Solicitation W9123824Q0009 Amendment 0001.pdf
PDF 2 MB Posted
- Attached to
- USFS – Installation of New Insulation Material
- Solicitation number
- W9123824Q0009
About this file
This amendment modifies a solicitation for installation of new insulation material. The U.S. Forest Service Pacific Southwest Research Station seeks a contractor to install new faced fiberglass batt insulation and baffles in the attic of the Institute of Forest Genetics Administrative Building in Placerville, California. An updated performance work statement and extended due date of January 29, 2024 at 11:00AM are included. The contractor must meet standards for employees, safety, reporting, and installing approximately 6,600 square feet of R-38 faced fiberglass insulation batts under the roof deck and 405 square feet of R-13 batts on end walls. The quality assurance surveillance plan establishes performance requirements and acceptance criteria.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation W9123824Q0009 Amendment 0002.pdf | ||
| Responses to submitted questions.pdf | ||
| Solicitation W9123824Q0009.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
1. Incorporate an updated Performance Work Statement (PWS)
2. Extend the due date for quotes.
No other changes made or implied.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 15
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 17-Jan-2024
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9123824Q0009
X 9B. DATED (SEE ITEM 11)
21-Dec-2023
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
17-Jan-2024
CODE
USACE SACRAMENTO DISTRICT
ATTN: CONTRACTING DIVISION
1325 J STREET
SACRAMENTO CA 95814-2922
W91238 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9123824Q0009
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
SOLICITATION/CONTRACT FORM
The required response date/time has changed from 23-Jan-2024 11:00 AM to 29-Jan-2024 11:00 AM.
The following have been modified:
PERFORMANCE WORK STATEMTN
PERFORMANCE WORK STATEMENT
U.S. FOREST SERVICE PACIFIC SOUTHWEST RESEARCH STATION
INSTITUTE OF FOREST GENETICS ADMIN BLDG INSTALL NEW INSULATION
PLACERVILLE, CALIFORNIA
3 Nov 2023 17 January 2024
1.0 GENERAL STATEMENT OF SERVICES
1.1 Introduction and Purpose. The contractor shall furnish all necessary labor, material, equipment, and operating personnel to install new insulation material in the attic space of the Administrative Building within the Institute of Forest Genetics (IFG) located at Placerville, California.
1.2 Location.
U.S. Forest Service, Institute of Forest Genetics 2480 Carson Road Placerville, CA 95667
1.3 Security Requirements. The Contractor will be required to comply with all U.S. Forest Service (USFS) Pacific Southwest (PSW) Research Station entrance and security requirements. Contractor shall coordinate access to the building with onsite personnel through the Contracting Officer’s Representative (COR).
2.0 OBJECTIVE
The insulation material was removed from the attic space of the USFS PSW IFG Admin Bldg. It is the objective of this contract to install new insulation material to improve the building envelope’s thermal performance in preparation for the winter season.
3.0 DETAILED DESCRIPTION OF SERVICES
3.1 General Requirements. All work performed by the Contractor shall be designed and implemented in a manner which conforms to the requirements in this PWS including all applicable Federal, and state and local regulations, and all accepted Work Plans and submittals. If there is a conflict between Federal, state, and local regulations and the PWS, the Contractors shall immediately inform the COR who will inform the Contracting Officer. The Contracting Officer will make a determination. If a conflict does arise, the most stringent rule will apply.
3.2 Period of Performance. The Period of Performance for this contract will be 90 calendar days following the receipt of purchase order.
3.3 Employees. The contractor shall furnish competent personnel. If employees furnished prove to be incompetent in the opinion of the COR after discussions with the Contracting Officer, the contractor shall remove them and furnish satisfactory employees. Contractor personnel shall obtain and maintain in good standing all certifications, inspections, and licenses necessary or appropriate to perform all work contained in this PWS. The Contractor shall maintain the training skills and qualifications of all personnel throughout the period of performance. All persons performing under the contract shall remain employees of the Contractor and not of the Government. The Government has the right to restrict employment under the contract of any contractor employee, or prospective contractor employee, who is identified by the COR/Contracting Officer as a potential threat to the health, safety, security, general well-being or operational mission of the installation and its population. All Contractor employees performing work under the contract shall be physically able to do their assigned work. The Contractor shall not allow any employee(s) to perform any work who is under the influence of alcohol or is incapacitated in any way.
