Amendment 0002 Revised Quantities. No extension of bid opening date.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| C1_Abstract_of_Bids_or_Proposals.pdf | ||
| Amend-0003_W9126G-16-B-0025.pdf | ||
| AMEND_0001.pdf | ||
| B3_W9126G-16-B-0025-Specs.pdf | ||
| B3_W9126G-16-B-0025-Plans.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICIATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 11)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPIRATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable m3adekaj
W9126G-16-B-0025
A0002-2
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
1. The specifications for Solicitation No. W9126G-16-B-0025, GULF INTRACOASTAL
WATERWAY, TEXAS, ROLLOVER TO CAUSEWAY IN CHAMBERS AND GALVESTON
COUNTIES, TEXAS, PIPELINE DREDGING, are hereby amended as follows:
a) Specifications.
(1) SECTION 00 11 00.00 45, BID SCHEDULE – The enclosed SECTION 00 11 00.00 45 entitled BID SCHEDULE supersedes that issued with this Solicitation.
(2) SECTION 00 73 00.01 45 - SPECIAL CONTRACT REQUIREMENTS, STANDARD – The enclosed SECTION 00 73 00.01 45 entitled SPECIAL CONTRACT REQUIREMENTS, STANDARD supersedes that issued with this Solicitation.
(3) SECTION 35 20 23.16 45 - PIPELINE DREDGING – The enclosed SECTION 35 20 23.16 45 entitled PIPELINE DREDGING supersedes that issued with this Solicitation.
b) Drawings.
(1) DRAWINGS NO. 11 THROUGH 15 - The enclosed Drawings No. 11 through 15, supersedes that issued with this Solicitation.
2. This amendment shall be attached to and become a part of the solicitation.
4 Encls:
1. SECTION 00 11 00.00 45 - BID SCHEDULE
2. SECTION 00 73 00.01 45 - SPECIAL CONTRACT REQUIREMENTS, STANDARD
3. SECTION 35 20 23.16 45 - PIPELINE DREDGING
4. DRAWINGS NO. 11 THROUGH 15
SWG FILE NO.:IWW 1101-293 SOLICITATION NO.:W9126G-16-B-0025
Document 00 11 00.00 45 Page 1
(TO ACCOMPANY AMENDMENT NO. 0002 TO SOLICITATION NO. W9126G-16-B-0025)
SECTION 00 11 00.00 45
BID SCHEDULE
AMENDMENT NO. 0002
PART 1 GENERAL
1.1 1.1 BID SCHEDULE
BID SCHEDULE
(TO BE ATTACHED TO STANDARD FORM 1442)
1.1.1 Schedule No. 1
Item No.
Description Estimated Quantity
Unit Unit Price Estimated Amount
SCHEDULE NO. 1
0001 Mobilization and Demobilization
JOB
SUM
0002 Dredging - Rollover Pass, Section No. 2
45,000
C.Y.
0003 Dredging - Rollover Pass, Section Nos. 3-4
121,000
0004 Pipeline Management - Rollover Pass, Section Nos. 3-4
0005 Dredging - Bolivar Flare, Section Nos. 5-
401,000
0006 Endangered Species Monitoring - West Rollover Beach
TOTAL SCHEDULE NO. 1
NOTE: Completion time stated in SECTION 00 73 00.01 45 is for SCHEDULE NO.
1 work.
Document 00 11 00.00 45 Page 2
BID SCHEDULE (CONT'D)
1.1.2 Option No. 1
Description Estimated Quantity
Unit Unit Price Estimated Amount
OPTION NO. 1
0007 Dredging - Rollover Pass, Section No. 1
42,000
TOTAL OPTION NO. 1
TOTAL SCHEDULE NO. 1 AND OPTION NO. 1
NOTE: The Government may exercise Option No. 1 singly or in combination with other Options by written notice to the Contractor prior to completion of all authorized work. Award of Option No. 1 is contingent upon availability of funds. An additional time of 7 calendar days will be added to this contract for completion of Option No. 1.
Document 00 11 00.00 45 Page 3
1.1.3 Option No. 2
No.
Description Estimated Quantity
Unit Unit Price Estimated Amount
OPTION NO. 2
0008 Dredging - Channel to Port Bolivar, Section No. 7
39,000
TOTAL OPTION NO. 2
TOTAL SCHEDULE NO. 1 AND OPTIONS NOS. 1 AND 2
NOTE: The Government may exercise Option No. 2 singly or in combination of all authorized work. Award of Option No. 2 is contingent upon availability of funds. An additional time of 10 calendar days will be added to this contract for completion of Option No. 2.
Document 00 11 00.00 45 Page 4
1.1.4 Option No. 3
Description Estimated Quantity
Unit Unit Price Estimated Amount
OPTION NO. 3
Dredging - Texas City Junction, Section No. 8
62,000
TOTAL OPTION NO. 3
TOTAL SCHEDULE NO. 1 AND OPTIONS NOS. 1, 2, AND 3
NOTE: The Government may exercise Option No. 3 singly or in combination of all authorized work. Award of Option No. 3 is contingent upon availability of funds. An additional time of 10 calendar days will be added to this contract for completion of Option No. 3.
