Statement of Work WG-300-2J ED-302-2J TPG Bridge 2024.pdf

PDF 414 KB Posted

Attached to
IDIQ Bridge Repair
Solicitation number
W9124M24S0003
Issued by

About this file

This sources sought notice seeks information from small businesses for a potential bridge repair Indefinite Delivery Indefinite Quantity (IDIQ) contract. The U.S. Army Materiel Command Mission and Installation Contracting Command plans to set aside this requirement for small businesses provided two or more qualify and can fulfill the work between $5 million to $10 million. Firms should indicate if they can meet the size standard of $45 million for NAICS code 237310, Highway, Street, and Bridge Construction, and have experience as a prime or subcontractor on similar bridge repair projects. Responses are requested to include company information, interest as a prime or subcontractor, relevant experience, ability to meet limitations on subcontracting, pricing details for bridge repair work, and recommendations to improve the draft statement of work or performance requirements.

View the file

Other files

File Type Posted
QUESTIONS AND ANSWERS TO SOURCES SOUGHT.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TECHNICAL PROVISIONS

GENERAL

Maintain and Repair Bridges (IDIQ)

IJO Nos. WG-300-2J/ED-302-2J

FS-4217/H-2127

1 DESCRIPTION OF WORK:

1.1 Work to be Done: The work covered by this contract consists of furnishing all plant, labor, materials and performing all operations required in connection with Maintain and Repair Bridges (IDIQ) complete in strict accordance with specifications and drawings. The work includes, but is not necessarily restricted to, the following items.

1.2 SCOPE OF WORK:

The work covered by this contract consists of furnishing all plant, labor, materials and performing all operations required in connection with Maintain and Repair Bridges (IDIQ), Ft Stewart and Hunter AAF and shall be complete in strict accordance with specifications and drawings. The work includes, but is not necessarily restricted to, the following items.

1.2.1 After receipt of contract award and upon notification by the Contracting

Officer, the Contractor shall meet Government personnel for the purpose of verifying existing site conditions of each bridge. The contractor and Government will visit each bridge for the purpose of scoping the work to be done. Performance time will be cited on each delivery order in accordance with the contract provision entitled, “Delivery Order Performance Time”.

1.2.2 Contractor shall demolish as issued by the delivery order existing bridge(s) which may include bulkheads, wingwalls, stringers, piles, caps, decking, and miscellaneous items.

1.2.3 Contractor shall remove all debris and demolished material to the appropriate sites. No landfills are available to use on Ft. Stewart or Hunter AAF.

1.2.4 Contractor shall construct new timber bridges or repair by component replacement as issued by the delivery order to include bulkheads, wingwalls, stringers, decking, piles, caps, signs, miscellaneous bolts and fasteners, etc., as directed in the scope of work to the details shown on the drawings and as described in the specifications. The work also includes clearing brush, excavation, backfilling, compacting, and grading as required in each individual delivery order.

1.2.5 Contractor shall repair cracks and spalls in concrete bridges and culverts.

1.2.6 Contractor shall seal joints in concrete bridge and culvert decks and substructures.

1.2.7 Contractor shall install concrete bridge approaches for timber bridges.

1.2.8 Contractor shall install and repair signs for bridge classification information, regulations and warnings.

1.2.9 Contractor shall install storm piping in location directed. This work includes excavation, backfilling, compacting, and grading as necessary as required in each individual delivery order.

1.2.10 Contractor shall seed and establish grass in all disturbed areas.

1.3 Additives – N / A

1.4 Government Furnished – Government Installed (GF-GI) Furniture and

Equipment: – N / A

1.5 Government Furnished – Contractor Installed (GF-CI) Furniture and

Equipment: – N / A

1.6 Contractor Furnished – Contractor Installed (CF-CI) Furniture and

Equipment: – N / A

1.7 WORK BY OTHERS: The Contractor shall afford the Government and separate contractors reasonable opportunity for the introduction and storage of their materials and equipment and the execution of their work, and shall connect and coordinate his work with theirs as required by the Contract Documents.

1.8 DRAWINGS AND SITE VISITS

The drawings provide details for the maintenance and repair of bridges on

Fort Stewart and Hunter Army Airfield. It is strongly recommended that the Contractor visit the site to determine the complexity of the work and the amount of material required to perform this project. Field measurements may be necessary to determine the size and quantity of materials. Conditions which are obvious/visible or which should be reasonably anticipated by the Contractor on inspection will not be considered under the Differing Site Conditions provision of the contract.

1.9 ENVIRONMENTAL REQUIREMENTS

Contractor shall comply with “Attachment A - Environmental

Requirements” for the following items:

• Recycling, Salvage and Disposal of Materials Fort Stewart and Hunter Army Airfield

• Toxic Substances Control Act (TSCA) Requirements

• Stormwater / Erosion and Sedimentation Control (E & S) Requirements

• Painting Operations

• Cultural Resource Management (CRM)

2 CONSTRUCTION CONSTRAINTS

2.1 Time of Performance

2.1.1 Access to Buildings – N / A

2.1.2 Work Requiring Outages – N / A

2.2 Outages – N / A

2.3 Continuity – N / A

2.4 Road and/or Railroad Closures

2.4.1 Contractor shall request closure of the road, railroad or bridges by written request to the Contracting Officer’s Representative at least 15 working days prior to the desired closing date for any road, railroad or bridge, or portion thereof, to traffic. The request shall also include a schedule of work for each phase of work for each bridge to be replaced or repaired. A sketch shall be provided showing locations of closure area and placement of barricades and signs for traffic control.

