W45VAK61389836 018130
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Unrestricted Procurement - Texas City Ship Channel, Texas, Main Channel and Turning Basin in Galveston County, Texas, Pipeline Dredging is hereby amended as follow s:
Continued on Page 2.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9126G-17-B-0001
X 9B. DATED (SEE ITEM 11)
02-Dec-2016
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
30-Mar-2017
CODE
US ARMY CORPS OF ENGINEERS FORT WORTH
2000 FORT POINT ROAD
GALVESTON TX 77550-1229
W9126G 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9126G-17-B-0001
A0004-2
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
1. The specifications for Solicitation No. W9126G-17-B-0001, Texas City Ship Channel, Texas, Main Channel And Turning Basin In Galveston County, Texas, Pipeline Dredging, are hereby amended as follows:
THE REQUIRED RESPONSE DATE/TIME HAS CHANGED FROM 06 APRIL 2017 2:00 PM
TO 17 MAY 2017 2:00 PM CST
a) Specifications.
(1) SECTION 35 20 23.16 45, PIPELINE DREDGING – The enclosed SECTION 35 20 23.16
45, entitled PIPELINE DREDGING, supersedes that issued with this Solicitation
(2) APPENDICES NOS. 2, 3, AND 4 – The enclosed Appendices Nos. 2, 3, and 4, containing grain size summaries, are added to this Solicitation.
b) Drawings.
(1) DRAWING NOS. 3, 4, AND 14 – The enclosed Drawing Nos. 3, 4, and 14, supersede that issued with this Solicitation.
(2) APPENDIX 5 – The enclosed Exhibits extracted from “WIIN_WRDA 2016 Section 1312” are included FOR INFORMATION ONLY.
2. This amendment shall be attached to and become a part of the solicitation.
4 Encls:
1. SECTION 35 20 23.16 45, PIPELINE DREDGING
2. APPENDICES 2, 3, AND 4
3. DRAWING NOS. 3, 4, and 14
4. APPENDIX 5
SWG FILE NO.:GALV 308-383 SOLICITATION NO.:W9126G-17-B-0001
SECTION TABLE OF CONTENTS
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
SECTION 35 20 23.16 45
PIPELINE DREDGING
PART 1 GENERAL
1.1 SUMMARY
1.2 MEASUREMENT AND PAYMENT
1.3 WORK COVERED BY CONTRACT PRICE
1.3.1 Existing Conditions
1.4 REFERENCES
1.5 SUBMITTALS
1.6 CHARACTER OF MATERIAL
1.6.1 Debris Within the Dredging Limits
1.7 EASEMENTS
1.8 UTILITIES ACROSS THE LIMITS OF DREDGING
1.8.1 Known Pipeline/Utility Crossings
1.9 ORDER OF WORK
1.10 OBSTRUCTION OF CHANNEL
1.11 TEMPORARY REMOVAL OF AIDS TO NAVIGATION
1.12 NOTIFICATION PRIOR TO COMMENCEMENT OF DREDGING OPERATIONS
1.13 SIGNAL LIGHTS
1.14 PLANT
1.14.1 General Requirements
1.14.2 Capacity
1.14.3 Inspectors (Government Agents) Transportation
PART 2 PRODUCTS
2.1 BRIDGE-TO-BRIDGE RADIOTELEPHONE EQUIPMENT
2.2 LOOKOUTS AND RADIO COMMUNICATIONS
PART 3 EXECUTION
3.1 ESTIMATED QUANTITY OF MATERIAL
3.1.1 Quantity Summary
3.1.2 Required Dredging Prism
3.1.3 Allowable Overdepth
3.1.4 Side And End Slopes
3.1.5 Excessive Dredging
3.2 AREAS TO BE DREDGED
3.3 CONDUCT OF DREDGING WORK
3.3.1 Pre-Operations Safety Coordination Meeting
3.3.2 Protection of Existing Waterways
3.3.3 Adjacent Property and Structures
3.4 PLACEMENT OF EXCAVATED MATERIAL
3.4.1 General
3.4.1.1 Misplaced Material
3.4.1.2 Placement Operations Inspection
3.4.1.3 Placement Area Drainage
3.4.1.4 Maintenance of Existing Levees and Drop-outlet Structures
3.4.2 Spillway Operations
SECTION 35 20 23.16 45 Page 1
(TO ACCOMPANY AMENDMENT 0004 TO SOLICITATION NO. W9126G-17-B-0001)
3.4.3 Placement Areas
3.4.3.1 Shoal Point Placement Area (SPPA) 3, 4, 5
3.4.3.2 (AM#4)Shoal Point Placement Area (SPPA) 2
3.4.3.3 (AM#3)Confined Placement Area No. 5/6
3.5 PRESERVATION OF PUBLIC AND PRIVATE PROPERTY
3.5.1 Damages
3.5.2 Accountability and Restoration
3.6 ALTERNATE PLACEMENT AREA(S) PROPOSED BY CONTRACTOR WITH BID AFTER
AWARD OF CONTRACT
3.6.1 Data Submittal
3.7 METHOD OF PLACEMENT
3.7.1 Pipeline Route
3.8 DISPOSAL IN PLACEMENT AREA
3.8.1 Utilities within the Placement Area
3.8.2 Unauthorized Placement of Material
3.8.3 Debris Disposal
3.9 DREDGE PIPELINES
3.9.1 Submerged Pipeline
3.9.2 Submerged Pipeline Lighting Requirements
3.9.3 Floating Pipeline
3.9.4 Pipeline Leaks
3.9.5 Magnetometer Survey Report
3.10 HOUSTON-GALVESTON VESSEL TRAFFIC SERVICE AREA
3.10.1 General
3.10.2 Report Changes
3.10.3 Vessel Traffic Service Location
3.10.4 Communications
3.10.5 Operations
3.11 WORK IN THE VICINITY OF OTHER GOVERNMENT CONTRACTORS
3.12 DREDGING AND DREDGE RELATED MARINE WORK (CESWG)
3.13 AUTOMATIC IDENTIFICATION SYSTEM
3.14 DREDGE PLANT INSTRUMENTATION
ATTACHMENTS:
Appendix 1 - QUANTITY SUMMARY TABLE
Appendix 1 - QUANTITY SUMMARY TABLE
-- End of Section Table of Contents --
SECTION 35 20 23.16 45 Page 2
SECTION 35 20 23.16 45
PIPELINE DREDGING
AMENDMENT NO. 0004
PART 1 GENERAL
1.1 SUMMARY
The work in this Section consists of furnishing plant, labor, materials, and equipment and performing the operations necessary for the removal of materials to the required dimensions shown, satisfactory disposal thereof, and other operations incidental thereto.