Document 00 11 00.00 45 Page 5
1.1.5 Option No. 4
Description Estimated Quantity
Unit Unit Price Estimated Amount
OPTION NO. 4
Dredging - Bolivar Mooring Basin, Section
No. 9
93,000
TOTAL OPTION NO. 4
TOTAL SCHEDULE NO. 1 AND OPTIONS NOS. 1, 2, 3, AND 4
NOTE: The Government may exercise Option No. 4 singly or in combination of all authorized work. Award of Option No. 4 is contingent upon availability of funds. An additional time of 13 calendar days will be added to this contract for completion of Option No. 3.
Document 00 11 00.00 45 Page 6
1.2 MODIFICATIONS (CESWG)
If a modification to a bid based on unit prices is submitted, which provides for a lump sum adjustment to the total estimated cost, the application of the lump sum adjustment of each unit price in the bid schedule must be stated. If it is not stated, the bidder agrees that the lump sum adjustment shall be applied on a pro rata basis to every unit price in the bid schedule.
1.3 EVALUATION OF OPTIONS (JULY 1990) (FAR 52.217-5)
Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
-- End of Document --
Document 00 73 00.01 45 Page 1
(TO ACCOMPANY AMENDMENT NO. 0002 TO SOLICITATION NO. W9126G-16-B-0025)
SECTION 00 73 00.01 45
SPECIAL CONTRACT REQUIREMENTS, STANDARD
AMENDMENT NO. 0002
PART 1 GENERAL
1.1 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) (FAR
52.211-10)
The Contractor shall be required to:
(a) Commence work under this contract within 10 calendar days after the date Contractor receives Notice to Proceed;
(b) Prosecute the work diligently, and
(c) Complete the entire work ready for use not later than (AM#2)120 110 calendar days. The time stated for completion shall include final cleanup of the premises.
1.2 PHYSICAL DATA (APR 1984) (FAR 52.236-4)
Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
(a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by survey.
(b) Weather Conditions. Under ordinary conditions, the mean tidal range is about 1.5 feet. The height of tide is largely dependent on the force, direction, and duration of the wind. Strong northerly winds may depress the water surface as much as, and in some instances more than 2 feet below Mean Lower Low Water (MLLW), while southerly winds may raise the water surface as much as, and in some instances more than 4 feet above MLLW.
(c) Transportation Facilities. The immediate vicinity is served by railroad, highway, and deep and shallow draft channels. The work site is accessible by water via the Gulf Intracoastal Waterway, Houston Ship Channel, Galveston Harbor and Channel, and Texas City Ship Channel.
(d) Condition of Channel. The general shape of the existing section of channel to be dredged is shown by cross sections on the Contract drawings.
(e) Channel Traffic. Channel traffic consists of (small boats of various sizes, fishing vessels, ferries, tugs, tows consisting of a tug and one or more barges). Traffic will interfere with dredging operations to some extent.
Document 00 73 00.01 45 Page 2
1.3 LIQUIDATED DAMAGES - CONSTRUCTION (SEPT 2000) (FAR 52.211-12)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $1,330.00 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed.
These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
1.4 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE (MAR 1995)
(a) This special contract requirement does not apply to terminations. See 52.249-5000, Basis for Settlement of Proposals, and FAR Part 49.
(b) Allowable cost for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a contractor or subcontractor at any tier shall be based on actual cost data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the con- tractor's accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series equipment from the contractor's accounting records, costs for that equipment shall be based upon the applicable provisions of EP 1110-1-8, Construction Equipment Ownership and Operating Expense Schedule, Region VI. Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the contracting officer.
For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retroactive pricing, the schedule in effect at the time the work was performed shall apply.
(c) Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-36, Rental Costs. Rates for equipment rented from an organization under common control, lease-purchase arrangements, and sale-leaseback arrangements, will be determined using the schedule, except that actual rates will be used for equipment leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees.
(d) When actual equipment costs are proposed and the total amount of the pricing action exceeds the SAT, the contracting officer shall request the contractor to submit either certified cost or pricing data, or partial/limited data, as appropriate. The data shall be submitted on Standard Form 1411, Contract Pricing Proposal Cover Sheet.
NOTE: A copy of EP 1110-1-8, "CONSTRUCTION EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE," is available at the following website:http://www.publications.usace.army.mil/USACE- Publications/Engineer-Pamphlets/udt_43545_param_page/11/
Document 00 73 00.01 45 Page 3
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
-- End of Document --
Section 35 20 23.16 45 Page 1
(TO ACCOMPANY AMENDMENT NO. 0002 TO SOLICITATION NO. W9126G-16-B-0025)
SECTION 35 20 23.16 45
PIPELINE DREDGING
AMENDMENT NO. 0002
PART 1 GENERAL
1.1 SUMMARY
The work in this Section consists of furnishing plant, labor, materials, and equipment and performing the operations necessary for the removal of materials to the required dimensions shown, satisfactory disposal thereof, and other operations incidental thereto.
1.2 MEASUREMENT AND PAYMENT
Measurement and payment for pipeline dredging will be paid for in accordance with provisions of the SECTION 01 22 00.10 MEASUREMENT AND PAYMENT.