The COR/Contracting Officer may require the Contractor to remove from the job site any employee for misconduct or security reasons. The removal from the job site of such person shall not relieve the Contractor of the requirement to perform adequate and timely service. The Contractor shall cooperate with other contractors and Government personnel performing work at USFS.
3.5 Order of Work. The work shall be carried on in such order of precedence as may be found necessary by the
COR.
3.6 Point of Contact. The point of contact for this requirement will be furnished upon award of the purchase order.
3.7 Authorities/Technical Direction. The Contractor shall take no direction from any Government employee or any other person other than the Government Contracting Officer that changes the terms and conditions of this contract action, the scope, or any change that impacts the cost, price or schedule. Changes authorized by the Contracting Officer will be in the form of a written, official, signed modification to the contract action received by the Contractor before the Contractor will act upon those changes. The Contractor will comply with the Changes clause of this contract when the contractor believes direction has been given from persons other than the Government Contracting Officer that equate to a change by notifying the Contractor Officer as directed by the clause. Any direction given by any Government employee or any other person outside their authority must be reported to the Contracting Officer. The COR is limited to the authorities stated in the COR appointment letters.
3.8 Mutual Understanding (Preconstruction) Meeting. Ten days before the start of work, a meeting will be held with the contractor, US Army Corps of Engineers (USACE) Contracting Officer or Contracting Officer Representative (COR) to discuss matters of mutual interest concerning the contract, general conditions, work schedule, phasing and coordination, security, safety, permits, and other matters pertinent to work accomplishments will be discussed in the meeting. The Contractor shall provide a Work Plan at the mutual understanding meeting that identifies in detail the work to be completed as indicated below.
3.10 Operating Hours. The Contractor shall perform the services required under this contract during the following hours: 8:00 a.m. to 4:30 p.m. Monday through Friday, excluding Federal holidays. The COR shall be notified by telephone (followed in writing by 10:00 a.m. the next workday) of all emergency work, which extends beyond normal working hours.
Federal Holidays. Except as otherwise specified, routine work shall not be scheduled on holidays.
Federal holidays observed are as follows:
New Years Day – January 1 M.L. King Birthday – 3rd Monday in January President’s Day – 3rd Monday in February Memorial Day – last Monday in May Juneteenth Day – June 19 Independence Day – July 4 Labor Day – 1st Monday of September Columbus Day – 2nd Monday of October Veterans Day – November 11 Thanksgiving Day – 4th Thursday of November
Christmas Day – December 25
3.11 Invoices. Invoices for payment shall be submitted upon completion of tasks as outlined in the contract.
Invoices shall be submitted to:
Original invoice only WITHOUT additional information or supporting documentation:
USAED, FINANCE CINETER
ATTN: CEFC-AO-P
5270 Integrity Drive
Millington, TN 38054-5005 CEFC-Payments@usace.army.mil
One copy of each invoice WITH all required information including any necessary supporting documentation:
COR – TBD at contract award U.S. Army Corps of Engineers, Sacramento District
1325 J. Street, Sacramento, CA 95814
Email: given at contract award
NOTE: All invoices must reflect the contract order number and invoice number and the final invoice must be marked “FINAL”.
Contract Payments: The Government shall pay the Contractor upon submission of proper invoices for services delivered and accepted for the portion of the work actually performed under the contract. Deliverables as defined in the contract must be accepted by the Government before payment will be made.
4.0 WORK TO BE PERFORMED
4.1 Service Scheduling. Within seven (7) days after award of contract, the contractor shall submit to the COR for approval a service schedule indicating the time and sequence of work. If unforeseen events cause a variation in the scheduled service, the contractor shall notify the COR in advance of the delay or as soon as possible if unable to notify in advance. Failure to provide the service or variation from the agreed schedule will require written explanation by the contractor. If and when additional service(s) are added, the schedule will be modified.