2.4.2 Before closing or removing a road or bridge, contractor shall furnish and erect approved barricades, warning lights, signals and signs to protect the public as approved by the Contracting Officer Representative. Contractor will be responsible for maintaining traffic control devices during construction at each bridge location.

2.4.3 During minor repairs and deck cleaning on bridge the contractor shall maintain one-way traffic on bridges where applicable.

2.5 Entry – Entry to all areas, except the cantonment area, shall be coordinated with the Contracting Officer’s Representative and Range Control, Building 8302, 2405 Georgia Highway 144 East (intersection of Highway 144 and Fort Stewart Road 47) and the Provost Marshal’s Office.

The contractor shall notify the Contracting Officer’s Representative 30 working days in advance to coordinate the contract performance with the Range Control office.

2.6 Fire Zone – The contractor is required to provide 72-hour notice to the

Contracting Officer prior to the final programming of the fire zone information at the main fire station.

2.7 Foreign Object Debris (FOD) – The Contractor shall take special precautions to contain Foreign Object Debris (FOD) in and around any runways, taxiways and aprons.

2.8 Operational Safety on the Airfield During Construction – N / A

3 CONSTRUCTION ACTIVITIES:

3.1 Contractor shall submit a Safety Plan and Construction Schedule to the

Contracting Officer’s Representative (COR) 10 days in advance of any construction activities to arrange specific schedule for performing work as required by this Contract.

3.2 The contractor shall provide and maintain an effective quality control program that complies with the contract clause entitled "Inspection of Construction" (FAR 52.246-12), the below stated quality control requirements and the quality control requirements stated in the respective section of the specifications.

3.2.1 The contractor shall establish a quality control system to perform sufficient inspection and testing of all items of work, including that of his subcontractors. The quality control system shall ensure conformance with applicable specifications and drawings with respect to materials, workmanship, construction, finish, functional performance, and identification. The quality control system shall be established for all construction except where the technical provisions of the contract provide for specific Government control by inspections, tests, or other means. The contractor's control system shall specifically include the surveillance and tests required in the technical provisions of the contract specifications.

Quality control personnel shall also be charged with the responsibility of policing Contractor's Safety Program. This duty shall be clearly set forth in the quality control program.

3.2.2 Before construction operations are commenced, the Contractor shall meet with the Contracting Officer and discuss his quality control plan. The meeting shall develop mutual understanding relative to details of the system, including the forms to be used for recording the quality control operations, inspections, administration of the system, and the interrelationship of Contractor and Government Inspection.

3.2.3 Safety and Health; All work shall be in compliance with U.S. Army Corps of Engineers USACE Engineering Manual 385-1-1.

3.3 Key Personnel

3.3.1 Site Superintendent: The Contractor shall provide a single, Site

Superintendent and an alternate for each resulting order. The Site Superintendent shall have a minimum of five (5) years' experience in the types of projects described in Paragraph 1.1, “Work to be Done”, with a minimum of three (3) years' experience in a supervisory position. A resume of this experience shall be submitted within 15 days after award and shall indicate the superintendent position possesses the particular knowledge, skills, and abilities to successfully perform the duties of the position. The candidate shall show evidence of journeyman level experience in an accepted construction trade. Supervisory experience may run concurrent with general construction experience. The education qualifications shall, at a minimum include a graduate of an accredited technical school in an appropriate field of study relating to an accepted construction trade, equitable qualifications through a recognized union in the construction trades arena, or current or former licensed owner/operator of a business specializing in the construction field.

Depending on the experience, the education requirement may be waived on a case-by-case basis.

3.3.2 Quality Control Manager: The Contractor shall provide Quality Control personnel who are on-site at all times during construction and employed by the Prime Contractor. The proposed CQC System personnel shall have a minimum of five (5) years of experience in the construction field with a minimum of three (3) years of experience in construction quality control inspection/management. A resume of this experience shall be submitted within 15 days after award and shall indicate the QC representative position possesses the particular knowledge, skills, and abilities to successfully perform the duties of the position. This experience should be on projects that have a dollar value greater than $100,000 and of a type similar to the types of projects listed in the Scope of Work.

4 FACTORS AFFECTING PERFORMANCE UNDER THIS CONTRACT:

4.1 The Contractor shall coordinate use of work sites for access, staging, and parking with the COR.

4.2 Contractor shall be responsible for limiting access of its employees and subcontractors to the area of work defined in the Contract.

4.3 Contractor shall maintain haul routes to and from the job sites and the borrow pits, to include the borrow pit. In addition, it is the contractor’s responsibility to meet all Local, State and Federal regulations for the operation of a borrow pit. Contractor shall control runoff and erosion on all excavation and backfilling operations.

4.4 Electric power will not be available for use at job site. It shall be the contractor’s responsibility to furnish all necessary electrical power, temporary wiring and safety devices necessary to comply with the applicable codes/safety requirements.

4.5 Maintenance work on bridges shall be limited to 10 bridges at one time unless approved by the COR. Total bridge replacement shall be limited to two bridges at one time unless approved by the COR.

4.6 Excavation Permits: Permits shall be issued by using the Georgia 811, Utilities Protection Center, Inc. Phone number is 1-800-282-7411.

Excavation of any type is prohibited after normal working hours without prior approval of the Contracting Officer.

4.7 Contractor office trailers and storage yard will be in accordance with “US

Army Garrison, Ft. Stewart and Hunter AAF Policy memorandum #16 - Design and Maintenance of Contractor Storage” dated 25 January 2013.

