Amend-0002_W9126G17B0014.pdf

PDF 224 KB Posted

Attached to
Houston Ship Channel, Alexander Island Placement Area Dewatering in Harris County, Texas
Solicitation number
W9126G-17-B-0014
Issued by

About this file

Amendment No. 0002

View the file

Other files

File Type Posted
Amend-0001-W9126G17B0014.pdf PDF
W9126G17B0014-PLANS.pdf PDF
W9126G17B0014-SPECS.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W45VAK63273583 007780

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Unrestricted Procurement for Houston Ship Channel, Alexander Island Placement Area in Harris County, Texas, Dew atering in w hich bid opening is schedule for 21 Aug 17 @ 2:00 PM (CST) is hereby amended as follow s:

Continued on Page 2.

1. CONTRACT ID CODE PAGE OF PAGES

J 1

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X 9A. AMENDMENT OF SOLICITATION NO.

W9126G17B0014

X 9B. DATED (SEE ITEM 11)

07-Jul-2017

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

07-Aug-2017

CODE

US ARMY CORPS OF ENGINEERS FORT WORTH

2000 FORT POINT ROAD

GALVESTON TX 77550-1229

W9126G 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

M3ODXMAN

Text Box

W9126G17B0014

A0002-2

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

1. The specifications for Solicitation No. W9126G17B0014, Houston Ship Channel, Texas, Alexander Island Placement Area in Harris County, Texas, Dewatering, are hereby amended as follows:

a) Specifications.

(1) SECTION 00 11 00.00 45, BID SCHEDULE – The enclosed SECTION 00 11 00.00 45, entitled BID SCHEDULE, supersedes that issued with this Solicitation.

(2) SECTION 01 00 50, SCOPE OF WORK – The enclosed SECTION 01 00 50, entitled SCOPE OF WORK, supersedes that issued with this Solicitation.

b) Drawings.

(1) None.

2. This amendment shall be attached to and become a part of the solicitation.

2 Encls:

1. SECTION 00 11 00.00 45, BID SCHEDULE

2. SECTION 01 00 50, SCOPE OF WORK

SWG FILE NO.:HSC 401-560 SOLICITATION NO.:W9126G17B0014

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SECTION 00 11 00.00 45

BID SCHEDULE

PART 1 GENERAL

1.1 BID SCHEDULE

1.1.1 Schedule No. 1

1.2 MODIFICATIONS (CESWG)

-- End of Section Table of Contents --

DOCUMENT 00 11 00.00 45 Page 1

(TO ACCOMPANY AMENDMENT NO. 0002 TO SOLICITATION NO. W9126G17B0014)

SECTION 00 11 00.00 45

BID SCHEDULE

AMENDMENT NO. 0001

PART 1 GENERAL

1.1 BID SCHEDULE

(TO BE ATTACHED TO STANDARD FORM 1442)

1.1.1 Schedule No. 1

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

SCHEDULE NO. 1

0001 Mobilization and Demobilization

1 JOB SUM $___________

0002 Condition Survey

1 JOB SUM $___________

0003 Perimeter Ditching` 17,815 L.F. $_________ $___________

0004 Lateral Ditching 38,171 L.F. $_________ $___________

TOTAL SCHEDULE NO. 1 $___________

NOTE: Completion time stated in SECTION 00 73 00.00 45 SPECIAL CONTRACT REQUIREMENTS, STANDARD is for Schedule No. 1 work. The Government may delay issuance of the Notice to Proceed up to 60 days after award.

DOCUMENT 00 11 00.00 45 Page 2

1.2 MODIFICATIONS (CESWG)

If a modification to a bid based on unit prices is submitted, which provides for a lump sum adjustment to the total estimated cost, the application of the lump sum adjustment of each unit price in the bid schedule must be stated. If it is not stated, the bidder agrees that the lump sum adjustment shall be applied on a pro rata basis to every unit price in the bid schedule.

-- End of Document --

DOCUMENT 00 11 00.00 45 Page 3

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 00 50

SCOPE OF WORK

PART 1 GENERAL

1.1 PROJECT TITLE AND LOCATION

1.2 Existing Conditions

1.3 SCOPE OF WORK

1.3.1 General

1.4 SUBMITTALS

1.5 PERIOD OF PERFORMANCE

1.6 SAFETY

1.7 CLOSEOUT SUBMITTALS

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION (Not Used)

-- End of Section Table of Contents --

SECTION 01 00 50 Page 1

SECTION 01 00 50

SCOPE OF WORK

AMENDMENT NO. 0001

PART 1 GENERAL

1.1 PROJECT TITLE AND LOCATION

Houston Ship Channel, Alexander Island Placement Area Dewatering, in Harris County, Texas

Alexander Island Placement Area is an upland confined placement area adjacent to the Houston Ship Channel. The approximate center of the placement area is latitude 29°43'3.29"N; longitude 95° 2'3.18"W.

1.2 Existing Conditions

Surface water may exist throughout the Alexander Island Placement Area.

1.3 SCOPE OF WORK

1.3.1 General

The work includes excavation to construct perimeter and lateral drainage ditches within the placement area to drain standing and subsurface water to two (2) existing drop outlet structures. The purpose of dewatering is to consolidate dredged material placed within the site. Dredged material was last placed into the site in June 2017. (AM#1)However, non-governmental entities may place approximately 210,000 cubic yards of dredged maintenance material prior to issuance of Notice to Proceed. The Government may delay Notice to Proceed up to 60 days from award date to allow for the completion of above-mentioned dredging operations. Due to the soft conditions of the dredge material within the worksite footprint, the Contractor should expect the sides of the newly dug ditches to slough as work proceeds and shall excavate as necessary to maintain constant drainage and ultimate acceptance of the ditches. These ditches shall be constructed to the lines and grades as shown. After completing the work, the Contractor shall conduct a condition survey of the entire site.

While excavating ditches, the Contractor shall avoid pipeline easements to every extent allowable. Contractor shall not disturb avoidance areas indicated on the drawings.

1.4 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:

1.5 PERIOD OF PERFORMANCE

The period of performance shall be in accordance with the SECTION

SECTION 01 00 50 Page 2

00 73 00.00 45 NON-REGULATED SPECIAL CONTRACT REQUIREMENTS, Paragraph:

COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK.

1.6 SAFETY

Complete the work in accordance with the safety requirements of SECTION

01 35 26.01 45 GOVERNMENTAL SAFETY REQUIREMENTS.

1.7 CLOSEOUT SUBMITTALS

Complete the work in accordance with the requirements of SECTION 02 21 00.00 45 paragraph 1.2; SD-11 Closeout Submittals.

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION (Not Used)

-- End of Section --

SECTION 01 00 50 Page 3

SF-30_Amend-0002-W9126G17B0014
Amend 0002 page-2
00 11 00.00 45
00 11 00.00 45 - BID SCHEDULE
00 11 00.00 45 - BID SCHEDULE
PART 1 GENERAL
1.1 BID SCHEDULE
1.1.1 Schedule No. 1

1.2 MODIFICATIONS CESWG

01 00 50
01 00 50 - SCOPE OF WORK
01 00 50 - SCOPE OF WORK
PART 1 GENERAL
1.1 PROJECT TITLE AND LOCATION
1.2 Existing Conditions
1.3 SCOPE OF WORK
1.3.1 General
1.4 SUBMITTALS
1.5 PERIOD OF PERFORMANCE
1.6 SAFETY
1.7 CLOSEOUT SUBMITTALS
PART 2 PRODUCTS Not Used
PART 3 EXECUTION Not Used

File details come from the government source that posted it. Updated .