4.2 Scope of work.
The roof of the Admin Building is constructed of wood trusses and wood deck, and between and below the ceiling joists is hard lid lath and plaster ceiling system throughout the entire interior of the facility. The attic space roof and walls currently have no insulation which impacts the building envelope thermal performance and overall building energy efficiency. There are currently 2 ceiling access panels (approximately 24”x 24”) for personnel access to the attic, located proximate to the breakroom and to the library. There are two non-operable windows located at the attic end walls, caution shall be exercised with these windows due to their historic value.
The Contactor shall provide and install faced fiberglass batt insulation and baffles to the underside of the roof deck and insulation on the end walls in the attic above the ceilings. Blown-in insulation on top of the lath and plaster ceiling or ceiling-mounted water and electrical utilities is not permitted. The insulation must be installed between structural elements throughout the entire underside of the roof deck enclosing the attic space and wall studs. The insulation must be secured to avoid sliding and sagging with 14 ga wire batt supports; the wires support must extend to the width of the batt provided. Baffle installation must go all the way up to the ridge of the underside of the roof deck. The work to be performed must ensure that the insulation and baffles do not block the existing attic vents and wall windows. Care must be taken to verify footing when working in the attic, and some spots could be missing lathe and plaster. The Contractor shall submit the insulation and accessory materials for Government review and approval; the Government estimates that 6,600 SF of R-38 kraft faced fiberglass insulation batts would be adequate for the underside of the deck area and 405 SF of R-13 kraft faced fiberglass insulation batts would be adequate for the wall areas. All applicable manufacturer accessories and recommendations shall be followed and products used shall be free of hazardous materials. The Contractor shall exercise caution to not to damage the integrity of the existing roof, lath and plaster ceiling structure, walls, utilities, and conduits during the installation process and take proactive steps to protect and preserve those features. Any damages incurred during the installation process shall be restored to original condition. Any damages to the historic windows shall be restored to its original condition per historical preservation standards and guidelines. Submit workplan and material data for Government review and approval prior to start of work on site.
Quantity Take Off is estimated as follow (Contractor shall field verify quantities):
Roof Area Approx.6,600 SF
Roof Slope Approx.6”:12”
Wall Area (at ends) Approx. 405 SF
4.3 Contractor Reporting.
4.3.1 Status Updates. The contractor shall submit status report via email to the Government COR at the request of the Government but at no more frequently than a bi-weekly basis. These status updates shall include, at a minimum:
a) A summary of work completed in the field, permit status, and any significant events.
b) Progress photos (in electronic format) depicting major work activities accomplished during the reporting period.
4.3.2 Progress Reports. The Contractor shall submit a Progress Report no later than 1700 hours on Friday afternoon, as warranted but not more frequently than a bi-weekly basis, and according to the distribution and quantities in paragraph 4.5.3 below. These weekly Progress Reports shall address the following:
a) A summary of work completed in the field with respect to all schedule milestones. Annotate and explain all deviations. Denote anticipated or actual delay of a scheduled field activity, to include basis and any effect on subsequent events or scheduled activities.
b) Any outside inspection reports, audits, or other administrative information developed/completed or anticipated.
c) Copies of all Quality Assured Data, sampling and test results and any other laboratory deliverables received, if any.
d) Documentation of material recycling including receipts of recycle centers. Project photos are acceptable provided a sufficient explanation is attached.
4.3.3 Final Report. The Contractor shall provide a final report no later than 10 working days after completion of project. The final report shall include a detailed description of work performed and lessons learned. A summary of the disposition of all project debris materials will include the quantity and type of debris materials recycled, salvaged, reused, and disposed of and shall be presented in chart form showing original material quantity estimated, quantity recycled, percentage recycled, and approximate cost or cost savings versus a commercial landfill alternative.