1.3 WORK COVERED BY CONTRACT PRICE
Base bids on the quantity of dredging indicated. If the total quantity of dredging varies from that specified as the basis for bidding, the Contract price will be adjusted in accordance with the CONTRACT CLAUSE entitled CHANGES. The dredging conditions specified and indicated describe conditions which are known. However, the Contractor is responsible for other conditions encountered which are not unusual when compared to the conditions recognized in the dredging business as usual in dredging activities such as those required under this Contract. The Contract price for dredging will include the cost of removal and placement of the material as specified in the Paragraphs: CHARACTER OF MATERIAL and PLACEMENT OF EXCAVATED MATERIAL. The Contract price for dredging shall include the costs for maintenance of levees and ditches necessary to confine the material within the areas shown.
1.3.1 Existing Conditions
The drawings already prepared as specified in the CONTRACT CLAUSES Paragraph entitled CONTRACT DRAWINGS AND SPECIFICATIONS represent conditions existing as of the date of their preparation using average existing conditions.
However, to reflect anticipated shoaling occurring between the dates of preparation of the drawings and the dates of the "before-dredging" sections, the estimated dredging quantities stated in the Bid Schedule have been adjusted accordingly. The depths and elevations shown will be verified and corrected by fathometer soundings taken by the Government before dredging.
The Government will normally use a frequency of 200 kHz to conduct hydrographic surveys. If the surveys indicate the presence of fluff in the channel, a frequency of 40 kHz will be used. Determination of quantities removed and the deductions made from them to determine quantities by in-place measurement to be paid for in the area specified, after having once been made will not be reopened, except on evidence of collusion, fraud, or obvious error.
Section 35 20 23.16 45 Page 2
1.4 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 1110-2-5027 (1987) Confined Disposal of Dredged Material
EM 385-1-1 (2014) Safety and Health Requirements Manual
1.5 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with the SECTION 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Notification Prior To Commencement of Dredging Operations
Indicate commencement of dredging operations, and location of dredge(s).
Temporary Removal of Aids To Navigation
The Contractor shall not remove, change the location of, obstruct, willfully damage, make fast to, or interfere with aids to navigation. Indicate temporary removal or changes in locations of channel markers required to facilitate dredging operations.
Debris Control and Cleanup Plan; G, AO
Prior to commencement of any work at West Rollover Beach Placement Area, including delivery of any plant, equipment or construction materials to the site, submit a Debris Control and Cleanup (DCCP). The DCCP shall consist of the items as specified herein.
"Before Dredging" Beach Placement Site Conditions; G, AO
Submit "Before Dredging" beach photos prior to the start of disposal operations at the West Rollover Beach Placement Area.
"Before Dredging" Beach Profile Cross Sections; G, AO
Provide "Before Dredging" beach profiles prior to the start of disposal operations at the West Rollover Beach Placement Area.
Endangered Species Protection Plan; G, AO
Submit an Endangered Species Protection Plan (ESPP) to include the name and qualifications of the consultant that will be conducting training along with training documentation.
Section 35 20 23.16 45 Page 3
SD-02 Shop Drawings
Submerged Pipeline; G, AO
Indicate pipeline location and installation details as outlined in the Subparagraph: Submerged Dredge Pipeline.
Pipeline Route; G, AO
A detailed pipeline diagram for each Placement Area detailing the pipeline route and anchor locations shall be submitted prior to commencing work on this project.
SD-04 Samples
Discharge End Screening Device; G, AO
Prior to commencement of any dredge material placement work at West Rollover Beach Placement Area, provide working demonstration that the discharge end screening device operates as designed, subject to approval by Contracting Officer.
SD-06 Test Reports
Magnetometer Survey Report; G
No later than 10 working days after demobilization of submerged pipeline routes, submit a magnetometer survey report..
SD-11 Closeout Submittals
"After Dredging" Beach Placement Site Conditions; G, AO
Upon completion of disposal operations and prior to demobilization at the West Rollover Beach Placement Site, submit "After Dredging" beach photos.
"After Dredging" Beach Profile Cross Sections; G, AO
No later than 10 working days after completion of disposal operations at the West Rollover Beach Placement Site, submit "After Dredging" beach profiles.
1.6 CHARACTER OF MATERIAL
The material to be removed is shoals which have accumulated over a period of time. However, some virgin material may be encountered in allowable overdepth, or side slope dredging. Bidders are expected to examine the worksite and the records of previous dredging, which are available in the Galveston Resident Office and after investigation decide for themselves the character of materials.
1.6.1 Debris Within the Dredging Limits
Debris including but not limited to, metal bands, pallets, pieces of broken cable, rope, stumps, and broken piles may be encountered. The Government
Section 35 20 23.16 45 Page 4 has no knowledge of existing wrecks, wreckage, or other material of that size or character as to require the use of explosives or special or additional plant for its economical removal. Debris removed from the dredged area shall be removed from the water. Disposal shall be the responsibility of the Contractor and disposal shall be outside the limits of Government property. If the actual conditions differ from those stated or shown, an adjustment in Contract price or time of completion, or both, will be made in accordance with the CONTRACT CLAUSE entitled DIFFERING SITE CONDITIONS.
1.7 DEBRIS CONTROL AND CLEANUP PLAN REQUIREMENTS
The Debris Control and Cleanup Plan shall include the following:
(1) Shop drawings and detailed descriptions of the required screening device at the discharge end of the pipeline. The plan shall also include the materials, equipment, procedures and personnel to be used in the construction, operations, and oversight of such devices.
