SEE ADDENDUM

(No Collect Calls)

W9126G-16-T-0029 20-Jan-2016

b. TELEPHONE NUMBER

817-886-1051

8. OFFER DUE DATE/LOCAL TIME

10:00 AM 12 Feb 2016

5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA – FAR (48 CFR) 53.212

(TYPE OR PRINT)

(SIGNATURE OF CONTRACTING OFFICER)

ADDENDA X ARE

26. TOTAL AWARD AMOUNT (For Gov t. Use Only )

23.

CODE 10. THIS ACQUISITION IS

SUCH ADDRESS IN OFFER

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT

BELOW IS CHECKED

TELEPHONE NO.

W9126G9. ISSUED BY

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME

DAISY CIARLARIELLO

2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER

(TYPE OR PRINT)

30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA

1 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.X

25. ACCOUNTING AND APPROPRIATION DATA

1. REQUISITION NUMBER

20.

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

ARE NOT ATTACHED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

. YOUR OFFER ON SOLICITATION

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

% FOR:SET ASIDE:UNRESTRICTED OR X

SMALL BUSINESSX WOMEN-OWNED SMALL

BUSINESS (WOSB)

17a.CONTRACTOR/ CODE FACILITY

OFFEROR CODE

US ARMY CORPS OF ENGINEERS FORT WORTH

819 TAYLOR ST, RM 2A17

FORT WORTH TX 76102-0300

18a. PAYMENT WILL BE MADE BY CODE

RATED ORDER UNDER

DPAS (15 CFR 700)

13a. THIS CONTRACT IS A

13b. RATING

CODE15. DELIVER TO CODE 9674CD 16. ADMINISTERED BY

12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

14. METHOD OF SOLICITATION

RFQ IFB RFPX

BELTON LAKE OFFICE

RONALD BRUGGMAN

3110 FM 2271

BELTON TX 76513-9717

TEL: 254-939-2461 FAX: 254-939-8150

(817) 886-6403FAX:

TEL: (817) 886-1077 SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

8(A)

HUBZONE SMALL

BUSINESS

ECONOMICALLY DISADVANTAGED

WOMEN-OWNED SMALL BUSINESS

(EDWOSB)

SIZE STANDARD:

11,000,000

NAICS:

721211

X

OFFER DATED

29. AWARD OF CONTRACT: REF.

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

EMAIL:

TEL:

31c. DATE SIGNED

SEE SCHEDULE

SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT

24.22.21.19.

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

(CONTINUED)

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

32b. SIGNATURE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

37. CHECK NUMBER

FINALPARTIALCOMPLETE

36. PAYMENT35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER

FINAL

33. SHIP NUMBER

PARTIAL

38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT 41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE

42a. RECEIVED BY (Print)

42b. RECEIVED AT (Location)

42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS

STANDARD FORM 1449 (REV. 2/2012) BACK

Prescribed by GSA – FAR (48 CFR) 53.212

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

SEE SCHEDULE

20.

SCHEDULE OF SUPPLIES/ SERVICES

21.

QUANTITY UNIT

22. 23.

UNIT PRICE

24.

AMOUNT

19.

ITEM NO.

W9126G-16-T-0029

Section SF 1449 - CONTINUATION SHEET

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job

Funded Amt:

FY16 Belton/Canyon Lakes Gate Attendants

Provide all labor, materials, supplies and equipment to furnish gate attendant services at various parks in accordance with the attached performance work statements.

Locations: - Temple Lake Park, Westcliff Park, White Flint Park, Canyon Beach, Canyon Park, Comal Park, Cranes Mill Park, North Park and Potters Creek Park.

Multiple awards will be made for several parks within the Fort Worth District Capital Region.

Incomplete bids shall be considered non-responsive and will not be evaluated. If a quoter declines to accept a purchase order for a park, the quoter will not be considered for any other awards offered in the solicitation. Only one offer will be made by the government.

Point of Contact: Daisy Ciarlariello, 817-886-1051 Email: daisy.ciarlariello@usace.army.mil

Email Proposal to: CIV-OPS.Proposals@usace.army.mil

Only a warranted Contracting Officer either a Procuring Contracting Officer (PCO), or an Administrative Contracting Officer (ACO), acting within their delegated limits, has the authority to issue modifications or otherwise change the terms and conditions of this contract. If an individual other than the Contracting Officer attempts to make changes to the terms and conditions of this contract you shall not proceed with the change and shall immediately notify the Contracting Officer.

mailto:CIV-OPS.Proposals@usace.army.mil

INSTRUCTIONS TO QUOTER

QUOTER DUE DATE/LOCAL TIME: see block 8, SF 1449 Central Standard Time (CST) POINT OF CONTACT: Daisy Ciarlariello, Contract Specialist Phone: (817) 886-1051 EMAIL your proposal to: CIV-OPS.Proposals@usace.army.mil

Quotes shall be accepted via “EMAIL ONLY,” no fax, mail, express mail, or hand carry, “NO EXCEPTIONS.” Subject line of email must include the solicitation number.

For additional help contact your local Procurement Technical Assistance Centers (PTAC).

Centers were created by Congress to assist businesses seeking to compete on federal contracts.

Services are generally free; however, a small fee may be charged for certain services. Please use website http://www.aptac-us.org/new/ to contact a center to assist you in the preparation for a federal contract, registering in SAM or other required systems.

