B08 IFB W9123824B0012 Preaward Survey.docx

DOCX document 26 KB Posted

Attached to
USACE SPK DBB Construction - MOTCO Holding Pad and Berm Repair ? Military Ocean Terminal Concord (MOTCO), Concord, CA
Solicitation number
W9123824B0012
Issued by

About this file

This document is a Pre-Award Survey for a federal construction contract opportunity. It requests information from the construction contractor on their current payroll personnel, equipment owned, financial data, past construction work, and the types of construction specialties. The related federal contract opportunity is for the USACE SPK DBB Construction - MOTCO Holding Pad and Berm Repair project at Military Ocean Terminal Concord (MOTCO) in Concord, CA. The project involves excavation, installation of wire mesh, increasing berm heights, extending storm drain pipes, and other required work to repair the explosives safety berms. The contract is a firm-fixed price construction contract with a period of performance of 365 calendar days. The contract is set aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB) and the magnitude of construction is between $5,000,000 and $10,000,000.

View the file

Other files

File Type Posted
OF 1419 - Abstract for Construction_24B0012.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 4 – Pre-Award Survey Pre-Award Survey Information

CONSTRUCTION CONTRACTOR DATA
DATE:
Firm Name and Telephone Number
Main Office Address (Street, City, and State)
Branch Offices
Services Rendered

· Construction

· Design

· Consultant

Organization
· IndividualJoint Venture
· PartnershipCorporation
Date Organized
Date Incorporated:

State:

Names of Officers and Other Key Personnel

I – PRESENT PAYROLL PERSONNEL (List Number of Each Category Below)

Partners:

Officers: Other Key:

Remainder:
Subtotal Permanent:

Maximum Personnel at Any Time: Date:

Total:

II—EQUIPMENT OWNED
III—FINANCIAL DATA AS OF (DATE):

Present Value ($)

Current Assets:

Acquisition Cost ($)
Current Liabilities:

Net Worth:

IV—TOTAL VALUE OF CONSTRUCTION AND DEMOLITION WORK IN PAST 6 YRS EXCLUSIVE OF JOINT VENTURE (LIST MOST

RECENT FIRST)

V—LARGEST JOB EVER CONTRACTED

(If Other Than in Past Six Years)

$
LARGEST JOB IN PAST 6 YRS
Contract Amount: Date: Description:

Owner:

$
Contract Amount: Date: Description:

Owner:

Avg. Annual Income

VI—TYPE OF WORK IN WHICH FIRM SPECIALIZES

NAME AND POSITION/TITLE OF PERSON SIGNING
SIGNATURE

See attachment for explanations or detailed description of item(s) reported above.

CONSTRUCTION CONTRACTOR DATA – SCHEDULE A – EXISTING COMMITMENTS

List below the construction projects your firm currently has under way, including recent awards. Also list construction projects for which your firm is the apparent successful offeror/bidder, but for which a contract has not yet been awarded.

CONTRACT NUMBER

CONTRACT AMOUNT

DESCRIPTION/ LOCATION

ORGANIZATION/ CONTACT PERSON/ PHONE NUMBER

PERCENT COMPLETE

CONSTRUCTION CONTRACTOR DATA – SCHEDULE B – COMPLETED PROJECTS

List below the principal construction projects your firm has completed within the past six years, including all DOD contracts with a total value exceeding $10,000,000.00.

CONTRACT NUMBER

CONTRACT AMOUNT

DESCRIPTION/ LOCATION

ORGANIZATION/ CONTACT PERSON/ PHONE NUMBER

PERCENT SUBLET

Pre-Award Survey Information

CONSTRUCTION CONTRACTOR DATA – SCHEDULE C – CONSTRUCTION AND/OR TECHNICAL EQUIPMENT

List total equipment and facilities owned for performing the prospective contract and present status as to whether or not it is currently committed to existing contracts.

QUANTITY

DESCRIPTION

CONDITION

YEARS OF SERVICE

PRESENT STATUS