COMBINED SYNOPSIS/SOLICITATION
For
W9124D-20-Q-0032 Graphic Wrap
1. This is a combined synopsis/solicitation for commercial items prepared in accordance with FAR 12.6, “Streamlined Procedures for Evaluation and Solicitation for Commercial Items,” as supplemented with additional information included in this notice. This announcement constitutes the only solicitation; quotes are being requested and a written solicitation will not be issued. Award shall be made on a standard form 1449.
2. Solicitation number W9124D-20-Q-0032 is issued as a Request for Quote (RFQ). If appearing in this combined synopsis/solicitation the terms “RFP” shall mean “RFQ” and the term “proposal” or “offer” shall mean “quote.”
3. The solicitation document and incorporated provisions and clauses are those in effect through Federal Acquisition Circular 2020-02, effective 23 December 2019. See Acquisition.gov for full content information.
4. This requirement is solicited as 100% Small Business Set-Aside with the associated North American Industry Classification System (NAICS) code being 541850 and the size standard being $16.5M.
5. For the complete list of line item number(s) and items, quantities, and units of measure refer to the following Contract Line Item Numbers (CLIN) structure of the combined synopsis/solicitation.
CLIN Structure (Schedule B):
| CLIN |
| DESCRIPTION |
| QUANTITY |
| UNIT OF |
ISSUE
UNIT
PRICE
TOTAL
PRICE
| 0001 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (SEMITRACTORS): |
CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED SEMI- TRACTORS IN ACCORDANCE WITH (IAW) THE STATEMENT OF WORK INCLUDED HEREIN.
PERIOD OF PERFORMANCE: 15 FEBRUARY 2020 THROUGH 14 FEBRUARY 2021.
| 0002 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (SEMI-TRACTORS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED SEMI-TRACTORS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2020THROUGH 14 FEBRUARY 2021.
| 0003 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (DRASH AND STEM TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED (TRUCK- STRAIGHT WITH BOX) IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OFPERFORMANCE: 15 FEBRUARY 2020 THROUGH 14 FEBRUARY 2021
| 0004 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (DRASH AND STEM TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCK- STRAIGHT WITH BOX IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2020 THROUGH 14 FEBRUARY 2021.
| 0005 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (EXPANDABLE/SEMI-TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED (EXPANDABLE/SEMI-TRAILERS) IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2020 THROUGH 14 FEBRUARY 2021.
| 0006 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (EXPANDABLE/SEMI-TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED (EXPANDABLE/SEMITRAILERS) IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2020 THROUGH 14 FEBRUARY 2021.
| 0007 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (F-350 TRUCKS): |
CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN.
PERIOD OF PERFORMANCE: 15 FEBRUARY 2020 THROUGH 14 FEBRUARY 2021.
| 0008 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (F-350 TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, ANDEQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2020 THROUGH 14 FEBRUARY 2021.
| 0009 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (CHEVY 3500TRUCK): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2020 THROUGH 14 FEBRUARY 2021.
| 0010 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (CHEVY 3500 TRUCK): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2020 THROUGH 14 FEBRUARY 2021.
| 0011 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (SILVER HAWK TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2020 THROUGH 14 FEBRUARY 2021.
| 0012 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (SILVER HAWK TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2020 THROUGH 14 FEBRUARY 2021.
| 0013 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (NIGHTHAWK TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2020 THROUGH 14 FEBRUARY 2021.
| 0014 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (NIGHTHAWK TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2020 THROUGH 14 FEBRUARY 2021.
| 0015 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (53 FT TRAILER): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2020 THROUGH 14 FEBRUARY 2021.
| 0016 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (53FT TRAILER): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2020 THROUGH 14 FEBRUARY 2021.
| 0017 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (MOTIV TRAILER): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2020 THROUGH 14 FEBRUARY 2021.
| 0018 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (MOTIV TRAILER): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2020 THROUGH 14 FEBRUARY 2021.
