SF30 Amendment 0001 W9124X22Q0009.pdf
PDF 552 KB Posted
- Solicitation number
- W9124X22Q0009
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
0011749203
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
This amendment provides answ ers to RFIs and exends the due date for qoutes.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 14-Mar-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9124X22Q0009
X 9B. DATED (SEE ITEM 11)
25-Feb-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
14-Mar-2022
CODE
USPFO NV P&C
2452 FAIRVIEW DRIVE
CARSON CITY NV 89701-6807
W9124X 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9124X22Q0009
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
ANSWERS TO RFIS
CERFP Exercise - Responses to Requests for Information
1. Per Section 4 CFE - it states "toilets" are to be provided, yet Tech Exhibit 7.4 states onsite resources include...e) Toilets: Port-a-potties - YES.
-Toilets/Port-a-potties are to be provided by the government and are not required by this contract.
2. Does the contractor need to provide a forklift for SCVS reset?
-A forklift will NOT be provided by the government. The contractor will need a forklift to move slabs and/or training props around the site for training each day. Government representative on site each day will determine if props need to be moved or adjusted, as a result daily coordination is required.
3. Will concrete slabs need to be emplaced as part of the preparation and/or reset of the SCVS?
- Concrete slabs are available for use at the site already, but must be replaced by the contractor following the training exercise.
- Concrete slabs are not currently in place for training and will need to be moved to the government representative’s desired location prior to the start of the training exercise.
- Approximately 15 Slabs of concrete are expected to be moved/replaced over the entire 3-day period.
4. Please define the requirements for the Lumber Kit.
Lumber Package:
a. 24x – 4”x4”x10’ Wood
b. 11x – 2”x4”x10’ Wood
c. 3x – 2”x6”x8’ Wood
d. 2x – 3/4 Plywood Sheet
e. 2x – 500 Box 16D Nails
f. 1x – 500 Box 8D Nails
5. Per Section 5.3 - Task 3 - the task title states..."Real World Medical Support" but no mention of the exact requirements. Please advise if Advanced or Basic Life Support is required for this training. If yes, which level of support, ALS or BLS and days and hours of support?
-Real world medical EMS is not required by this contract. Standby EMS will be provided by another vendor in case of an emergency on site during training. “Real World Medical Support” in the title for Section 5.3 was a mistake, Section 5.3 is intended to explain requirements for Moulage/Manikins/Role Players only.
6. Per Section 5.6.1.2 - it contains the language, "(if required)", in reference to providing 3 SMEs. Please confirm these SMES are required.
-3 SME’s are required to assist with S&E service members.
-The venue will not support a collapsed structure or training on a collapsed structure.
-The 3 SME’s are intended to assist in the skillsets listed in 5.6.1.3. Most S&E training will be preliminary, to include tool instruction, breaching and breaking slabs, shoring, etc.
7. Please provide a Map of the SCVS training area to include RP parking and the "fixed" moulage site. Also, please provide distances between each area so Offerors may determine proper transportation requirements.
-See attached. Distances between Moulage Site / Parking / Rubble pile are projected to be no more than 150 yards.
8. How many manikins are required by the contractor?
-10 manikins will be required of the contractor.
9. Is the contractor required to fabricate any breaching slabs? Or will cured breaching slabs already be in place on site?
-Refer to answer to question 3.
10. Is there a Lumber pack requirement for the contractor?
-Refer to answer to question 4.
11. The PWS requires only one moulage artist. Can the government confirm that this is all they are requiring to support 50 daily casualty role players?
The contractor is required to support 50 daily casualty players, anticipate 25 role players requiring moulage each day.
12. Can the government confirm that the contractor does not have to provide forklift or other heavy equipment and that this will be provided by another contractor?
-Refer to answer to question 2.
13. Can the government confirm that there is no building/structure available for role player player operations and the contractor will be required to provide tentage, tables/chairs, and air conditioning?
-There are no facilities or buildings at the training site. Tents, tables, chairs and AC will not be provided by the government.
14. Is there a real world ambulance requirement on this contract?
-No, the Government will provide real world ambulance and EMS support.
15. Can the government confirm if porta-johns for the role players and staff will be provided by the government?
-Refer to answer to question 1.
16. Can the government confirm how “relevant past performance” will be defined an applied in the proposals and the award selection?
-Relevant past performance will be defined as exercises similar in scope performed by the contractor. Please provide brief summary of exercises, dates, requiring activities, number of participants, contract numbers, and award amounts.
17. Can the government confirm how many Prime past performance CERFP exercises will be required to determine acceptable past performance?
-The contractor can submit descriptions of up to 5 exercises previously performed.
18. Can the government confirm if this will be a BEST VALUE TRADE OFF award selection?
This contract will utilize best value criteria. Refer to the evaluation factors stated in the solicitation. 52.212-2 Evaluation- Commercial Items
19. Will there be any mandatory meetings with the unit personnel or evaluators on 13 April, the day before STARTEX, for any of the contractor personnel. If so, who is required and when and where will these meetings be?
-Attendance on 13 April will be required by the contractor’s lead representative at a minimum. The location will be at the training site.
-The government only expects to coordinate the training event and give a concept of operations brief on 13 April.
This includes setup locations for contactors, expectations for where training aids are to be placed, and any preliminary information for trainers/evaluators.
SECTION SF 1449 - CONTINUATION SHEET
SOLICITATION/CONTRACT FORM
The required response date/time has changed from 16-Mar-2022 10:00 AM to 21-Mar-2022 10:00 AM.
(End of Summary of Changes)