1.2 MEASUREMENT AND PAYMENT
Measurement and payment for pipeline dredging will be paid for in accordance with provisions of the SECTION 01 22 00.10 MEASUREMENT AND
PAYMENT.
1.3 WORK COVERED BY CONTRACT PRICE
Base bids on the quantity of dredging indicated. If the total quantity of dredging varies from that specified as the basis for bidding, the Contract price will be adjusted in accordance with the CONTRACT CLAUSE entitled CHANGES. The dredging conditions specified and indicated describe conditions which are known. However, the Contractor is responsible for other conditions encountered which are not unusual when compared to the conditions recognized in the dredging business as usual in dredging activities such as those required under this Contract. The Contract price for dredging will include the cost of removal and placement of the material as specified in the Paragraphs: CHARACTER OF MATERIAL and PLACEMENT OF EXCAVATED MATERIAL. The Contract price for dredging shall include the costs for maintenance of levees and ditches necessary to confine the material within the areas shown.
1.3.1 Existing Conditions
The drawings already prepared as specified in the CONTRACT CLAUSES Paragraph entitled CONTRACT DRAWINGS AND SPECIFICATIONS represent conditions existing as of the date of their preparation using average existing conditions. However, to reflect anticipated shoaling occurring between the dates of preparation of the drawings and the dates of the "before-dredging" sections, the estimated dredging quantities stated in the Bid Schedule have been adjusted accordingly. The depths and elevations shown will be verified and corrected by fathometer soundings taken by the Government before dredging. The Government will normally use a frequency of 200 kHz to conduct hydrographic surveys. If the surveys indicate the presence of fluff in the channel, a frequency of 40 kHz will be used.
Determination of quantities removed and the deductions made from them to determine quantities by in-place measurement to be paid for in the area specified, after having once been made will not be reopened, except on evidence of collusion, fraud, or obvious error.
SECTION 35 20 23.16 45 Page 3
1.4 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 1110-2-5027 (1987) Confined Disposal of Dredged Material
EM 385-1-1 (2014) Safety and Health Requirements Manual
1.5 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with the SECTION 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Notification Prior To Commencement of Dredging Operations; G
Indicate commencement of dredging operations, and location of dredge(s).
Temporary Removal of Aids To Navigation; G, AO
SD-02 Shop Drawings
Submerged Pipeline; G, AO
Indicate pipeline location and installation details as outlined in the Subparagraph: Submerged Dredge Pipeline.
Pipeline Route; G, AO
A detailed pipeline diagram for each Placement Area detailing the pipeline route and anchor locations shall be submitted prior to commencing work on this project.
SD-06 Test Reports
Magnetometer Survey Report; G
Report shall be submitted as specified.
1.6 CHARACTER OF MATERIAL
The material to be removed is shoals which have accumulated over a period of time. However, some virgin material may be encountered in allowable overdepth, or side slope dredging. Bidders are expected to examine the worksite and the records of previous dredging, which are available in the Galveston Resident Office and after investigation decide for themselves the character of materials.
SECTION 35 20 23.16 45 Page 4
1.6.1 Debris Within the Dredging Limits
Debris including but not limited to, metal bands, pallets, pieces of broken cable, rope, stumps, and broken piles may be encountered. The Government has no knowledge of existing wrecks, wreckage, or other material of that size or character as to require the use of explosives or special or additional plant for its economical removal. Debris removed from the dredged area shall be removed from the water. Disposal shall be the responsibility of the Contractor and disposal shall be outside the limits of Government property. If the actual conditions differ from those stated or shown, an adjustment in Contract price or time of completion, or both, will be made in accordance with the CONTRACT CLAUSE entitled DIFFERING SITE
CONDITIONS.
1.7 EASEMENTS
Permits authorizing the laying of shore pipe, and for placement of dredge material in the Placement Area(s), are on file and available for examination in the Galveston Resident Office of the U.S. Army Corps of Engineers, Jadwin Building, 2000 Fort Point Road, Galveston, Texas. The instruments authorizing the laying of shore pipelines may contain certain restrictions relative to specific route, location, and general use of the land. These instruments form a part of these specifications and the Contractor shall strictly comply with the terms thereof.
1.8 UTILITIES ACROSS THE LIMITS OF DREDGING
It is the Contractor's responsibility to investigate the location of utility crossings. The Contractor shall take precautions against damages which can result from dredging operations in the vicinity of the utility crossings. If damage occurs as a result of dredging operations, the Contractor will be required to suspend dredging until the damage is repaired and approved. Costs of these repairs and downtime of the dredge and attendant plant shall be at the Contractor's expense.
1.8.1 Known Pipeline/Utility Crossings
There are pipelines and or utilities which are within the work limits. The following pipeline/utilities cross the area(s) to be dredged:
Approximate Station
Permit No. Description Owner
13+600 T.C.C. 22929 One 24-inch pipeline
Manta Ray Gathering, Co.
EVERY EFFORT HAS BEEN MADE TO GIVE ALL PERTINENT DETAILS ON THE LOCATION OF
PIPELINES/UTILITIES. THE DATA FURNISHED ON THE PLANS ARE BELIEVED TO BE
SUBSTANTIALLY CORRECT. HOWEVER, THE EXACT LOCATIONS MAY VARY FROM THAT
SHOWN: THEREFORE THE CONTRACTOR SHALL COOPERATE WITH THE RESPECTIVE OWNERS
TO ESTABLISH THE ACTUAL POSITION OF THE PIPELINES/UTILITIES. THE U.S. ARMY
CORPS OF ENGINEERS PERMITS OF THE RESPECTIVE PIPELINES AND PREVIOUS SURVEYS
ARE AVAILABLE IN THE GALVESTON RESIDENT OFFICE.