| 0019 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (EXTREME TRUCK - F650): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON A GOVERNMENT OWNED TRUCK (EXTREME TRUCK - :F650) IAW THE STATEMENT OF WORK INCLUDED HEREIN. PERIOD OF PERFORMANCE: 15 FEBRUARY 2020 THROUGH 14 FEBRUARY 2021. |
| 1 |
| JOB |
| 0020 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (EXTREME TRUCK - F650): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON A GOVERNMENT OWNED TRUCK (EXTREME TRUCK - F650) IAW THE STATEMENT OF WORK INCLUDED HEREIN. PERIOD OF PERFORMANCE: 15 FEBRUARY 2020 THROUGH 14 FEBRUARY 2021. |
| 1 |
| JOB |
| 0021 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (GAMING AND MUSIC TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT- OWNED TRAILERS THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2020 THROUGH 14 FEBRUARY 2021.
| 0022 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (GAMING AND MUSIC TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2020 THROUGH 14 FEBRUARY 2021.
| 0023 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (F-250 TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW STATEMENT OF WORK. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2020 THROUGH 14 FEBRUARY 2021.
| 0024 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (F-250 TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN. PERIOD OF PERFORMANCE: 15 FEBRUARY 2020 THROUGH 14 FEBRUARY 2021. |
| 1 |
| JOB |
| 0025 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (DODGE 3500 TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2020 THROUGH 14 FEBRUARY 2021.
| 0026 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (DODGE 3500 TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2020 THROUGH 14 FEBRUARY 2021.
TOTAL Base Year
| 1001 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (SEMITRACTORS): |
CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED SEMI- TRACTORS IAW THE STATEMENT OF WORK INCLUDED HEREIN.
PERIOD OF PERFORMANCE: 15 FEBRUARY 2021 THROUGH 14 FEBRUARY 2022.
| 1002 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (SEMI-TRACTORS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ONGOVERNMENT-OWNED SEMI-TRACTORS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2021 THROUGH 14 FEBRUARY 2022.
| 1003 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (DRASH ANDSTEM TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED (TRUCK- STRAIGHT WITH BOX) IAW THE STATEMENT OF WORK INCLUDED HEREIN. PERIOD OF PERFORMANCE: 15 FEBRUARY 2021 THROUGH 14 FEBRUARY 2022. |
| 2 |
| JOB |
| 1004 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (DRASH AND STEM TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCK- STRAIGHT WITH BOX IAW THE STATEMENT OF WORK INCLUDED HEREIN. PERIOD OF PERFORMANCE: 15 FEBRUARY 2021 THROUGH 14 FEBRUARY 2022. |
| 2 |
| JOB |
| 1005 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (EXPANDABLE/SEMI-TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED (EXPANDABLE/SEMI-TRAILERS) IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2021 THROUGH 14 FEBRUARY 2022.
| 1006 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (EXPANDABLE/SEMI-TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED (EXPANDABLE/SEMITRAILERS) THE STATEMENT OF WORK INCLUDED HEREIN. PERIOD OF PERFORMANCE: 15 FEBRUARY 2021 THROUGH 14 FEBRUARY 2022. |
| 15 |
| JOB |
| 1007 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (F-350 TRUCKS): |
CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN.
PERIOD OF PERFORMANCE: 15 FEBRUARY 2021 THROUGH 14 FEBRUARY 2022.
| 1008 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (F-350 TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, ANDEQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN. PERIOD OF PERFORMANCE: 15 FEBRUARY 2021 THROUGH 14 FEBRUARY 2022. |
| 7 |
| JOB |
| 1009 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (CHEVY 3500TRUCK): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2021 THROUGH 14 FEBRUARY 2022.
| 1010 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (CHEVY 3500 TRUCK): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2021 THROUGH 14 FEBRUARY 2022.
| 1011 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (SILVER HAWK TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. PERIOD OF PERFORMANCE: 15 FEBRUARY 2021 THROUGH 14 FEBRUARY 2022. |
| 3 |
| JOB |
| 1012 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (SILVER HAWK TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. PERIOD OF PERFORMANCE: 15 FEBRUARY 2021 THROUGH 14 FEBRUARY 2022. |
| 3 |
| 1013 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (NIGHTHAWK TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. PERIOD OF PERFORMANCE: 15 FEBRUARY 2021 THROUGH 14 FEBRUARY 2022. |
| 3 |
| JOB |
| 1014 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (NIGHTHAWK TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2021 THROUGH 14 FEBRUARY 2022.
