Person for Confined Space Entry
1.6.1.4 Dredging Contract Requirements
1.6.1.4.1 Dredging Safety Personnel Requirements
1.6.1.4.2 SSHO Requirements for Dredging
1.6.1.4.3 Safety Personnel Training Requirements for Dredging
1.6.1.5 Crane Operators/Riggers
1.6.2 Personnel Duties
1.6.2.1 Duties of the Site Safety and Health Officer (SSHO)
1.6.3 Meetings
1.6.3.1 Preconstruction Conference
1.6.3.2 Safety Meetings
1.7 ACCIDENT PREVENTION PLAN (APP)
1.7.1 Names and Qualifications
1.7.2 Plans
1.7.2.1 Confined Space Entry Plan
SECTION 01 35 26.01 45 Page 1
1.7.2.2 Standard Lift Plan (SLP)
1.7.2.3 Critical Lift Plan - Crane or Load Handling Equipment
1.8 ACTIVITY HAZARD ANALYSIS (AHA)
1.8.1 AHA Management
1.8.2 AHA Signature Log
1.9 DISPLAY OF SAFETY INFORMATION
1.9.1 Safety Bulletin Board
1.9.2 Safety and Occupational Health (SOH) Deficiency Tracking System
1.10 SITE SAFETY REFERENCE MATERIALS
1.11 EMERGENCY MEDICAL TREATMENT
1.12 NOTIFICATIONS AND REPORTS
1.12.1 Mishap Notification
1.12.2 Accident Reports
1.12.3 LHE Inspection Reports
1.12.4 Certificate of Compliance and Pre-lift Plan/Checklist for LHE and Rigging
1.13 HOT WORK
1.13.1 Permit and Personnel Requirements
1.13.2 Work Around Flammable Materials
1.14 CONFINED SPACE ENTRY REQUIREMENTS
1.14.1 Entry Procedures
1.14.2 Forced Air Ventilation
1.14.3 Rescue Procedures and Coordination with Local Emergency
Responders
1.15 DIVE SAFETY REQUIREMENTS
1.16 SEVERE STORM PLAN
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION
3.1 CONSTRUCTION AND OTHER WORK
3.1.1 Worksite Communication
3.1.2 Unforeseen Hazardous Material
3.2 EQUIPMENT
3.2.1 Material Handling Equipment (MHE)
3.2.2 Load Handling Equipment (LHE)
3.2.3 Machinery and Mechanized Equipment
3.3 SUBMERGED AND FLOATING PIPELINE
-- End of Section Table of Contents --
SECTION 01 35 26.01 45 Page 2
SECTION 01 35 26.01 45
GOVERNMENTAL SAFETY REQUIREMENTS
AMENDMENT NO. 0001
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF SAFETY ENGINEERS (ASSE/SAFE)
ASSE/SAFE A10.34 (2001; R 2012) Protection of the Public on or Adjacent to Construction Sites
ASSE/SAFE Z359.0 (2012) Definitions and Nomenclature Used for Fall Protection and Fall Arrest
ASME INTERNATIONAL (ASME)
ASME B30.20 (2013; INT Oct 2010 - May 2012) Below-the-Hook Lifting Devices
ASME B30.22 (2016) Articulating Boom Cranes
ASME B30.26 (2015; INT Jun 2010 - Jun 2014) Rigging Hardware
ASME B30.3 (2016) Tower Cranes
ASME B30.5 (2014) Mobile and Locomotive Cranes
ASME B30.8 (2015) Floating Cranes and Floating Derricks
ASME B30.9 (2014; INT Feb 2011 - Nov 2013) Slings
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 10 (2018; TIA 18-1) Standard for Portable Fire Extinguishers
NFPA 241 (2013; Errata 2015) Standard for Safeguarding Construction, Alteration, and Demolition Operations
NFPA 51B (2014) Standard for Fire Prevention During Welding, Cutting, and Other Hot Work
NFPA 70 (2017; ERTA 1-2 2017; TIA 17-1; TIA 17-2;
TIA 17-3; TIA 17-4; TIA 17-5; TIA 17-6;
TIA 17-7; TIA 17-8; TIA 17-9; TIA 17-10;
SECTION 01 35 26.01 45 Page 3
TIA 17-11; TIA 17-12; TIA 17-13; TIA
17-14) National Electrical Code
NFPA 70E (2018; TIA 18-1; TIA 18-2) Standard for Electrical Safety in the Workplace
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1910 Occupational Safety and Health Standards
29 CFR 1910.146 Permit-required Confined Spaces
29 CFR 1915 Confined and Enclosed Spaces and Other Dangerous Atmospheres in Shipyard Employment
29 CFR 1926 Safety and Health Regulations for Construction
29 CFR 1926.1400 Cranes and Derricks in Construction
29 CFR 1926.16 Rules of Construction
CPL 2.100 (1995) Application of the Permit-Required Confined Spaces (PRCS) Standards, 29 CFR 1910.146
1.2 DEFINITIONS
1.2.1 Competent Person (CP)