5.0 QUALITY CONTROL
5.1 Quality Control and Assurance: The Contractor is responsible for performing or having performed all inspections and tests necessary to substantiate that the services furnished under this contract conform to contract requirements, including any applicable technical requirements for specified manufacturers’ parts.
5.2 Quality Control Plan. The Contractor shall furnish for review by the Government, not later than ten days after receipt of award, the Contractor Quality Control (CQC) Plan proposed to implement the requirements of section 4.0 WORK TO BE PERFORMED. The CQC plan shall identify personnel, procedures, control, instructions, tests, records, and forms to be used. This documentation shall be made available to the Government throughout the term of the contract. At any time it is determined by the Contracting Officer that the quality control system, personnel, instructions, controls, tests, or records are not providing results which conform to contract requirements, action shall be taken by the Contractor to correct the deficiency, i.e., replacement of personnel, additional quality control inspections, etc.
5.3 Quality Assurance Surveillance Plan. The Government will evaluate the Contractor’s performance under the enclosed Quality Assurance Surveillance Plan (QASP). The QASP provides a systematic method to evaluate performance for this contract. The Contractor is fully expected to comply with all requirements in the PWS. The COR will monitor the Contractors performance to ensure it meets the standards of the contract. When an observation indicates defective performance, the Contracting Officer will require the COR or on-site representative to initial the observation. The initialing of the observation does not necessarily constitute concurrence with the observation, only acknowledgement that he or she has been made aware of the defective performance. Unacceptable performance may result in the Contracting Officer taking any of the following actions: Require the Contractor to take necessary action to ensure that future performance conforms to the contract requirements, reduce the contract price to reflect the reduced value of the services, issues a Contract Discrepancy Report (CDR), or require the Contractor to re-perform the service. The Contracting Officer may require the Project Manager to meet with the Contracting Officer, contractor administrator, COR, and other Government personnel as deemed necessary. The Contractor may request a meeting with KO when he or she believes such a meeting is necessary. Written minutes of any such meetings shall be recorded by the Contractor, approved by the Contracting Officer and signed by the Project Manager and the Contracting Officer or Contract Administrator. Copies of any such meeting minutes shall be maintained by the Contracting Officer. If the Contractor does not concur with any portion of the minutes, such non-concurrence shall be provided in writing to the Contracting Officer within one calendar day following receipt of the approved minutes.
All work performed and equipment used under the contract will be subject to inspection at all times by the Government. The Government’s inspection program is not a substitute for the Quality Control by the Contractor.
(Appendix A).
6.0 SAFETY
6.1 Safety Requirements. In order to provide safety control for protection to the life and health of employees and other persons; for prevention of damage to property, materials, supplies, and equipment; and for avoidance of work interruptions in the performance of this contract, the Contractor shall comply with OSHA and all pertinent provisions of the publication 29 CFR 1910 (Occupational Safety and Health Standards), and EM 385-1-1 (Safety and Health Requirement Manual – online. https://www.publications.usace.army.mil/USACE-Publications/Engineer- Manuals/). Contractor is subject to all USFS health and safety regulations and requirements.
Appropriate signs designated by Fire, Safety & Security shall be provided by the contractor and placed as indicated in work areas. Within one calendar day after commencement of work, erect a safety bulletin board at the job site.
Where size, duration, or logistics of project do not facilitate a bulletin board, an alternative method, acceptable to the COR that is accessible and includes all mandatory information for employee and visitor review, shall be deemed as meeting the requirement for a bulletin board. Include and maintain information on safety bulletin board as required by EM 385-1-1 section 01.A.07.
The work areas shall be closed off to unauthorized personnel. All project-associated activities shall be performed without damaging or contaminating adjacent work and areas. Where such work or areas are damaged or contaminated, the Contractor shall restore work and areas to the original condition at no additional cost to the Government.