| 1015 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (53 FT TRAILER): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2021 THROUGH 14 FEBRUARY 2022.
| 1016 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (53FT TRAILER): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. PERIOD OF PERFORMANCE: 15 FEBRUARY 2021 THROUGH 14 FEBRUARY 2022. |
| 3 |
| JOB |
| 1017 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (MOTIV TRAILER): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2021 THROUGH 14 FEBRUARY 2022.
| 1018 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (MOTIV TRAILER): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2021 THROUGH 14 FEBRUARY 2022.
| 1019 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (EXTREME TRUCK - F650): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON A GOVERNMENT OWNED TRUCK (EXTREME TRUCK - F650) IAW THE STATEMENT OF WORK INCLUDED HEREIN. PERIOD OF PERFORMANCE: 15 FEBRUARY 2021 THROUGH 14 FEBRUARY 2022. |
| 1 |
| JOB |
| 1020 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (EXTREME TRUCK - F650): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON A GOVERNMENT OWNED TRUCK (EXTREME TRUCK - F650) IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2021 THROUGH 14 FEBRUARY 2022.
| 1021 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (GAMING AND MUSIC TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT- OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. PERIOD OF PERFORMANCE: 15 FEBRUARY 2021 THROUGH 14 FEBRUARY 2022. |
| 2 |
| JOB |
| 1022 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (GAMING AND MUSIC TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2021 THROUGH 14 FEBRUARY 2022.
| 1023 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (F-250 TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN. PERIOD OF PERFORMANCE: 15 FEBRUARY 2021 THROUGH 14 FEBRUARY 2022. |
| 1 |
| JOB |
| 1024 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (F-250 TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2021 THROUGH 14 FEBRUARY 2022.
| 1025 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (DODGE 3500 TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2021 THROUGH 14 FEBRUARY 2022.
| 1026 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (DODGE 3500 TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2022 THROUGH 14 FEBRUARY 2023.
TOTAL Option Year One
| 2001 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (SEMITRACTORS): |
CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED SEMI- TRACTORS IAW THE STATEMENT OF WORK INCLUDED HEREIN.
PERIOD OF PERFORMANCE: 15 FEBRUARY 2022 THROUGH 14 FEBRUARY 2023.
| 2002 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (SEMI-TRACTORS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ONGOVERNMENT-OWNED SEMI-TRACTORS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2022 THROUGH 14 FEBRUARY 2023.
| 2003 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (DRASH ANDSTEM TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED (TRUCK- STRAIGHT WITH BOX) IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2022 THROUGH 14 FEBRUARY 2023.
| 2004 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (DRASH AND STEM TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCK- STRAIGHT WITH BOX IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2022 THROUGH 14 FEBRUARY 2023.
| 2005 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (EXPANDABLE/SEMI-TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED (EXPANDABLE/SEMI-TRAILERS) IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2022 THROUGH 14 FEBRUARY 2023.
| 2006 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (EXPANDABLE/SEMI-TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED (EXPANDABLE/SEMITRAILERS) IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2022 THROUGH 14 FEBRUARY 2023.
| 2007 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (F-350 TRUCKS): |
CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN.