The CP is a person designated in writing, who, through training, knowledge and experience, is capable of identifying, evaluating, and addressing existing and predictable hazards in the working environment or working conditions that are dangerous to personnel, and who has authorization to take prompt corrective measures with regards to such hazards.
1.2.2 Competent Person, Confined Space
The CP, Confined Space, is a person meeting the competent person requirements as defined EM 385-1-1 Appendix Q, with thorough knowledge of OSHA’s Confined Space Standard, 29 CFR 1910.146, and designated in writing to be responsible for the immediate supervision, implementation and monitoring of the confined space program, who through training, knowledge and experience in confined space entry is capable of identifying, evaluating and addressing existing and potential confined space hazards and, who has the authority to take prompt corrective measures with regard to such hazards.
1.2.3 Competent Person, Cranes and Rigging
The CP, Cranes and Rigging, as defined in EM 385-1-1 Appendix Q, is a person meeting the competent person, who has been designated in writing to be responsible for the immediate supervision, implementation and monitoring
SECTION 01 35 26.01 45 Page 4 of the Crane and Rigging Program, who through training, knowledge and experience in crane and rigging is capable of identifying, evaluating and addressing existing and potential hazards and, who has the authority to take prompt corrective measures with regard to such hazards.
1.2.4 Competent Person, Excavation/Trenching
A CP, Excavation/Trenching, is a person meeting the competent person requirements as defined in EM 385-1-1 Appendix Q and 29 CFR 1926, who has been designated in writing to be responsible for the immediate supervision, implementation and monitoring of the excavation/trenching program, who through training, knowledge and experience in excavation/trenching is capable of identifying, evaluating and addressing existing and potential hazards and, who has the authority to take prompt corrective measures with regard to such hazards.
1.2.5 Competent Person, Fall Protection
The CP, Fall Protection, is a person meeting the competent person requirements as defined in EM 385-1-1 Appendix Q and in accordance with ASSE/SAFE Z359.0, who has been designated in writing by the employer to be responsible for immediate supervising, implementing and monitoring of the fall protection program, who through training, knowledge and experience in fall protection and rescue systems and equipment, is capable of identifying, evaluating and addressing existing and potential fall hazards and, who has the authority to take prompt corrective measures with regard to such hazards.
1.2.6 Competent Person, Scaffolding
The CP, Scaffolding is a person meeting the competent person requirements in EM 385-1-1 Appendix Q, and designated in writing by the employer to be responsible for immediate supervising, implementing and monitoring of the scaffolding program. The CP for Scaffolding has enough training, knowledge and experience in scaffolding to correctly identify, evaluate and address existing and potential hazards and also has the authority to take prompt corrective measures with regard to these hazards. CP qualifications will be documented and include experience on the specific scaffolding systems/types being used, assessment of the base material that the scaffold will be erected upon, load calculations for materials and personnel, and erection and dismantling. The CP for scaffolding will have a documented, minimum of 8-hours of scaffold training to include training on the specific type of scaffold being used (e.g. mast-climbing, adjustable, tubular frame), in accordance with EM 385-1-1 Section 22.B.02.