All accidents shall be reported to the COR immediately both verbally and followed up in writing (email) as soon as possible. As warranted, the Safety Office shall be notified using ENG 3394 through the Technical POC. This is to be accomplished within the same shift, preferably as soon after the accident as is practical. A completed Occupational Safety and Health Administration (OSHA) Form 300; and ENG 3394 shall be submitted to the Safety
Office within 5 days after an accident. In the event of serious injury or damage, work shall stop, and everything shall be left in place exactly as it was at the time of the accident, except when rendered safe actions are warranted to prevent the possibility of more damage or injury. Medical expenses for Contractor personnel are the responsibility of the Contractor.
Designate a Safety person at the project site to function as the Site Safety and Health Officer (SSHO). The SSHO or an equally-qualified Designated Alternate SSHO shall be at the work site at all times to implement and oversee the Contractor's safety program and government-accepted Accident Prevention Plan. The SSHO's training, experience, and qualifications shall be IAW EM 385-1-1 paragraph 01.A.17, entitled Site Safety and Health Officer (SSHO), and all associated sub-paragraphs. The SSHO must ensure the requirements of EM 385-1-1 section 1 and 29 CFR
1926.16 are met for the project. Any observed violation of safety requirements can be grounds for the Government to stop work. Work shall not continue until the violation is corrected.
USACE shall hold contractors accountable for their safety and health performance.
A Competent Person shall be provided for all of the hazards identified in the Contractor's Safety and Health Program in accordance with the accepted Accident Prevention Plan and shall be on-site at all times when the work that presents the hazards associated with their professional expertise is being performed. Provide proper credentials of the Competent Persons(s) to the COR for acceptance in consultation with the Safety Office prior to start of the project.
The equipment used by the Contractor for the specified service shall be in satisfactory operating condition and shall be maintained in good condition. The Government reserves the right to require the Contractor to discontinue the use of unsatisfactory equipment and to require that such equipment be replaced with acceptable equipment to maintain contract compliance. The decision of the COR as to serviceability of the equipment shall be final. Equipment shall meet current Federal, State and local safety requirements and all applicable requirements of the USACE EM 385-1-1.
6.2 Accident Prevention Plan (APP). The Contractor shall obtain the USACE Project Safety Officer’s approval of the Accident Prevention Plan BEFORE starting any on-site work.
a) The Contractor shall use a qualified Safety and Health Manager (SHM) to prepare the written site-specific Accident Prevention Plan (APP) in accordance with the format and requirements of USACE EM 385-1-1. Cover all paragraph and subparagraph elements in Appendix A of USACE EM 385-1-1 "Minimum Basic Outline for Preparation of Accident Prevention Plan.” Activity Hazard Analyses (AHAs) shall be appended to the APP. The SHM must have been engaged in safety and occupational health for at least 3 years with at least 50% of the time each year devoted to safety and occupational health.
b) The APP shall be job specific and shall address any unusual or unique aspects of the project or activity for which it is written. The APP shall interface with the Contractor's overall safety and health program (SHP). Any portions of the Contractor's overall safety and health program referenced in the APP shall be included in the applicable APP element and made site-specific. The Government considers the Prime Contractor to be the "controlling authority" for all work site safety and health of the Subcontractors. The Contractor is responsible for informing their Subcontractors of the safety provisions under the terms of the contract and the penalties for noncompliance, coordinating the work to prevent one craft from interfering with or creating hazardous working conditions for other crafts, and inspecting Subcontractor operations to ensure that accident prevention responsibilities are being carried out. The Contractor, COR, and Site Safety and Health Officer (SSHO) shall sign the APP.
c) The Contractor shall submit the APP to the USACE Project Safety Officer within 10 days of award. The Government will review the documents within 10 days. The Contractor shall resubmit the documents, with any requested changes, within 5 days of request.
6.3 Injury and Illness Prevention Program (IIPP) Appendix to the APP. For projects within California, the Contractor shall develop and implement an Injury and Illness Prevention Program (IIPP) that shall be attached to the APP as an appendix. The IIPP shall address all elements of Title 8 California Code of Regulations (CCR) Section
3203 and Section 1509. IIPP appendix elements that overlap with APP elements need not be duplicated in the IIPP, provided each safety and occupational health issue is adequately documented in the APP. The IIPP shall be developed under the direct supervision of a qualified SHM.
