Mariposa Questions and Answers.pdf

PDF 102 KB Posted

Attached to
Mariposa Dam Spillway Road Repair Service
Solicitation number
W9123824Q0019
Issued by

About this file

This document contains questions and answers regarding a solicitation for the Mariposa Dam Spillway Road Repair Service. The solicitation involves repairing roads surrounding culverts at Mariposa Dam, including replacing Class III base rock and asphalt. No compaction testing or materials testing is required beyond that for earthworks surrounding the culverts. Task 2 is optional and will involve reinforcing the roadway with 18-24 inch riprap to a depth of 6 feet on the stream side. The Army Corps of Engineers Engineering District Sacramento is the contracting agency, and all questions must be submitted by February 29, 2024 to be considered. No diagrams or specifications are provided for the road cross-section, woven geotextile fabric, or thicknesses of base rock and asphalt.

View the file

Other files

File Type Posted
Solicitation.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Mariposa Dam Spillway Road Repair Questions and Answers

W9123824Q0019

1. I was looking into the Quality Control requirements for the Mariposa Dam Spillway Road Repair

Project and noticed that the only listed requirements were for the earthworks/base material surrounding the culverts. I did not see any compaction requirements or anything for the actual roadway repairs. Am I correct in assuming no materials testing or compaction testing is required for these roadways or am I missing something?

Review PWS 2.1.2.1 in the solicitation.

2. Is Task 2 going to be implemented?

Task 2 is optional and will be exercised at the discretion of the Government.

3. RFP section 2.1.1 states “…except for material around the conduits.” Is this a mistake referencing to the culverts or is there utility conduits within the roadway?

Culverts are shown in the photo Map C.1 for 2.1.1.

4. Can you provide required spec for clay backfill and road base?

See answer to question 1.

5. Can you provide required spec for woven geotextile fabric?

The type of woven geotextile fabric is up to the contractor.

6. Please provide cross section diagram for Task 1.

No diagram was provided. See answer to question 1.

7. Regarding Task 1, what is the required thickness for the Class III base rock and asphalt?

See answer to question 1.

8. Regarding Task 2, what is the required thickness for the Class III base rock?

See: PWS 2.1.3.1 The finished road repairs will support 55,000 pounds without damage and be reinforced with riprap 18-24 inches, 6 feet in depth on the stream side of the roadway to the height of the finished road section.