(2) Personnel, equipment, and procedures to be used to perform visual inspections of debris accumulation at the discharge end of the pipeline at West Rollover Beach Placement Area.
(3) The measures to be followed if oversized material is discovered in the screening devices (defined as any object large enough to cause damage to the screening device or restrict the flow of dredged material passing through the screening device).
(4) The procedures to inspect, remove, and dispose of all debris collected in the screening device. Inspection of debris accumulation and debris removal from the basket shall be scheduled during standard dredge delays such as non-operating times due to barge traffic or moving pipeline at West Rollover Beach Placement Area.
(5) Estimated downtime per day (in hours) to remove debris from the screening device.
(6) The measures to be followed if any debris are identified as deposited on the West Rollover Beach Placement Area.
1.8 EASEMENTS
Permits authorizing the laying of shore pipe, and for placement of dredge material in the Placement Area(s), are on file and available for examination in the Galveston Resident Office of the U.S. Army Corps of Engineers, Jadwin Building, 2000 Fort Point Road, Galveston, Texas. The instruments authorizing the laying of shore pipelines may contain certain restrictions relative to specific route, location, and general use of the land. These instruments form a part of these specifications and the Contractor shall strictly comply with the terms thereof.
1.9 UTILITIES ACROSS THE LIMITS OF DREDGING
It is the Contractor's responsibility to investigate the location of utility crossings. The Contractor shall take precautions against damages which can result from dredging operations in the vicinity of the utility crossings.
Section 35 20 23.16 45 Page 5
If damage occurs as a result of dredging operations, the Contractor will be required to suspend dredging until the damage is repaired and approved.
Costs of these repairs and downtime of the dredge and attendant plant shall be at the Contractor's expense.
1.9.1 Known Pipeline/Utility Crossings
There are pipelines and/or utilities which are within the work limits. The following pipeline/utilities cross the area(s) to be dredged:
PIPELINE CROSSINGS
APPROXIMATE
STATION
DESCRIPTION
TOP OF PIPE
ELEVATION (feet
MLLW)
OPERATOR
PERMIT NO.
302+339 Two (2) 10-inch Pipelines, (Natural Gas)
-26 Centenas Intrastate Pipeline, LP (303)595-3331
14091
302+441 16-inch Pipeline (Natural Gas)
-29 Williams Field Services Company, LLC (918)573-3454
06950
NOTE: Reasonable effort has beem made to give relevant details on the locations of existing pipelines/utilities. The information provided in the table above and shown on the plans is believed to be substantially correct;
however, exact locations can vary from those shown. Contractor is to coordinate with the respective owner to ascertain the actual position of each pipeline or utility.
THE FOLLOWING IS FURNISHED FOR INFORMATION ON VERIFYING PIPELINE OWNERSHIPS:
Lonestar Notification Center 1-713-223-4567 or 1-800-669-8344
Texas 811 (Dig-Tess) 1-800-344-8377
1.10 ORDER OF WORK
In order to avoid Sea Turtle nesting season, the Contractor shall commence dredging in Section Nos. 3 and 4, from Station 211+000 to Station 221+000, within 10 calendar days of the acknowledgement date of Notice To Proceed, and complete beach placement and debris clean-up at the West Rollover Beach Placement Area no later than March 15 of the calendar year. The Contractor may commence dredging of the remaining sections in the order it desires. The Government reserves the right to change the order of work at any time.
1.10.1 Dredging Options
The Government may award Dredging Options as specified.
1.11 OBSTRUCTION OF CHANNEL
Section 35 20 23.16 45 Page 6
The Government will not undertake to keep the Channel free from vessels or other obstructions, except to the extent of applicable regulations, if any, as may be prescribed by the Secretary of the Army, in accordance with the provisions of Section 7 of the River and Harbor Act approved 8 August 1917.
The Contractor will be required to conduct the work using a method that will obstruct navigation as little as possible, and if the Contractor's plant does obstruct the Channel and makes passage of vessels difficult or endangers them, the plant shall be promptly moved on the approach of a vessel as far as may be necessary to afford a practicable passage.Upon completion of the work, the Contractor shall promptly remove its plant, including ranges, buoys, piles, and other marks placed under this Contract.
1.12 TEMPORARY REMOVAL OF AIDS TO NAVIGATION
The temporary removal or changes in locations of channel markers may be required to facilitate dredging operations. The Contractor shall notify the Contracting Officer at least 21days prior to the date that the removal or change in location of channel markers will be required so the U.S. Coast Guard can perform the work and so navigation interests may be informed sufficiently in advance of the proposed removal or change in location.
The Contractor shall not remove, change the location of, obstruct, willfully damage, make fast to, or interfere with aids to navigation. Indicate temporary removal or changes in locations of channel markers required to facilitate dredging operations.
1.13 NOTIFICATION PRIOR TO COMMENCEMENT OF DREDGING OPERATIONS
Notify the Galveston Resident Office, in writing, at least 10 days prior to commencement of dredging operations, the location or locations at which a dredge or dredges will be placed on the work. This information is required in addition to the progress charts and schedule provided for in the CONTRACT CLAUSE entitled SCHEDULE FOR CONSTRUCTION CONTRACTS.