6.4 Environmental Safety Program. Contractor must comply with all Environmental and Occupational Safety and Health Laws. The contractor shall perform in compliance with Federal, State and local laws, rules, and regulations pertaining to environmental protection, occupational health and safety, transportation, storage, and disposal of hazardous materials and hazardous waste.
6.5 Deliverable schedule for health and safety plans. The contractor shall provide submittals required by Section 6.0 to the COR within 15 days of award. The Government will review the documents within 10 days. The contractor shall resubmit the documents, with any requested changes, within 5 days of request. Submissions shall be provided in Microsoft Office Word 2007 and shall be provided on a CD and/or electronic format.
7.0 GENERAL SUBMITTAL REQUIREMENTS
7.1 Submittals. Submittals shall include but not be limited to the following list of items to be provided by the Contractor. This list does not relieve the Contractor of the responsibility of ensuring the accuracy or completeness of the list or responsibility of providing all submittals required by regulatory and contract documents (Reference Appendix D). The Government will review the documents within 10 days. The contractor shall resubmit the documents, with any requested changes, within 5 days of request. Submissions shall be provided in Microsoft Office Word 2007 and shall be provided on a CD and/or electronic format.
- Contractor Quality Control (CQC) Plan (Sections 5.1 and 5.2)
- APP/AHA/IPP (Section 6.0)
- Attic Access Plan and Work Plan (Section 7.2)
- Product data including manufacturer’s instructions
- Indoor air quality certificates (insulation material and adhesives)
Submissions shall be provided in Microsoft Office Word 2007 or Adobe Acrobat (.pdf) and shall be provided in electronic format.
7.2 Work Plan. The contractor shall prepare a Project Work Plan (PWP) that identifies in detail the work to be completed as indicated below. All work shall be completed in accordance with all applicable laws, regulations and Regulatory Agency guidance or instructions. As a minimum, the PWP shall include project description, project objectives, schedule, and detailed sketches, schematics and PEMB Plans.
8.0 DEFINITIONS, ABBREVIATIONS AND ACRONYMS
8.1 Contracting Officer's Representative (COR): A person designated in writing by the Contracting Officer to conduct specific and limited technical administrative actions under the contract. The COR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract; perform inspections necessary in connection with contract performance; maintain written and oral communications with the Contractor concerning technical aspects of the contract; issue written interpretations of technical requirements, including Government drawings, designs, specifications: monitor Contractor's performance and notifies both the Contracting Officer and Contractor of any deficiencies; coordinate availability of government furnished property, and provide site entry of Contractor personnel.
8.2 Test: Any operation or series of operations under fixed conditions which compares actual performance to design standards.
9.0 REFERENCES
All applicable Federal and State regulations. It shall be the contractor’s responsibility to adhere to all applicable federal and state regulations pertaining to the specific work.
The Contractor’s APP/IPP, SSHP Appendix and subsequent activities must comply with the following referenced documents (most current version, if different than the date referenced), at a minimum:
EM 385-1-1, USACE Safety & Health Requirements Manual, EM 385-1-1, 2014 Edition
Title 29 Code of Federal Regulations (CFR) 1910, Occupational Safety and Health Standards.
29 CFR 1926, Safety and Health Regulations for Construction.
29 CFR 1926.65/29 CFR1910.120, Hazardous Waste Operations and Emergency Response.
USACE, Safety and Occupational Health Document Requirements for Hazardous, Toxic and Radioactive
Waste (HTRW) Activities, ER 385-1-92 (1 July 2003).
NIOSH/OSHA/USCG/EPA, Occupational Safety and Health Guidance Manual for Hazardous Waste Activities (October 1985).
American Conference of Governmental Industrial Hygienists (ACGIH®), TLVs® and BELs®, Threshold Limit Values for Chemical Substances and Physical Agents & Biological Exposure Indices (2005).
Title 8 California Code of Regulations (CCR) Chapter 4 Subchapter 4, Construction Safety Orders.