SYSTEM FOR AWARD MANAGEMENT (SAM) is REQUIRED to receive an award on all federal government contracts. Therefore, contractors are encouraged to begin this process sooner rather than later. If already registered, please ensure your registration is ACTIVE. The website to register with SAM is: www.sam.gov.

DATA UNIVERSAL NUMBERING SYSTEM (DUNS) is REQUIRED. Dun & Bradstreet (D&B) provides a DUNS Number, a unique nine digit identification number, for each physical location of your business. DUNS Number assignment is FREE for all businesses required to register with the US Federal government for contracts or grants in the System for Award Management (SAM see below).

The website to obtain your DUNS number: http://fedgov.dnb.com/webform for technical difficulties, contact govt@dnb.com

ONLINE REPRESENTATIONS AND CERTIFICATIONS APPLICATIONS (ORCA)

allows contractors to complete a one-time certification and representations for your use on any solicitation. The website to complete ORCA is available at the System for Award Manager (SAM): www.sam.gov. The information previously maintained in CCR, FedReg and ORCA now is contained within the Entity Management area in SAM. Legacy EPLS information resides in the Performance Information area of SAM. Contractors MUST be certified in the NAICS Code and Size Standard applicable with this solicitation.

ATTENTION TO OFFEROR(s)/CONTRACTOR(s): On July 14, 2014, Small Business Administration (SBA) increased the monetary-based industry size standards to account for inflation. You must update your Representations (Reps) and Certifications (Certs) for the impacted North American Industry Classification System (NAICS) codes identified with an exclamation point "!" next to the "Small Business" value in the System for Award Management (SAM). Please log into SAM, review, and resubmit your registration to apply the new size standard.

WAGE RATES: The Service Contract Act applies (see attached wage rates in Section J). Note: Does not apply to Contractors registered in System for Award Management (SAM) as Sole Proprietorships.

http://www.aptac-us.org/new/ http://www.sam.gov/ http://fedgov.dnb.com/webform mailto:govt@dnb.com http://www.sam.gov/

Below is a checklist to assist you to ensure all the proper documents are returned for consideration on this solicitation. Only those items checked below as “required” must be returned

Required Contractor Item

Complete page 1 of Solicitation (SF 1449-Sign and date in block 30).

Complete Bid Schedule(s) Solicitation Contract Task Order 1

Fill out bid schedules “SEPARATELY“when bidding multiple Park Positions

Complete Contractor Information Sheet below: Include your SSN or firm’s Tax ID Number (TIN) and active email address.

You may be notified of your selection by this method!!!

Offerors shall complete electronically ORCA profile on line in SAMS:

Clause 52.212-3 paragraph (b) of solicitation AND submit complete ORCA profile.

Offerors shall submit an active SAM registration (Attach first page).

The System for Award Management (SAM) is the Official U.S. Government system that consolidated the capabilities of CCR/FedReg, ORCA and EPLS. Website: www.sam.gov

Add NAICS Code 561990 to your Representations and Certification in SAMS.

Complete clause 52.209-5 of the solicitation

EMAIL Past Performance Questionnaire to a former employer or person who can vouch for your work capability or volunteer work.

Ensure former employer return the form and references the solicitation number in the email subject line. CIV-OPS.Proposals@usace.army.mil

Provide Experience in the form of a resume

Scan all documents into a single.pdf file. (For Help contact your local Library, copy centers or PTACs-http://www.aptac-us.org/new/

EMAIL your proposal to: CIV-OPS.Proposals@usace.army.mil

Subject line of email: Include the solicitation number and your name

Clause 52.228-5: See Insurance Information and Requirements http://www.aptac-us.org/new/

Contractor Information Sheet

**THIS MUST BE COMPLETED AND RETURNED WITH YOUR QUOTE**

I am submitting on several gate attendant contracts. The team below shall be available for all.

I am submitting on several gate attendant contracts and this team only applies to:

______________________(identify the Lake) ____________________(identify the Park)

Team Members

NAME: Person #1 SSN/TIN:

(Last, First Middle) (Social Security Number)

Person #2 SSN/TIN:

(Last, First Middle) (Social Security Number)

IN THE EVENT OF AWARD, ISSUE CONTRACT TO:

NAME

(Last, First Middle)

ADDRESS

(Number & Street) (City, State and Zip)

HOME PHONE NUMBER MOBILE

(Area code and number) (Area code and number)

EMAIL ADDRESS________________________________________________________________

DUNS NUMBER CAGE CODE NUMBER

SSN/TIN NUMBER ______________________________

NAVFAC/USACE PAST PERFORMANCE QUESTIONAIRE (Form PPQ-0)

CONTRACT INFORMATION (Contractor to complete Blocks 1-4)

1. Contractor Information Firm name: CAGE Code:

Address: DUNS Number:

Phone Number:

Email Address:

Point of Contact: Contact Phone Number:

2. Work Performed as: Prime Contractor Sub Contractor Joint Venture Other (Explain) Percent of Project work performed:

If subcontractor, who was the prime (Name/Phone #):

3. Contract Information Contract Number:

Delivery/Task Order Number (if applicable):

Contract type: Firm Fixed Price Cost Reimbursement Other (please specify):

Contract Title:

Contract Location:

Award Date (mm/dd/yy):

Contract Completion Date (mm/dd/yy):

Actual Completion Date (mm/dd/yy) Explain Differences:

Original Contract Price (Award Amount):

Final contract Price (to include all modifications, if applicable):

Explain Differences:

4. Project Description:

Complexity of Work High Med Routine How is this project relevant to project of submission? (Please provide details such as similar equipment, requirements, conditions, etc.)