4.8 Electrical power for temporary construction office during contract will be accomplished through coordination and paid to Canoochee EMC.

5 AS-BUILT RECORD DRAWINGS: – N / A

6 SECURITY REQUIREMENTS.

6.1 All contractor employees, to include subcontractor employees, requiring access to government installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee to the COR or the Contracting officer (if a COR has not been designated) within 30 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website:

https://jkodirect.jten.mil/

The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 30 calendar days after contract award. The Contractor and all associated sub-contractor employees shall comply with applicable Installation, facility, and area Commander’s local access and security policies and procedures. If required by this contract, the contractor shall also provide all information for background checks to meet Installation access requirements to be accomplished by Installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or Installation change, the Government may require changes in contractor security matters or processes.

https://jkodirect.jten.mil/

ATTACHMENT A – ENVIRONMENTAL REQUIREMENTS

1. RECYCLING, SALVAGE, AND DISPOSAL OF MATERIALS FORT STEWART

AND HUNTER ARMY AIRFIELD

1.1 Disposal: All waste generated from construction, demolition, and renovation contracts must be disposed of off the installation in a permitted disposal facility and in accordance with all Federal, State, and Local rules and regulations unless otherwise stated in the contract. At the end of each month, the contactor will provide copies of all disposal weight/scale tickets to the Contracting Officer’s Representative (COR) showing the in, out, and tare weights of each load taken from the installation. The COR will provide copies of these tickets to the DPW Environmental Division, Solid Waste Management Section for tracking and regulatory reporting requirements.

1.2 Recycling/Salvage: Fort Stewart and Hunter Army Air Field has a mandatory recycling program. The Installation Command Policy Letter #30 and Command Recycling SOP can be accessed at http://www.stewart.army.mil/info/?id=443&p=1. All recyclable materials (listed in the recycling SOP) generated during the entire term of any construction, demolition, or renovation contract will be turned over to the Fort Stewart or HAAF Recycling Program. Contractors must contact the COR who will coordinate with the DPW Environmental Waste Management Section (912-767-2010) to arrange for turn-in of recyclable/salvageable materials. In areas where large amounts of scrap metal or cardboard will be generated, it is possible that a collection bin/container could be provided to the Contractor at no cost to deposit these materials. Salvage materials, unless otherwise specified, become the property of the contractor upon removal from the job site and should be taken into consideration in formulating bids.

1.3 Hauling/Transport Requirements: All vehicles and containers used to transport waste or recyclables on or off the Installations will meet all Federal and State DOT requirements. All waste or recyclable materials being transported will be loaded, tied, and covered in such a manner that will prevent any of the materials from leaking, spilling, falling or blowing from/off the vehicle or container. It is the contractor’s responsibility to ensure immediate pick-up/clean-up of any material that is accidentally dropped, spilled or blown from a vehicle or container while in transit on and off the Installation.

1.4 Custodial Contract: If this contract is for custodial services or will include a custodial service requirement, the Contractor shall empty or otherwise transfer the contents from the blue recycling containers located inside buildings/facilities to the nearest blue recycling dumpster located outside.

The contactor will ensure that all recycled paper products are first placed inside a clear plastic bag and the top is tied closed before it too is placed inside the nearest blue recycle dumpster.

1.5 Payment/Funding: If any of the conditions listed under the Recycling, Salvage, and Disposal section are not met, it will be considered a failure to comply with the terms of the contract as discussed in the inspection clause herein.

1.6 Guidance/Question: Anyone requiring further guidance, recycling training for contractors, or has additional questions on this section should contact the DPW Environmental Division, Solid Waste Management Section at 912-767-2010.

1.7 Chillers, pumps, HVAC units, and similar equipment must be logged on an applicable inventory/certification document prior to turn-in to recycling yard (on DD Form 1348). The form will be used to track the removal of units from facilities, refrigerant removal certification (if applicable), and a chain of custody from removal technician thru supply manager to recycling technician. The serial number and facility number will be listed on each form and one form may contain more than one like item. Recycling Yard personnel will verify document to items turned in, sign the document, and retain a file copy. Contractor shall submit this form to the KO. Additionally, damaged HVAC system may be accepted as scrap metal at the FSGA Recycling Scrap Metal Yard, Building 1143, or the HAAF Recycling Yard, Building 728, provided any and all freon has been certified as being removed from the system.

2. Toxic Substances Control Act (TSCA) Requirements

2.1 Asbestos Containing Materials (ACM)

2.1.1 If ACM will either be disturbed or removed, the contractor must perform asbestos abatement, containment, disposal and a 10-day notification to the Georgia Environmental Protection Division (GA EPD), as required by the Georgia Asbestos Safety Act, Official Code of Georgia Annotated Section 12-12-1. The disposal of ACM must be in accordance with both the GA EPD and Occupational Safety and Health Administration regulations.

2.1.2 REQUIRED SUBMITTAL ITEM: The Installation TSCA POC (Craig

Christopher at 912-767-1234 / Craig.W.Christopher.civ@mail.mil) must be provided a copy of the 10-day notification at the time the contractor informs GA EPD of their intent to properly abate the ACM. A copy of the Georgia asbestos shipment record must also be provided to the TSCA POC.