PERIOD OF PERFORMANCE: 15 FEBRUARY 2022 THROUGH 14 FEBRUARY 2023.
| 2008 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (F-350 TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, ANDEQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2022 THROUGH 14 FEBRUARY 2023.
| 2009 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (CHEVY 3500TRUCK): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2022 THROUGH 14 FEBRUARY 2023.
| 2010 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (CHEVY 3500 TRUCK): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2022 THROUGH 14 FEBRUARY 2023.
| 2011 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (SILVER HAWK TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2022 THROUGH 14 FEBRUARY 2023.
| 2012 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (SILVER HAWK TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2022 THROUGH 14 FEBRUARY 2023.
| 2013 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (NIGHTHAWK TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2022 THROUGH 14 FEBRUARY 2023.
| 2014 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (NIGHTHAWK TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2022 THROUGH 14 FEBRUARY 2023.
| 2015 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (53 FT TRAILER): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2022 THROUGH 14 FEBRUARY 2023.
| 2016 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (53FT TRAILER): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2022 THROUGH 14 FEBRUARY 2023.
| 2017 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (MOTIV TRAILER): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2022 THROUGH 14 FEBRUARY 2023.
| 2018 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (MOTIV TRAILER): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2022 THROUGH 14 FEBRUARY 2023.
| 2019 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (EXTREME TRUCK - F650): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON A GOVERNMENT OWNED TRUCK (EXTREME TRUCK - :F650) IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2022 THROUGH 14 FEBRUARY 2023.
| 2020 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (EXTREME TRUCK - F650): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON A GOVERNMENT OWNED TRUCK (EXTREME TRUCK - F650) IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2022 THROUGH 14 FEBRUARY 2023.
| 2021 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (GAMING AND MUSIC TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT- OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2022 THROUGH 14 FEBRUARY 2023.
| 2022 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (GAMING AND MUSIC TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2022 THROUGH 14 FEBRUARY 2023.
| 2023 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (F-250 TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2022 THROUGH 14 FEBRUARY 2023.
| 2024 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (F-250 TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2022 THROUGH 14 FEBRUARY 2023.
| 2025 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (DODGE 3500 TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2022 THROUGH 14 FEBRUARY 2023.
| 2026 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (DODGE 3500 TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2022 THROUGH 14 FEBRUARY 2023.
TOTAL Option Year Two
| 3001 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (SEMITRACTORS): |
CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED SEMI- TRACTORS IAW THE STATEMENT OF WORK INCLUDED HEREIN.
PERIOD OF PERFORMANCE: 15 FEBRUARY 2023 THROUGH 14 FEBRUARY 2024.
| 3002 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (SEMI-TRACTORS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ONGOVERNMENT-OWNED SEMI-TRACTORS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2023 THROUGH 14 FEBRUARY 2024.
| 3003 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (DRASH ANDSTEM TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED (TRUCK- STRAIGHT WITH BOX) IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OFPERFORMANCE: 15 FEBRUARY 2023 THROUGH 14 FEBRUARY 2024.
| 3004 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (DRASH AND STEM TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCK- STRAIGHT WITH BOX IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2023 THROUGH 14 FEBRUARY 2024.
| 3005 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (EXPANDABLE/SEMI-TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED (EXPANDABLE/SEMI-TRAILERS) IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2023 THROUGH 14 FEBRUARY 2024.
| 3006 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (EXPANDABLE/SEMI-TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED (EXPANDABLE/SEMITRAILERS) IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2023 THROUGH 14 FEBRUARY 2024.
| 3007 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (F-350 TRUCKS): |
CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN.
PERIOD OF PERFORMANCE: 15 FEBRUARY 2023 THROUGH 14 FEBRUARY 2024.
| 3008 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (F-350 TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, ANDEQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2023 THROUGH 14 FEBRUARY 2024.
| 3009 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (CHEVY 3500TRUCK): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2023 THROUGH 14 FEBRUARY 2024.
| 3010 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (CHEVY 3500 TRUCK): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2023 THROUGH 14 FEBRUARY 2024.
| 3011 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (SILVER HAWK TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2023 THROUGH 14 FEBRUARY 2024.
| 3012 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (SILVER HAWK TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2023 THROUGH 14 FEBRUARY 2024.
| 3013 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (NIGHTHAWK TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2023 THROUGH 14 FEBRUARY 2024.
| 3014 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (NIGHTHAWK TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2023 THROUGH 14 FEBRUARY 2024...
| 3015 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (53 FT TRAILER): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2023 THROUGH 14 FEBRUARY 2024.
| 3016 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (53FT TRAILER): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2023 THROUGH 14 FEBRUARY 2024.