1.14 SIGNAL LIGHTS
Display signal lights and conduct operations in accordance with the General Regulations of the Department of the Army and of the Coast Guard governing lights and day signals to be displayed by towing vessels with tows on which no signals can be displayed, vessels working on wrecks, dredged, and vessels engaged in laying cables or pipe or in submarine or bank protection operations, lights to be displayed on dredge pipelines, and day signals to be displayed by vessels of more than 65 feet in length moored or anchored in the fairway or channel, and the passing of other vessels of floating plant working in navigable channels, as set forth in Commandant U.S. Coast Guard Instruction M16672.2, Navigation Rules: International-Inland (COMDTINST M16672.2), or 33 CFR 81 Appendix A (International) and 33 CFR 84 through 33 CFR 89 (Inland) as applicable. Navigation Center website location http://www.navcen.uscg.gov/?pageName=navRuleChanges.
1.15 PLANT
1.15.1 General Requirements
Keep the necessary dredge equipment and attendant plant on the job to meet the requirements of the work. The dredge equipment and attendant plant shall be in satisfactory operating condition and capable of safely and
Section 35 20 23.16 45 Page 7 efficiently performing the work as set forth in specifications and shall be subject to inspection by the Contracting Officer's representative at all times.
1.15.2 Capacity
The effective production rate of the dredge plant shall not be less than 360,000 cubic yards per month. No reduction in the capacity of the dredge equipment and attendant plant employed to execute the work shall be made except by written direction of the Contracting Officer. The measure of the "Capacity of the Dredge and Attendant Plant" shall be its actual performance on the work to which these specifications apply.
PART 2 PRODUCTS
2.1 BRIDGE-TO-BRIDGE RADIOTELEPHONE EQUIPMENT
Dredge and self-propelled attendant floating plant shall be radiotelephone equipped to comply with the provisions of the Vessel Bridge-to-Bridge Radiotelephone Act (Public Law 92-63). This will require, as a minimum, the radiotelephone equipment capable of transmitting and receiving on 156.65 MHz (Channel 13). Multi-channel equipment will also require 156.8 MHz (Channel 16). Dredge tugs and tenders will be considered towing vessels within the meaning of the Act.
2.2 LOOKOUTS AND RADIO COMMUNICATIONS
When working in the Gulf Intracoastal Waterway, the Contractor shall have a lookout person posted in the dredge control room at all times to visually monitor the movement of vessels around the dredge plant; to perform radio communications with company workboats; and to deliver passing arrangements with other commercial, fishing and recreational vessels. The lookout shall be competent in U.S. Coast Guard and Federal Communications Commission radio communications procedures and requirements and shall be trained in the Vessel Bridge to Bridge Radiotelephone Act. The lookout shall maintain up to the minute information on the status of each company workboat and approaching vessels, and will communicate this information as required to prevent collisions. Each company workboat shall check in with the lookout when arriving at the dredge and shall receive radio clearance from the lookout before departing the dredge.
FAILURE TO COMPLY WITH THIS REQUIREMENT WILL BE CONSIDERED A VIOLATION OF
THE SAFETY PROTOCOL ESTABLISHED HEREIN. PURSUANT TO THE DIRECTION OF THE
CONTRACTING OFFICER, THE CONTRACTOR MAY BE REQUIRED TO CEASE OPERATIONS
UNTIL THIS PROVISION IS COMPLIED WITH. A SUSPENSION, DELAY OR INTERRUPTION
OF WORK ARISING FROM NON-COMPLIANCE OF THIS PROVISION SHALL NOT CONSTITUTE A
BREACH OF THIS CONTRACT ON THE GOVERNMENT'S BEHALF AND SHALL NOT ENTITLE THE
CONTRACTOR TO A PRICE ADJUSTMENT IN ACCORDANCE WITH THE CONTRACT CLAUSE
ENTITLED SUSPENSION OF WORK OR ANY OTHER PROVISION UNDER THIS CONTRACT.
PART 3 EXECUTION
3.1 DISCHARGE END SCREENING DEVICES
3.1.1 General
Section 35 20 23.16 45 Page 8
Prevent debris from being placed on the West Rollover Beach Placement Site by utilizing a Discharge End Screening Device. The required screening device shall meet the following requirements:
(1) The screening device shall be made of rugged steel or composite material, one-piece or welded members, and constructed as a basket-type device to retain debris and prevent debris from spreading across the footprint of West Rollover Beach Placement Site during dredging operations.
(2) Relief windows will be permitted only to the side opposite of the inflow and at least 12 inches from the bottom of the basket. Windows shall be sized and located to prevent large items from escaping the basket during dredging operations.
(3) The screening device shall be designed to retain all items 0.75 inches in diameter and larger. The openings on the screening device shall be of uniform dimension (i.e. a grid or a series of round holes).
Slotted openings will not be permitted. The maximum allowable opening size is 0.75 inches x 0.75 inches.
(4) The screening device shall be removable for easy replacement if damaged and shall provide a production rate that allows the Contractor to complete all dredging and beach placement area work within the contract duration.
(5) The screening device shall be designed for easy access to periodically remove accumulated debris within the basket.