2.2 Lead-Based Paint (LBP)

2.2.1 If survey results, as reviewed by the Installation TSCA POC (Craig

Christopher at 912-767-1234 / Craig.W.Christopher.civ@mail.mil), indicate LBP removal is necessary, the contractor will be required to collect, contain, and dispose of the LBP off-Post in accordance with local, state, and Federal regulations. The contractor will be required to provide the disposal manifest to the TSCA POC.

2.2.2 REQUIRED SUBMITTAL ITEM: LBP survey must be provided to the TSCA

POC, as applicable. The LBP disposal manifest must be provided to the TSCA POC if LBP removal was determined necessary by the TSCA POC.

3. Installing Storage Tanks on Fort Stewart and Hunter Army Airfield

N / A

4. Removing Underground Storage Tanks (USTs) on Fort Stewart and

5. Removing Aboveground Storage Tanks (ASTs) on Fort Stewart and

6. Potable Water Utility Environmental Compliance Requirements

7. Wells and Water Storage Tanks

8. Electrical Meters and Instrument Transformers

9. Water / Waste Water Systems

10. Stormwater / Erosion and Sedimentation Control (E&S) Requirements

10.1 Requirements for Sites with Soil Disturbance Greater Than 0.75 Acres

10.1.1 A Notice of Intent (NOI) for coverage under the Georgia National Pollution

Discharge Elimination System (NPDES) Permit must be applied for through the DPW Environmental Office Stormwater POC (Russell Moncrief at 912- 767-0271). The land disturbance calculation must include project entrances /exits, material lay down areas, equipment storage areas, soil stockpile, fill, and muck out areas. The NOI package has a mandatory 14-day waiting period once mailed to the Georgia Environmental Protection Division (EPD).

Land disturbing activities cannot occur until the 14-day waiting period has ended.. The NOI package includes an Erosion & Sedimentation and Pollution Control (ESPC) Plan, fees in the amount of $80/acre, the fee form, and the NOI application. In addition to meeting those requirements under the Georgia Erosion and Sedimentation Control Act, the contractor must also follow Federal and local E&S control regulations. A summary of the applicable stormwater / E&S requirements are provided below:

10.1.1.1 E&S Control Best Management Practices (BMPs) will be identified in the

ESPC Plan and must be utilized by the contractor. The ESPC Plan will include those requirements identified in the “Green Book” (Manual for Erosion & Sedimentation Control for the State of Georgia), the Coastal Stormwater Supplement, the Energy Independence and Security Act Section 438, the US Environmental Protection Agency (EPA) Technical Guidance (EPA 841-B-09-001 December 2009), the United Facilities Criteria (UFC) Manual for Low Impact Design, and those additional applicable Federal and local requirements found at the following web link:

http://www.stewart.army.mil/info/?id=443&p=1 and a summary of how these materials apply is provided in the three sub-bullets below.

Reference DPW Stormwater Management Policy Letter #11 and the USACE Hydrology and Low Impact Development site:

https://mrsi.erdc.dren.mil/sustain/cx/lid is used to house official documents, planning and design tools for use in development of Army projects. Army LID implementation will be accomplished using Army LID guidance "Army Stormwater Management Using Low Impact Development" (this document), the Army Low Impact Development Technical User Guide (see Best Practices section of the mrsi site), and the Army's LID Planning Tool and LID Cost Planning Tool (see Design Tools section of Army Stormwater Management Using Low Impact Development the mrsi site).

10.1.1.2 The ESPC Plan must also include flow calculations demonstrating concentrated runoff flows from peak rain events will not impact (a) any existing stream, (b) upstream systems and (c) downstream systems of the site as required for Total Maximum Daily Loads to maintain water quality standards by the removal of any potential pollutants.

http://www.stewart.army.mil/info/?id=443&p=1

10.1.1.3 When preparing the ESPC Plan, refer to the following web link:

http://www.stewart.army.mil/info/?id=443&p=1 for a copy of two Installation Policies (#10 and #11) that require engineers / proponents to take a more holistic approach to stormwater management of individual construction projects. Specifically, engineers must use Low Impact Development (LID) and Green Infrastructure (GI) stormwater control practices along with water quantity management practices found in the Georgia Stormwater Management Manual and the Coastal Stormwater Supplement. This is necessary to completely satisfy aquatic resource protection, overbank flood protection, and extreme flood protection which are criterion found in these documents for post-construction BMPs. In addition, it is required the utilization of the following guidance at the following site for DoD facilities:

https://mrsi.erdc.dren.mil/sustain/cx/lid

10.1.2 Dry detention basins must be located downstream of other LID/GI structural controls. Hydraulic considerations are necessary to ensure dry detention basins are sized to store the entire water quality design volume or have adequate structural controls to meet the minimum criteria for a 1-year, 24-hour storm event. PLEASE NOTE: Wet retention ponds are not a BMP option for FSGA/HAAF; reference DPW Policy Letter #10.

10.1.3 Site dewatering requires prior approval from the Environmental Office.

10.1.4 The site operator for the proposed action is required to continuously maintain all BMPs through the duration of site disturbing activities (regardless of NOI requirement). In order for the Army to accept the project as complete, the site must be stabilized to prevent silts and sediments from leaving the construction site. The Installation, through its Contracting Officer’s Representative, NRCS, and the DPW Environmental Office, must agree that the project site meets necessary site stabilization parameters as required by the State of Georgia prior to project acceptance by the Army.

10.1.5 At a minimum, a Level 1A E&S Control Certified individual must be on the site during any land disturbance activity in the State of Georgia.

10.1.6 Cross drainage facilities that transport stormwater runoff under roadways must meet the 25- to 100-year design storm, or be in accordance with GA Department of Transportation requirements, whichever is more stringent.