| 3017 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (MOTIV TRAILER): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2023 THROUGH 14 FEBRUARY 2024.
| 3018 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (MOTIV TRAILER): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2023 THROUGH 14 FEBRUARY 2024.
| 3019 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (EXTREME TRUCK - F650): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON A GOVERNMENT OWNED TRUCK (EXTREME TRUCK - :F650) IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2023 THROUGH 14 FEBRUARY 2024.
| 3020 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (EXTREME TRUCK - F650): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON A GOVERNMENT OWNED TRUCK (EXTREME TRUCK - F650) IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2023 THROUGH 14 FEBRUARY 2024.
| 3021 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (GAMING AND MUSIC TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT- OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2023 THROUGH 14 FEBRUARY 2024.
| 3022 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (GAMING AND MUSIC TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2023 THROUGH 14 FEBRUARY 2024.
| 3023 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (F-250 TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2023 THROUGH 14 FEBRUARY 2024.
| 3024 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (F-250 TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2023 THROUGH 14 FEBRUARY 2024.
| 3025 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (DODGE 3500 TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2023 THROUGH 14 FEBRUARY 2024.
| 3026 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (DODGE 3500TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, |
AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN.
PERIOD OF PERFORMANCE: 15 FEBRUARY 2023 THROUGH 14 FEBRUARY 2024.
TOTAL Option Year Three
| 4001 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (SEMITRACTORS): |
CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED SEMI- TRACTORS IAW THE STATEMENT OF WORK INCLUDED HEREIN.
PERIOD OF PERFORMANCE: 15 FEBRUARY 2024 THROUGH 14 FEBRUARY 2025.
| 4002 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (SEMI-TRACTORS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ONGOVERNMENT-OWNED SEMI-TRACTORS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2024 THROUGH 14 FEBRUARY 2025.
| 4003 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (DRASH ANDSTEM TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED (TRUCK- STRAIGHT WITH BOX) IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2024 THROUGH 14 FEBRUARY 2025.
| 4004 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (DRASH AND STEM TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCK- STRAIGHT WITH BOX IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2024 THROUGH 14 FEBRUARY 2025.
| 4005 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (EXPANDABLE/SEMI-TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED (EXPANDABLE/SEMI-TRAILERS) IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2024 THROUGH 14 FEBRUARY 2025.
| 4006 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (EXPANDABLE/SEMI-TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED (EXPANDABLE/SEMITRAILERS) IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
| 4007 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (F-350 TRUCKS): |
CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN.
| 4008 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (F-350 TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, ANDEQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
| 4009 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (CHEVY 3500TRUCK): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
| 4010 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (CHEVY 3500 TRUCK): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
| 4011 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (SILVER HAWK TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
| 4012 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (SILVER HAWK TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
| 4013 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (NIGHTHAWK TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2024 THROUGH 14 FEBRUARY 2025.
| 4014 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (NIGHTHAWK TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2024 THROUGH 14 FEBRUARY 2025.
| 4015 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (53 FT TRAILER): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2024 THROUGH 14 FEBRUARY 2025.
| 4016 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (53FT TRAILER): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2024 THROUGH 14 FEBRUARY 2025.
| 4017 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (MOTIV TRAILER): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2024 THROUGH 14 FEBRUARY 2025.
| 4018 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (MOTIV TRAILER): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2024 THROUGH 14 FEBRUARY 2025.
| 4019 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (EXTREME TRUCK - F650): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON A GOVERNMENT OWNED TRUCK (EXTREME TRUCK - :F650) IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2024 THROUGH 14 FEBRUARY 2025.
| 4020 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (EXTREME TRUCK - F650): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON A GOVERNMENT OWNED TRUCK (EXTREME TRUCK - F650) IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2024 THROUGH 14 FEBRUARY 2025.
| 4021 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (GAMING AND MUSIC TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT- OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2020 THROUGH 14 FEBRUARY 2021.
| 4022 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (GAMING AND MUSIC TRAILERS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRAILERS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2024 THROUGH 14 FEBRUARY 2025.
