Attachment 6 - General Questions and Answers Part Two_W9124G-24-R-0006.xlsx

XLSX spreadsheet 16 KB Posted

Attached to
W9124G-24-R-0006 110AB VSS
Solicitation number
W9124G_24_R_0006
Issued by

About this file

This document is a set of questions and answers related to a federal contract opportunity for upgrading and installing a Video Surveillance System (VSS) for the 110th Aviation Brigade Barracks Complex at Fort Novosel, Alabama. The key details are:

The contract is for a non-personnel services to provide the VSS upgrade and installation, as well as four option years of maintenance. The contractor shall utilize certified, qualified technicians and the proposal should include all costs for labor, travel, and materials. The contract will cover a 12-month base year for installation and maintenance, and four 12-month option years for maintenance. The questions and answers cover various technical details such as camera specifications, storage requirements, integration, and infrastructure considerations. The government has provided a Statement of Work and building layout attachments to assist with the technical requirements. Offerors will be required to provide a 2-page summary of their technical approach in addition to a 40-page technical volume.

View the file

Other files

File Type Posted
W9124G-24-R-0006 0004.pdf PDF
W9124G-24-R-0006 0003.pdf PDF
Attachment 5 - General Questions and Answers_W9124G-24-R-0006.xlsx XLSX spreadsheet
Attachment 4 - Camera and Buildings Layout.pptx PPTX presentation
W9124G-24-R-0006 0002.pdf PDF
W9124G-24-R-0006 0001.pdf PDF
Attachment 3 - Pricing Schedule.xlsx XLSX spreadsheet
Attachment 2 - Past Performance Questionnaire.docx DOCX document
Attachment 1 - Statement of Work.pdf PDF
W9124G-24-R-0006.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

W9124G-24-R-0006 110AB VSS

QUESTIONS FROM SITE VISIT

Question NumberQuestionAnswer
42

Are the systems in each building to be integrated together with one monitoring location or is each system to operate individually?

There is no longer a requirement for a central monitoring system. Each system will operate individually for the responsible party to view video feed for downloading video
43

Can the Government provide a list of the required certifications for the installation and maintenance of the VSS?

No certification requirement
44

Can the Government confirm that the equipment listed under “Building 8650 & 8353” is a total count of equipment between the two buildings or does each building require the equipment listed?

They are recommendations on cameras needed. Please refer to "Attachment 4 - Camera and Buildings Layout" for desired coverage.
45

Can the Government confirm that the equipment listed under “Building 8364 & 8365” is a total count of equipment between the two buildings or does each building require the equipment listed?

They are recommendations on cameras needed. Please refer to "Attachment 4 - Camera and Buildings Layout" for desired coverage.
46

Will the monitors in each building need to be wall mounted or will they sit atop a desk?

Monitors to be equipped with NVR system in a similar way to what is in place now in the barracks kitchen areas. There are no desks in the mechanical rooms
47

Are there existing pathways between each building? If so, are these pathways conduit and are they in usable/serviceable condition? Also, if there are pathways, are the pathways underground?

Please refer to DPW, systems operating individually
48

What type of communications cabling is used to interconnect the buildings? If fiber, what type and is there any available unused fiber that can be used? If category cable, what type? Approximately, how long are the communication cable?

Please refer to DPW
49

Does each building have a communications closet?

Please refer to DPW; communications room is owned by Network Enterprise Center not the customer. An agreement has been made with DPW for using the mechanical room for the NVRs
50

Are there existing racks in the communications rooms or onsite for each building?

An agreement with DPW is allowing access to install NVR system in the mechanical rooms located in each building. The communications rooms are owned by the Network Enterprise Center-Ft. Novosel. Current NVR is in a rack mount.
51

What is the approximate mounting height for the cameras? Will a lift be needed to access the cameras?

Refer to DPW for height. A ladder shuold be sufficient to reach the highest camera locations
52

Can we get a Resolution and Frame Rate requirement for this project?

30 fps / 1080p 3mp min.
53

What is the required storage in days for this project?

Recording retention storage: 60 days minimum; 90-120 preferred
54

Is continuous recording required for this project?

motion only
55

Are drawings/floor plans for each building with camera locations available to accurately calculate wire distance and pathways?

Please refer to DPW and camera layout
56

Is the network infrastructure between buildings for the VSS already in place? If not, will the installation (Ft. Novosel) be responsible for providing connectivity between buildings?

Stand alone system for B8362/8363, B8364/8365, B8360, and B8353. There is no requirement to connect the systems to a central monitor station. Only local monitors required at each NVR to be able to view data for pulling.
57

Clarify if intention of project is to connect all buildings into a local isolated CCTV network with all camera locations installed to be viewable at Bldg 8350 "BOSS BLDG". Or if intention of project, or at least as an initial phase of project, is to have all buildings recording and viewable only from building's new NVR to be installed within that building. If intent is for all buildings to connect at this time into interconnected CCTV network, is fiber optic infrastructure between building to be installed by contractor or by Base Novosel.

Stand alone system for B8362/8363, B8364/8365, B8360, and B8353. There is no requirement to connect the systems to a central monitor station. Only local monitors required at each NVR to be able to view data for pulling.
58

Confirm or provide drawings indicating if attic space above 2nd floor of all buildings is readily accessible and permitted to have low-voltage cabling installed within.

Please refer to DPW
59

Confirm if there are any restrictions/reservations to performing additional penetrations throughout the buildings.