THE FOLLOWING IS FURNISHED FOR INFORMATION ON VERIFYING PIPELINE OWNERSHIPS:
Lonestar Notification Center 1-713-223-4567 or 1-800-669-8344
SECTION 35 20 23.16 45 Page 5
Texas 811 (Dig-Tess) 1-800-344-8377
1.9 ORDER OF WORK
The Contractor may commence dredging in the order desired. The Government reserves the right to change the order of work at any time.
1.10 OBSTRUCTION OF CHANNEL
The Government will not undertake to keep the Channel free from vessels or other obstructions, except to the extent of applicable regulations, if any, as may be prescribed by the Secretary of the Army, in accordance with the provisions of Section 7 of the River and Harbor Act approved 8 August 1917. The Contractor will be required to conduct the work using a method that will obstruct navigation as little as possible, and if the Contractor's plant does obstruct the Channel and makes passage of vessels difficult or endangers them, the plant shall be promptly moved on the approach of a vessel as far as may be necessary to afford a practicable passage.Upon completion of the work, the Contractor shall promptly remove its plant, including ranges, buoys, piles, and other marks placed under this Contract.
1.11 TEMPORARY REMOVAL OF AIDS TO NAVIGATION
The temporary removal or changes in locations of channel markers may be required to facilitate dredging operations. The Contractor shall notify the Contracting Officer at least 21days prior to the date that the removal or change in location of channel markers will be required so the U.S. Coast Guard can perform the work and so navigation interests may be informed sufficiently in advance of the proposed removal or change in location.
The Contractor shall not remove, change the location of, obstruct, willfully damage, make fast to, or interfere with aids to navigation.
Indicate temporary removal or changes in locations of channel markers required to facilitate dredging operations.
1.12 NOTIFICATION PRIOR TO COMMENCEMENT OF DREDGING OPERATIONS
Notify the Galveston Resident Office, in writing, at least 10 days prior to commencement of dredging operations, the location or locations at which a dredge or dredges will be placed on the work. This information is required in addition to the progress charts and schedule provided for in the CONTRACT CLAUSE entitled SCHEDULE FOR CONSTRUCTION CONTRACTS.
1.13 SIGNAL LIGHTS
Display signal lights and conduct operations in accordance with the General Regulations of the Department of the Army and of the Coast Guard governing lights and day signals to be displayed by towing vessels with tows on which no signals can be displayed, vessels working on wrecks, dredged, and vessels engaged in laying cables or pipe or in submarine or bank protection operations, lights to be displayed on dredge pipelines, and day signals to be displayed by vessels of more than 65 feet in length moored or anchored in the fairway or channel, and the passing of other vessels of floating plant working in navigable channels, as set forth in Commandant U.S. Coast Guard Instruction M16672.2, Navigation Rules: International-Inland (COMDTINST M16672.2), or 33 CFR 81 Appendix A (International) and 33 CFR 84
SECTION 35 20 23.16 45 Page 6 through 33 CFR 89 (Inland) as applicable. Navigation Center website location http://www.navcen.uscg.gov/?pageName=navRuleChanges.
1.14 PLANT
1.14.1 General Requirements
Keep the necessary dredge equipment and attendant plant on the job to meet the requirements of the work. The dredge equipment and attendant plant shall be in satisfactory operating condition and capable of safely and efficiently performing the work as set forth in specifications and shall be subject to inspection by the Contracting Officer's representative at all times.
1.14.2 Capacity
No reduction in the capacity of the dredge equipment and attendant plant employed to execute the work shall be made except by written direction of the Contracting Officer. The measure of the "Capacity of the Dredge and Attendant Plant" shall be its actual performance on the work to which these specifications apply.
1.14.3 Inspectors (Government Agents) Transportation
Furnish throughout the Contract period, for the exclusive use of the Government: a motorboat, minimum 18 feet in length, with enclosed cabin, a minimum of a 50 horsepower motor and equipped with safety equipment as required by EM 385-1-1. Furnish fuel, oil, and maintenance for the motorboat throughout the Contract period. Assume full responsibility for the storage and security of the motorboat when not in use by the Government employees. There shall be no separate payment for these items and the cost shall be distributed throughout the existing bid items. Equipment which fails to perform because of insufficient power or other mechanical deficiencies shall be replaced and inexperienced operators unable to operate the equipment shall be replaced within 12 hours after the Contractor is directed to do. No smoking shall be allowed inside the cabin and operator's space while occupied by Government personnel. No Smoking signs shall be posted.
PART 2 PRODUCTS
2.1 BRIDGE-TO-BRIDGE RADIOTELEPHONE EQUIPMENT
Dredge and self-propelled attendant floating plant shall be radiotelephone equipped to comply with the provisions of the Vessel Bridge-to-Bridge Radiotelephone Act (Public Law 92-63). This will require, as a minimum, the radiotelephone equipment capable of transmitting and receiving on
156.65 MHz (Channel 13). Multi-channel equipment will also require 156.8 MHz (Channel 16). Dredge tugs and tenders will be considered towing vessels within the meaning of the Act.
2.2 LOOKOUTS AND RADIO COMMUNICATIONS
When working in the Texas City Ship Channel and Texas City Turning Basin, the Contractor shall have a lookout person posted in the dredge control room at all times to visually monitor the movement of vessels around the dredge plant; to perform radio communications with company workboats; and to deliver passing arrangements with other commercial, fishing and recreational vessels. The lookout shall be competent in U.S. Coast Guard
SECTION 35 20 23.16 45 Page 7 and Federal Communications Commission radio communications procedures and requirements and shall be trained in the Vessel Bridge to Bridge Radiotelephone Act. The lookout shall maintain up to the minute information on the status of each company workboat and approaching vessels, and will communicate this information as required to prevent collisions.