CLIENT INFORMATION (Client to complete Blocks 5-8)

5. Client Information Name:

Title:

Phone Number:

Email Address:

6. Describe the client’s role in the project:

7. Date Questionnaire was completed (mm/dd/yy):

8. Client’s Signature:

NOTE: NAVFAC/USACE REQUESTS THAT THE CLIENT COMPLETES THIS QUESTIONNARIE AND SUBMITS DIRECTLY BACK TO THE OFFEROR. THE OFFEROR WILL SUBMIT THE COMPLETED QUESTIONNARIE TO USACE WITH THEIR PROPOSAL, AND MAY DUPLICATE THIS QUESTIONNAIRE FOR FUTURE SUBMISSION ON USACE SOLICITATION. CLIENTS ARE HIGHLY ENCOURAGED TO SUBMIT QUESTIONNAIRES DIRECTLY TO THE OFFEROR. HOWEVER, QUESTIONNAIRES MAY BE SUBMITTED DIRECTLY TO USACE. PLEASE CONTACT THE OFFEROR FOR USACE POC INFORMATION. THE GOVERNMENT

RESERVES THE RIGHT TO VERIFY ANY AND ALL INFORMATION ON THIS FORM.

AFTER COMPLETION, PLEASE EMAIL TO: CIV-OPS.Proposals@usace.army.mil Ensure the former employer references the solicitation number in the email subject line.

ADJECTIVE RATINGS AND DEFINITIONS TO BE USED TO BEST REFLECT

YOUR EVALUATIONOF THE CONTRACTOR’S PERFORMANCE

RATING DEFINITION NOTE

(E) Exceptional Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor was highly effective.

An Exceptional rating is appropriate when the Contractor successfully performed multiple significant events that were of benefit to the Government/Owner. A singular benefit, however, could be of such magnitude that it alone constitutes an Exceptional rating.

Also, there should have been NO significant weaknesses identified.

(VG) Very Good Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.

A Very Good rating is appropriate when the Contractor successfully performed a significant event that was a benefit to the Government/Owner. There should have been no significant weaknesses identified.

(S) Satisfactory Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.

A Satisfactory rating is appropriate when there were only minor problems, or major problems that the contractor recovered from without impact to the contract.

There should have been NO significant weaknesses identified. Per DOD policy, a fundamental principle of assigning ratings is that contractors will not be assessed a rating lower than Satisfactory solely for not performing beyond the requirements of the contract.

(M) Marginal Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor’s proposed actions appear only marginally effective or were not fully implemented.

A Marginal is appropriate when a significant event occurred that the contractor had trouble overcoming which impacted the Government/Owner.

(U) Unsatisfactory Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains serious problem(s) for which the contractor’s corrective actions appear or were ineffective.

An Unsatisfactory rating is appropriate when multiple significant events occurred that the contractor had trouble overcoming and which impacted the Government/Owner. A singular problem, however, could be of such serious magnitude that it alone constitutes an unsatisfactory rating.

(N) Not Applicable No information or did not apply to your contract

Rating will be neither positive or negative.

TO BE COMPLETED BY CLIENT

PLEASE CIRCLE THE ADJECTIVE RATING WHICH BEST REFLECTS

YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE.

1. QUALITY

a) Quality of technical data/report preparation efforts E VG S M U

N

b) Ability to meet quality standards for technical performance E VG S M U

N

c) Timeliness/effectiveness of contract problem resolution without extensive customer guidance.

E VG S M U

N

d) Adequacy/effectiveness of quality control program and adherence to contract quality assurance requirements (without adverse effect on performance)

E VG S M U

N

2. SCHEDULE/TIMELINESS OF PERFORMANCE:

a) Compliance with contract delivery/completion schedules including any significant intermediate milestones. (If liquidated damages were assessed or the schedule was not met, please address below)

b) Rate the contractor’s use of available resources to accomplish tasks identified in the contract E VG S M U

N

3. CUSTOMER SATISFACTION:

a) To what extent were the end users satisfied with the project? E VG S M U

N

b) Contractor was reasonable and cooperative in dealing with your staff (including the ability to successfully resolve disagreements/disputes; responsiveness to administrative reports, businesslike and communication)

c) To what extent was the contractor cooperative, businesslike, and concerned with the interests of the customer? E VG S M U

N

d) Overall customer satisfaction E VG S M U

N

4. MANAGEMENT/PERSONNEL/LABOR

a) Effectiveness of on-site management, including management of subcontractors, suppliers, materials, and /or labor force? E VG S M U

N

b) Ability to hire, apply, and retain qualified workforce to this effort E VG S M U

N

c) Government Property Control E VG S M U

N

d) Knowledge/expertise demonstrated by contractor personnel E VG S M U

N

e) Utilization of Small Business concerns E VG S M U

N

f) Ability to simultaneously manage multiple projects with multiple disciplines E VG S M U

N

g) Ability to assimilate and incorporate changes in requirement and/or priority, including planning, execution and response to Government changes

h) Effectiveness of overall management (including ability to effectively lead, manage and control the program) E VG S M U

5. COST/FINANCIAL MANAGEMENT

a) Ability to meet the terms and conditions within the contractually agree price(s)? E VG S M U

N

b) Contractor Proposed innovative alternative methods/processes that reduced cost, improved maintainability or other factors that benefited the client

c) If this is/was a Government cost type contract, please rate the Contractor’s timeliness and accuracy in submitting monthly invoices with appropriate back-up documentation, monthly status reports.

