Industry Day Slides - F-35 CRT_M Facilities - 20261117.pdf

PDF 4 MB Posted

Attached to
F-35 Composite Repair and Training Facility / F-35 Maintenance Facility, Hill Air Force Base, Utah
Solicitation number
W9123827X
Issued by

About this file

This document is an Industry Day presentation issued by the U.S. Army Corps of Engineers (USACE) Sacramento District on behalf of the Air Force Civil Engineer Center (AFCEC) for a consolidated Other Transaction (OT) procurement.

The solicitation consolidates two F-35 related construction projects at Hill Air Force Base, Utah: the F-35 Composite Repair & Training Facility (KRSM163012) with a programmed amount of $177 million, and the F-35 Maintenance Facility, Phase 1 (KRSM163011) with a programmed amount of $250 million. The combined affordability limit is $371.6 million ($157.886 million for the Composite Repair and Training Facility and $213.716 million for the Maintenance Facility). The Composite Repair facility will be a two-story, secure specialized training facility plus a one-story medium bay (30' high) repair facility with multiple anechoic chambers supporting approximately 300 personnel across 225,289 square feet. The Maintenance Facility will be a 309,021 square foot multi-dock medium bay fighter aircraft maintenance hangar with parts storage, back shop, and administrative areas, including composite aircraft corrosion control capability with paint and de-paint bays. The procurement utilizes OT Authority under 10 U.S.C. § 2808a and allows selection of either a Progressive Design-Build (PDB) or Construction Manager at Risk (CMAR) delivery method. The two-step acquisition process begins with a 10-page qualifications-based white paper submission evaluating technical approach, past relevant experience, and management approach, followed by pitch meetings for up to three invited teams consisting of 2 hours of oral presentation and 1.5 hours of interactive government Q&A. Award will occur in two phases: Phase 1 covers design and pre-construction services funded with appropriated funds, and Phase 2 covers final design and construction funded with Military Construction funds, subject to negotiation of a fair and reasonable Guaranteed Maximum Price (GMP) or firm-fixed-price. The government reserves an off-ramp right to solicit construction separately if fair pricing cannot be negotiated. The draft solicitation will be posted on SAM.gov from December 1-11, 2026, with questions submitted via ProjNet (Project IDs 494772 and 494773, Bidder Inquiry Key ZSZE7J-79EQ2F) by December 11, 2026 at 2:00 PM MT. The final solicitation is anticipated for release in January 2027, with competitive selection anticipated within approximately 180 days of release. Construction laws including Davis-Bacon wage requirements, OSHA compliance, environmental requirements, payment and performance bonds, and cybersecurity/CMMC Level 1 requirements apply. Small business participation is encouraged but not required. Points of contact are Melissa DeNigris (Agreements Officer) at Melissa.A.DeNigris@usace.army.mil and Melita Doyle (Agreements Specialist) at Melita.S.Doyle@usace.army.mil.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. ARMY CORPS OF ENGINEERS:

INDUSTRY DAY

F-35 Composite Repair & Training Facility (KRSM163012) & F-35 Maintenance Facility, PH1 (KRSM163011), Hill Air Force Base, UT Issued as an Other Transaction

17 November 2026 Solicitation Number: W91238279A002

Hosted By: U.S. Army Corps of Engineers (USACE), Sacramento District (SPK)

On Behalf of: Air Force Civil Engineer Center (AFCEC)

Agenda

1. Welcome & Introduction

2. Project Overview & Strategic Importance

3. Our Collaboration Approach: CMAR or PDB and OT

4. The Acquisition Pathway

5. The Two-Step Process: From White Paper to Award

6. Step 1 Deep Dive: Your Qualifications White Paper

7. Step 2 Deep Dive: The Pitch Meetings

8. Evaluation, Award Structure & The Off-Ramp

9. Key Project Requirements

10. Scope of Work & Technical Requirements

11. Funding & Affordability Limit ($371.6M)

12. Small Business Partnership Goals

13. Your Next Steps

14. Government Resources for Bidders

15. Summary & Key Takeaways

16. Open Forum & Thank You

Introductions USACE – Sacramento District (SPK) F-35 Composite Repair &

Training Facility & F-35 Maintenance Facility, Phase 1 at Hill Air Force Base, UT - Project Delivery Team (PDT)

- Ms. Liz Rodriguez Torres – Project Manager

- Ms. Melissa DeNigris – Agreements Officer (AO)

- Ms. Natasha Jackson – Engineering Technical Lead

- Mr. Ryan Lamb – SPK Cost/Price Analyst

- Mr. Christopher Paxman – Administrative Agreements Officer (AAO)

- Mr. Jese Syme – Agreements Officer Representative (AOR)

- Ms. Melita Doyle – Agreements Specialist

- Mr. Tré Santos – SPK Chief of Contracting

• Thank you for joining us for this Industry Day.