Each company workboat shall check in with the lookout when arriving at the dredge and shall receive radio clearance from the lookout before departing the dredge.
FAILURE TO COMPLY WITH THIS REQUIREMENT WILL BE CONSIDERED A VIOLATION OF
THE SAFETY PROTOCOL ESTABLISHED HEREIN. PURSUANT TO THE DIRECTION OF THE
CONTRACTING OFFICER, THE CONTRACTOR MAY BE REQUIRED TO CEASE OPERATIONS
UNTIL THIS PROVISION IS COMPLIED WITH. A SUSPENSION, DELAY OR INTERRUPTION
OF WORK ARISING FROM NON-COMPLIANCE OF THIS PROVISION SHALL NOT CONSTITUTE
A BREACH OF THIS CONTRACT AND SHALL NOT ENTITLE THE CONTRACTOR TO A PRICE
ADJUSTMENT IN ACCORDANCE WITH THE CONTRACT CLAUSE ENTITLED SUSPENSION OF
WORK OR ANY OTHER PROVISION UNDER THIS CONTRACT.
PART 3 EXECUTION
3.1 ESTIMATED QUANTITY OF MATERIAL
Within the limits of available funds, the Contractor will be required to excavate the entire quantity of material necessary to complete the work specified whether the quantities involved are greater or less than those estimated. The work is to be done in accordance with this Contract and at the Contract price or prices, subject to the provisions of the SECTION 01 10 00.01 45 NON-REGULATED SPECIAL CONTRACT REQUIREMENTS, Paragraph entitled VARIATIONS IN ESTIMATED QUANTITIES - DREDGING.
3.1.1 Quantity Summary
The quantities listed in Appendix 1 - QUANTITY SUMMARY TABLE include the volumes present at the time of the surveys indicated on the Contract drawings, plus anticipated shoaling before dredging begins. For the purpose of acceptance, the pipeline dredging work in the Bid Item(s) of the Bidding Schedule are divided into Sections.
3.1.2 Required Dredging Prism
The total estimated amount of material to be removed from within the specified limits, including side and end slopes and including anticipated shoaling occurring prior to the dates of the "before-dredging" surveys but excluding overdepths, in cubic yards is listed in Appendix 1 - QUANTITY
SUMMARY TABLE.
3.1.3 Allowable Overdepth
To cover unavoidable inaccuracies of the dredging process, material actually removed from the designated areas to be dredged, will be measured and paid for at full Contract price. The maximum amount of allowable overdepth dredging is estimated, including anticipated shoaling occurring prior to the dates of the "before-dredging" surveys in cubic yards is listed in Appendix 1 - QUANTITY SUMMARY TABLE.
3.1.4 Side And End Slopes
Dredging of the side and end slopes shall follow, as closely as practicable, the lines indicated or specified. Material actually removed
SECTION 35 20 23.16 45 Page 8 from within the limits as approved, to provide for final side and end slopes as specified, but not in excess of the amounts originally above the limiting side and end slopes will be estimated and paid for, whether dredged in original position or by dredging the space below the pay slope plane at the bottom of the slope for upslope material capable of falling into the cut. In computing the limiting amount of side and end slope dredging, net dimensions, without allowance for overdepth, will be used.
3.1.5 Excessive Dredging
Material taken from beyond the limits specified will be deducted from the total amount dredged as excessive overdepth dredging or excessive side or end slope dredging, for which payment will not be made. Nothing herein shall be construed to prevent payment for the removal of shoals performed in accordance with the applicable provisions of the SECTION 01 10 00.01 45 NON-REGULATED SPECIAL CONTRACT REQUIREMENTS, Paragraph FINAL EXAMINATION AND ACCEPTANCE or Paragraph SHOALING.
3.2 AREAS TO BE DREDGED
Based on information currently available to the Government, areas known to require dredging are shown.
3.3 CONDUCT OF DREDGING WORK
3.3.1 Pre-Operations Safety Coordination Meeting
Prior to arrival on location and commencing dredge operations, the Contractor shall attend a pre-dredging safety coordination meeting between the dredge operators, pilots, towing industry representatives, VTS, and the affected port. It is the Contractor's responsibility to contact Houston Vessel Traffic Service (VTS) at 713-671-5103 to coordinate and schedule this meeting. Contractor shall inform the Government at least 48 hours prior to the scheduled meeting so that a Government Representative may attend.
3.3.2 Protection of Existing Waterways
Conduct dredging operations using a method that will ensure that material or other debris are not pushed outside of the dredging limits or otherwise deposited in existing side channels, basins, docking areas, or other areas being used by vessels. The Contractor will be required to change its method of operations as may be required to comply with the above requirements. If bottom material or other debris is pushed into areas noted above, as a result of the Contractor's operations, the same shall be promptly removed by and at the expense of the Contractor to the satisfaction of the Contracting Officer.
3.3.3 Adjacent Property and Structures
No dredging will be permitted within 25 feet of a structure. Damage to private or public property or structures resulting from the disposal or dredging operations shall be repaired promptly by and at the Contractor's expense. Damage to structures as a result of Contractor's negligence will result in suspension of dredging and require prompt repair at the Contractor's expense as a prerequisite to the resumption of dredging. Where dredging to obtain the required dimensions might endanger a structure, the Contracting Officer, upon request, may reduce the required excavation in the vicinity of this structure.
SECTION 35 20 23.16 45 Page 9
3.4 PLACEMENT OF EXCAVATED MATERIAL
3.4.1 General
Material excavated shall be transported to and deposited in the Placement Area designated. Inspect the Placement Area to ensure that using the Area for placement operations will not place it in violation of the applicable Federal, State, or local statutes concerning fish and wildlife. Particular statutes which the Contractor shall consider include, but are not limited to, the Federal Migratory Bird Treaty Act and the Endangered Species Act of 1973.