Budget variance reports, compliance with established budgets and avoidance of significant and/or unexplained variances (under runs or overruns)

d) In the Contractor’s accounting system adequate for management and tracking of costs? If no, please explain in Remarks section. YES NO

e) If this is/was a Government contract, has/was this contract been partially or completely terminated for default or convenience or are there any pending terminations? Indicate if show cause or cure notices were issued, or any default action in comment section below.

YES NO

f) Have there been any indication that the contractor has had any financial problems? If yes, please explain below. YES NO

6. SAFETY/SECURITY

a) To What extent was the contractor able to maintain an environment of safety, adhere to its approved safety plan, and respond to safety issues? (Includes: following the users rules, regulations, and requirements, regarding housekeeping, safety, correction of noted deficiencies, etc.)

b) Contractor complied with all security requirements for the project and personnel security requirements. E VG S M U

N

7. GENERAL

a) Ability to successfully respond to emergency and/or surge situations (including notifying COR, PM or Contracting Officer in a timely manner regarding urgent contractual issues)

b) Compliance with contractual terms/provisions (explain if specific issues)

E VG S M U

N

c) Would you hire or work with this firm again? (If no, please explain below)

YES NO

d) In Summary, provide an overall rating for the work performed by this contractor. E VG S M U

N

AFTER COMPLETION, PLEASE EMAIL TO: CIV-OPS.Proposals@usace.army.mil Please provide responses to the questions above (if applicable) and/or additional remarks. Furthermore, please provide a brief narrative addressing specific strengths, weaknesses, deficiencies, or other comments which may assist our office in evaluating performance risk (Please attach additional pages in necessary):

Bid Sheet Belton Lake

Contract Gate Attendant Services

Belton Lake

Base Year: 1 March 2016 through 30 September 2016 (Period of Performance 1 March 2016 through 28 February 2017) Option Year 1: 1 March 2017 through 30 September 2017 (Period of Performance 1 March 2017 through 28 February 2018) Option Year 2: 1 March 2018 through 30 September 2018 (Period of Performance 1 March 2018 through 28 February 2019)

Please note that Period of Performance, required for contract funding and contract administration purposes, is referred to in Bid Schedule as one year in duration; however, actual Contractor’s services will only be performed during the months described for the position. For example, a Summer Season Gate Attendant position will only work the months of March through September although Period of Performance shows March through following February.

Temple’s Lake Park (4 Day) A Shift

Item # Gate Attendant Position Price Per Day Total Cost

BN001

Base Year:

108 days during 1 March 2016 - 30 September 2016 Period of Performance 1 March 2016 through 28 February 2017

BN001A

Option Year 1:

108 days during 1 March 2017 - 30 September 2017 Period of Performance 1 March 2017 through 28 February 2018

BN001B

Option Year 2:

108 days during 1 March 2018 - 30 September 2018 Period of Performance 1 March 2018 through 28 February 2019

TOTAL COST $

Temple’s Lake Park (4 Day) B Shift

Per Day Total Cost

BN001

Base Year:

106 days during 1 March 2016 - 30 September 2016 Period of Performance 1 March 2016 through 28 February 2017

BN001A

Option Year 1:

106 days during 1 March 2017 - 30 September 2017 Period of Performance 1 March 2017 through 28 February 2018

BN001B

Option Year 2:

106 days during 1 March 2018 - 30 September 2018 Period of Performance 1 March 2018 through 28 February 2019

Westcliff Park (4 Day) A Shift

Per Day Total Cost

BN001

Base Year:

108 days during 1 March 2016 - 30 September 2016 Period of Performance 1 March 2016 through 28 February 2017

BN001A

Option Year 1:

108 days during 1 March 2017 - 30 September 2017 Period of Performance 1 March 2017 through 28 February 2018

BN001B

Option Year 2:

108 days during 1 March 2018 - 30 September 2018 Period of Performance 1 March 2018 through 28 February 2019

White Flint Park (4 Day) A Shift

Per Day Total Cost

BN001

Base Year:

108 days during 1 March 2016 - 30 September 2016 Period of Performance 1 March 2016 through 28 February 2017

BN001A

Option Year 1:

108 days during 1 March 2017 - 30 September 2017 Period of Performance 1 March 2017 through 28 February 2018

BN001B

Option Year 2:

108 days during 1 March 2018 - 30 September 2018 Period of Performance 1 March 2018 through 28 February 2019

White Flint Park (4 Day) B Shift

Per Day Total Cost

BN001

Base Year:

106 days during 1 March 2016 - 30 September 2016 Period of Performance 1 March 2016 through 28 February 2017

BN001A

Option Year 1:

106 days during 1 March 2017 - 30 September 2017 Period of Performance 1 March 2017 through 28 February 2018

BN001B

Option Year 2:

106 days during 1 March 2018 - 30 September 2018 Period of Performance 1 March 2018 through 28 February 2019

Gate Attendant Services Canyon Lake Canyon Beach A-Shift

1 April 2016 through 25 September 2016 (Base) No Options

Canyon Beach A Shift

Per Day Total Cost

CN005

Base Year Only:

90 days during 1 April 2016 - 25 September 2016

Canyon Lake Canyon Beach B-Shift

1 April 2016 through 23 September 2016 (Base)

Canyon Beach B Shift

Per Day Total Cost

CN006

88 days during 1 April 2016 - 23 September 2016

Canyon Lake Canyon Park A-Shift

Canyon Park A Shift

Per Day Total Cost

CN007

Canyon Lake Canyon Park B-Shift

1 April 2016 through 23 September 2016 (Base)

Canyon Park B Shift

Per Day Total Cost

CN008

88 days during 1 April 2016 - 23 September 2016

Canyon Lake Comal Park A-Shift

Comal Park A Shift

Per Day Total Cost

CN002

Canyon Lake Comal Park B-Shift

1 April 2016 through 30 September 2016 (Base)

Comal Park A Shift

Per Day Total Cost

CN002

88 days during 1 April 2016 - 30 September 2016

Canyon Lake Crane’s Mill Park A Shift

Crane’s Mill Park A Shift

Per Day Total Cost

CN001

92 days during 1 April 2016 - 30 September 2016

Canyon Lake North Park

North Park

Per Day Total Cost

CN004

81 days during 1 April 2016 - 25 September 2016

Canyon Lake Potters Creek A-Shift

Potters Creek Park A Shift

Per Day Total Cost

CN009

92 days during 1 April 2016 – 30 September 2016

Canyon Lake Potters Creek B Shift

Potters Creek Park B Shift

Per Day Total Cost

CN010

91 days during 1 April 2016 – 30 September 2016

FORT WORTH DISTRICT

PERFORMANCE WORK STATEMENT (PWS)

GATE ATTENDANT SERVICES

1. GENERAL: This is a non-personal services contract to provide Gate Attendant Services. The Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.

1.1 Description of Services/Introduction: The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform Gate Attendant Services for the duration of the contract period as defined in this Performance Work Statement, except for those items specified as Government-furnished property and services in each lakes appendices in this solicitation. The contractor shall perform to the standards in this contract. Work to be accomplished under this contract shall be in accordance with this PWS, the lake appendices and the Lake Office Gate Attendant Handbook, for the recreation area named and described herein. The successful contractor must pass a criminal background check. Site visits are highly recommended prior to bidding.

See Lake-specific PWS appendices for gate attendant team requirements.

1.1.1 Definitions:

(a) Contractor: The person awarded the contract.

(b) Contracting Officer (KO): The person with the authority to enter into, administer, and/or terminate contracts and make related determination and findings on behalf of the Government. This person will be identified on the SF 1449 (Solicitation/Contract/Order for Commercial Items).

(c) Lake Manager: The manager of the local lake. The Lake Manager may appoint an authorized representative to act on their behalf.

1.1.2 Basic Requirements: The following requirements for submitting a quote and receiving an award are now mandatory for conducting business with the DOD Government.

(a) All offerors are required to obtain a Data Universal Numbering System (DUNS) number by calling 1-800-333-0505 or by visiting www.dnb.com.

(b) All prospective contractors must be registered in System for Award Management (SAM) database prior to any award resulting from this solicitation. If at time of award, contractor is not registered, award will be made to the next successful “registered” offer.

Registration may be accomplished via the internet at www.sam.gov.

(c) All payments shall be made by Electronic Funds Transfer (EFT) or “direct deposit”.

(d) E-Verify Verification of Eligibility. The Contractor must use the U.S. Department of Homeland Security E-Verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Contractor must provide to the Government two valid forms of Government-issued identification prior to beginning work to ensure the correct information is entered into the E-Verify system.

http://www.dnb.com/ http://www.uscis.gov/e-verify

1.2 Scope: Gate Attendant services as described in Section 1.11, Work to be Performed, and in lake-specific appendices.

1.3 Period of Performance: The term of the contract and required services are defined in this solicitation in each lake’s appendix.

1.4 General Information

1.4.1 Quality Control: Not Applicable.

1.4.2 Quality Assurance: The Government shall evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan. This plan is primarily focused on what the Government must do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the minimum acceptable defect rate(s).

1.4.2.1 Inspection and Contract Performance: The service performed by the contractor under the provisions of this contract shall be subject to inspections by the Contracting Officer or his designated representative to ensure strict compliance with the terms of the contract.

(a) Notification of Deficiencies: Contractor shall be notified verbally and/or in writing of any serious or recurring minor deficiency in service observed by the Contracting Officer or his/her authorized representative. Verbal notification will be recorded in a memorandum for record.

(b) Documentation of Deficiencies: Written notifications and memoranda for the record shall be prepared in triplicate by the Contraction Officer or his/her authorized representative. The original will be part of the Contractor’s permanent file at the Operations Manager’s Office, a copy will be issued to the contractor, and a copy will be forwarded to the Contracting Officer at the U.S.

Army Corps of Engineers, Fort Worth District Office.

(c) Correction of Contract Deficiencies: Upon receipt of notification of deficiency in service, Contractors will immediately correct deficiencies and /or take steps to prevent recurrence of the deficiency.

(d) Deficiencies of Service: This contract may be terminated by the Contracting Officer upon receipt of any “Notification of Contract Deficiency”. Termination will be based on the seriousness of the deficiency.

(e) Evaluation of Performance: All contractors will have their performance evaluated no less than mid-term and at the conclusion of their contract.