Please refer to DPW
60

Clarify requested UPS power retention time for NVRs/Cameras upon site power failure (ie, 15,20,30 minutes)

At least 15 minutes
61

Confirm if the camera and NVR makes/models listed in the SOW are simply recommendations and the project is not restricted to these makes/models.

They are recommendations
62

Confirm required video retention on NVRs is requested to be no less than 90 days for all camera views recorded.

Recording retention storage: 60 days minimum; 90-120 preferred
63

Clarify minimum video resolution/frame rate requested for all cameras locations.

30 fps / 1080p 3mp min.
64

Clarify if project is to require contractor performing demobilization of existing CCTV cameras/equipment.

Any existing material that can be used such as wiring, conduit, etc, that does not diminish the specified resolution can be re-used. Any equipment, such as the obsolete cameras, will be the responsibility of the customer to remove
65

The SOW material list will likely not achieve desired coverage, will the government provide a map with associated coverage requirements to aid in recommended camera placement?

Refer to map with requested coverage labeled "Attachment 4 - Camera and Buildings Layout"
66

SOW appears to support each NVR/server being isolated with no intended centralized monitoring. If centralized monitoring is required, please provide location of video wall, if monitor(s) is needed, and if network infrastructure is in place to support. If not , please provide scope guidance on desired infrastructure resolution?

Stand alone system for B8362/8363, B8364/8365, B8360, and B8353. There is no requirement to connect the systems to a central monitor station. Only local monitors required at each NVR to be able to view data for pulling.
67

NVR storage sizing is dependent upon total camera count, frame rate, resolution, recording duration and characteristics and motion frequency. Can you please provide required retention requirements and recording parameters?

Recording retention storage: 60 days minimum; 90-120 preferred
68

Is the government anticipating a EFI&T change to this scope given the complexity of the requirement and the current shortfall of the scope to address?

There is no longer a requirement for a monitor system at building 8350
69

Please confirm no cable path will require entrance into soldier individual barracks room.

No installation or work will require entrance into individual Soldier rooms.
70

Please confirm the only conduit required for cable path will be exterior runs where required.

Please refer to DPW for conduit requirements
71

Please identify all areas that are to be excluded from camera view in SERE.

Refer to map with requested coverage labeled "Attachment 4 - Camera and Buildings Layout" building labeled "SERE BLDG"
72

Can the government supply an overview of the barracks complex showing actual building numbers on each?

Refer to Attachment 4 - Camera and Buildings Layout
73

The SOW states “The monitoring portion of the system will be set up in Building 8350.” Can the government confirm there is network connectivity between all buildings included in this project so monitoring can be set up in building 8350?

No equipment will need to be installed in building 8350
74

Can the government supply floorplans for a typical building in this facility with camera mounting locations?

Please refer to DPW
75

Can the government supply floorplans for the facilities with recording equipment, monitor and network switch locations?

Please refer to DPW
76

Can the government confirm that cabling and infrastructure can be run utilizing attic spaces above units when required?

Please refer to DPW
77

What is the minimum required retention time for the camera recordings? Are there specific regulations or standards that need to be adhered to for recording retention?

60 days minimum; 90-120 preferred
78

What is the minimum required uptime for the UPS backup battery?

15 minutes
79

Are there access doors or hatches available to the attics of all buildings? If not, will the contractor be responsible for creating access points?

Please refer to DPW
80

Is the existing infrastructure (network cables, enclosures, etc.) in Buildings 8362, 8363, 8364, 8365, and 8360 expected to be replaced or can it be reused? If reuse is allowed, is there an assessment of its current condition

Any existing material that can be used such as wiring, conduit, etc, that does not diminish the specified resolution can be re-used. Any equipment, such as the obsolete cameras, will be the responsibility of the customer to remove
81

Is the contractor required to install new 120V power outlets inside all new network enclosures?

This is yet to be determined. Mechanical room has not been accessed to confirm 120V outlets
82

The Statement of Work does not list any equipment for Building 8350. Is the contractor expected to provide and install new infrastructure such as network cabling, a >42” wall-mounted TV monitor, and a workstation?

No equipment will need to be installed in building 8350
83

What is the manufacturer and model of the existing surveillance system installed in Building 8350? Is the contractor expected to integrate with this existing system or replace it entirely?

No equipment will need to be installed in building 8350
84

Are there any specific permits or approvals that the contractor needs to obtain before starting the installation? If so, who is responsible for obtaining them?

Please refer to DPW. Contractor will be responsible for obtaining permits
85

If there are any existing surveillance systems or security infrastructure, will the new system need to integrate with them? Are there any specific integration requirements or protocols to be followed?

If there is any existing sureveillance system, the new system will not need to integrate with them
86

What are the network requirements for the new VSS? Are there any specific bandwidth or latency requirements that need to be considered?

VSS will not connect to any internet/intranet connected networks
87

Will the contractor be responsible for providing training and documentation for the new system? If so, what level of training is required, and who will be the recipients?

Yes, contractor is responsible for providing training and documentation. Training should include at a minimum, the operation of the system and how to pull and download data from the system. The recipients will be the the Company Commander and his designees.
88

The Gov’t states that in Vol II (Technical) that the offeror will provide a 2-page summary of the contractors proposed technical approach. Further, our technical volume shall not exceed 40 pages. Please remove the summary requirement since its redundant to the 40-page technical writeup?

The Government is not removing the summary page requirement.

File details come from the government source that posted it. Updated .