8 CCR Chapter 4 Subchapter 7, General Industry Safety Orders.
8 CCR Sections 3203 & 1509, Injury and Illness Prevention Program.
OSHA ancillary safety and health regulations governing certain aspects for this contract include:
Respiratory Protection (29 CFR 1910.134/8 CCR Section 5144)
Occupational Noise Exposure (29 CFR 1910.95/8 CCR Sections 5095-5100)
Hazard Communication (29 CFR 1910.1200/29 CFR 1926.59/8 CCR Section 5194)
The Control of Hazardous Energy (Lockout/Tagout) (29 CFR 1910.147)
Proposition 65 (22 CCR Section 12000) Chemicals Know to the State to Cause Cancer or Reproductive Toxicity
QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)
Quality Assurance Surveillance Plan (QASP)
1.0 Performance Requirements Summary
The table on the following page lists the PWS requirements/deliverables that the Government shall monitor. The absence of any contract requirement from the PRS/QASP does not detract from its enforceability nor limit the rights or remedies of the Government under any other provision of the contract, including the clauses entitled “Inspection of Services” and “Default.”
The table defines the standard for each listed PWS service, sites the respective specification, provides the method of surveillance, and describes disincentives for not meeting acceptable standards.
2.0 Government Quality Assurance
The Contracting Officer (KO) has overall responsibility for overseeing the Contractor’s performance. The COR shall monitor day-to-day contract compliance and administration. The COR is responsible for administration of the project. The COR also assures proper Government surveillance of the Contractor’s performance and shall monitor, record, and report on the technical performance of the Contractor on a day-to-day basis. The COR, along with USACE subject matter experts, shall assure the Contractor is meeting contract PWS standards, as well as all Federal, state, and local regulatory requirements. The Government intends to use the following methods to monitor standards:
Inspection and review of all required documents and submittals.
Periodic inspection of work processes or output.
100% inspection at the completion of key work segments and deliverables.
Customer feedback.
3.0 Performance Evaluation
Performance of services shall be evaluated to determine whether or not it meets the performance requirements of the contract. The COR shall evaluate and report Contractor performance to the Contracting Officer at each milestone and delivery per the project schedule. Progress inspection reports shall be submitted as required. When the performance requirement is not met, a contract discrepancy report (CDR) shall be issued to the Contractor by the Contracting Officer. The Contractor must respond to the CDR and return it to the contracting officer within five (5) calendar days of receipt. Failure to meet acceptable performance standards may result in one or all of the following actions:
Issue a temporary work stoppage awaiting corrective action.
Withdrawal of work Terminate the contract.
Quality Assurance Surveillance Plan
Required Service Standards Acceptable Quality
Level Method of surveillance
Preparation and submittal of all pre-project, documents, forms, permit requests, and notifications.
Permitting documentation, requests and notifications shall be performed by Contractor prior to start of work associated with those activities
100% approval of all submitted documents.
Government inspection
Install new insulation as stated in the PWS
Contractor shall meet 100% of all material and work requirements as stated in the
PWS.
Work product meets performance standards with no meaningful regulatory deviation.
100 % inspection
Debris disposal to include handling, transporting, and disposal means and methods.
Recycle, and reuse debris materials per industry best practices to the maximum economic extent. Effort also includes tracking, reporting, and accounting for all debris material quantities and respective disposition method.
Contractor shall follow good business practices and sustainability guidelines to dispose of materials in the most Environmentally sound and economically feasible manner
Work product meets performance standards with no meaningful regulatory deviation.
Periodic progress and final inspection
Reporting to include bi-weekly, monthly, and final reports.
Contractor shall follow approved procedures for reporting in the Quality
Control Plan (QCP) in order to meet the requirements in this PWS.
Contractor schedules bi-weekly coordination meetings
Work product meets performance standards with no meaningful regulatory deviation.
Government review
PICTURES
Attic Pictures:
Exterior Pictures:
SITE MAPS
(End of Summary of Changes)