| 4023 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (F-250 TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2024 THROUGH 14 FEBRUARY 2025.
| 4024 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (F-250 TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2024 THROUGH 14 FEBRUARY 2025.
| 4025 |
| MANUFACTURE & INSTALL GRAPHIC WRAPS (DODGE 3500 TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO MANUFACTURE AND INSTALL GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2024 THROUGH 14 FEBRUARY 2025.
| 4026 |
| REMOVAL OF EXISTING GRAPHIC WRAPS (DODGE 3500 TRUCKS): CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO REMOVE PREVIOUSLY APPLIED GRAPHIC WRAPS ON GOVERNMENT-OWNED TRUCKS IAW THE STATEMENT OF WORK INCLUDED HEREIN. |
PERIOD OF PERFORMANCE: 15 FEBRUARY 2024 THROUGH 14 FEBRUARY 2025.
TOTAL Option Year Four
TOTAL
6. The Mission and Installation Contracting Command (MICC) Center – Fort Knox will establish a Firm-Fixed Price, Requirements Type Contract to manufacture and install removable wrap-around graphics and remove existing wraps from various Government owned vehicles located on Fort Knox, Kentucky in support of the United States (US) Army Mission Support Battalion (MSBN), Fort Knox Kentucky.
7. Date and place of performance: The Offeror’s (or subcontractor’s) performance facility shall be within a 50 mile radius of Fort Knox, Kentucky. The Government will deliver the vehicles to the contractor’s location.
This is a Requirements Type Contract, with a base period of one year and four, one-year option periods. Base period shall commence upon issuance of award and continue for a period of 12 months. Each option period, if exercised at Government discretion,, shall be for a duration of 12 months, respectively. Delivery orders will be issued against the base contract as needed by the Government.
8. FAR Provision 52.212-1, Instructions to Offerors -- Commercial Items, applies to this acquisition and the addenda provides additional instructions for Offerors compliance. Offeror's SAM registration shall be active in order to be eligible for award. Quotes containing a name and address different from that registered in SAM may be deemed ineligible for award.
Addendum to FAR Provision 52.212-1, Instructions to Offerors – Commercial Items
OFFEROR SHALL COMPLETE THE FOLLOWING INFORMATION:
a. The Offeror shall provide a cover letter containing the following information:
Company Name
Company Address
Point of Contact
Phone Number
Email Address
DUNS Number
CAGE Code
Tax Identification Number
DFACConfirm interest in participating in Supplier Self Service Pilot IAW DFARS 252.232-7998 SUPPLIER SELF-SERVICE PILOT (DEVIATION 2018-A000l) (DEC 2017)
Yes or No
b. Offeror shall provide the name, title and telephone number of the company/division point of contact regarding decisions made with respect to offeror’s quote and who can obligate its company contractually, in addition to information requested above.
c. Offeror’s (or subcontractor’s) performance facility shall be within a 50 mile radius of Fort Knox, Kentucky, 40121 and subsequently indicated on the cover letter. The government will use determine the 50 mile driving distance by using https://www.zip-codes.com/distance_calculator.asp. Offers must provide the zip code for its facility. Failure to provide a zip code for the location will render the offer non-compliant. Offers (or subcontractor’s) with a performance facility greater than 50 miles from Fort Knox, Kentucky will not be evaluated.
d. Submission of Quote. Submit signed and dated quote via email to the Contract Specialist and Contracting Officer identified below at or before the exact time specified in this solicitation. Only signed quotes submitted will be accepted.
e. Complete FAR Provision 52.212-3, Alt 1-Offeror Representation and Certification-Commercial Items. The Offeror shall ensure that these provisions are submitted thoroughly completed with all blocks in each certification/ representation completed truthfully and completely.
f. Offeror’s System of Award Management (SAM) registration shall be active in order to be eligible for award.
g. Offerors shall submit any questions regarding this solicitation in writing to the Contract Specialist and Contracting Officer no later than 1:00 PM Eastern Time, 17 January 2020, in order to allow a written response prior to the quote due date. No remarks or written responses to questions by government personnel shall change the terms or conditions of this RFQ. The RFQ shall only be changed by a formal written amendment issued by MICC Center – Fort Knox.
h. Offers are due January 22, 2020 at 1:00pm ET.
i. The government will check the quotes for conformity with the solicitation. A quote shall address ALL material requirements of the RFQ, otherwise it will considered non-conforming and will not be given further consideration. The government will evaluate only conforming quotes.