1.2.7 Competent Person (CP) Trainer
A competent person trainer as defined in EM 385-1-1 Appendix Q, who is qualified in the material presented, and who possesses a working knowledge of applicable technical regulations, standards, equipment and systems related to the subject matter on which they are training Competent Persons. A competent person trainer will be familiar with the typical hazards and the equipment used in the industry they are instructing. The training provided by the competent person trainer will be appropriate to that specific industry. The competent person trainer will evaluate the knowledge and skills of the competent persons as part of the training process.
SECTION 01 35 26.01 45 Page 5
1.2.8 High Risk Activities
High Risk Activities are activities that involve work at heights, crane and rigging, excavations and trenching, scaffolding, electrical work, and confined space entry.
1.2.9 High Visibility Accident
A High Visibility Accident is any mishap which may generate publicity or high visibility.
1.2.10 Load Handling Equipment (LHE)
LHE is a term used to describe cranes, hoists and all other hoisting equipment (hoisting equipment means equipment, including crane, derricks, hoists and power operated equipment used with rigging to raise, lower or horizontally move a load).
1.2.11 Medical Treatment
Medical Treatment is treatment administered by a physician or by registered professional personnel under the standing orders of a physician. Medical treatment does not include first aid treatment even through provided by a physician or registered personnel.
1.2.12 Near Miss
A Near Miss is a mishap resulting in no personal injury and zero property damage, but given a shift in time or position, damage or injury may have occurred (e.g., a worker falls off a scaffold and is not injured; a crane swings around to move the load and narrowly misses a parked vehicle).
1.2.13 Operating Envelope
The Operating Envelope is the area surrounding any crane or load handling equipment. Inside this "envelope" is the crane, the operator, riggers and crane walkers, other personnel involved in the operation, rigging gear between the hook, the load, the crane's supporting structure (i.e. ground or rail), the load's rigging path, the lift and rigging procedure.
1.2.14 Qualified Person (QP)
The QP is a person designated in writing, who, by possession of a recognized degree, certificate, or professional standing, or extensive knowledge, training, and experience, has successfully demonstrated their ability to solve or resolve problems related to the subject matter, the work, or the project.
1.2.15 Qualified Person, Fall Protection (QP for FP)
A QP for FP is a person meeting the requirements of EM 385-1-1 Appendix Q, and ASSE/SAFE Z359.0, with a recognized degree or professional certificate and with extensive knowledge, training and experience in the fall protection and rescue field who is capable of designing, analyzing, and evaluating and specifying fall protection and rescue systems.
1.2.16 Recordable Injuries or Illnesses
Recordable Injuries or Illnesses are any work-related injury or illness
SECTION 01 35 26.01 45 Page 6 that results in:
a. Death, regardless of the time between the injury and death, or the length of the illness;
b. Days away from work (any time lost after day of injury/illness onset);
c. Restricted work;
d. Transfer to another job;
e. Medical treatment beyond first aid;
f. Loss of consciousness; or
g. A significant injury or illness diagnosed by a physician or other licensed health care professional, even if it did not result in (a) through (f) above.
1.2.17 USACE Property and Equipment
Interpret "USACE" property and equipment specified in USACE EM 385-1-1 as Government property and equipment.
1.2.18 Load Handling Equipment (LHE) Accident or Load Handling Equipment Mishap
A LHE accident occurs when any one or more of the eight elements in the operating envelope fails to perform correctly during operation, including operation during maintenance or testing resulting in personnel injury or death; material or equipment damage; dropped load; derailment;
two-blocking; overload; or collision, including unplanned contact between the load, crane, or other objects. A dropped load, derailment, two-blocking, overload and collision are considered accidents, even though no material damage or injury occurs. A component failure (e.g., motor burnout, gear tooth failure, bearing failure) is not considered an accident solely due to material or equipment damage unless the component failure results in damage to other components (e.g., dropped boom, dropped load, or roll over).