The design must ensure that the structure/s will not impact any facilities upstream or downstream during heavy rain events. Culverts, bridges, and/or roadway drainage structures require bank stabilization to prevent erosion during rain events.

10.1.7 Equipment cleanout (brushes, rollers, spray guns/lines, etc.) must occur in designated areas (sink basins or washracks which discharge to sanitary or http://www.stewart.army.mil/info/?id=443&p=1 https://mrsi.erdc.dren.mil/sustain/cx/lid industrial wastewater treatment plants) and must not discharge to the stormwater conveyance system. Ensure all washouts of trucks and equipment is controlled and is discharged with adequate E&S control BMPs.

10.1.8 Ensure proper drip pans and secondary containment are utilized for staging, storing, loading, fueling, maintenance, repairs, etc.

10.1.9 Place all fuel storage tanks within plastic lined earthen berms, drive-on, or drive-over containment. The containment area must have a minimum capacity of 110% of the fuel storage tanks capacity for spill prevention, and to capture incidental spills.

10.2 Requirements for Sites with Soil Disturbance Less Than 0.75 Acres

10.2.1 An NOI for coverage under the Georgia NPDES will not be necessary.

The following requirements still apply:

10.2.2 The site operator must utilize and implement Best Management Practices

(BMPs) in accordance with the “Green Book” (Manual for Erosion & Sedimentation Control for the State of Georgia-most current edition).

10.2.3 Site dewatering requires prior approval from the Installation

Environmental Office.

10.2.4 The site operator is required to continuously maintain all BMPs through the duration of site disturbing activities (regardless of NOI requirement). In order for the Army to accept the project as complete, the site must bestabilized to prevent silts and sediments from leaving the construction site. The Installation, through its Contracting Officer Representative, NRCS, and the DPW Environmental Office, must agree that the project site meetsnecessary site stabilization parameters as required by the State of Georgia prior to project acceptance by the Army.

10.2.5 At a minimum, a Level 1A E&S Control Certified individual must be on the site during any land disturbance activity in the State of Georgia.

10.2.6 Cross drainage facilities that transport stormwater runoff under roadways must meet the 25- to 100-year design storm, or be in accordance with GA Department of Transportation requirements, whichever is more stringent.

The design must ensure that the structure/s will not impact any facilities upstream or downstream during heavy rain events. Culverts, bridges, and/or roadway drainage structures require bank stabilization to prevent erosion during rain events.

10.2.7 Ensure all washouts of trucks and equipment is controlled and discharged with adequate E&S control BMPs. Waste material and/or debris must be disposed of properly (not into streams, ditches, or stormwater conveyance systems).

10.2.8 Ensure proper drip pans and secondary containment are utilized for staging, storing, loading, fueling, maintenance, repairs, etc.

10.2.9 Place all fuel storage tanks within plastic lined earthen berms, drive-on, or drive-over containment. The containment area must have a minimum capacity of 110% of the fuel storage tanks capacity for spill prevention, and to capture incidental spills.

10.3 The Army is required to report as-built conditions of low impact development features annually (end of Fiscal Year) on compliance with requirements under Section 438 of the 2007 Energy Independence and Security Act (EISA). Therefore, the Designer of Record shall provide the completed reporting form to the Installation DPW COR / Real Property Officer as part of the DD Form 1354 Transfer and Acceptance of DoD real property contract close-out process.

10.3.1 REQUIRED SUBMITTAL ITEM: The Designer of Record shall determine the Low Impact Development Volume required to be retained on site (difference between pre-project and post-project runoff, ft3) and complete section A-E of the Maintaining Hydrology on Army Construction Projects reporting form.

10.4 Requirements for Offsite Soils:

10.4.1 Test offsite soils brought in for use as backfill for Total Petroleum

Hydrocarbons (TPH), Benzene, Toluene, Ethyl Benzene, and Xylene (BTEX) and full Toxicity Characteristic Leaching Procedure (TCLP) including ignitability, corrosivity and reactivity. Backfill shall contain no more than 100 parts per million (ppm) of total petroleum hydrocarbons (TPH) and no more than 10 ppm of the sum of Benzene, Toluene, Ethyl Benzene, and Xylene (BTEX), and shall pass the TCLP test. Determine TPH concentrations by using EPA 600/4-79/020 Method 418.1. Determine BTEX concentrations by using EPA SW-846.3-3 Method 5030/8020.

Perform TCLP in accordance with EPA SW-846.3-3 Method 1311. Provide Borrow Site Testing for TPH, BTEX and TCLP from a composite sample of material from the borrow site, with at least one test from each borrow site.

10.4.2 REQUIRED SUBMITTAL ITEM: Within 24 hours of conclusion of physical tests, submit 2 copies of test results, including calibration curves and results of calibration tests. Do not bring material onsite until tests have been approved by the Contracting Officer.

11. HVAC / Refrigerant Requirements:

12. Boilers, Hot Water Heaters, Heating Units, and Burners

13 Generators (500 HP or Greater)

14 Painting Operations

14.1 Surface coating of stationary structures (building, water towers, etc.) are exempt from permitting.

14.2 Surface coating of mobile sources (vehicles, portable generators, containers, etc.) are not exempt from Georgia EPD regulations. Surface coating must be conducted within a paint booth or an off-permit change notification must be submitted to the Georgia EPD if the operation will take place outdoors.