3.4.1.1 Misplaced Material
Material shall not be deposited or allowed to flow into project channels or into a bayou, stream tributary to the Channel, or into an existing drainage outlet ditch, canal, water intake or outlet facility, nor shall materials be allowed to flow onto improved areas including highways and roads in or adjacent to the Placement Area. If a stream, bayou drainage outlet, ditch, canal, water intake or outlet facility becomes shoaled as a result of the pipeline dredging or placement operations, promptly remove these shoals and the material shall be placed in the Placement Area. Dragging or washing operations to remove the shoals will not be permitted.
3.4.1.2 Placement Operations Inspection
Adequately inspect placement operations in the Placement Area(s) daily to reduce the possibility of accidental breaching of levees and spillway with resulting spillage of dredged materials outside the Area. If levee failures occur while materials are being pumped into the Placement Area, dredging operations shall be stopped immediately, and the deposit of material in the Area shall not be resumed until the confining structures have been restored to an approved condition. Holes dug on the banks for deadmen or anchorage shall be filled. Confined areas shall be maintained in an operational condition until completion and acceptance of the work under this Contract. The SECTION 01 10 00.01 45 NON-REGULATED SPECIAL CONTRACT REQUIREMENTS, Paragraph DAMAGE TO WORK is only applicable to damage of levees and other non-dredging items.
3.4.1.3 Placement Area Drainage
Deposited materials shall not impound water or impede natural drainage.
The Contractor shall, if necessary, excavate and maintain ditches to drain the low areas in the dredged material and Placement Area to the weirs. The ditches shall be of adequate number and size to eliminate ponding of water within the limits of the Placement Area.
3.4.1.4 Maintenance of Existing Levees and Drop-outlet Structures
The available information regarding the heights and dimensions of levees and dimensions and elevations of the drop-outlet structures are contained in these Contract documents; however, it is the responsibility of the Contractor to verify the current condition of the levees prior to commencement of dredging and to notify the Contracting Officer of slumped or failed areas where there appears to be a potential for failure or overtopping during ponding. The Contractor will have the responsibility of continually monitoring the levees condition and to maintain the levees in a condition and elevation equal to or better than the condition of the levees
SECTION 35 20 23.16 45 Page 10 at the date of this Contract award. The Contractor shall also construct temporary access from the existing roadway to each drop-outlet structure in each Placement Area.
3.4.2 Spillway Operations
Once placement operations are completed in a confined area for which the Placement Area is being used, the boards on the spillway of that Placement Area shall be removed at a proper rate to allow drainage of the Area. In confined areas, levee and spillway work required shall be completed and accepted prior to placement operations in that Area. Spillways shall be operated in general accordance with guidelines contained in the Engineering Manual EM 1110-2-5027 entitled "Confined Disposal of Dredged Material", to maintain uniformity of weir elevation around the drop-out structure, as is practicable, during discharge of effluent. Boards shall be uniform in width and of proper length so insertion and removal is not difficult.
Cracked, warped or boards of improper length shall be replaced. Seepage between boards during ponding shall be eliminated using plastic sheeting or other effective methods. Upon completion of discharge within a particular Area, the Contractor shall remove the boards as soon as practicable to accomplish drainage of the Area.
3.4.3 Placement Areas
Place dredge material from each section defined in Appendix 1 - QUANTITY SUMMARY TABLE into the appropriate Placement Area as follows:
3.4.3.1 Shoal Point Placement Area (SPPA) 3, 4, 5
Material dredged from Section Nos. 1-4 shall be deposited into the discharge points located in SPPA 3, 4, 5, as shown. The Contractor shall designate which dredging sections will be placed into each of the defined discharge points. All of the defined discharge points shall be used for this contract. The material shall be placed within 100 feet in any direction of the designated discharge points; however, the discharge point of the pipe may not be placed within 100 feet of the existing levee toe.
Placement of material shall be accomplished with a spreader to avoid any deep depressions and to allow quick settlement of the heavier materials.
Monitor and control the movement of the discharge point to ensure even build up of material. At no point shall the material placed into SPPA 3, 4, 5 exceed an elevation of +3.5 feet MLLW.
3.4.3.2 (AM#4)Shoal Point Placement Area (SPPA) 2
If Option No. 1 is exercised, material dredged from Section No. 5 shall be deposited into one of the discharge points located in SPPA 2, as shown.
Material dredged from Section No. 6 under Option No. 1Schedule No. 1 shall be deposited into the discharge points located in SPPA 2, as shown. The Contractor shall designate which dredging sections will be placed into each of the defined discharge points. All of the defined discharge points shall be used for this contract. The material shall be placed within 100 feet in any direction of the designated discharge points; however, the discharge point of the pipe may not be placed within 100 feet of the existing levee toe. Placement of material shall be accomplished with a spreader to avoid any deep depressions and to allow quick settlement of the heavier materials. Monitor and control the movement of the discharge point to ensure even build up of material. At no point shall the material placed into SPPA 2 3, 4, 5 exceed an elevation of +3.5 feet MLLW.
SECTION 35 20 23.16 45 Page 11
3.4.3.3 (AM#3)Confined Placement Area No. 5/6
If Option No. 2 is exercised, material dredged from Section Nos. 7, 8, and 9 shall be deposited into Confined Placement Area No. 5/6, as shown. The perimeter dike of Confined Placement Area No. 5/6 shall be maintained to the existing elevation and repaired as necessary for the duration of the contract. The Contractor shall monitor and control the movement of the discharge point to ensure even build-up of material throughout the discharge corridor. Contractor should be prepared to move discharge points if pool elevation in PA 5/6 rises to three feet below crest of dike.
3.5 PRESERVATION OF PUBLIC AND PRIVATE PROPERTY
3.5.1 Damages
Fences, roads, ditches, private or public grounds, and other structures or improvements damaged as a result of the Contractor's operations herein specified shall be repaired or rebuilt by and at the Contractor's expense.
The areas used by the Contractor in laying and maintaining pipelines shall be restored to the same or as good a condition as existed prior to commencement of the work. Upon completion of the work, the ends of culverts shall be fully closed with wooden bulkheads and trenches and bank cuts shall be backfilled to original ground level.