• Our intent is clear – we want to execute CMAR or PDB as closely as possible to the way you successfully operate in the private sector.

• Leveraging Other Transaction (OT) Authority process, which we believe frees us from traditional FAR constraints and provides the flexibility needed to mirror industry best practices.

• We need you as a collaborative partner. Request candid feedback when we issue our draft Program Solicitation – tell us what works, and more importantly what we can improve.

• Your insights today will do more than shape this single acquisition; they will help us establish a strong, commercially sound foundation for the USACE enterprise going forward.

What is an Other Transaction (OT)?

• An Other Transaction (OT) is a legally binding agreement used by the Government under specific statutory authority (e.g., 10 U.S.C. § 2808a) that is not governed by the Federal Acquisition Regulation

(FAR).

• OT provides maximum flexibility to structure agreements that support collaboration, innovation, and speed, especially for complex or non-traditional projects.

What is Progressive Design Build (PDB)?

• PDB is a collaborative delivery method where owners, such as Government agencies, select a design-build team based primarily on qualifications and technical approach rather than price. The team works jointly with the Owner to develop the design and establish a guaranteed maximum price (GMP) before construction begins, often reducing risk.

• Key Characteristics

• Qualifications-based selection (QBS)

• Early Design-Build

Team’s involvement

• Open collaboration & transparency

• Progressive cost development

• Reduced risk before construction

What is Construction Management at Risk (CMAR)?

• A phased project-delivery approach in which the Government engages a construction manager early— during planning, design, and preconstruction—to provide constructability reviews, cost estimating, scheduling, market intelligence, and risk-management support. The construction manager later assumes responsibility for delivering the construction work, typically after negotiating a Guaranteed Maximum Price (GMP) or comparable not-to-exceed price.

Construction laws applicable to 10 U.S.C.

§ 2808a to OT OT Flexibilities

• Not governed by FAR Part 15 source selection procedures

• Flexible evaluations (white papers, pitch sessions, iterative discussions)

• Tailored OT agreement structure

• Open-book pricing and iterative scope refinement

• Early stakeholder collaboration and iterative refinement

• Faster acquisition timelines and stakeholder engagement

• Milestone-based fixed-price structure

Construction Laws Still Apply

• Davis-Bacon / applicable labor law compliance

• OSHA & EM 385-1-1 safety requirements

• Environmental compliance (NEPA/UFC/installation standards)

• Payment & Performance bonds

• Cybersecurity / CMMC Level 1 requirements

• Fiscal law / Anti-Deficiency Act compliance

• Security, export control, DPAS priority rating

• Brooks Act

Why Other Transaction (OT)?

• Why This Approach? Acquisition Strategy Rationale:

• Consolidate the two F-35 facilities under a single OT agreement offers significant benefits. It streamlines the acquisition process, generates cost savings, provides necessary flexibility for incremental funding, and accelerates the delivery of critical infrastructure to the warfighter —while adhering to an urgent, mission-critical schedule. The Government recognizes that a traditional, FAR-based procurement is incompatible with these constraints. It would introduce unacceptable schedule delays and force Design-Build Teams to prematurely price unquantified risks, likely resulting in inflated proposals that exceed the $371.6M budget.

• To mitigate these risks and ensure mission success, the Government is executing this requirement utilizing OT Authority (10 U.S.C. § 2808a).

• This approach replaces the traditional design-build process with a collaborative acquisition approach using either CMAR or PDB.

OT is the Solution

• OT: This is not a FAR-based contract. The OT authority gives us the speed and flexibility to tailor the process, focus on technical excellence, and build a team.

• PDB: Government selects a Design-Build Team based on qualifications, collaborative price. The DB Team works with the Government to develop the design and open book pricing, reducing risk for everyone.

• CMAR: Government selects a construction manager based on qualifications, collaborative price. The CM works with the Government during planning, design, and preconstruction establishing early work packages and phasing to reduce risk. Open book pricing established.

Why Provide the $371.6M Budget to Industry?