15 Fire Suppression - Halon

16 Cultural Resources Management (CRM)

16.1 Should the Installation Environmental Office specify consultation with CRM, this consultation must happen prior to implementation of project.

16.2 Accidental Discovery of Remains and Artifacts

16.2.1 Should artifacts and/or human remains be encountered during the project, all actions must cease and the Cultural Resources POC must be contacted immediately. The Cultural Resources POC is Brian Greer, (912) 767-0992.

17 Integrated Pest Management Program

SECTION 02 41 00

DEMOLITION

1. SUBMITTALS:

The procedures proposed for the accomplishment of salvage and demolition work shall be submitted for approval. The procedures shall provide for safe conduct of the work, careful removal and disposition of materials specified to be salvaged, protection of property which is to remain undisturbed, coordination with other work in progress, and timely disconnection of utility services. The procedures shall include a detailed description of the methods and equipment to be used for each operation. The sequence of operations shall be submitted to the Contracting Officer’s Representative for review and approval before starting work on any bridges.

2. GENERAL REQUIREMENTS:

The work includes demolition or removal of all construction indicated or specified. All materials resulting from demolition work, except as indicated or specified otherwise, shall become the property of the Contractor and shall be removed from the limits of Government property. Rubbish and debris shall be removed from Government property daily unless otherwise directed so as to not allow accumulation. Materials that cannot be removed daily shall be stored in areas specified by the Contracting Officer.

3. PROTECTION:

Protection of Existing Work: Before beginning any cutting or demolition work, the Contractor shall carefully survey the existing scope of work and examine the drawings and specifications to determine the extent of the work. The Contractor shall take all necessary precautions to ensure against damage to existing work to remain in place, to be reused, or to remain the property of the Government, and any damage to such work shall be repaired or replaced as approved by the Contracting Officer at no additional cost to the Government. The Contractor shall carefully coordinate the work of this section with all other work and construct and maintain shoring, bracing and supports as required. The Contractor shall ensure that structural elements are not overloaded and be responsible for increasing structural supports or adding new supports as may be required as a result of any cutting, removal, or demolition work performed under any part of this Contract. Trees within project site shall be protected from damage.

4. BURNING:

The use of burning at the project site for the disposal of refuse and debris will not be permitted.

5. USE OF EXPLOSIVES:

Use of explosives will not be permitted.

6. EXISTING FACILITIES:

6.1 Structures or Concrete: Existing structure and material shall be removed in their entirety.

6.2 Removal of Utilities: Existing utilities shall be removed as required. When utilities lines are encountered that are not on the drawings the Contracting Officer’s Representative shall be notified.

7. DISPOSITION OF MATERIAL:

7.1 Title to Materials: Title to all materials and equipment to be demolished is vested in the Contractor upon receipt of notice to proceed. The Government will not be responsible for the condition, loss or damage to such property after notice to proceed.

7.2 Material for Contractor Salvage: Material for salvage shall be stored as approved by the Contracting Officer. Salvage materials shall be removed from Government property before completion of the Contract. Material for salvage shall not be sold on the site.

7.3 Damaged Items: Items damaged during removal or storage shall be repaired or replaced to match existing.

8. CLEAN-UP:

8.1 Debris and Rubbish: Debris and rubbish shall be removed from job site daily.

Material becomes property of the contractor and must be removed from government property.

8.2 Debris Control: Debris shall be removed and transported in a manner so as to prevent spillage on streets or adjacent areas.

8.3 Regulations: Local regulations regarding hauling and disposal apply.

SECTION 03 30 00

CONCRETE FOR BUILDING CONSTRUCTION

(MINOR REQUIREMENTS)

PART 1 - GENERAL

1. APPLICABLE PUBLICATIONS: The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

American Concrete Institute (ACI) Standard:

ACI 301 (2016) Specification for Structural Concrete

ACI PRC 347 (2014; Errata 2008; Errata 2012) Guide to Formwork for Concrete

ACI 305.1 (2014) Specification for Hot Weather Concreting

ACI 306.1 (1998, Reapproval Notice, 2002) Specification for Cold Weather Concreting

ACI 318 (2019) Building Code Requirements for Structural Concrete and Commentary

American Society for Testing and Materials (ASTM) Publication:

ASTM A1064 (2013) Standard Specification for Steel Wire and Welded Wire Reinforcement, Plain and Deformed, for Concrete

ASTM C94 (2021) Standard Specification for Ready-Mixed Concrete

ASTM C150 (2021) Standard Specification for Portland Cement

ASTM C920 (2018) Standard Specification for Elastomeric Joint Sealants

ASTM D1751 (2008) Standard Specification for Preformed Expansion Joint Filler for Concrete Paving and Structural Construction (Nonextruding and Resilient Bituminous Types)

ASTM D6690 (2021) Standard Specification for Joint and Crack Sealants, Hot Applied, for Concrete and Asphalt Pavements

2. GENERAL REQUIREMENT: The work shall be in conformance with ACI 318, part entitled "Construction Requirements," except as specified herein.

2.1 Compressive Strength: Concrete mixes shall be proportioned to obtain compressive strength in 28 days of 4000 PSI. The compressive strengths shall be reached in 7 days when high-early-strength cement is used.