3.5.2 Accountability and Restoration
Preserve and protect the existing informational and directional signs, camp facilities, water wells and tanks, station markers, mile markers, and mooring piles which have been established along either bank of the Waterway within the reaches of the dredging operations covered herein. The Contractor shall be accountable for and will be required to replace or restore at its expense the signs, camp facilities, water wells and tanks, markers, and mooring piles damaged or destroyed as a result of dredging operations herein specified.
3.6 ALTERNATE PLACEMENT AREA(S) PROPOSED BY CONTRACTOR WITH BID AFTER AWARD
OF CONTRACT
If, after award of this Contract, placement area(s) other than those specified herein are proposed, their acceptance will be subject to approval. Furnish written permission from the owners for the use of the substitute placement area(s) and written permission from the owners of the properties involved in obtaining access to the substitute placement area(s). The Contractor shall coordinate the use of the substitute placement area(s) with Federal and State Natural Resource Agencies and shall submit, with its proposal, documentation that demonstrates compliance with the applicable laws and regulations pertinent to designation and coordination of dredged material placement area(s). The Galveston District shall be consulted for specific requirements. Expenses incurred in connection with providing and making available another placement area(s) shall be borne by the Contractor. Materials deposited thereon and operations in connection therewith shall be at the Contractor's risk.
3.6.1 Data Submittal
The award of the modification will be subject to the approval of the proposed Contractor-furnished Placement Area(s) and unless the foregoing required data are furnished with the Contractor's request, the modification for the use of the proposed substitute Placement Area(s) will not be
SECTION 35 20 23.16 45 Page 12 considered.
3.7 METHOD OF PLACEMENT
Deposit dredged material by the hydraulic process. Pipeline for hydraulic dredging shall discharge into the Placement Area as shown or indicated.
3.7.1 Pipeline Route
The dredge pipeline route to the Placement Area shall follow closely the location shown or approved. Detailed right-of-way drawings showing the location of the pipeline route(s) with respect to property lines are available for inspection at the Galveston Resident Office.
3.8 DISPOSAL IN PLACEMENT AREA
Dredged material shall be placed to the lines and grades shown and as specified in the SECTION 35 20 23.16 45. The order of work for construction is as specified in the SECTION 35 20 23.16 45.
3.8.1 Utilities within the Placement Area
Every effort has been made to give pertinent details of the location of utilities, pipelines, and other facilities which may be encountered in trenching or jacking operations. The Contractor shall investigate existing conditions and shall be satisfied that no additional construction which may interfere with dredge pipeline laying specified herein exists.
3.8.2 Unauthorized Placement of Material
Excavated material that is deposited elsewhere than in places designated or approved will not be paid for and the Contractor may be required to remove the misplaced excavated material and deposit it where directed at Contractor's expense.
3.8.3 Debris Disposal
During the progress of the work, the Contractor shall not deposit worn out discharge pipe, wire rope, scrap metal, timbers, or other rubbish or obstructive material in the Placement Area, or along the banks of the navigable waters, except as specified herein. This material, together with scrap rope, wire cable, piles, pipe, or other obstructive material which may be encountered during the dredging operations, shall be disposed by the Contractor at approved locations.
3.9 DREDGE PIPELINES
Plainly mark the pipeline access routes with conspicuous stakes, targets and buoys which shall be maintained throughout this Contract period. The pipeline shall be inspected at least twice daily for leaks. Reference the SECTION 01 35 26.01 45 GOVERNMENTAL SAFETY REQUIREMENTS for additional dredge pipeline safety requirements.
3.9.1 Submerged Pipeline
If the Contractor elects to use a submerged section in the dredge discharge pipeline for crossing a navigable channel it may do so without the formality of obtaining a Department of the Army permit for work or structures in navigable waters. The Contractor shall discuss the submerged
SECTION 35 20 23.16 45 Page 13 section of dredge pipeline during the pre-operations safety meeting.
Coordinate the submerged pipeline crossing(s) with the U.S. Coast Guard Marine Safety Office (MSO), U.S. Coast Guard Vessel Traffic Service (VTS), and the Houston Pilots Association (HPA). At least 5 days shall be allowed for comments and their comments shall be coordinated with the Contracting Officer. Concerns regarding impact to navigation will be considered and final resolution will be made by the Contractor, Contracting Officer, MSO, VTS, and HPA. The submittal of the detailed plans of the submerged pipeline section shall be submitted and approved prior to use of the submerged pipeline section. The plans shall indicate clearly the width and depth of the navigation opening and the method used to mark it by day and by night for the safety of navigation. The minimum bottom width of the submerged section shall not be less than 200-feet wide for channels whose authorized width is greater than 200 feet. The minimum bottom width of the submerged section for channels whose authorized width is less than 200 feet shall be the width of the authorized Federal Channel. The highest point on the pipe or ball connection occurring across the bottom width of a submerged section shall not be higher than the required depth of the channel. Submerged pipelines shall also be in accordance with SECTION 01
35 26.01 45 GOVERNMENTAL SAFETY REQUIREMENTS.
3.9.2 Submerged Pipeline Lighting Requirements
Lighted buoys, meeting the requirements of the U.S. Coast Guard Regulation 33 C.F.R. 62.25 Lateral marks, shall be provided by the Contractor to mark the navigation opening. A red buoy exhibiting a quick flashing red light shall be used to mark the right side of the opening and a black buoy exhibiting a quick flashing green light shall be used to mark the left side of the opening. The frequency of the flashes shall be not less than 60 per minute. "Right side" and "left side" of the opening shall be in conformance with the lateral system of buoyage established by the U.S.
Coast Guard. Requirements for lighted buoys and description of the lateral system of buoyage will be found in the U.S. Coast Guard Publication entitled "Aids to Navigation." Lights to be displayed on pipelines shall be in accordance with the U.S. Coast Guard Regulation 33 CFR 84 Annex 1:
Positioning and Technical Details of Lights and Shapes:
http://www.ecfr.gov/cgi-bin/text-idx?SID=af0fba13c030ab68deca2ccd17a 3493a&node=pt33.1.84&rgn=div5.