1. Establishes Realistic Design Boundaries

• Aligns all teams to a defined affordability limit

• Prevents overdesign and inexecutable concepts

• Focuses solutions on what can actually be delivered

2. Enables Collaborative cost development (open-book)

• Early budget transparency allows:

• Design decisions tied to cost

• Continuous cost validation during design

• Negotiation of a realistic Target Price / GMP

Industry? (cont’d)

3. Reduces Risk Pricing & Contingency

• Without a budget, contractors must price unknown risk

• Leads to:

• Inflated contingencies

• Conservative (and expensive) proposals

• Budget clarity drives more accurate and competitive pricing

4. Improves Competition & Industry Engagement

• Attracts serious, capable teams aligned to the project size

• Filters out firms that cannot realistically perform

• Encourages innovative, cost-conscious solutions

5. Accelerates Acquisition Timeline

• Minimizes redesign cycles due to cost misalignment

• Reduces back-and-forth during negotiations

• Supports faster path to award

6. Strengthens Government– Industry Partnership

• Signals transparency and trust

• Reinforces collaborative intent of:

• OT Authority under 10 U.S.C.

§ 2808a

• Aligns both parties toward a shared outcome

Industry? (cont’d)

Project Overview

• Project Title: F-35 Composite Repair & Training Facility, Phase 1

• Location: Hill Air Force Base at Utah

• Programmed Amount: $177M

• Scope: Design and construct a two-story, secure specialized training facility for personnel assigned to repair composite components for F-35 fighter aircraft.

Also, design and construct a one-story, secure medium bay (30' high) F-35 composite repair facility with multiple anechoic chambers for a workforce of approximately 300 personnel. Shop, aircraft, general purpose: 225,289 SF.

Intellectual Property Partnership agreement with Lockheed Martin is required to ensure the 3 anechoic chambers are adequately designed & constructed.

• Authorization: Awaiting new directive for OT using PDB or CMAR.

• Strategic Importance: This project will allow both the training and repair missions of the of the F-35 fighter aircraft which have been arriving at HAFB, in significant numbers since September 2015, to undergo Depot repairs or modifications.

Project Overview

• Project Title: F-35 Maintenance Facility, Phase 1

• Location: Hill Air Force Base at Utah

• Programmed Amount: $250M – Incremental Funding

• Scope: Design and construct a 309,021 SF multi-dock medium bay fighter aircraft maintenance hangar with parts storage/equipment areas, back shop, and administrative areas. Project scope includes composite aircraft corrosion control capability to include one paint bay and one de-paint bay.

The proposed facility will have reinforced concrete footings, foundation, floor slab, structural steel frame, insulated walls, insulated roof, lightning protection, fire detection/suppression, and intrusion detection.

• Authorization: Awaiting new directive for OT using PDB or CMAR.

• Strategic Importance: This project will provide space for routine scheduled maintenance, specialized modification, and incident repair on the F-35 fighter aircraft.

Hill AFB F-35 Program

• Procurement Instrument: Other Transaction (OT)

• Authorized under Title 10 U.S.C. §2808a

• Provides flexibility compared to traditional FAR-based contracts, allowing the process to be tailored to the project's unique needs

• Delivery Model: Progressive Design-Build (PDB) or Construction Manager at Risk (CMAR)

• A collaborative partnership between the Government and the Contractor from the early stages of design

• Focuses on identifying project risk early, optimizing design, and alignment on cost and schedule

Procurement Approach

The Overall Process

The Overall Process

Procurement Approach Notes

• The sam.gov announcement, including all stated attachments and any websites incorporated by reference, constitutes the entire solicitation and forms the basis for all content resulting in the Other Transaction (OT).

• The Government anticipates completing the competitive selection process and making an award within approximately one-hundred eighty (180) days of solicitation release. Performers who are interested in proposing but unable to meet the approximate timeline may be removed from consideration for award.

Acquisition Pathway

STEP 1: The Qualifications Based Down-Select •Submit a 10-Page White Paper •Government anticipates evaluating technical approach, past relevant experience, and management approach.

•Government invites Up to 3 Team(s) to Step 2 Interview

STEP 2: The Final Selection

• Invited Team(s) participate in the Pitch Meeting which includes up to 2 hours oral presentation and 1.5 hours of interactive Government Q&A discussion.

• During this Pitch Meeting, the Government will evaluate each Offeror’s:

• Technical understanding

• Collaborative approach

• Problem-solving capability

• The Government then selects the Contractor that will advance to begin negotiations and advance to Phase 1 award.

GOAL: To demonstrate that your team is one of the most highly qualified Contractor for this specific type of complex project and demonstrate proven success together as a Contractor Team.

Acquisition Pathway (cont’d)

Note: The evaluation criteria and evaluation process are tentative, have not yet been finalized and are subject to change. We are soliciting industry inputs after Industry Day to finalize the criteria. This information is provided for informational purposes only to communicate the Government’s current intended approach.