2.2 Air Content: Total air content of exterior concrete shall be maintained at 5 to 7 percent by volume of concrete.

2.3 Slump: Maximum slump shall be 3 inches.

3. STORAGE: Materials shall be stored so as not to deteriorate or become contaminated.

PART 2 - PRODUCTS

4. MATERIALS shall conform to the following:

4.1 Abrasive Aggregate: Aluminum oxide, emery, or silicon-carbide abrasive.

4.2 Anchorage Items: Standard manufactured item of the types indicated or required for the application.

4.3 Portland Cement: Material shall conform to ASTM C150.

4.4 Concrete Materials: ASTM C94, cement type optional. Only one brand of any one type of cement shall be used for exposed concrete surfaces of any individual structure.

4.5 Curing Materials: Impervious sheet or membrane-forming curing compound.

Impervious sheet shall be white opaque polyethylene 4 mil thick, waterproof kraft paper, or polyethylene-coated burlap. Membrane-forming curing compound shall be of commercial formulation, sprayable, nontoxic, and of the type that will dry within 4 hours and form a film highly resistant to moisture loss from concrete while curing. Compound shall be clear with fugitive dye, resin-base or chlorinated-rubber-base-type.

4.6 Form Coating: Nonstaining form oil or form release agent that will not deleteriously affect concrete surfaces nor impair subsequent applications.

4.7 Form Materials: Plywood or hardboard especially made for concrete form use or other materials that will produce the specified finish without adversely affecting the concrete surfaces. Form work cost is included in unit price.

4.8 Reinforcement: Welded Wire Fabric shall conform to ASTM A1064. Cost for Welded Wire Fabric shall be included in the cost of the concrete slab.

4.9 Expansion Joint Filler Strip: ASTM D 1751. Material used shall be sized as specified. Full slab depth.

4.10 Joint Sealant:

4.10.1 Horizontal Surfaces, 3 Percent Slope, Maximum: ASTM D6690 or ASTM C920, Type M, Class 25, Use T.

4.10.2 Vertical Surfaces Greater Than 3 Percent ASTM C 920, Type M, Grade NS, Class 25.

4.10.3 Backer Rod Material: Backer rods and bond breaking tape shall be compatible with the sealant and sealant installation requirements. Backer material shall a have a width of 25% ±5% greater than joint sealant reservoir.

PART 3 - EXECUTION

5. FORMWORK shall be made mortar tight, properly aligned and adequately supported to produce concrete conforming accurately to the indicated shapes, lines, dimensions, and with surfaces free of offsets, waviness, or bulges. Where surfaces are to be exposed or painted, panels shall be manufacturer's stock size material, using smaller panels cut to required dimensions only where required by openings and joints. Panel joints in exposed or painted work shall occur at control joints, including alignment with masonry control joints and construction joints. Unless otherwise shown, exposed external corners shall be chamfered, beveled, or rounded by moldings placed in the forms. Surfaces shall be thoroughly cleaned and coated before each use. Forms shall be removed at a time and in a manner that will not injure the concrete. Construct in accordance with ACI 301 and ACI 347. Formwork cost shall be included in the square yard cost of concrete.

6. REINFORCEMENT: Welded-wire fabric shall be placed in slabs as indicated. Fabric placed in slabs on grade shall be continuous between expansion, construction, and contraction joints. Fabric placement at joints shall be as indicated. Lap splices shall be made in such a way that the overlapped area equals the distance between the outermost crosswires plus 2 inches. Laps shall be staggered to avoid continuous laps in either direction. Fabric shall be wired or clipped together at laps at intervals not to exceed 4 feet. Fabric shall be positioned by the use of supports. Cost for Welded Wire Fabric shall be included in the square yard cost of the concrete material.

7. INSTALLATION OF ANCHORAGE ITEMS shall be as indicated or required to ensure sufficient anchorage for purpose intended.

8. EXPANSION JOINTS: Expansion joint filler shall be as shown on drawings.

9. TRANSPORTING: Transport concrete from the mixer to the forms as rapidly as practicable. Prevent segregation or loss of ingredients. Clean transporting equipment thoroughly before each batch. Do not use aluminum pipe or chutes. Remove concrete which has segregated in transporting and dispose of as directed.

10. MIXING: ASTM C 94 and ACI 301. Machine mix concrete. Being mixing within 30 minutes after the cement has been added to the aggregates. Additional water may be added, provided that both the specified maximum slump and water-cement ratio are not exceeded. When additional water is added, an additional 30 revolutions of the mixer at maximum speed is required. Dissolve admixtures in the mixing water and mix in the drum to uniformly distribute the mixture throughout the batch.

10.1 Surface Preparation

Before placing the concrete, thoroughly clean the vertical exposed faces of the existing slabs to remove contaminates. Use a wire brush or other approved methods to remove contaminates. Remove existing sealant from exposed concrete faces.

10.2 Preparing Base

Remove debris and standing water from the base. Thoroughly compact loose base material by tamping before placing concrete. Reinforcement shall be placed as directed.

New concrete slabs shall be placed upon compacted soil free from ice, frost or water.

Base material shall be compacted to at less 95% of laboratory maximum density.

11. CONCRETE PLACEMENT: Deliver concrete from mixer to forms continuously until approved unit of operation is completed. Provide scaffolding, ramps and walkways so that personnel and equipment are not supported by in-place reinforcement. Placing will not be permitted when sun, heat, wind, or limitations of facilities furnished by the Contractor prevent proper consolidation, finishing and curing. Deposit concrete as close as possible to its final position in the forms. When a vertical drop greater than 8 feet is authorized, provide equipment to prevent segregation. Regulate depositing of concrete so that it will be consolidated in horizontal layers not more than 12 inches thick. Place slabs in one layer. Screed concrete to provide levels and profiles indicated.