3.9.3 Floating Pipeline
If the Contractor's pipeline does not rest on the bottom, it will be considered a floating pipeline and shall be visible on the surface and clearly marked. The Contractor's pipeline shall not be allowed to fluctuate between the surface and, or lie partly submerged. Lights shall be installed on the floating pipeline as required in the Paragraph: SIGNAL LIGHTS. The lights shall be supported either by buoys or by temporary piling, provided by the Contractor and approved. Where the pipeline does not cross a navigable channel, the flashing yellow all-around lights shall be spaced not over 200 feet apart, unless closer spacing is required by U.S. Coast Guard personnel, in which case the requirements of the U.S.
Coast Guard shall govern, at no additional cost to the Government.
Floating pipelines shall also be in accordance with SECTION 01 35 26.01 45
GOVERNMENTAL SAFETY REQUIREMENTS.
3.9.4 Pipeline Leaks
If a leak occurs in the discharge pipeline, immediately discontinue using the line until leaks are repaired. The Contractor shall be responsible for
SECTION 35 20 23.16 45 Page 14 removing material placed due to leaks or breaks.
3.9.5 Magnetometer Survey Report
At the completion of dredging, perform magnetometer surveys to verify removal of all submerged pipeline. Surveys shall be taken over the length of the submerged pipeline route and at all channel crossings. The survey results shall be submitted in a magnetometer survey report along with a certification from the Contractor that all submerged pipeline and appurtenances have been located and removed.
3.10 HOUSTON-GALVESTON VESSEL TRAFFIC SERVICE AREA
Comply with the following requirements while operating within the Houston-Galveston Vessel Traffic Service (VTS) area.
3.10.1 General
When a dredge or floating plant is to be operated within the Houston- Galveston VTS Area the master shall furnish the Vessel Traffic Center the following report at least 30 minutes prior to beginning operations:
(1) Location of intended operation.
(2) Description of intended operation including Channel obstructions.
(3) Configuration of pipelines and equipment in or along the Channel.
(4) Termination point of pipelines in or along the Channel.
(5) Time required to re-open Channel or move for vessel traffic.
(6) Operating impairments, including VHF-FM radios.
(7) Names of the assist boats being used.
(8) Traffic considerations required, for example: slow bell, no meeting or overtaking, and advance notice requirements.
(9) Point of Contact phone numbers and working frequencies.
3.10.2 Report Changes
The master of a dredge of floating plant shall immediately notify the VTS of changes to the above report and at the completion of operations.
3.10.3 Vessel Traffic Service Location
The Houston-Galveston VTS Area consists of the navigable Channels between the Galveston Entrance Channel Buoy 1 and the Houston Turning Basin, Galveston Channel, Texas City Channel, the Gulf Intracoastal Waterway Bayport Channel and Galveston-Freeport Cutoff from mile 346 to mile 352.
3.10.4 Communications
Communications with the Vessel Traffic Center, call sign "HOUSTON TRAFFIC," shall be accomplished via VHF-FM Channel 12. The Traffic Center guards
SECTION 35 20 23.16 45 Page 15 both Channel 12 and Channel 13 on a 24 hour basis.
3.10.5 Operations
The master of a dredge of floating plant shall be aware of and comply with the provisions of the Order Relating to Lightering and Bunkering Operations and Multiple Vessel Moorings and will notify the Houston-Galveston VTS when refueling operations are to be conducted.
3.11 WORK IN THE VICINITY OF OTHER GOVERNMENT CONTRACTORS
Coordinate dredging operations through the Contracting Officer, with other Government Contractors who may be working in the vicinity (for example:
revetment, jetty repairs, and dike construction).
3.12 DREDGING AND DREDGE RELATED MARINE WORK (CESWG)
Prepare an Accident Prevention Plan (APP) as required in accordance with the provisions of EM 385-1-1 and as specified in SECTION 01 35 26.01 45
GOVERNMENTAL SAFETY REQUIREMENTS.
3.13 AUTOMATIC IDENTIFICATION SYSTEM
A Class "A" Automatic Identification system (AIS) in accordance with the Code of Federal Regulations (CFR) title 33 CFR 164.46, as amended, is required for dredges used on this Contract.
3.14 DREDGE PLANT INSTRUMENTATION
The Dredge Plant Instrumentation is a part of the dredge plant and shall be functional at all times. If failure of any part thereof occurs, the Contractor shall repair the failed part within the next 36 hours restoring full operations. If the system is not fully functional within this period, the particular plant affected will be considered non-responsive to this Contract requirement and shall either be replaced or a redundancy part added to render the plant fully operational to include the monitored data at no additional increase in price or time to this Contract.
SECTION 35 20 23.16 45 Page 16
(project-year-sample#)
Sample No. Station Sand % Silt % Clay % D50 (mm)
TC-81-07 13+000 51.0 21.3 27.7 0.076
TC-81A-07 13+000 16.7 22.1 61.2 0.001
TC-84-07 13+000 21.7 50.9 27.4 0.031
TCC-84-GS-02 13+000 10.2 66.5 23.3 0.024
TC-86-07 13+000 49.8 38.8 11.4 0.073
TC-89-07 13+000 12.6 57.3 30.1 0.051
TC-92-07 13+000 63.5 21.0 15.5 0.195
TC-95-07 13+000 31.9 18.3 49.8 0.005
TC-98-07 13+000 13.6 26.7 59.7 0.005
TC-03-07 13+000 25.3 60.5 14.2 0.010
TC-12-07 13+000 14.5 44.9 40.6 0.018
TCC-84-GS-03 11+000 37.9 37.0 25.1 0.062
TCC-84-GS-03A 9+000 16.4 59.9 23.7 0.029
TC-81-08 8+000 60.0 16.6 23.4 0.093
TC-81A-08 8+000 49.4 25.9 24.7 0.074
TC-84-08 8+000 31.3 38.7 30.0 0.040
TCC-84-GS-04 8+000 71.4 19.2 9.4 0.154
TC-86-08 8+000 90.1 8.5 1.5 0.164
TC-89-08 8+000 81.7 11.9 6.4 0.147
TC-92-08 8+000 69.4 18.7 11.9 0.387
TC-95-08 8+000 61.1 11.1 27.8 0.101
TC-98-08 8+000 90.8 0.0 9.2 0.146
TC-03-08 8+000 63.3 26.8 9.9 0.120
TC-12-08 8+000 4.7 69.7 25.6 0.045
TC-12-08 Dup 8+000 2.7 75.2 22.1 0.049
TCC-84-GS-08 6+500 14.2 41.2 44.7 0.006
TC-89-09 3+000 94.0 5.7 0.3 2.000
TC-92-09 3+000 46.6 38.9 14.5 0.068
TC-98-09 3+000 90.9 3.0 6.1 0.152
TCC-84-GS-11 2+000 71.1 14.5 14.5 1.234
AVG 45.3 31.7 23.1 0.185
TEXAS CITY CHANNEL
Texas City Main Channel -- Sta. 1+000 to Sta. 13+000
Contracting specifications are written in accordance with NEPA documents and environmental clearance. Water quality certificates are wrapped into the NEPA coordination. Effluent standard of 8g/L for decant water will be met as detailed in specifications.