Contractors are responsible for reviewing and complying with all instructions, requirements, and evaluation criteria contained in the official Program Solicitation posting.

STEP 1 Deep Dive: The White Paper

• Focus: On your qualifications, not a detailed design.

• Factor 1: Technical Approach

• Understanding of Project Goals

• Mission, technical requirements, constraints, affordability

• Factor 2: Past Relevant Experience

• Relevant Experience

• Similar size, scope, and complexity

• PDB or CMAR Expertise

• Experience with collaborative acquisition methods (e.g., OTA)

• Factor 3: Management Approach & Key Personnel

• Management Philosophy

• Clear, collaborative execution strategy

• Key Personnel, qualified, experienced team members

• Ability to staff two project sites

• Organizational Structure

• Logical roles, responsibilities, and reporting relationships

• The White Paper is a "Corporate Resume," not a technical proposal.

• Page Limit: 10 Pages. Be concise.

STEP 2 Deep Dive: The Pitch Meetings (By Invitation Only)

Step 2 determines which Contractors are the best fit to work collaboratively with the Government and advance toward award. The Step 2 invitation will provide detailed instructions for all submission requirements and evaluation activities.

Interview:

• An interactive oral presentation used to evaluate the team’s communication, collaboration, problem-solving ability, PDB or CMAR experience, and overall project understanding.

• During the next 1.5 hours, the Government will conduct an interactive Q&A discussion.

Goal: To prove to the Government that your company has both the technical expertise and the collaborative mindset to be our long-term partner for this critical project.

Award Structure & The Off-Ramp The OT will be awarded in two parts Phase 1 and Phase 2:

• Phase 1 Award — Design and Pre-Construction Services:

The selected Contractor Team will be awarded an OT for Phase 1. No construction work will be performed during the design and pre-construction phase unless separately authorized by the Government. Phase 1 will be funded with appropriated funds available for the authorized purpose.

• If Negotiations fail for Design Efforts and Target Construction Price during Phase 1:

• The Government may:

• Terminate negotiations

• Initiate negotiations with the next qualified Contractor

Phase 2 Award— Final Design and Construction or Construction (at Risk):

Phase 2 may be awarded as a modification to the OT upon successful negotiation of a fair and reasonable GMP or FFP at a future design milestone. Phase 2 is anticipated to be funded with Military Construction funds, subject to availability of funds and required approvals.

The Off-Ramp: The Government's Protection The Government is not obligated to award Phase 2.

• If a fair price cannot be negotiated for 65% or 95%, we have the right to take the completed Phase 2 design and solicit the construction separately.

Non-Selection Feedback

• The Government may provide non-selection feedback to

Contractors at appropriate points in the selection process. If the Government conducts a down-select after Interview 1, feedback may be provided to Contractors not invited to proceed to Interview 2.

• Feedback will be limited to the Government’s evaluation of the Offeror’s own submission, interview performance, and demonstrated approach. The Government will not disclose proprietary information, internal deliberative information, source selection sensitive information, or detailed information regarding other Contractors.

• Feedback provided under this process is intended to promote transparency and improve industry understanding. It does not constitute a FAR Part 15 debriefing and does not reopen the evaluation or provide an opportunity to revise a submission unless expressly authorized by the Government.

What Happens After Award? (The Partnership Begins)

Post-Award: The Phase 1 Partnership

• The award of the Phase 1 OT is the beginning of our collaborative partnership, not the end of the acquisition.

• Upon award, the selected Contractor will immediately integrate with the USACE and Air Force team to begin the Phase 1 design and pre-construction phase. This is a transparent, hands-on process.

Key Activities in Phase 1:

• Jointly Develop the Design: We will participate in regular "Over-the-Shoulder" design reviews to advance the facility design from concept to a mature, buildable solution (~65% completion).

• Build the "Open Book" Cost Model: Contractor will be required to transparently build the construction cost estimate, sharing actual subcontractor quotes and material pricing with the Government team.

• Manage Risk Together: Contractor will co-manage a Joint Risk Register with USACE, working together to identify, price, and mitigate project risks before they become problems.

• Negotiate the Final Price: At the end of Phase 1, we will use the transparent Open Book model and our IGE to negotiate a fair and reasonable Firm-Fixed-Price for the Phase 2 construction work.

• Our goal in Phase 1 is to work as a single, unified team to de-risk the project and establish a credible, data-driven price for construction.

Small Business Partners

• Commitment to Small Business Participation is not a separately rated evaluation factor.

• Small business participation is encouraged but is not required as a condition of eligibility under 10 U.S.C. § 2808a.