1.4.3 Government Holidays: The Contractor will work the holidays that fall on their shift.

New Year’s Day Labor Day Martin Luther King Jr.’s Birthday Columbus Day President’s Day Veteran’s Day Memorial Day Thanksgiving Day Independence Day Christmas Day

1.4.4 Hours of Operation: The hours of park operation are as specified in Lake-specific appendices. The contractor will provide adequate staffing during all posted hours of park operation.

1.4.5 Place of Performance: The work to be performed under this contract will be performed as described in Lake-specific appendices.

1.4.6 Type of Contract: The Government will award a Firm Fixed Price contract.

1.4.7 Security Requirements:

1.4.7.1 Physical Security: The contractor shall be responsible for safeguarding all Government equipment, information and property provided for contractor use. At the close of each work period, Government facilities, equipment, and materials shall be secured.

1.4.7.2 Key Control: Government keys provided to the contractor will be issued and controlled in accordance with IAW AR 190-51 and the U.S. Army Corps of Engineers, Southwestern Division Recreation Use Fee Program Regulation, SWDR 1130-2-550-1.

The Contractor shall establish and implement methods of making sure all keys/key cards issued to the Contractor by the Government are not lost or misplaced and are not used by unauthorized persons. NOTE: All references to keys include key cards. No keys issued to the Contractor by the Government shall be duplicated. The Contractor shall develop procedures covering key control that shall be included in the Quality Control Plan. Such procedures shall include turn-in of any issued keys by personnel who no longer require access to locked areas. The Contractor shall immediately report any occurrences of lost or duplicate keys/key cards to the Contracting Officer.

(a) The Contractor shall prohibit the use of Government issued keys/key cards by any persons other than the Contractor and team member. The Contractor shall prohibit the opening of locked areas by persons other than the Contractor and team member.

1.4.7.3 Lock Combinations: The Contractor shall establish and implement methods of ensuring that all lock combinations are not revealed to unauthorized persons. The Contractor shall ensure that lock combinations are changed when personnel having access to the combinations no longer have a need to know such combinations. These procedures shall be included in the Contractor’s Quality Control Plan.

1.4.8 Special Qualifications: Not Applicable.

1.4.9 Pre-Work Conference: The Contractor will be required to attend a pre-work conference at no additional cost to the Government to review the policies outlined in the PWS. This conference will be conducted by the Lake Manager or their representative, at each local lake office or other agreed upon location, and at a time specified in each Lake Appendix.

1.4.9.1 Training. The Contractor will be provided I-Watch and CorpsWatch Training and Southwestern Division Authorized Collectors Training.

1.4.10 Contracting Officer Representative (COR): Not applicable unless otherwise established by the Contracting Officer.

1.4.11 Contractor Key Personnel: Not Applicable.

1.4.12 Identification of Contractor Employees: The Government will provide photo identification cards to all contractors. Contractors will wear photo badges on their person as they perform duties to execute the work items under this contract (PWS 1.11).

1.4.13 Contractor Travel: Not Applicable.

1.4.14 Data Rights: The Government has unlimited rights to all documents/material produced under this contract. All documents and materials, to include the source codes of any software, produced under this contract shall be Government owned and are the property of the Government with all rights and privileges of ownership/copyright belonging exclusively to the Government.

These documents and materials may not be used or sold by the contractor without written permission from the Contracting Officer. All materials supplied to the Government shall be the sole property of the Government and may not be used for any other purpose. This right does not abrogate any other Government rights.

1.4.15 Organizational Conflict of Interest: Not Applicable.

1.5 Government-Furnished Items and Services:

1.5.1 Facilities: The Government will provide a gate house in the park in which the contractor will work.

1.5.2 Equipment: The Government will provide a non-networked computer for non-sensitive data entry, computer monitors, printers, telephone and radio communication equipment.

1.5.3 Materials: The Government will provide gate house supplies, including forms, maps, brochures, handouts, light bulbs, air condition filters, computer paper, staplers, staples, china markers, water hose and sprinklers. The Government will provide other items as specified in the lake-specific appendices.

1.5.4 Trailer Site: Unless otherwise indicated in the Lake Offices’ park information sheet or additional scope of work, the Government will furnish a site for self-contained travel trailer or motor home with 110- volt electricity, water, and sewer hook-ups and/or dump station nearby. If the contractor’s travel trailer is not configured or adaptable to the sewage, water or electric hookups available at the site, the Government will not be responsible for providing attachments, etc. No reimbursement will be made whenever utilities are not available and must be secured elsewhere. The use of the facilities is at the contractors own risk and damage to equipment will be the sole responsibility of the contractor.

1.6 Contractor-Furnished Items and Responsibilities:

1.6.1 General: The Contractor shall furnish all supplies, equipment, facilities and services required to perform work under this contract that are not listed under Section 1.5, Government-Furnished Items and Responsibilities, of this PWS.

1.6.2 Equipment: The contractor will provide a transportation vehicle, which can be operated independently of the RV free of leaks and in good mechanical condition for use in performing the requirements of the contract. Minimum state required liability insurance must be carried. Proof of liability insurance will be submitted during the pre-work meeting and prior to the work start date.

All motor vehicles and operators will comply with state laws such as licensed operators, vehicle safety equipment, etc. The Gate Attendant may be required to display the vehicle identification provided by the Corps of Engineers on the vehicle while on duty. The Gate Attendant’s vehicle will not display Emergency Red and/or Blue Lights, use a siren, or otherwise represent an appearance of an emergency vehicle while on duty. The contractor will supply the gas for operation of the vehicle while on duty.