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:
Government acceptance, as defined in EM 385-1-1, is required for submittals with a "G,A" designation.
SD-01 Preconstruction Submittals
Accident Prevention Plan (APP); G,A
SD-06 Test Reports
Monthly Exposure Reports
SECTION 01 35 26.01 45 Page 7
Notifications and Reports Accident Reports LHE Inspection Reports
SD-07 Certificates
Crane Operators/Riggers Standard Lift Plan Critical Lift Plan Naval Architecture Analysis Activity Hazard Analysis (AHA) Confined Space Entry Permit Hot Work Permit Certificate of Compliance License Certificates Radiography Operation Planning Work Sheet
1.4 MONTHLY EXPOSURE REPORTS
Provide a Monthly Exposure Report for the previous month's work and submit to the Government not later than the fifth calendar day of each month.
This report is a compilation of employee-hours worked each month for all site workers, both Prime and subcontractor. Use the RMS CM module described in SECTION 01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM) to prepare the report. Failure to submit the report may result in retention of up to 10 percent of the voucher.
1.5 REGULATORY REQUIREMENTS
In addition to the detailed requirements included in the provisions of this Contract, comply with the most recent edition of USACE EM 385-1-1, and the following federal, state, and local laws, ordinances, criteria, rules and regulations. Submit matters of interpretation of standards to the appropriate administrative agency for resolution before starting work.
Where the requirements of this specification, applicable laws, criteria, ordinances, regulations, and referenced documents vary, the most stringent requirements govern.
1.6 SITE QUALIFICATIONS, DUTIES, AND MEETINGS
1.6.1 Personnel Qualifications
1.6.1.1 Site Safety and Health Officer (SSHO)
Provide an SSHO that meets the requirements of EM 385-1-1 Section 1. The SSHO will ensure that the requirements of 29 CFR 1926.16 are met for the project. Provide a Safety oversight team that includes a minimum of one
(1) person at each project site to function as the Site Safety and Health Officer (SSHO). The SSHO or an equally-qualified Alternate SSHO will be at the work site at all times to implement and administer the Contractor's safety program and government-accepted Accident Prevention Plan. The SSHO and Alternate SSHO will have the required training, experience, and qualifications in accordance with EM 385-1-1 Section 01.A.17, and all associated sub-paragraphs. The SSHO and Alternate SSHO may not have other collateral duties.
If the SSHO is off-site for a period longer than 24 hours, an equally-qualified alternate SSHO will be provided and will fulfill the same roles and responsibilities as the primary SSHO.
SECTION 01 35 26.01 45 Page 8
1.6.1.2 Contractor Quality Control (QC) Manager:
The Contractor Quality Control Manager cannot be the SSHO on this project, even though the QC has safety inspection responsibilities as part of the QC duties.
1.6.1.3 Competent Person Qualifications
Provide Competent Persons in accordance with EM 385-1-1, Appendix Q and herein. Competent Persons for high risk activities include confined space, cranes and rigging, excavation/trenching, fall protection, and electrical work. The CP for these activities will be designated in writing, and meet the requirements for the specific activity (i.e. competent person, fall protection).
The Competent Person identified in the Contractor's Safety and Health Program and accepted Accident Prevention Plan, will be on-site at all times when the work that presents the hazards associated with their professional expertise is being performed. Provide the credentials of the Competent Persons(s) to the the Contracting Officer for information in consultation with the Safety Office.
1.6.1.3.1 Competent Person for Confined Space Entry
Provide a Confined Space (CP) Competent Person who meets the requirements of EM 385-1-1, Appendix Q, and herein. The CP for Confined Space Entry will supervise the entry into each confined space.
1.6.1.4 Dredging Contract Requirements
1.6.1.4.1 Dredging Safety Personnel Requirements
a. Provide a minimum of one full time SSHO assigned per project site for the primary working shift.
b. For a project involving multiple work shifts, provide one full-time SSHO for each additional shift.
c. An example of one dredging project site is reflected in each of the following:
(1) a mechanical dredge, tug(s) and scow(s), scow route, and material placement site; or
(2) a hydraulic pipeline dredge, attendant plant, and material placement site; or,
(3) a hopper dredge (include land-based material placement site - if applicable.)