• Contractor Teams have full flexibility to structure their teams in a manner that best supports successful project performance. If a Contractor Team identifies a small business partner, the partner’s role should be clearly described and may be incorporated into the resulting Agreement, as applicable.

Funding & Affordability

Limit

• Affordability Limit (Not-to-Exceed) = $317.6M: F-35 Composite Repair and Training Facility:

$157,886,000, and for F-35 Maintenance Facility:

$213,716,000.

• This is the maximum funding available for the OT, covering all design, construction, and commissioning activities

• This is a critical project constraint: proposals must adhere to this limit

• Maintenance Facility – incremental funding anticipated. Funding likely to be available for Phase 1 award in FY27.

Government Resources for Contractors

• The U.S. Government provides no-cost resources to assist businesses:

• APEX Accelerators (https://www.apexaccelerators.us/#/about-us )

• Free expert coaching on government contracting, from readiness to proposal writing and performance

• Project Spectrum (https://www.projectspectrum.io/#/ )

• A DoW-funded initiative to help businesses improve cybersecurity and meet CMMC requirements through free tools, training, and support https://www.apexaccelerators.us/#/about-us https://www.apexaccelerators.us/#/about-us https://www.apexaccelerators.us/#/about-us https://www.projectspectrum.io/#/

Summary & Key Takeaways

• Industry Day is a high-level informational briefing for the consolidation under one

Other Transaction for the F-35 Composite Repair and Training Facility and F-35 Maintenance Facility projects. It provides the Government and industry an early opportunity to understand each other before the official Program Solicitation is released.

• Due to the complexity of these two projects, F-35 Composite repair and training Facility and F-35 Maintenance Facility, Industry Day is important because it helps ensure industry understands the mission, acquisition strategy, project constraints, schedule, and the Government’s expectations. It also gives industry early insight into the collaborative approach needed to successfully support this mission-critical project.

• The Government anticipates posting the draft solicitation on SAM.gov on 1 December 2026. This draft will allow industry to review the Government’s proposed approach, including the scope, evaluation criteria, schedule, submission requirements, and overall acquisition process.

• Providing the draft before the official solicitation gives industry an opportunity to identify areas that may be unclear, overly restrictive, unrealistic, or inconsistent. This feedback helps the Government improve the final solicitation, reduce acquisition risk, and support stronger competition.

• The overall goal is to promote collaboration, teamwork, transparency, and shared understanding in order to meet the mission successfully.

Draft Solicitation Posting: Feedback and Input:

• Points of Contact: Melissa DeNigris, AO, Melissa.A.DeNigris@usace.army.mil and Melita Doyle, AS, Melita.S.Doyle@usace.army.mil

• The Draft Program Solicitation will be posted from 1 December through 11 December on sam.gov.

• All questions related to the draft program solicitation must be submitted via ProjNet.

• Bidder Inquiry System: https://www.projnet.org/projnet.

• Project IDs & Names: 494772 & 494773 F35 Maintenance Facility and F35 Composite repair and training Facility

• Bidder Inquiry Key: ZSZE7J-79EQ2F

• Inquiry Deadline: ProjNet will be closed to new inquiries on 11 December 2026 @ 2:00 PM

MT.

mailto:Melissa.A.DeNigris@usace.army.mil mailto:Melita.S.Doyle@usace.army.mil https://www.projnet.org/projnet

Questions & Thank You

• Anticipated Program Solicitation Release: January 2027

• General Comments/Questions?

Thank you for your interest and looking forward to your input!

U.S. Army Corps of Engineers:�Industry day
Agenda
Introductions
Slide Number 4
What is an Other Transaction (OT)?
What is Progressive Design Build (PDB)?
What is Construction Management at Risk (CMAR)?
Construction laws applicable to 10 U.S.C. § 2808a to OT
Why Other Transaction (OT)?
OT is the Solution
Why Provide the $371.6M Budget to Industry?
Why Provide the $371.6M Budget to Industry? (cont’d)
Why Provide the $371.6M Budget to Industry? (cont’d)
Project Overview
Project Overview
Hill AFB F-35 Program
Slide Number 17
The Overall Process
The Overall Process
Procurement Approach Notes
Acquisition Pathway�
Acquisition Pathway (cont’d)
STEP 1 Deep Dive: The White Paper
STEP 2 Deep Dive: The Pitch Meetings (By Invitation Only)
Award Structure & The Off-Ramp
Non-Selection Feedback�
What Happens After Award? (The Partnership ��Begins)�
Small Business Partners
Funding & Affordability Limit
Government Resources for Contractors
Summary & Key Takeaways
Draft Solicitation Posting: Feedback and Input:
Questions & Thank You