1.6.3 Materials: The Contractor shall furnish all materials, excluding those furnished by Government as specified above, and needed to operate the gatehouse. This list includes, but is not limited to highlighters, color markers, notepads, pens, pencils, tape, trash bags, cleaning supplies, restroom supplies and any other items that may be necessary to operate the gatehouse.

1.6.4 Temporary Living Quarters: The contractor shall furnish a fully operable “self-contained” recreational vehicle (RV) of the travel trailer or motor home type to serve as temporary living quarters for the duration of the contract. Maximum size of the trailer is determined by physical limitations of the site furnished. It will be located near the entrance to the park at a location to be designated by the Lake Manager. Pickup (shell-type) campers, pop-up tent trailer, tents, mini-travel trailers, mobile homes, buses, or any other types of recreation vehicles which do not meet general size requirements or the self-contained classification as determined by inspection of the Contracting Officer or his/her authorized representative will not be acceptable. The Contractor will be the sole occupants of the site. Adult family members and friends will not live with the contractor.

1.7 Contractor Management Reporting (CMR): Not Applicable.

1.8 Applicable Publications (Current Editions): The Contractor must abide by all applicable regulations, publications, manuals, and local policies and procedures.

1.9 Attachment/Technical Exhibit List:

1.9.1 Attachment 1/Technical Exhibit 1 – Performance Requirements Summary. See Lake-specific appendices.

1.9.2 Attachment 2/Technical Exhibit 2 – Deliverables Schedule. See Lake-specific appendices.

1.10 Safety:

1.10.1 Safety Manual Requirements: The Contractor(s) shall comply with all pertinent sections of the Corps of Engineers' Safety and Health Requirements Manual, EM 385-1-1, current at the time of award, and any subsequent revisions. This manual can be found on-line at:

www.usace.army.mil/usace-docs/eng-manuals/em385-1-1/toc.htm.

1.11 Work to be Performed:

1.11.1 User Fees: The Contractor will follow fee collection, credit voucher, refund, campsite reservation and remittance procedures established by the U.S. Army Corps of Engineers, Southwestern Division Recreation Use Fee Program Regulation, SWDR 1130-2-550-1.

(a) User Fee Collection: The Contractor is required to collect User Fees daily, to ensure visitors have paid applicable user fees, utilizing the U.S. Army Corps of Engineers User Permit (ENG Form 4457), National Recreation Reservation Service (NRRS), Outdoor Recreation Management Suite (ORMS) Field Manager Program, an automated cash register, and/or collection from an honor vault. This includes going through the park to collect and safeguard fees when necessary. The Contractor is required to collect user fees for specialized recreation sites, facilities and services provided by the Corps of Engineers.

This may include, but is not limited to, camping, group facility use, day use, special facility use, and multiple site rental use. The Contractor is required to accept cash, http://www.usace.army.mil/usace-docs/eng-manuals/em385-1-1/toc.htm personal check, traveler’s checks, money orders or credit card payments as methods of use fee payment.

(b) Audits and Fee Security: The Contractor will be responsible for User Fee Permits (ENG Form 4457), cash register receipts and journal, computer generated receipts, signed credit card receipts, and all collected forms of use fee payments until turned over to an authorized fee collector/cashier. The Contractor may be audited at any time, with or without prior notice, and is required to place all forms of collected use fee payments/monies in the gatehouse cash drawer or fee safe provided immediately upon receipt. The cash drawer or fee safe will remain closed immediately after every transaction and the automatic lock shall not be defeated at any time.

(c) Cash on Hand: The Contractor/Gate Attendant is required to have personal cash on hand at all times (minimum of $50.00) to make change. A signed statement with the amount of personal funds in use will be placed in the cash drawer and updated immediately anytime this amount changes. Refer to the lake appendences for amounts required at each park.

(d) Remittance Procedures and Inspection of Use Fees: All Lakes require User Fee remittance a minimum of once a week. See “Use Fee Collections” in each lake appendix, for which process is used at the location(s) on which you are bidding. Inspections will be performed during the contract period as deemed necessary by the Lake Manager.

1.11.2 Campsite Reservations: The Contractor will comply with local and District policies for reservations. The contractor will adhere to guidelines and procedures established under the National Recreation Reservation System, using Outdoor Recreation Management Suite (ORMS) Field Manager program in the campground. The contractor may also be required to take advance campsite reservations, which would consist of receiving and booking reservations requests, collecting and processing camping fees, and handling cancellation and refund requests. The Contractor will be required to perform some or all the following duties daily:

(a) Pick up reservation data reports, i.e. bookings, arrival reports, cancellation reports, etc., from the local lake office or accept the reports delivered in person, and /or transmitted by telephone, electronic mail received through a computer, facsimile machine, etc.

(b) Maintain and update necessary status reports utilizing charts, status boards, note pads, card systems, computer/cash register systems, ORMS, Field Manager, NRRS, etc., to ensure that campsite status is kept current at all times.

(c) Keep records and monitor date of arrivals, departures, no-shows, cancellations, etc.

(d) Fill out refund and credit voucher forms according to policy.

(e) Post or identify reserved and vacant campsites by positing provided signs or markers.

The Contractor will also maintain records as necessary for the administration of the campsite reservation program as directed by the Lake Manager. The Contractor will accept the campsite reservation permit/confirmation letter as both proof and payment of the reservation.