(6) Maintain adequate replacement parts and additional screening devices on site to ensure the production for the work does not stop due to damaged devices, or delays in the inspection and cleanup process.
(7) The screening device to be used shall be demonstrated on site by the Contractor to meet all requirements as specified and are subject to approval of the Contracting Officer.
Provide minor adjustments to the beach screening devices as directed by the Contracting Officer to accommodate varying types and amounts of material being screened at the beach, at no additional cost to the Government. Minor adjustments to the beach screening devices will be made during standard dredge delays or while devices are out of rotation and not in use. As an example, relief windows other than the required screen apertures are sometimes needed to be enlarged, reduced, or relocated to minimize residual debris in the basket during the inflow process.
3.1.2 Inspection of Oversized Material
Implement a method for inspection of all oversized material collected during beach placement pumping operations. Every effort shall be made to flush all sand out of the residual material to allow for 100 percent inspection.
3.2 DEBRIS CLEANUP WEST ROLLOVER BEACH PLACEMENT AREA
The Contractor may encounter debris passing through the screening device and onto the beach during dredging operations. The Contractor shall thoroughly remove all debris discharged within the limits of the West Rollover Beach
Section 35 20 23.16 45 Page 9
(TO ACCOMPANY AMENDMENT NO. 0002 TO SOLICITATION NO. W9126G-16-B-0025)
Placement Site by their dredging operations. The Contractor shall inspect the entire footprint of the West Rollover Beach Placement Site and remove all non-metal and metal debris.
3.3 EXISTING CONDITIONS WEST ROLLOVER BEACH PLACEMENT AREA
3.3.1 "Before Dredging" Beach Placement Site Conditions
Document, with photos, the "before dredging" condition of West Rollover Beach Placement Site and provide such documentation to the Galveston Resident Office prior to the start of placement operations. Include the contract title, the contract number, the date the photo was taken and the station number or approximate location where each photo was taken. At a minimum, take the "before dredging" beach condition photos at 500 foot increments along the entire West Rollover Beach Placement site. Submitted photos shall be of sufficient quality to distinguish the "before dredging" debris and trash along the beach.
3.3.2 "After Dredging" Beach Placement Site Conditions
Document, with photos, the "after dredging" condition of West Rollover Beach Placement Site and provide such documentation to the Galveston Resident Office prior to demobilization from the jobsite. Include the contract title, the contract number, the date the photo was taken and the station number or approximate location where each photo was taken. At a minimum, take the "after dredging" beach condition photos at 500 foot increments along the entire West Rollover Beach Placement site. "After dredging" photos shall be taken at the same locations as the "Before dredging" photos.
Submitted photos shall be of sufficient quality to distinguish the "after dredging" debris and trash along the beach. Upon review of the "After Dredging" Beach Placement Site Conditions, the Government will make a determination if additional site cleanup will be required at the Contractor's expense.
3.4 ESTIMATED QUANTITY OF MATERIAL
Within the limits of available funds, the Contractor will be required to excavate the entire quantity of material necessary to complete the work specified whether the quantities involved are greater or less than those estimated. The work is to be done in accordance with this Contract and at the Contract price or prices, subject to the provisions of the SECTION 01 10
00.01 45 NON-REGULATED SPECIAL CONTRACT REQUIREMENTS, Paragraph entitled
VARIATIONS IN ESTIMATED QUANTITIES - DREDGING.
3.4.1 Quantity Summary
The quantities listed in Appendix 1 - QUANTITY SUMMARY TABLE include the volumes present at the time of the surveys indicated on the Contract drawings, plus anticipated shoaling before dredging begins. For the purpose of acceptance, the pipeline dredging work in the Bid Item(s) of the Bidding Schedule are divided into Sections.
3.4.2 Required Dredging Prism
The total estimated amount of material to be removed from within the specified limits, including side and end slopes and including anticipated shoaling occurring prior to the dates of the "before-dredging" surveys but
Section 35 20 23.16 45 Page 10 excluding overdepths, in cubic yards is listed in Appendix 1 - QUANTITY
SUMMARY TABLE.
3.4.3 Allowable Overdepth
To cover unavoidable inaccuracies of the dredging process, material actually removed from the designated areas to be dredged, will be measured and paid for at full Contract price. The maximum amount of allowable overdepth dredging is estimated, including anticipated shoaling occurring prior to the dates of the "before-dredging" surveys in cubic yards is listed in Appendix
1 - QUANTITY SUMMARY TABLE.
3.4.4 Side And End Slopes
Dredging of the side and end slopes shall follow, as closely as practicable, the lines indicated or specified. Material actually removed from within the limits as approved, to provide for final side and end slopes as specified, but not in excess of the amounts originally above the limiting side and end slopes will be estimated and paid for, whether dredged in original position or by dredging the space below the pay slope plane at the bottom of the slope for upslope material capable of falling into the cut. In computing the limiting amount of side and end slope dredging, net dimensions, without allowance for overdepth, will be used.
3.4.5 Excessive Dredging
Material taken from beyond the limits specified will be deducted from the total amount dredged as excessive overdepth dredging or excessive side or end slope dredging, for which payment will not be made. Nothing herein shall be construed to prevent payment for the removal of shoals performed in accordance with the applicable provisions of the SECTION 01 10 00.01 45 NON- REGULATED SPECIAL CONTRACT REQUIREMENTS, Paragraph FINAL EXAMINATION AND ACCEPTANCE or Paragraph SHOALING.