12. VIBRATION: Work in accordance with ACI 301. Furnish a spare working vibrator on the job site whenever concrete is placed. Consolidate concrete slabs greater than 4 inches in depth with high frequency mechanical vibrating equipment supplemented by hand spading and tamping. Consolidate concrete slabs 4 inches or less in depth by wood tampers, spading and settling with heavy leveling straightedge. Use vibrators adequate in effectiveness and number to properly consolidate the concrete. Insert and withdraw vibrators approximately 18 inches apart. Penetrate the previously placed lift with the vibrator when more than one lift is required. External vibrators shall be used on the exterior surface of a form when internal vibrators do not provide adequate consolidation of the concrete.

13. CURING shall start as soon as free water has disappeared from concrete surfaces after placing and finishing. Curing materials shall be applied and maintained so as to protect the concrete from moisture loss for 7 days. Curing shall be accomplished by impervious sheet or membrane-forming curing compound. Concrete surfaces shall be thoroughly wetted before covering with impervious-sheet materials. Membrane-forming curing compound shall be applied with mechanical spraying equipment at a coverage rate of not more than 300 square feet per gallon. Surfaces of compound damaged during curing shall be resprayed. Follow requirements of ACI 305.1 for Hot Weather concreting and ACI 306.1 for Cold Weather concreting.

14. CONSOLIDATION OF CONCRETE: Each layer of concrete shall be consolidated with internal concrete vibrators supplemented by hand spading, rodding, and tamping.

Vibrating equipment shall be adequate to thoroughly consolidate the concrete.

15. FINISHING CONCRETE:

15.1 Formed Surfaces: Fins and loose material shall be removed. Unsound concrete, voids over 1/2 inch in diameter, and tie-rod and bolt holes shall be cut back to solid concrete, reamed, brush-coated with cement grout, and filled solid with a stiff portland-cement-sand mortar mix. Patchwork shall finish flush with adjoining concrete surfaces and, where exposed, shall match adjoining surfaces in texture and color.

Patchwork shall be cured for 72 hours. White portland cement shall be used as needed to attain color match.

15.2 Unformed Surfaces: Surfaces shall be finished to a true plane with no deviation exceeding 5/16 inch when tested with a 10-foot straightedge. Surfaces shall be pitched to drain. Surfaces shall be screeded and floated to the required finish level with no coarse aggregate visible before finishing as specified below.

15.3 Nonslip Finish: The concrete shall receive a nonslip finish so indicated by brooming with a fiber-bristle brush in a direction transverse to that of main traffic. Do not use a burlap drag on fiber reinforced concrete. Finish concrete in accordance with ACI 301 Section 5 for a broom finish.

15.4 Expansion Joints: Form expansion joints where required and specified. Install around any structure and features that project through or onto the pavement, using preformed joint filler of the type, thickness, and width indicated. Expansion joints shall extend the full slab depth. Finish the edges of the concrete at the joint face with an edger with a radius of 0.125 inch. Install the joint filler strip to form a recess at the pavement surface to be filled with joint sealant.

15.5 New Sawed Joints in Concrete: Construct sawed joints by sawing a groove in the concrete with a 0.125 inch blade to the indicated depth. The time of initial sawing will vary depending on existing and anticipated weather conditions and will be such as to prevent uncontrolled cracking of the pavement. Commence sawing of the joints as soon as the concrete has hardened sufficiently to permit cutting the concrete without chipping, spalling, or tearing. Saw the joints at the required spacing consecutively in the sequence of the concrete placement. Discontinue sawing at a given joint location when a crack develops ahead of the saw cut. Immediately after the joint is sawed, thoroughly flush the saw cut and adjacent concrete surface with water until all waste from sawing is removed from the joint. Respray the surface with curing compound as soon as free water disappears. The top of the joint opening and the joint groove at the exposed edges shall be tightly sealed with cord or backer rod before the concrete in the region of the joint is resprayed with curing compound.

15.5.1 Contraction Joints: Transverse and longitudinal contraction joints shall be the weakened-plane or dummy type. Construct longitudinal contraction joints by sawing a groove in the hardened concrete with a power-driven saw. Construct transverse contraction joint in conformance with the requirements for the sawed joint.

15.5.2 Transverse Construction Joints: Transverse contraction joints shall be installed at the end of each day’s placing operations and at any point within a paving lane when placement is interrupted for 30 minutes or longer. The transverse contraction joints shall be constructed by utilizing headers or by paving through the joint, then full-depth sawcutting the excess concrete. Pavement shall be constructed with the paver as close to the header as possible. Transverse construction joints installed at a planned transverse joint shall be constructed as shown.

16. TESTING: Contractor is responsible for testing concrete to determine concrete strength. Each test shall comprise of taking three (3) test cylinders to determine 7, 14 and 28-day strengths of the new concrete. A minimum of one test each day that concrete is placed is required and a minimum of one test for each 50 cubic yards of concrete placed in one day is required.

17. REMOVAL OF EXISTING CONCRETE APPROACH: Contractor may be required to remove existing concrete approach. If required, contractor shall remove existing slab complete to size as directed. Saw cut existing slab for removal and smooth tie-in between new and existing surfaces. Existing concrete material shall be removed from bridge site and disposed of off government property. Excavate, backfill and compact area as required to install new slab.

18. SEALING EXISTING CONCRETE BRIDGE DECK JOINTS: A scoping will be held on each job site, between the contractor and government, and an agreement will be made on the slabs, joints, etc. to be repair or replaced.

This is the start of the file's text. The full file is on GovTribe.