APPENDIX 2
(TO ACCOMPANY AMENDMENT NO. 0004 TO SOLICITATION NO. W9126G-17-B-0001)
(project-year-sample#)
TC-86-02 36+201 10.1 65.8 24.2 0.007
TC-92-01 36+000 26.9 37.3 35.8 0.013
TC-95-01 36+000 6.5 46.9 46.6 0.006
TC-98-01 36+000 2.1 27.3 70.6 0.004
TC-03-01 36+000 49.0 36.8 14.2 0.070
TC-TB-12-01 32+00 2.4 26.1 71.5 0.000
TC-92-02 35+000 22.1 46.8 31.1 0.029
TC-95-02 35+000 2.8 45.4 51.8 0.004
TC-98-02 35+000 1.3 18.9 79.8 0.004
TC-03-02 35+000 45.2 40.4 14.4 0.060
TC-TB-12-02 10+00 4.4 33.5 62.1 0.001
TC-81-03 33+000 2.0 43.3 54.7 0.004
TC-81A-03 33+000 2.0 36.4 61.6 0.001
TC-84-03 33+000 7.1 49.4 43.4 0.022
TC-86-03 33+000 0.7 80.3 19.0 0.011
TC-92-03 33+000 53.7 32.9 13.4 0.146
TC-95-03 33+000 3.1 32.5 64.4 0.000
TC-98-03 33+000 5.6 25.7 68.7 0.004
TC-03-03 33+000 34.9 23.3 41.8 0.010
TC-12-03 33+000 6.5 39.3 54.2 0.003
TC-81-04 28+000 2.0 41.8 56.2 0.003
TC-81A-04 28+000 0.4 28.0 71.5 0.001
TC-84-04 28+000 1.3 77.2 21.5 0.016
TC-86-04 28+000 4.6 80.6 14.9 0.015
TC-89-04 28+000 3.8 61.6 34.6 0.050
TC-92-04 28+000 31.7 40.0 28.3 0.050
TC-95-04 28+000 4.7 39.9 55.4 0.003
TC-98-04 28+000 1.0 20.4 78.6 0.004
TC-03-04 28+000 4.2 47.9 47.9 0.030
TC-03-04 Dup 28+000 31.2 8.7 60.1 0.004
TC-12-04 28+000 4.7 31.5 63.8 0.000
TC-81-05 23+000 2.0 35.0 63.0 0.002
TEXAS CITY CHANNEL
Texas City Channel -- Sta. 15+000 to Sta. 36+201 & TB -- Sta. 0+00 to Sta. 44+78
Contracting specifications are written in accordance with NEPA documents and environmental clearance. Water quality certificates are wrapped into the NEPA coordination. Effluent standard of 8g/L for decant water will be met as detailed in specifications.
APPENDIX 3
TC-81A-05 23+000 5.3 31.4 63.4 0.001
TC-84-05 23+000 1.8 63.4 34.7 0.011
TC-86-05 23+000 4.1 72.1 23.8 0.008
TC-89-05 23+000 4.6 95.4 0.0 0.050
TC-92-05 23+000 39.9 30.8 29.3 0.052
TC-95-05 23+000 4.0 31.3 64.7 0.000
TC-98-05 23+000 1.7 19.1 79.2 0.004
TC-03-05 23+000 5.0 69.9 25.1 0.010
TC-12-05 23+000 4.8 39.0 56.2 0.002
TC-81-06 18+000 6.0 25.8 68.2 0.002
TC-81A-06 18+000 4.4 25.2 70.3 0.001
TC-86-06 18+000 4.3 73.9 21.8 0.014
TC-89-06 18+000 3.6 53.4 43.0 0.051
TC-92-06 18+000 68.2 19.2 12.6 0.182
TC-95-06 18+000 11.4 31.5 57.1 0.002
TC-98-06 18+000 1.4 27.6 71.0 0.004
TC-03-06 18+000 6.6 71.7 21.7 0.010
TC-12-06 18+000 23.6 30.4 46.0 0.007
TCC-84-GS-01 15+000 12.5 55.2 32.3 0.019
AVG 11.6 42.5 45.9 0.020
APPENDIX 3
TI-92-01 92+00 11.5 40.8 47.7 0.006
TI-98-01 92+00 5.0 51.6 43.4 0.007
TI-12-01 90+00 5.5 35.3 59.2 0.004
TI-12-01 Dup 90+00 24.6 23.8 51.6 0.004
TI-87-02 60+00 16.0 68.7 15.3 0.015
TI-92-02 60+00 4.4 55.7 39.9 0.009
TI-98-02 60+00 14.6 70.1 15.3 0.008
TI-12-02 50+00 15.5 42.1 42.4 0.008
TI-92-03 25+00 9.7 62.5 27.8 0.034
Industrial Canal & TB -- Sta.