3.5 AREAS TO BE DREDGED
Based on information currently available to the Government, areas known to require dredging are shown.
3.6 CONDUCT OF DREDGING WORK
3.6.1 Pre-Operations Safety Coordination Meeting
Prior to arrival on location and commencing dredge operations, the Contractor shall attend a pre-dredging safety coordination meeting between the dredge operators, pilots, towing industry representatives, VTS, and the affected port. It is the Contractor's responsibility to contact Houston Vessel Traffic Service (VTS) at 713-671-5103 to coordinate and schedule this meeting. Contractor shall inform the Government at least 48 hours prior to the scheduled meeting so that a Government Representative may attend.
3.6.2 Protection of Existing Waterways
Conduct dredging operations using a method that will ensure that material or other debris are not pushed outside of the dredging limits or otherwise deposited in existing side channels, basins, docking areas, or other areas being used by vessels. The Contractor will be required to change its method
Section 35 20 23.16 45 Page 11
(TO ACCOMPANY AMENDMENT NO. 0002 TO SOLICITATION NO. W9126G-16-B-0025)
of operations as may be required to comply with the above requirements. If bottom material or other debris is pushed into areas noted above, as a result of the Contractor's operations, the same shall be promptly removed by and at the expense of the Contractor to the satisfaction of the Contracting Officer.
3.6.3 Adjacent Property and Structures
No dredging will be permitted within 25 feet of a structure. Damage to private or public property or structures resulting from the disposal or dredging operations shall be repaired promptly by and at the Contractor's expense. Damage to structures as a result of Contractor's negligence will result in suspension of dredging and require prompt repair at the Contractor's expense as a prerequisite to the resumption of dredging. Where dredging to obtain the required dimensions might endanger a structure, the Contracting Officer, upon request, may reduce the required excavation in the vicinity of this structure.
3.7 PLACEMENT OF EXCAVATED MATERIAL
3.7.1 General
Material excavated shall be transported to and deposited in the Placement Area designated. Inspect the Placement Area to ensure that using the Area for placement operations will not place it in violation of the applicable Federal, State, or local statutes concerning fish and wildlife. Particular statutes which the Contractor shall consider include, but are not limited to, the Federal Migratory Bird Treaty Act and the Endangered Species Act of 1973.
3.7.1.1 Misplaced Material
Material shall not be deposited or allowed to flow into project channels or into a bayou, stream tributary to the Channel, or into an existing drainage outlet ditch, canal, water intake or outlet facility, nor shall materials be allowed to flow onto improved areas including highways and roads in or adjacent to the Placement Area. If a stream, bayou drainage outlet, ditch, canal, water intake or outlet facility becomes shoaled as a result of the pipeline dredging or placement operations, promptly remove these shoals and the material shall be placed in the Placement Area. Dragging or washing operations to remove the shoals will not be permitted.
3.7.1.2 Placement Operations Inspection
Adequately inspect placement operations in the Placement Area(s) daily to reduce the possibility of accidental breaching of levees and spillway with resulting spillage of dredged materials outside the Area. If levee failures occur while materials are being pumped into the Placement Area, dredging operations shall be stopped immediately, and the deposit of material in the Area shall not be resumed until the confining structures have been restored to an approved condition. Holes dug on the banks for deadmen or anchorage shall be filled. Confined areas shall be maintained in an operational condition until completion and acceptance of the work under this Contract.
The SECTION 01 10 00.01 45 NON-REGULATED SPECIAL CONTRACT REQUIREMENTS, Paragraph DAMAGE TO WORK is only applicable to damage of levees and other non-dredging items.
Section 35 20 23.16 45 Page 12
(TO ACCOMPANY AMENDMENT NO. 0002 TO SOLICITATION NO. W9126G-16-B-0025)
3.7.1.3 Placement Area Drainage
Deposited materials shall not impound water or impede natural drainage. The Contractor shall, if necessary, excavate and maintain ditches to drain the low areas in the dredged material and Placement Area to the weirs. The ditches shall be of adequate number and size to eliminate ponding of water within the limits of the Placement Area.
3.7.1.4 Maintenance of Existing Levees and Drop-outlet Structures
The available information regarding the heights and dimensions of levees and dimensions and elevations of the drop-outlet structures are contained in these Contract documents; however, it is the responsibility of the Contractor to verify the current condition of the levees prior to commencement of dredging and to notify the Contracting Officer of slumped or failed areas where there appears to be a potential for failure or overtopping during ponding. The Contractor will have the responsibility of continually monitoring the levees condition and to maintain the levees in a condition and elevation equal to or better than the condition of the levees at the date of this Contract award. The Contractor shall also construct temporary access from the existing roadway to each drop-outlet structure in each Placement Area.