1.11.3 Group Shelters: The contractor will keep records and ensure compliance of group shelter use as required by the Lake Manager including the use of the NRRS system, where applicable.

1.11.4 Camping Status: The Contractor will record the campsite occupied and maintain record of the current status for each campsite occupied. The contractor will keep written records of each camper’s length of stay to ensure compliance with the Fort Worth District camping policy. The contractor will register park users, issue appropriate passes and deliver messages to visitors as required by the Lake Manager. The Contractor will keep a written record of campers who are turned away due to lack of campsites or campsites with desired hook-ups. The Contractor shall also participate as required in all Recreation Use Surveys that may be conducted.

1.11.5 Park Inspection: The contractor will inspect the park area and facilities a minimum number of times each day as required by the lake appendices. Inspections will be made in a vehicle provided and maintained by the contractor. During all inspections, if the contractor observes park users violating Corps of Engineers rules and regulations, the contractor should advise the visitor of the violation, the contractor is not to pursue enforcement. If violations persist, the contractor should contact a Park Ranger. If a Park Ranger is not available, contractor will record any violations of USACE rules or regulations and forward them immediately to the Lake Manager.

1.11.6 Visitor Assistance: The gatehouse will be occupied by the contractor during the posted hours of the park during which time they will assist the park visitors by providing information concerning the visitors stay. This may include providing free copies of informational pamphlets, rules and regulations and/or maps. The contractor will conduct themselves in a professional and courteous manner at all times. The contractor will advise campers and park visitors: (1) to utilize only developed facilities or designated overflow areas and, (2) to operate and park all vehicles and campers only on paved surfaces or designated parking areas. The contractor will advise campers of quiet hours (10:00 P.M. until 6:00 A.M.) as they enter the park, and assist in maintaining quiet hours.

1.11.7 Disturbances: The contractor will promptly report all accidents, violations of law, disturbances and situations that could affect health and safety of visitors to the Park Ranger or Lake Manager. In the event the contractor is unable to communicate with the Park Ranger and the situation dictates, the contractor will contact the local law enforcement officers as soon as practical. All communications with local law enforcement officers will be reported to the Park Ranger or Lake Manager, on the next workday. The Contractor will not attempt to apprehend any violators or enforce rules, regulations, or laws. Attendants will inform park visitors of rules, regulations and laws and refer violations to the Park Ranger. NOTE: Serious incidents such as a fatality in the park or situations of significant public interest will be reported immediately to the local law enforcement agency and to the Lake Manager.

1.11.8 Complaints: The contractor will keep a written record of all complaints and criticisms of park facilities. These records will be given to the Lake Manager at regular intervals or upon request.

1.11.9 Lost and Found: The contractor will keep lost and found articles in the gatehouse or trailer and turn over all found articles with as much information as possible to a Park Ranger as soon as possible.

1.12 Image, Personal Appearance and Dress:

1.12.1 Favorable Image of the Corps: The contractor will promote a favorable image of the Corps through personal appearance, actions, attitude and a willingness to assist park visitors in a prompt, courteous manner.

1.12.2 Personal Appearance and Dress: The contractor shall, at all times when on duty and when dealing with the public, be required to maintain a fully-clothed and neat, well-groomed appearance. Contractor-furnished shirts, hats and/or vests identifying the contractor as the attendant are encouraged and may be required as noted in the lake appendices. In no way shall these clothing items create an appearance that the contractor or their employee is an employee of the Government. Government-furnished contractor identification badges or tags will be worn by the contractor during on-duty hours at all locations. Cut-offs are not allowed, and shorts must be knee-length or longer. Shoes shall be worn at all times; flip flops or similar footwear will not be permitted.

1.13 Cooperation with Others: The contractor will maintain good communications and relations with the public, other contractors, volunteers, Corps employees and others who work with the Corps of Engineers for the construction of new facilities, repair of existing facilities, sanitation services, trash pick-up services, and grass mowing, etc. The contractor will allow Corps employees to utilize communication facilities furnished by the Government. Cooperation will include, but not be limited to summoning assistance and reporting all instances of vandalism, harassment, public intoxication, speeding, etc., to proper authorities.

The contractor will diligently attempt to provide for the needs of our visiting public as public relations representatives for the Corps of Engineers. The contractor may be asked to work additional days with compensation in the event that another contractor requires emergency time off.

1.14 Living Area and Gatehouse Maintenance:

1.14.1 Trailer Area Maintenance: The contractor will maintain the area where the trailer is parked (Gate Attendant Site) in a clean and sanitary condition at all time. No dog pens, horse corrals, poultry cages or similar facilities for pets or the raising of animals will be allowed.

1.14.2 Pets: All pets will be confined in the contractor’s trailer or on a leash of 6-foot or less in length and must not disturb park visitors. The contractor’s site will remain clean of animal waste at all times. Pets will have all vaccinations as required by the state laws and will wear a collar that displays the vaccination tags at all times. No pets are allowed inside the gatehouse.

1.14.3 Excessive Personal Items: No washers, dryers, deep freezers, or excessive personal items will be permitted around trailer pad areas or inside the gatehouse.

1.14.4 Smoking: Smoking is not allowed in or within 30 feet of the gatehouse.

1.14.5 Gatehouse Maintenance: The contractor will maintain the gatehouse in a clean, orderly and sanitary condition at all times.