1.6.1.4.2 SSHO Requirements for Dredging
a. In addition to requirements stated elsewhere in this specification, an individual serving as a SSHO will be present at the project site, located so that they have full mobility and reasonable access to all major work operations, for at least one shift in each 24 hour period when work is being performed. The SSHO will be available during their shift for immediate verbal consultation and notification, either by phone or radio.
SECTION 01 35 26.01 45 Page 9
b. The SSHO is a full-time, dedicated position, except as noted above, who will report to a senior project (or corporate) official. When the SSHO is permitted to be a collateral duty, the SSHO is not permitted to be in another position requiring continuous mechanical or equipment operations, such as equipment operators.
c. The SSHO will inspect all work areas and operations during initial set-up and at least monthly observe and provide personal oversight on each shift during dredging operations for projects with many work sites, more often for those with less work sites.
d. If the SSHO is off-site for a period longer than 24 hours, another qualified SSHO will be provided and fulfill the same roles and responsibilities as the SSHO during their absence.
1.6.1.4.3 Safety Personnel Training Requirements for Dredging
A SSHO for dredging contracts will take either a formal classroom or online OSHA 30-hour Construction Safety Course, or an equivalent 30 hours of formal classroom or online safety and health training covering the subjects of the OSHA 30-hour Course in accordance with EM 385-1-1 Appendix A, paragraph 3.d.(3), applicable to dredging work, and given by qualified instructors. In exception to EM 385-1-1, Section 01.A.17, comply with the following:
a. The SSHO will maintain competency through having taken 8 hours of formal classroom or online safety and health related coursework every year. Hours spent as an instructor in such courses will be considered the same as attending them, but each course only gets credit once (for example, instructing a 1-hour asbestos awareness course 5 times in a year provides one hour credit for training).
b. The SSHO will have a minimum of three years of experience within the past five years in one of the following:
(1) Supervising/managing dredging activities
(2) Supervising/managing marine construction activities
(3) Supervising/managing land-based construction activities
(4) Work managing safety programs or processes
(5) Conducting hazard analyses and developing controls in activities or environments with similar hazards
1.6.1.5 Crane Operators/Riggers
Provide Operators meeting the requirements in EM 385-1-1, Section 15.B for Riggers and Section 16.B options 1 or 4 for Crane Operators.
1.6.2 Personnel Duties
1.6.2.1 Duties of the Site Safety and Health Officer (SSHO)
The SSHO will:
a. Conduct daily safety and health inspections and maintain a written log
SECTION 01 35 26.01 45 Page 10 which includes area/operation inspected, date of inspection, identified hazards, recommended corrective actions, estimated and actual dates of corrections. Attach safety inspection logs to the Contractors' daily production report.
b. Conduct mishap investigations and complete required accident reports.
Report mishaps and near misses.
c. Use and maintain OSHA's Form 300 to log work-related injuries and illnesses occurring on the project site for Prime Contractors and subcontractors, and make available to the Contracting Officer upon request. Post and maintain the Form 300A on the site Safety Bulletin Board.
d. Maintain applicable safety reference material on the job site.
e. Attend the pre-construction conference, pre-work meetings including preparatory meetings, and periodic in-progress meetings.
f. Review the APP and AHAs for compliance with EM 385-1-1, and approve, sign, implement and enforce them.
g. Establish a Safety and Occupational Health (SOH) Deficiency Tracking System that lists and monitors outstanding deficiencies until resolution.
h. Ensure subcontractor compliance with safety and health requirements.
i. Maintain a list of hazardous chemicals on site and their material Safety Data Sheets (SDS).
j. Maintain a weekly list of high hazard activities involving energy, equipment, excavation, entry into confined space, and elevation, and be prepared to discuss details during QC Meetings.
k. Provide and keep a record of site safety orientation and indoctrination for Contractor employees, subcontractor employees, and site visitors.