The government is evaluating the following factors: experience, past performance and price.
Experience: The Offeror shall provide citations of contracts and/or subcontracts that clearly demonstrate experience wrapping vehicles of similar size and complexity to the instant procurement and must provide actual photos of work performed in the past 36 months. Artist renditions or concept drawings are not acceptable. The citations shall include a brief description of the experience and how the effort is similar in scope and complexity to the effort required by this procurement.
Past performance: The offeror shall submit no more than three relevant references for this requirement. The references must indicate the period of performance or completion date, the contract value (base and option years), a description of the services provided (as prime or sub-contractor) and a point of contact with telephone number. The relevant references shall a short narrative that explains why the referenced is relevant to the scope and complexity of this requirement. If the offeror does not have any relevant references, then the offeror shall state it does not have any relevant references.
Price: The offeror shall complete the proposed unit and extended prices in the pricing schedule for each Contract Line Items Numbers (CLINS) in the Schedule B, Attachment 1. Insert the proposed unit and extended prices in the pricing scheduled for each CLIN. All CLINS must be priced to be an acceptable quote.
j. The MICC Center – Fort Knox points of contract responsible for providing information and responding to inquiries is the Contract Specialist, Mr. Dremayne Doyle, dremayne.t.doyle.civ@mail.mil and Contracting Officer, Mr. Daniel J. Hereford, daniel.j.hereford.civ@mail.mil.
9. FAR Provision 52.212-2, Evaluation -- Commercial Items, applies to this acquisition. (a) The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered, see addendum.
Addendum to FAR Provision 52.212-2, Evaluation – Commercial Items.
As allowed in the FAR 13.106-2(b)(3) the government will employ a comparative evaluations method to determine the best value of the offers for award. The method to be use is called “pairwise comparisons” and will include transitivity. There will be no tradeoffs.
The government will compare experience, past performance, and price. These factors are equally important. The government will not use “standards”, nor will it determine offers technical acceptable. Instead, the government will compare offers directly and, as such, there will be no debriefs for this procurement.
The “pairwise comparison” process works as follows. This example assumes four offers are received.
First, the government will evaluate for experience. The government will compare A’s description of its experience to B’s and decide, subjectively , which has the better experience by taking note of asserted facts, identifying differences, determining their significance to government, and documenting our conclusions. Based on a comparison, the government determines that A is better than B. Then government will then compare A to C. This time government determines C is better than A. Since C is better than A, then A is better than B; the government assumes that C is also better than B - this is transitivity. The government will then compare C to D. The government determines that D is better than C. Since D is better than C and C is better than A and B, D is also better than A and B. D is best on experience. Since the government received four offerors, and since D is best, the government will give D four points. Since C is better than A and B The government will give C three points. Since A is better than B the government will give A two points. Finally, the government will give B one point. Therefore, experience for the four offers is as follows: D = 4, C = 3, A = 2 and B = 1.
Second, the government will evaluate for past performance, using the same procedure as the government did for experience. This time the result is as follows: Past performance: D = 4, A = 3, B = 2, and C = 1.
Third, the government now compare the four prices on the quotes. This is easy. The lowest price gets four points and the highest gets 1 point. For this example assume the result is as follows: Price: B = 4, A = 3, C = 2, and D = 1.
Fourth, the government totals the points from the comparison and the results are as follows: A = 8, B = 7, C = 6, D - 9.
Finally, D is best overall, so the government award to D.
The government will evaluate on the basis of direct comparisons, based on subjective assessments and without standards. Again, this is not tradeoff. The method is in compliance with comparative evaluation of the offers as allowed in FAR 13.106-2(b)(3).