3.7.2 Spillway Operations
Once placement operations are completed in a confined area for which the Placement Area is being used, the boards on the spillway of that Placement Area shall be removed at a proper rate to allow drainage of the Area. In confined areas, levee and spillway work required shall be completed and accepted prior to placement operations in that Area. Spillways shall be operated in general accordance with guidelines contained in the Engineering Manual EM 1110-2-5027 entitled "Confined Disposal of Dredged Material", to maintain uniformity of weir elevation around the drop-out structure, as is practicable, during discharge of effluent. Boards shall be uniform in width and of proper length so insertion and removal is not difficult. Cracked, warped or boards of improper length shall be replaced. Seepage between boards during ponding shall be eliminated using plastic sheeting or other effective methods. Upon completion of discharge within a particular Area, the Contractor shall remove the boards as soon as practicable to accomplish drainage of the Area.
3.7.3 Placement Areas
The Contractor shall place dredged material from each Section into the appropriate Placement Areas as follows:
3.7.3.1 Confined Placement Area No. 35
If Option No. 1 is exercised, material dredged from Section No. 1 shall be deposited in Confined Placement Area No. 35. Material dredged from Section No. 2 under Schedule No. 1 shall be deposited in PA 35. The Contractor shall be required to place Section No. 1 dredged material into discharge corridor "A" and Section No. 2 dredged material into discharge corridor "B".
The perimeter levee of Confined Placement Area No. 35 shall be maintained to the existing elevation and repaired as necessary for the duration of the contract. Monitor and control movement of the discharge point to ensure even build-up of material throughout the discharge corridor.
Section 35 20 23.16 45 Page 13
(TO ACCOMPANY AMENDMENT NO. 0002 TO SOLICITATION NO. W9126G-16-B-0025)
Prior to the start of dredging operations, the Contractor shall remove the mounds of existing dredged material that have accumulated in the ditch between the training levees, to relieve the water in the placement area and facilitate drainage to the spillway. At a minimum, the accumulated material in ditch shall be excavated to 3 feet below the existing material elevation within the delineated area shown on the drawings. The excavated material shall be sidecasted evenly along the side slopes of the training levees.
3.7.3.2 West Rollover Beach Placement Area
Material dredged from Section Nos. 3 and 4 shall be deposited in the West Rollover Beach Placement Site. The dredge material shall be distributed evenly along the beach and the number of dredge pipeline movements shall be in direct proportion to the length of the channel reach and the length of the beach front to pump in. The Contractor shall not allow pipeline movement closer than 300 feet. The Contractor will be required to furnish "Before Dredging" Beach Profile Cross Sections to the Government, immediately prior to the start of dredging operations, and "After Dredging" Beach Profile Cross Sections upon the completion of dredging operations within Section Nos. 3 and 4. Establish a 3,000 foot baseline and a benchmark for vertical control, on which the profiles shall be based. The baseline shall follow a line extending the bulkhead on the west bank of Rollover Pass, to a point 4,000 feet west on the open beach. The beach profile shall be essentially perpendicular to the Rollover Pass Channel centerline, and shall be placed parallel to, and no closer than 50 feet from the vegetation line along Rollover Beach. Beach profiles shall be taken every 300 feet along the established baseline, starting 1,000 feet from the Rollover Pass West Bulkhead. Beach profiles shall also be taken at each discharge point. The beach profiles shall be 500 feet in length, extending 50 feet shoreward from the established baseline and extending 450 feet seaward from the established baseline. Point elevations shall be taken at all surface inflections or every 20 feet which ever is less. The "Before Dredging" and "After Dredging" beach profiles shall be taken at the same locations on the baseline, immediately prior to and after dredge disposal operations in West Rollover Beach Placement Area discharge corridor. The "Before Dredging" completed survey data, along with the plotted cross sections, drawn to scale shall be submitted to Galveston Resident Office, prior to start of any work at West Rollover Beach Placement Site. The "After Dredging" completed survey data, along with plotted cross sections, drawn to scale shall be submitted to the Galveston Resident Office, within 10 working days after completion of dredging operations in Section Nos. 3 and 4.
Provide a minimum of 4 temporary safe access ramps over the dredge pipeline corridor along the west bank of Rollover Pass. The safe access ramps shall be constructed to enable public foot traffic to traverse over the dredge pipeline corridor and access the west bank of Rollover Pass. The safe access ramp crossovers shall be spaced evenly along the dredge pipeline corridor on west bank and remain in place for public use during the entire duration of dredging operations at West Rollover Beach Placement Area.
Remove the safe access ramps and restore the area to pre-existing conditions once all of the dredge pipeline across Rollover Pass is demobilized from the jobsite. Construct the safe access ramps as required by EM 385-1-1.
3.7.3.3 Confined Placement Area No. 42
Section 35 20 23.16 45 Page 14
(TO ACCOMPANY AMENDMENT NO. 0002 TO SOLICITATION NO. W9126G-16-B-0025)
Material dredged from Section No. 5 shall be deposited in Confined Placement Area No. 42. The Contractor shall be required to place (AM#2)dredged material into both discharge corridor "A" and discharge corridor "B".a maximum of 100,000 cubic yards of dredged material into discharge corridor "A" and a maximum of 100,000 cubic yards of dredged material into discharge corridor "B". The Contractor will be required to use discharge corridors "A" and "B" for this contract. Material dredged from Section No. 9 shall be deposited in Confined Placement Area No. 42. The Contractor shall be required to place Section No. 9 dredged material into Discharge Corridor "C".
This is the start of the file's text. The full file is on GovTribe.