Superintendent, QC Manager, and SSHO are subject to dismissal if the above duties are not being effectively carried out. If Superintendent, QC Manager, or SSHO are dismissed, project work will be stopped and will not be allowed to resume until a suitable replacement is approved and the above duties are again being effectively carried out.
1.6.3 Meetings
1.6.3.1 Preconstruction Conference
a. Contractor representatives who have a responsibility or significant role in accident prevention on the project will attend the preconstruction conference. This includes the project superintendent, Site Safety and Occupational Health officer, quality control manager, or any other assigned safety and health professionals who participated in the development of the APP (including the Activity Hazard Analyses (AHAs) and special plans, program and procedures associated with it).
b. Discuss the details of the submitted APP to include incorporated plans, programs, procedures and a listing of anticipated AHAs that will be developed and implemented during the performance of the contract. This
SECTION 01 35 26.01 45 Page 11 list of proposed AHAs will be reviewed at the conference and an agreement will be reached between the Contractor and the Contracting Officer as to which phases will require an analysis. In addition, establish a schedule for the preparation, submittal, and Government review of AHAs to preclude project delays.
c. Deficiencies in the submitted APP, identified during the Contracting Officer's review, will be corrected, and the APP re-submitted for review prior to the start of construction. Work is not permitted to begin work until an APP is established that is acceptable to the Contracting Officer.
1.6.3.2 Safety Meetings
Conduct safety meetings to review past activities, plan for new or changed operations, review pertinent aspects of appropriate AHA (by trade), establish safe working procedures for anticipated hazards, and provide pertinent Safety and Occupational Health (SOH) training and motivation.
Conduct meetings at least once a month for all supervisors on the project location. The SSHO, supervisors, or foremen, will conduct meetings at least once a week for the trade workers. Document meeting minutes to include the date, persons in attendance, subjects discussed, and names of individual(s) who conducted the meeting. Maintain documentation on-site and furnish copies to the Contracting Officer on request. Notify the Contracting Officer of all scheduled meetings 7 calendar days in advance.
1.7 ACCIDENT PREVENTION PLAN (APP)
A qualified person will prepare the written site-specific APP. Prepare the APP in accordance with the format and requirements of EM 385-1-1, Appendix A, and as supplemented herein. Cover all paragraph and subparagraph elements in EM 385-1-1, Appendix A. The APP will be job-specific and address any unusual or unique aspects of the project or activity for which it is written. The APP will interface with the Contractor's overall safety and health program referenced in the APP in the applicable APP element, and made site-specific. Describe the methods to evaluate past safety performance of potential subcontractors in the selection process. Also, describe innovative methods used to ensure and monitor safe work practices of subcontractors. The Government considers the Prime Contractor to be the "controlling authority" for all work site safety and health of the subcontractors. Contractors are responsible for informing their subcontractors of the safety provisions under the terms of the contract and the penalties for noncompliance, coordinating the work to prevent one craft from interfering with or creating hazardous working conditions for other crafts, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out. The APP will be signed by an officer of the firm (Prime Contractor senior person), the individual preparing the APP, the on-site superintendent, the designated SSHO, the Contractor Quality Control Manager, and any designated Certified Safety Professional (CSP) or Certified Health Physicist (CIH). The SSHO will provide and maintain the APP and a log of signatures by each subcontractor foreman, attesting that they have read and understand the APP, and make the APP and log available on-site to the Contracting Officer. If English is not the foreman's primary language, the Prime Contractor will provide an interpreter.
Submit the APP to the Contracting Officer no later than 15 calendar days after award for acceptance. Work cannot proceed without an accepted APP.
Once reviewed and accepted by the Contracting Officer, the APP and
SECTION 01 35 26.01 45 Page 12 attachments will be enforced as part of the contract. Disregarding the provisions of this Contract or the accepted APP is cause for stopping of work, at the discretion of the Contracting Officer, until the matter has been rectified. Continuously review and amend the APP, as necessary, throughout the life of the contract.